Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 27, Cited by 0]

Calcutta High Court

Steel Authority Of India Limited vs Htc Engineering (1958) Private Limited on 5 December, 2023

Author: Soumen Sen

Bench: Soumen Sen, Ravi Krishan Kapur

                     IN THE HIGH COURT AT CALCUTTA
                      CIVIL APPELLATE JURISDICTION
                              ORIGINAL SIDE


    BEFORE:
    The Hon'ble Justice Soumen Sen
    And
    The Hon'ble Justice Ravi Krishan Kapur


                              APO/356/2016
                  IA No.GA/1/2016 (Old No.GA/2465/2016)

                  STEEL AUTHORITY OF INDIA LIMITED
                              VERSUS
                HTC ENGINEERING (1958) PRIVATE LIMITED


    For the Appellants               :Mr. Anindya Kumar Mitra, Sr. Adv.
                                      Mr. Sarathi Dasgupta, Adv.
                                      Ms. Supriya Dubey, Adv.
                                      Ms. Sneha Dutta, Adv.


    For the Respondent               : Mr. Debashis Kundu, Sr. Adv.
                                       Mr. Sayantan Bose, Adv.
                                       Mr. Jaydeb Ghorai, Adv.
                                       Mr. Dilip Ghosh, Adv.
                                       Mr. Sukrit Mukherjee, Adv.
                                       Mr. Diptesh Ghorai, Adv.


    Hearing Concluded On             : 18th August, 2023

    Judgment On                      : 5th December, 2023


       Soumen Sen, J.: The appeal is arising out of a judgment and order

passed by the learned Single Judge in connection with an application filed

by the appellant for setting aside of an award made and published on 17th

March, 2016 by the Arbitral Tribunal.


       2. The Arbitral Tribunal had partly allowed the claim of the parties.
                                         2



       3. In the arbitration proceeding Steel Authority of India (in short

'SAIL') was the claimant. The respondent HTC in the said proceeding filed a

counter-statement with a counter claim.


       4. On a set off being allowed the appellant had suffered an award of

Rs.7,45,56,134/- together with interest @ 18% per annum on the amount

from the date of the award till payment apart from the costs and expenses of

the arbitration.


       5. The arbitral tribunal was consisted of three former Hon'ble Judges

of this court.


       6. It was a unanimous award.


       7. The learned Single Judge on consideration of the submissions

made on behalf of the respective parties upheld the award and dismissed the

application for setting aside of the award.


       8. This order is now under challenge.


       9. Before we delve into the issues raised on behalf of the parties we

feel it necessary to indicate the relevant facts.


       10. Pursuant to an invitation to tender notice dated 5th/6th August,

1996 for handling iron and steel materials at the Stock-yard of SAIL located

at Paharpur, 20 Coal Berth and DP-II siding of Calcutta the respondent

participated in the said tender and after due evaluation of all the tenders

submitted by different parties, the contract was awarded to HTC Engineering

Pvt. Ltd. (in short "HTC") with effect from 23rd November, 1996. One of the
                                          3



stipulations made in the said tender was that the prospective contractors

must have an experience of handling at least 125 lacs MT of Steel materials

in any of the preceding five financial years. The tenderer must own at least

50 per cent of the equipment specified at clauses 2.1 of Instructions to

Tenderers in its own name.


       11. The estimated quantities proposed to be handled during the 1st

year of operation of the contract are mentioned in Clause 4. The said Clause

is reproduced below:


    4. The estimated quantities proposed to be handled during the first
    year of operation of the contract are expected to be as under
    (calculation based on sales plan):

             Particulars                     Receipt           Delivery

               Pig Iron                       5000              5000

                 Tool                        2,50,000         2,50,000

                Total                        2,55,000         2,55,000

                                                        (Emphasis supplied)


       12. Clause 5 states that the estimated quantities are only for the

purpose of finding out the value of the tender and SAIL would not be anyway

liable if the actual quantity of the work differs from the estimated quantity

indicated in Clause 4. The said Clause reads:


       "5. The estimated quantities for the first year of operation of
       contract are only for the purpose of finding out the value of the
       tender and SAIL is in no way liable if the actual quantity of work
                                          4



       differs from estimated quantity indicated above." (emphasis
       supplied)

       13. In Clause 9 of the Tender Notice for appointment of Handling

Contractor it is stated:


       "This Tender is subject to the interim order passed by the Hon'ble
       Calcutta High Court on 24th July, 1995 in FMAT No.1460 of 94
       (Steel Authority of India Ltd. & Ors. vs. Sheonayak Murai & Ors.
       by which the Hon'ble Calcutta High Court directed to maintain the
       status quo of the employment of the contract labour working in the
       Paharpur Stockyard till the disposal of the said Appeal."
       (emphasis supplied)

       14. The Clauses 3, 3.2 and 4.0 of the Instruction to Tenderers

Schedule of Operation and Rates are mentioned. The said Clauses read:


        3. Schedule of operation and payment:

       3.2. The rates quoted will be deemed to be inclusive of the cost of
       discharging all the general duties for performing the work
       efficiently.

       4.0. To enable the Tenderer to assess the quantum of work the
       estimated quantities proposed to be handled during the first year
       of operation are indicated below:         (emphasis supplied)

                               Receipt                  Delivery

       Steel                   2,50,000 M/T             2,50,000 M/T

       Pig Iron                5000 M/T                 5000 M/T

       15. Clause 11.1 of the "Instructions to Tenderers" refer to the

documents that shall constitute the contract. They are:-
                                          5



         i) The advertisement for tender

         ii) Instructions to tenders,

         iii) Terms and conditions of contract along with all its enclosures
         etc. and any other letters exchanged with the successful
         tenderer shall form part of the contract.

       16. The agreement/contract for handling iron and steel materials

executed on 23rd November, 1996 in Clause 2 refers to thirteen documents

as annexures 1 to 13 which shall constitute the contract for the purpose of

construction, interpretation and effect thereof. They are:


       a) Annexure - 1          : Contractor's letter

       b) Annexure - 2          : Invitation to tender.

       c) Annexure - 3          : Instructions to tenderers.

       d) Annexure - 4          : Terms and conditions of contract for

                                 handling Iron & Steel materials.

      e) Annexure - 5           : Terms and conditions for crane(s) and/or

                                 other equipment (s) to be hired out by the Co.

      f) Annexure - 6           : Custody & Indemnity bond.

      g) Annexure - 7           : Equipment utilization statement form.

      h) Annexure - 8           : Guarantee Bond.

      i) Annexure - 9           : Check lists for cranes.

      j) Annexure - 10          : Schedule of rates for general operation in

                                 yard.

      K) Annexure - 11          : Schedule of items : Pig Iron,

                                 Schedule - A, Schedule - B.

      l) Annexure - 12          : Schedule of cutting charges.
                                          6



      m) Annexure - 13           : (i) List of road transport;

                                  (ii) List of mechanical handling equipment.

       17. The Handling Contractor in terms of Clause 2 of Terms and

conditions of Contract for Handling Iron and Steel Materials in the

stockyards of Steel Authority of India Limited at Paharpur, 20 Coal Berth

and DP-II Siding shall handle the arrivals, deliveries and despatches of Iron

and Steel materials. The nature of the handling work will be as indicated in

the Schedule of Operations and Rates.


       18. The Liabilities of the Contractor is mentioned in Clause 4.8 of the

aforesaid terms which states:


          4.8 In the event of the contractor's failure or default to provide
          sufficient equipment and for timely labour at any time to do any of
          the jobs entrusted with to under the contract or in the event of the
          Contractor unilaterally terminating the contract, the company shall
          have the right to get the work done by directly employing labour,
          equipments or by employing another Agency and all charges and
          expenses incurred by the Company in this behalf shall be recovered
          from the Contractor either form his bills or from any other amount
          payable to the Contractor either under this contract or any other
          contract." (emphasis supplied

       19. The rates payable and escalation are mentioned in Clause 6.2 of

the aforesaid terms. It reads:


       6.2 ...... The rates quoted in the Schedule of Operation and Rates
       annexed hereto for major items as mentioned above will be deemed to
       comprise of various components as follows:

                  Composition of the rates and weightage of various
                                                 7



                                     Components of work involved

   Components           Traditional Wing            Mechanised Wing      Transportation

                        Sch -A         Sch-B                            Sch -A      Sch - B

                         Items         Items                             Items       Items

                            +                                               +

                           Pig                                             Pig

                          Iron                                            Iron



        Labour                  60             10           10            10             10

        Fuel                    -              35           -             45             35

        Overheads               25             40           40            30             40

        Profit                  15             15           15            15             15
         Total                100            100            100            100           100
----------------------------------------------------------------------------------------------
         20. The Tenure of the contract is mentioned in Clause 7.1 of the

aforesaid terms. It would be effective from the date of commencement of the

work as mentioned in the work order initially for a period of two years with

the option to extend the same at the sole discretion of the Company for a

further period of one year on the same rates and terms and conditions. The

company will also have the option to terminate the Contract at any time

during the period of Contract by giving 30 days' notice in writing without

assigning any reason whatsoever and without payment of any compensation.

In the event of Contractor's failure to discharge duties strictly in the manner

stipulated in the Contract, the Company may terminate the same summarily

and without notice. The decision of the Company or its representative
                                         8



regarding Contractor's failure to discharge his obligations strictly under the

Contract shall be final and binding upon the Contractor.


          21. Clauses 8.3 and 8.7 deals with the relative rights of the parties

with regard to guaranteed quantities. The said clauses are mentioned under

the general terms and are reproduced below:


    8.3 "The mere mention of any item or work in the contract does not
    by itself confer the right upon the contractor to demand that item of
    work at all times.

    8.7. The company gives no guarantee about the reasonable volume of
    work to be entrusted with the contractor at any time or even
    throughout of tenure of the contract." (emphasis supplied)

          22. The contract was awarded to HTC with effect from 23rd November,

1996 in the background of HTC's past experience and good performance as

Steel material handling contractors in SAIL's stock-yard continuously for 14

years and most importantly because of the competitive price/rate quoted by

HTC.


          23. Dispute arose between the parties with regard to supply of

minimum quantity of materials to be handled by the contractor under the

tender.


          24. The arbitration proceeding was initiated by SAIL on 1st     July,

1999 against HTC claiming inter alia, damages on account of alleged non

performance of HTC for the period from 23rd November, 1996 to 31st March,

1999. SAIL appears to have extended the duration of the contract

unilaterally for a further period of one year with effect from 22nd November,
                                        9



1998. SAIL enhanced their original claim with an additional claim for

balance period, that is, up to 22nd November, 1999.


       25. SAIL made the following claims:-


     Item of Claim               Original Claim         Supplementary Claim
                            (Calculated upto 31.3.99)     (Calculated upto
                                                             22.11.99)
 a. unpaid wages to the        Rs.3,48,86,400.00         Rs.1,67,29,600.00
      Contract Labour
     b. PF ques of the          Rs.96,01,947.00           Rs.32,44,270.00
      Contract Labour
 c. Unpaid bonus to the         Rs.75,29,508.00           Rs.15,30,064.00
  contract labour with
   effect from 23.11.96
  d. Unpaid gratuity to         Rs.30,16,629.00           Rs.10,26,683.78
   the Contract labour
       with effect from
            23.11.96
e. Unpaid Privilege leave       Rs.52,28,825.00           Rs.13,43,108.33
  salary to the contract
Labour with effect from
            23.11.96
      f. Claim towards          Rs.22,80,893.00
interest on outstanding
            advance
     g. Claim towards                                   Rs.28,36,53,203.00
   liquidated damages
h. Contingent liabilities       Rs.90,46,969.00           Rs.40,09,777.00
         i.Workmen's             Rs.30,000.00
        compensation
    j. Loss due to total        Rs.99,70,030.00
 stoppage in delivery of
       materials from
  Paharpur Coal Berth
Stock yards from 1.1.99
           to 31.3.99
              Total           Rs.36,52,04,404.00         Rs.2,78,83,503.11
                                        10



       26. Most of the claims mentioned aforesaid, pertains to the contract

labourers apart from liquidated damages.


       27. HTC made a counter claim against SAIL in the sum of Rs.

15,42,98,768/- the particulars whereof are mentioned below:


                                  PARTICULARS


 1) Non supply of promised and/or                Rs.12,40,93,043.00
 assured quantity of materials to be
             handled

 2. Wrongful detention of machinery                Rs.36,99,500.00

   3. Additional claims made on                  Rs.1,79,00,4000.00
  account of 224 contract labours

  4.Outstanding bills and interest                 Rs.86,05,825.00

  5. Refund of security deposit and                Rs.11,50,000.00
  performance guarantee by way of
          bank guarantee

                Total                            Rs.15,54,48,768.00




       28. The aforesaid claim of HTC from 1st May, 1998 to 22nd November,

1999 spanning over a period of 19 months was taken up for consideration

by the Arbitral Tribunal along with the claim of SAIL.


       29. After the completion of pleadings on consideration of the issues

raised by the parties the arbitral tribunal settled eleven issues. The issues

are indicated below:


   1. (a) Was not the claimant under the contract obliged to supply 21250 MT
      totalling 42500 MT per month on an average?

    (b) If yes, did the claimant commit breach of such obligation?
                                  11




2. (a) Is the claimant entitled to a sum of Rs.5,16,000.00 as enhanced up
to 2nd November, 1999 or any other sum on account of alleged unpaid
wages to the contract labourers claimed in Claim no.A of paragraph 27 in
the Statement of claim and Annexure I of paragraph 14 to the Rejoinder
to the counter statement of facts?

(b) Is the claimant entitled to a sum of Rs.1,28,46,217.00 as enhanced up
to 22nd November, 1999 or any other sum on account of alleged Provident
Fund dues of contract labourers as claimed in Claim No.B of paragraph
27 of the Statement of claim and Annexure II of paragraph 16 to the
Rejoinder to the counter statement of facts?

(c) Is the claimant entitled to a sum of Rs.74,40,240.00 enhanced up to
22nd November, 1999 or any other sum on account of alleged bonus to the
contract labourers with effect from 23rd November, 1996 as claimed in
claim No.C of paragraph 27 of the Statement of claim and Annexure III of
paragraph 16 to the Rejoinder to the counter statement of facts?
(d) Is the claimant entitled to a sum of Rs.40,43,312.78 as enhanced upto
22nd November, 1999 or any other sum on account of alleged unpaid
gratuity to the contract labourers with effect from 23rd November, 1996 as
claimed in claim No. D of paragraph 27 of the Statement of claim and
Annexure IV of paragraph 16 to the rejoinder to the counter statement of
facts?

(e) Is the claimant entitled to a sum of Rs.65,71,933.33 as enhanced up
to 22nd November, 1999 or any other sum on account of unpaid alleged
privilege leave salary of the contract labourers with effect from 23rd
November, 1996 as claimed in claim no.E of paragraph 27 of the
Statement of claim and Annexure V of paragraph 16 to the rejoinder to
the counter statement of facts?

(f) Is entitled to an alleged sum of Rs.14,37,273.00 or any other sum
towards alleged interest on advance as claimed in claim no.F of
paragraph 27 of the Statement of claim?

(g) Is the claimant entitled to a sum of Rs.28,36,53,203.00 or any other
sum on account of alleged liquidated damages as claimed in claim no.G
of paragraph 27 of the Statement of claim?

(h) Is the claimant entitled to a sum of Rs.1,29,26,188.00 as enhanced up
to 22nd November, 1999 or any other sum on account of alleged
contingent liabilities as claimed in claim no.H of paragraph 27 of the
Statement of claim and Annexure VIII of paragraph 16 to the rejoinder to
the counter statement of facts?
                                         12



    (i) Is the claimant entitled to a sum of Rs.30,000.00 or any other sum on
    account of alleged worker's compensation as claimed in as claimed in
    Claim No. I of paragraph 27 of the Statement of claim?

    (j) Is the claimant entitled to a sum of Rs.99,70,030.00 due to loss on
    account of alleged stoppage in delivery of materials from paharpur and
    Coal Berth Stock yards from 1.1.99 to 31.03.99 as claimed in claim no.J
    of paragraph 27 of the Statement of claim?

    3. Is the claimant entitled to interest at the rate of 18 per cent per annum
    as claimed in paragraph 31 of the Statement of claim?

    4. To what reliefs, if any, is the claimant entitled to?

    5. Is the respondent entitled to a sum of Rs.12,40,93,043.00 on account
    of non supply of promised and/or assured quantity of materials to be
    handled during the period of 1st May, 1998 to 22nd November, 1999 as
    pleaded in paragraph 29 of the counter claim?

    6. Is the respondent entitled to a sum of Rs.36,99,500.00 on account of
    wrongful detention of machinery as pleaded in paragraph 31 of the
    counter claim?

    7. Is the respondent entitled to a sum of Rs.1,79,00,400.00 towards
    additional claims made on account of 224 contract labours as pleaded in
    paragraphs 32 and 33 of the counter claim?

    8. Is the respondent entitled to a sum of Rs.86,05,825.00 on account of
    outstanding bills and interest as pleaded in paragraph 34 of the counter
    claim?

    9. Is the respondent entitled to a sum of Rs.11,50,000.00 on account of
    refund of security deposit and performance guarantee by way of bank
    guarantee as pleaded in paragraph 35 of the counter claim?

    10. is the respondent entitled to interest at the rate of 24 per cent per
    annum as claimed in paragraph 39 of the counter claim?

    11. To what reliefs, if any, is the respondent entitled to?


      30. The Arbitral Tribunal on consideration of the respective claims

passed an award on March 17, 2006 in favour of HTC for a sum of

Rs.7,48,56,134.00. The summary of the award is in paragraph 26, which is

as under:
                                       13



                 SAIL               HTC Engineering (1958) Private Ltd.
              (Claimant)            (Respondent)
Amount awarded on account of        SAIL was under an obligation to
reimbursement of advance paid to    provide at least 581737 MT of
the contract labours including wagesmaterials to be handled by HTC
for the period 23rd November, 1996  during       the    period     under
to 31st November, 1999              consideration i.e. 1st May, 1988 to
                                    22nd November, 1999. HTC is entitled
                  Rs.3,28,71,200.00 to loss and damages suffered by it for
                                    failure of SAIL to supply the said
                                    minimum quantity of materials to be
                                    handled by HTC.
                                                       Rs.9,51,63,982.00
                                    Award on account wrongful detention
                                    of machinery and equipment.
                                                         Rs.36,99,982.00
                                    Award on account of outstanding
                                    bills and interest
                                                         Rs.77,99,500.00

                                       Award on account of refund of
                                       security deposit and performance
                                       guarantee
                                                         Rs.11,50,000.00

TOTAL: Rs.3,28,71,200.00               TOTAL : Rs.10,77,27,334.00


    Rs.10,77,27,334.00 - Rs.3,28,71,200.00 = 7,48,56,134.00"

      31. Thereafter, in paragraph 27 and 30 of the award it is stated:

         "27. From the above it will be evident that SAIL will have to pay
         Rs.7,48,56,134.00 to HTC. We therefore, make an award of
         Rs.7,48,56,134.00 in favour of HTC against SAIL. SAIL will pay
         interest at the rate of 18% per annum on the awarded amount from
         the date of the award till payment.
         30.The costs and expenses of this arbitration are hereby fixed at
         Rs.6,65,000/-    (Rupees    six   lac   sixty-five   thousand    only),
         Rs.1,66,250/- (including conveyance of Rs.10,000/-) being each
         arbitrator's fee and Rs.1,66,250/- being the administrative fee of the
         Indian Council of Arbitration (ICA). The above payments shall be
         made out of the deposits made by the parties with the ICA."
                                       14



       32. Presently, we are only concerned with the award allowing the

claim of HTC for a sum of Rs.10,77,27,334/- which on a set off stands

reduced to Rs.7,48,56,134/-.


    Submissions on behalf of SAIL


       33. Mr. Anindya Kumar Mitra Sr. Advocate appearing on behalf of

SAIL has submitted that the award is liable to be set aside because of the

following reasons:


         i) It contains decision on matters beyond the scope of the
         submission of the arbitration and not falling within the terms of
         the arbitration.

         ii) The award is without jurisdiction

         iii) The arbitrator has made out a new case by adding a new term
         in the contract by ostensible means of interpretation.

         iv) The implied terms read into the contract is contrary to the
         settled law of the land.

       34. Mr. Mitra has submitted that under the guise of interpretation of

the contract certain terms have been introduced as implied terms and those

terms have been interpreted in a manner which contradict the express terms

of the contract. It is well settled that implied terms cannot be read into in a

contract where there is an express clause governing the transactions. The

terms are clear and certain. There is no ambiguity for which any implied

term could have been read into in the contract.         The learned Arbitral

Tribunal has not considered clauses 5 and 8.7 which clearly define the

obligation between the parties and non-consideration of such relevant
                                        15



clauses leads to legal perversity. In ignoring the aforesaid clauses and solely

relying upon clause 4 for the purpose of giving benefits to the award holder

is a clear case of legal perversity.   The Tribunal has wrongly applied the

principles of business efficacy in interpreting clause 4 and the other clauses

of the contract. When the terms are definite and clear the concept of

business efficacy could not have been applied by necessary implication as

they were never intended by the parties to be read into the contract at the

time of entering the contract and in conducting themselves during the

contract period. In any event the quantification of the compensation is also

based on conjecture and surmise. Moreover the basis of such quantification

is vague.


       35. Mr. Mitra has submitted that the award was passed in complete

misconstruction and misinterpretation of Clause 4 of the invitation of tender

as it has ignored Clause 5. The contract was initially for a period of two

years with liberty to extend the period by one year. The Tribunal construed

the aforesaid Clauses and more particularly Clause 5 to hold that

reasonable quantity was to be read into the said clause and that reasonable

quantity were to be made available to HTC by SAIL during the second and

third year. The reasonable quantity was assessed by the Tribunal at

6,12,072 MT for the period from 1st May, 1998 to 22nd November, 1999

which includes part of second year and whole of third year being 73 per cent

of the expected quantity of the material as mentioned in Clause 4 to be

supplied in the first year. In other words HTC had received only 30,335 MT

from SAIL as against 7,96,900 MT which was estimated and expected to be
                                         16



handled during the aforesaid period by HTC in terms of Clause 4 of the

terms and conditions of the contract.


       36. Mr. Mitra submits that the Tribunal has completely overlooked

that the quantities to be supplied in Clause 4 is qualified by Clause 5 and to

that extent the findings in the award in paragraph 7.1, 7.4 and 7.5 are

perverse. It is submitted that the award has three broad features, namely,


    Firstly, it assumes guaranteed supply of reasonable quantity in the
    contract.

    Secondly, such reasonable quantity was assessed by the Tribunal at
    quantities arrived at from Clause 4, and

    Thirdly, damage was awarded to the contractor on the basis of net
    profit as also amount of cost and expenses estimated to have been
    incurred by the contractor for earning such profit.

    It is submitted that HTC in its statement of claim has not at all
    referred to any claim on the aforesaid basis. The Arbitral Tribunal
    invented new disputes that were not referred to arbitration, namely,
    the claimant would be entitled to reasonable quantity for handle and
    such reasonable quantity would be determined by the Tribunal and
    further that the contractor would get compensation on the basis of
    profit @ 15% together with the cost involved in earning such profits.
    This is not permissible in view of the decisions in Booz Allen &
    Hamilton Inc v. SBI Home Finance Limited & Ors., 2011 (5) SCC
    532 which clearly states that dispute not submitted to arbitration
    cannot be decided.

       37. Mr. Mitra submits that since the assumption of jurisdiction by

the Tribunal is wrong the award is wholly without jurisdiction. The arbitral

tribunal based its award on its decision on disputes not falling within the
                                        17



terms of submission to arbitration and accordingly is liable to be set aside

under Section 34 (2)(iv) of the Arbitration and Conciliation Act, 1996.


         38. Apart from the aforesaid, it is submitted that the Tribunal has

inserted new clause and sentence into the contract namely in Clause 5 and

Clause 8.7. Insertion of such clauses in the existing clauses violated the very

integrity of the contract and resulted in a contract which the parties have

never contemplated at the time of entering into the contract. The expansive

interpretation of Clauses 4, 5 and 8.7 is perverse and is not a possible

interpretation of the contract.


         39. Mr. Mitra submits that by reason of the interpretation given to

the aforesaid two clauses, Clause 5 of the invitation to tender and Clause

8.7 of the terms and conditions of the contract they would now read as

under:


     "Clause 5: The estimated quantities for the first year of operation of
     contract are only for the purpose of finding out the value of the tender
     & SAIL is in no way liable if the actual quantity of work differs from
     estimated quantity indicated above. But the company (SAIL) would be
     liable if a reasonable quantity of work is not provided to the contractor
     throughout the tenure of the contract.

     Clause 8.7: The company gives no guarantee about the definite volume
     of work to be entrusted with the contractor at any time or even
     throughout of tenure of the contract. But a reasonable volume of work
     is guaranteed by the company during the tenure of the contract."
                                        18



       40. The underlined portions are additions which according to Mr.

Mitra have been added by way of necessary implication by the Tribunal

based on the business efficacy rule.


       41. Mr. Mitra submits that the aforesaid additions which we have

underlined would now if added to clause 5 and 8.7 as per the award of the

Arbitral Tribunal by necessary implication would result in a new contract for

the parties which they never intended to enter and on this ground alone the

award is liable to be set aside as it is without jurisdiction. These clauses

being specific clauses creating a no liability in favour of SAIL the

interpretation of the contract by the Arbitral Tribunal is contrary to the well

settled cannons of interpretation.


       42. Mr. Mitra has relied upon the decision in the Moorcock case

(1864) LR 14 PD 64 (CA) which has been adopted by Supreme Court in The

Union of India (UOI) v. D.N. Revri and Co. & Ors., reported in 1976(4)

SCC 147, Nabha Power Limited (NPL) v. Punjab State Power Corporation

Limited (PSPCL) & Anr., 2018 (11) SCC 508 and Adani Power (Mundra)

Limited v. Gujarat Electricity Regulatory Commission & Ors., 2019(19)

SCC 9 to emphasise that there are five prerequisite criteria and all the five

conditions are required to be fulfilled before any term could be implied into a

written contract. The law requires that all the five conditions have to be

fulfilled and not some of the five conditions. It is submitted that even if

considered reasonable or equitable or necessary to give business efficacy, a

term cannot be implied in violation of -
                                        19



       i). Officious Bystander test,
       ii) Not specified and
       iii) In contradiction of any express term of the contract.


       43. It is submitted that in Adani Power (super) it has been clearly

stated that the contract is to be interpreted giving the actual meaning of the

words contained in the contract and it is not permissible for the court to

make a new contract, however, reasonable, if the parties have not made it

themselves.   Mr. Mitra submits that it was not open for the tribunal to

substitute 'reasonable' in place of 'estimated' quality disregarding the no

guarantee clause. The parties have never intended that the SAIL would have

any obligation to supply the estimated quantity and hence the business

efficacy test would not be applicable.      This distorted interpretation has

resulted in a new contract. The contract has to be interpreted without any

external aid and without altering the nature of the contract.


       44. In elaborating his submission on the three tier test to assail the

award it is submitted that:


          (i) The condition added to the contract is in contradiction of
         express terms and conditions of contract namely, clause 5 of
         "Invitation to Tender" and clause 8.7 of the "Terms and Conditions
         of the Contract". It is settled law that no term which contradicts an
         express term of the contract can be implied into the contract.
         Secondly, the Arbitral Tribunal does not have the jurisdiction to
         override an express condition in the contract which is the fountain
         of its jurisdiction.
                                        20



       45. The arbitrator in view of Section 28(3) of the 1996 Act is required

to decide in accordance with the terms of the contract. The non-

consideration of prohibitory and no guarantee clauses vitiates the award.

Any award contrary to the terms of the contract would suffer from patent

illegality as held in Hisdustan Zinc Ltd. v. Friends Coal Carbonisation,

2006(4) SCC 445. Mr. Mitra submits that paragraph 14 of the Judgment

makes it clear that it is open to the court to consider whether the award is

against the specific terms of the contract and if so, interfere with it on the

ground that it is patently illegal and opposed to the public policy of India.

This view has been reiterated and reaffirmed in State of Chattisgarh & Anr

v. SAL Udyog Private Limited, 2022 (2) SCC 275 in which it has been

clearly stated that failure on the part of the sole arbitrator to decide in

accordance with the terms of the contract governing the parties, would

attract the "patent illegality ground" as the said oversight amounts to gross

contravention of Section 28(3) of the 1996 Act, that enjoins the Arbitral

Tribunal to take into account the terms of the contract while making an

award. It goes to the very root of the matter.


          (ii) The Tribunal has implied the above term solely relying upon
          clause 4 of the Invitation to Tender but did not advert to clause 5
          of the Invitation to Tender and Clause 8.7 of General Terms and
          Conditions while interpreting clause 4. Non-consideration of
          relevant clauses of the contract amounts to perversity and vitiates
          the Award.

          (iii) The above addition of terms by strenuous interpretation is in
          contradiction of 2nd portion of clause 5, namely, "SAIL is in no way
          liable if the actual quantity of work differs from the estimated
                                        21



         quantity indicated above." (emphasis supplied). On the basis of the
         said clause it is not possible to interpret that SAIL would be liable
         to supply the estimated quantity. The interpretation of the Arbitral
         Tribunal of expand the meaning of estimated quantity Clauses 4
         and 5 of NIT as reasonable quantity is perverse and is not a
         possible    interpretation   of    the   contract.   Any   unreasonable
         interpretation of the terms and considerations of the contract
         would be a ground for setting aside of the award as observed in
         South East Asia Marine Engineering & Constructions Limited
         (Seamec Limited) v. Oil India Limited, 2020 (5) SCC 164.

         (iv) The Tribunal have made out a new contract between the
         parties and the purported Award is beyond jurisdiction, because
         such case or dispute was not submitted to reference.

         (v) The Tribunal did not hold that implying of the above condition
         is by way of necessary implication. Merely that insertion of such
         terms appeared to be reasonable per se, without there being a
         requirement of necessary implication cannot support addition of a
         term into the contract or modification of the Contract.

         (vi) The criterion for implied term is that the term sought to be
         implied must not be vague but must be specific. The term
         "reasonable quantity" is not specific and cannot be implied into the
         contract.

       46. In so far as the assessment of reasonable quantity at 5,81,736

MT for the period from 1st May, 1998 to 22nd November, 1999 i.e. 18 months

22 days, it is submitted that:


         (i) The contract does not provide any term or provision for
         calculation of reasonable quantity since the contract does not at all
         provide for any reasonable quantity being made available to the
                                22



contractor.   The   Arbitral   Tribunal   acted   completely   without
jurisdiction in acting de hors the contract.

(ii) The Arbitral Tribunal had made out a new case for the parties.
The claimant did not submit to arbitration any dispute that if SAIL
had provided less than reasonable quantity during the relevant
period, SAIL would be liable to compensate HTC. HTC did not even
base its claim on any reasonable quantity basis.

(iii) In their Counter Statement in paragraph 25, HTC had
submitted that terms and conditions of the tender documents gave
rise to a "legitimate and bonafide expectation" that during the first
year of handling at least 5.10 lacs MT would be required to be
handled. This question was not raised by HTC at the hearing
before Arbitral Tribunal. This plea was thus abandoned. In
paragraph 29 of the Counter Statement the respondent HTC
claimed that in view of the clauses in "Instruction to Invitation",
SAIL had 'promised' a quantity and the promised quantity was at
3,90,339 Metric Ton to be received and 3,76,000 Metric Ton to be
delivered by the handling contractor during the period from
1.5.1998 to 22.11.1999. The case of promise and/or assurance of
a definite quantity has been changed into a reasonable quantity by
the Arbitral Tribunal, although not referred to arbitration and in
this regard attention of the court is drawn to Paragraphs 25 and
29 and Annexure B of the reply of HTC to SAIL's rejoinder and
also counter claim. The said paragraphs read:

"25. Accordingly the respondents submit as follows:-

(a) The jural and /or contractual relationship between the
Respondent and Claimant was entered into pursuant to a notice
inviting Tender which was published on 5th /6th August, 1996.

(b) In the said Notice Inviting Tender, it was provided that the
criteria for eligibility to be considered was an experienced of
                             23



handling Steel and Iron materials on at least 1,25,000 Metric
Tonnes during any of the proceeding five financial years.

(c) It is also pertinent to note that one of the salient terms and
conditions of the tender document handed over to the Respondent
was clause 4 where under estimated quantities proposed to be
handled per year of operation was given and the quantity
mentioned was 2,55,000 Metric Tonnes of materials being the
Receipt and an equivalent amount on account of delivery.

(d) In order to ensure the capability of the contractor to handle the
aforesaid quantity of materials per year, the contractor was obliged
to possess the various equipments more specifically set out in the
contract documents and also employ the workmen at the Paharpur
Stockyard as per the interim order passed by the Hon,ble Calcutta
High Court dated 25th July, 1995 in F.MAT. No. 1460 of 1995.

(e) The Respondent humbly submits that in the terms of the said
provision of the tender document a clear representation was made
by the Claimant which gave rise to a legitimate and bonafide
expectation on behalf of the Respondent that during the First year
of handling at least 5,10,000 Metric Tonnes of materials would be
required to be handled. Considering such huge quantity of
materials to be handled, the Respondent had given quotations."

29. The Respondent submits that in view of the clear instruction,
Respondent, however, had to acquire, keep ready men, materials
and machinery, so as to be able to handle the said promised
and/or reasonable expected quantity of materials. However, the
Claimant every year starting with 23rd November, 1996 till date,
had failed and neglected to place for disposal the promised
quantity and, as such the mobilization of men, materials and
machineries became onerous. In fact, the Respondent had suffered
loss and damages during the period of 1st May, 1998 to 22nd
                                       24



         November, 1999, on account of Non-Supply of promised and/or
         assured quantity of materials to be handled. The Respondent
         assesses such loss at Rs. 12,40,93,043/-, details whereof are
         specified in ANNEXURE-B hereof."

       47. Mr. Mitra has submitted that the assessment of 5,81,737 Metric

Ton as reasonable quantity is de hors the submission to reference, the

pleadings and the contract. The basis for assessing the quantity at 5,81,737

Metric Ton is given in paragraphs 7.1 to 7.5 of the Award which is not

supported by any provision of the contract and is wholly arbitrary,

unreasonable and perverse.


       48. Mr. Mitra was critical about the assessment of damages. It is

submitted that: a new case of loss of profit at the rate of 15% has been made

out by the Arbitral Tribunal which was contrary to the case of HTC as made

in its submission to arbitration. HTC claimed loss and damages "on account

of non-supply of promised and/or assured quantity of materials to be

handled", on the basis of total amount of handling charges to be received at

the contractual rate at Rs.9,00,31,650/-. In this regard attention of the

court was drawn to Annexure "B" to the Counter Statement and

paragraph 29 of the Counter Statement.


       49. It is submitted that awarding of damages on the basis of loss of

profit is contrary to the claim of HTC and is wholly without jurisdiction.


       50. Even if it is assumed that damages could be awarded on the

basis of loss of profit, it is submitted that a contractor cannot claim loss of

profit and also the amounts of expenses which the contractor would be
                                      25



required to spend for earning that profit. The Arbitral Tribunal in

paragraphs 19.11 to 19.14 of the award have granted both, by double

counting, which is ex facie illegal and void, and contrary to law and Public

Policy of India.


       51. HTC has never claimed loss of profit @ 15% of total handling

charges (receiving and delivery). The Tribunal has made out a new case. The

Tribunal has added the amount to be reimbursed to SAIL by HTC to

overhead costs assumed to have been incurred by HTC, without an iota of

proof for handling of 5,81,737 MT.


       Submission on behalf of HTC


       52. Per contra, Mr. Debashis Kundu learned Senior Counsel

representing the award holder has submitted that Clause 11.1 of the

"instruction of tenderers" referred to the document that shall constitute the

contract.   The terms and conditions of the tender are worded in such a

manner that the contractor upon going through the terms and conditions

and after taking into account of "estimated quantity" to be supplied by SAIL

in the first year of contract would have to quote the rates for various items

which were to be handled by HTC.          In other words the instructions to

tenders had given an estimate of materials to be handled by an incoming

contractor on basic terms and conditions which were more fully elaborated

and from the basis of an informed decision with regard to the rates to be

quoted for each items. Mr. Kundu has submitted that the tenderer would

also be required to take into account before quoting its price the estimated
                                          26



quantity to be handled which would not be different from what was stated in

Clause 4 NIT. This clause is in the nature of an enabling clause as it would

enable the contractor to quote the price of each items based on an estimated

quantity.


          53. The various schedules of operation and quantity have been fixed

by SAIL and on that basis a potential contractor would be required to quote

its rates for consideration by SAIL during the selecting of a successful

bidder.      It is a commercial contract and ordinarily in commercial

transactions a contractor ordinarily to quote rates/prices keeping in mind

the quantity to be supplied or handled and the prices likely to be quoted by

the highest/lowest bidder.      The higher the quantum of materials to be

handled the lower would be the handling charge per unit.


          54. Mr. Kundu accordingly submits that HTC having been declared

by SAIL to be the successful bidder could not now turn around and say that

it was not obliged to give the estimated amount of material to be handled as

stated both in the instructions to tender and NIT.      In both the cases the

quantum of materials is one and the same.         Mr. Kundu has referred to

paragraph 6.18 of the award where the learned tribunal has observed that

unless minimum quantity is known and ascertained it would be impossible

for the contractor to quote the rates.


          55. The rates of unloading as accepted by SAIL under the Schedule of

Operation and Rates in the Traditional Wing of the stockyard was for

2,56,000 MT of steel/pig iron. Similarly, the transportation costs were also
                                              27



required to be paid by the bidder on the basis of the expected quantity which

was fixed by SAIL.


          56. The details of rates of various materials which were supposed to

be delivered by SAIL and handled by HTC were fixed by SAIL and bidder had

only to quote its rate on the basis of the estimated quantity fixed by SAIL,

i.e., 2,55,000 MT.


          57. The rates of unloading as accepted by SAIL under the Schedule of

Operation and Rates in the Traditional wing of the stockyard was 2,56,000

MT of steel/pig iron.


          58. The quantity of delivery as accepted by SAIL under the schedule

of operation and rates in the Traditional wing of the stockyard was 2,56,000

MT of steel/pig iron.


          59. In the NIT it was stipulated that handling agent would have to

unload 2,56,000 MT of material as also to deliver 2,56,000 MT of material

amounting to 5,12,000 MT per year as required under Clause 4 of the NIT.


          60. Mr. Kundu has submitted that SAIL itself had obtained a

confirmation from HTC to the effect that -"we (HTC) hereby agree to abide by

instructions to tenderers and fulfil your "Terms and Conditions: of the

contact for handling Iron and Steel materials in your stockyard at Paharpur

and Coal Berth which shall be deemed to form an integral part of this

offer...................".   It was further stated that "HTC hereby note that this

tender and you (SAIL) acceptance after our full compliance with the
                                       28



requirements specified in your letter of intent shall constitute a valid and

binding contract between us".


       61. The aforesaid terms and conditions constitute a binding contract

between the parties SAIL cannot resile for the said terms and exonerate itself

from not supplying the estimated quantity stated in the said tender on the

basis whereof HTC had quoted its rates and SAIL had accepted such rates

and awarded the contract to HTC. Mr. Kundu has submitted that a bare

reading of Clause 4 of the Instruction to Tender, clause 8.4 of the NIT and

clause 8.7 of the Terms and Conditions of the tender does not lead to a

conclusion where SAIL can claim that it has no obligation to give any

amount of materials to HTC at all. In fact, the learned Arbitral tribunal had

correctly harmonised all the aforesaid three clauses and thereafter had come

to a conclusion that SAIL was obliged to supply a particular quantity of

materials after elaborate discussion on the aforesaid clauses.            The

calculations however has not been challenged by SAIL.


       62. Upon any reasonable person properly instructed in law and facts

after going through the entire terms and conditions and various clauses of

the entire contract could not have come to a conclusion that the instant

award is erroneous for the reasons which have been argued on behalf of

SAIL neither was the Learned Arbitral Tribunal guilty of inserting a new

clause or had created new implied terms and conditions which the parties

had never agreed to at the time of singing of the contract. Clause 8.3 could

not be said to override all the other terms and conditions of the contract as

has been emphatically argued by Mr. Mitra the learned Counsel for SAIL. If
                                          29



such an argument were to be accepted, in that event SAIL would have

incorporated a non-obstante clause before the Clause 8.3 in which event the

potential bidders might not have been inclined to quote for the tender due to

such a clause. Since it was never the intention of SAIL to give paramount

importance to Clause 8.7 by overlooking all the other terms and conditions

of the contract the contention of the award holder with regard to its claim for

estimate    quantity   is   justified   upon   a   reasonable   and   harmonious

interpretation of the contract. The Tribunal applied the accepted principles

for interpretation of contract in order to give business efficacy to the

contract. In Adani's case (Supra) at paragraph 24 which was relied on by

SAIL, a cursory reading of the same would on the contrary show that the

said paragraph under reference fully support the case of HTC. The five

conditions so laid down for invoking the business efficacy test and carving

out an implied condition not expressly found in the language of the contract

has to satisfy the five conditions which was laid down in Nabha Power Ltd.

(Supra), namely,


           i) Reasonable and equitable;

           ii) Necessary to give business efficacy to the contract;

           iii)The Officious Bystander Test,

           iv) Capable of clear expression; and

           v) Must not contradict any express tem of the contract.

       63. The above five conditions, from a cursory reading of the award

and the judgement passed by the Learned Single Judge, would clearly show
                                        30



that all the conditions have been fully satisfied and hence importing

business efficacy as a means to sustain the contract which was otherwise

sought to be opposed by SAIL merely on the basis of Clause 8.7 of the

contract was justified.


       64. In this context, it is stated that any person being an Officious

Bystander when asked that in view of Clause 8.7 of the Terms and

Conditions of the Contract, which stipulated that SAIL did not give any

guarantee to supply definite volume of work to be entrusted with the

contractor at any time or even throughout the tenure of the contract;

whether the contractor could have claimed supply of 5,10,000 MT of

materials more or less from SAIL in view of Clause 4 and 5 of the

Instructions to the Tenderer and Clauses 4 of NIT, the Officious Bystander

would have certainly said "Oh yes".


       65. It is submitted that the appellant could not also demonstrate the

basis on which the award would be deemed to be patently illegal. This case

has not been made out in the pleading.


       66. Mr. Kundu has submitted that certain differences will appear

from the two clauses which have been incorporated in NIT and in

"Instructions to Tenderer".     Clause 4 of NIT refers to the "estimated

quantity proposed to be handled during the first year of operation of the

contract are expected to be as under"........ whereas clause 5 refers to "the

estimated quantities ....... are only for the purpose of finding out the value of

the tender....." It thus makes it clear that SAIL would not be liable if the
                                         31



actual quantity of work differs from the estimated quantity indicated above.

However, clause 4 of the "Instruction to Tenderer" stipulates that "to enable

the tender to assess the quantum of work the estimated quantity proposed

to be handled during the first year of operation are indicated below.............:"


       67. Mr. Kundu submits that from reading of the aforesaid clauses it

would be evident that the wordings in NIT are vastly different from the terms

and conditions as appearing in the "Instructions to Tenderers". However

both the NIT and the "Instructions to Tenderers" are part of the contract.

The "Instructions to Tenderer" does not record that SAIL shall not be liable

for any short supply of materials.       It was in this context of any conflict

between the two clauses, namely, Clause 4 and 5 in the NIT and "Instruction

to Tenderer" and the general clauses namely, 8.3 and 8.7 of the terms and

conditions of the contract. Clauses 4 and 5 are to be read having an

overriding effect over the general clauses.


       68. Mr. Kundu has referred to the oral evidence of Sushanta Kumar

Bala and Raj Kumar on behalf of SAIL duly recorded in paragraph 6.14 and

6.15 in the award. Mr. Kundu has specifically referred to paragraph 6.5 if

the award where after appraisal of the evidence the arbitrator came to the

conclusion that the main commercial purpose of the contract was not for

evaluation but for performance and the contractor is entitled to proceed

relying on the representation made regarding the quantity of materials to be

handled and for that purpose tenderer made all arrangements including

infrastructure in accordance with the requirement of the contract. Mere

omission to mention specific quantity does not mean that the contract
                                      32



cannot be harmoniously construed if the contractor does not rely on the

contractual stipulations then no offer could have been made and any

contract based on without having specific quantity be it "minimum" or

"maximum" would not be capable of execution or at all.


       69. It is submitted that the arbitrator also reprimanded SAIL for its

conduct as would appear from paragraph 6.8, 6.19, 6.23, 6.24 of the award.

The arbitrator has interpreted the word "expectation and estimation" at

paragraph 6.8 of the award. Mr. Kundu has referred to clause 8.7 of the

general conditions of the contract and the observation made by the

arbitrator in interpreting the relevant clauses in paragraphs 6.14, 6.17 and

6.18 of the award.


       70. It is submitted that in the event it is found that some of the

clauses in a contract are at variance with each other, it is the bounden duty

of the court/tribunal to ensure that a harmonious construction be given to

the apparently conflicting and inconsistent clauses of the contact so that

contract can be upheld and make it efficacious.


       71. The Court will not readily set aside a contract merely because one

of the clauses differs from the meaning and contents of another clause

unless the two clauses cannot be reconciled in any manner whatsoever.


       72. In the instant case, the learned Arbitral Tribunal after examining

all the relevant clauses of the contact and without considering Clause 8.7 in

isolation harmoniously interpreted the said terms based on the principle of

business efficacy upon noticing the terms of the contract which are inter
                                        33



related and compliance of which would only ensure performance of the

contract and not otherwise. The Arbitral Tribunal has interpreted the

contact in a manner which was within their jurisdiction to do and has not

incorporated any fresh terms or conditions or implied any terms to make out

a new case as has been attempted to be argued by the appellant. The

Arbitrators have harmoniously interpreted various terms and conditions of

the contract and arrived at a finding in favour of HTC with regard to its

reasonable entitlement and such an interpretation made by the Arbitrators

cannot be faulted and interfered with, since such an interpretation was well

within the jurisdiction of the Arbitrators.


       73. Mr. Kundu has referred to few passages from the Interpretation

of Contract (Third Edition) by Kim Lawison more particularly paragraph

8.3, 9.08 and 9.19 to emphasis that the endeavour of the court should be

given certainty to the contract and in the case of repugnancy the earlier

clauses must prevail. In certain circumstances the later clause can be read

as qualifying rather than destroying the effect of the earlier clause.   The

main object of the contract has to be ascertained on a whole reading of the

contract.


       74. The paragraphs relied upon by Mr. Kundu are stated below:


            "8.13 "Where parties have entered into what they believe to be a
            binding agreement the court is most reluctant to hold that their
            agreement is void for uncertainty, and will only do so as a last
            resort."
                                       34



         "9.08 "If a clause in a contract is followed by a later clause which
         destroys the effect of the first clause, the later clause is to be
         rejected as repugnant and the earlier clause prevails. If, however,
         the later clause can be read as qualifying rather than destroying
         the effect of the earlier clause, then the two are to be read together,
         and effect given to both."

         "9.09 "Words and even whole clauses may be rejected if they are
         inconsistent with the main object of the contract, as ascertained
         from a reading of it as a whole."

       75. Mr. Kundu has also referred to Law of Contract, 3rd Edn.

Butterworths series 369 clause 2.181 on the interpretation of a clause

giving right of an option. The relevant portions of the clause relied upon by

Mr. Kundu reads:


         "However a clause which purports to give one party an option not
         only as to the mode of performance but whether or not to perform at
         all will have the effect of denying the contract of an obligative effect
         and a court must therefore, either find that it negates any intention
         to create legal relation or reject the clause as repugnant to the main
         purpose of the contract."

       76. It is submitted that the interpretation of the contract of the

arbitral tribunal has been accepted by Justice Tandon.         The paragraphs

from the judgment relied upon in this regard are:


       "I am not unmindful of the proposition that each terms of the contract
       must be construed and given effect to the plain and simple meanings of
       the words irrespective of the fact that it may not harshly on the parties
       as held in case of Central Bank of India Limited v. Hartford Fire
                                35



Insurance         Company   Limited   reported   in   AIR    1965    SC
1288................."

"The distinction must be drawn between an error in construction of the
contract and an addition and / or incorporation of some words within
the contract as in case of former, it is an error within the jurisdiction
but in later case, it is jurisdictional error which may invite an
interference in the award by the Court under Section 34 of the Act.
.............."

"There may be a situation where the Arbitral Tribunal have proceeded
to pass an award in total disregard to the express terms of the
contract and therefore acts arbitrarily, capriciously and without
jurisdiction."

"No Guarantee Clause" envisaged under Clause 8.7 of the terms and
condition of the contract was taken into account by the Arbitral
Tribunal which is reflected from the following observations made in
Paragraph 6.14 of the impugned award."

"It is, therefore manifest that the Arbitral Tribunal have not
proceeded in complete disregard to the express terms of the contract
rather took into account those clauses for the purpose of the
interpretation and gathering an intention of the contracting parties.
In paragraph 6.18 of impugned award the Arbitral Tribunal held that
if there is any ambiguity regarding a term relating to quantity, an
obligation may have to be implied to uphold the contract and to do
justice to the parties on a true reading and construction of the
contract."

"In case of McDermott International Inc. -Vs- Burn Standard Co.
Ltd. & Ors. reported in (2006)11 SCC 181 the Supreme Court held
that the Court should be slow in interfering with the award if the
arbitrator have given due regard to the various terms of the contract
and provided the reasons relating to construction thereof which
                                       36



       cannot be impinged on perversity or contrary to law. It would be apt
       to quote the observations recorded in paragraph 111 and 112 of the
       said report..."

       "This court is, therefore cannot accept the contention of the Petitioner
       that the Arbitral Tribunal have unnoticed Clause 4 of the Invitation
       to Tender and Clause 8.3 and 8.7 of the terms and conditions of the
       contract. The interpretation of the contract is within the realm of the
       Arbitral Tribunal and if the view expressed therein is plausible one it
       does not invite interference merely because another view is possible.
       The Court does not act as an Appellate Court where the entire issue
       is at large nor exercises the review jurisdiction for the purpose of
       finding error in the award."

       "Though the relevant clauses contemplate that the Petitioner does not
       guarantee the definite quantities of work to be entrusted upon the
       Respondent during the tenure of the contract which cannot mean
       that the Petitioner is exonerated and/or relieved of providing no
       quantity of work"

       "The arbitrator further noticed that there was no work entrusted
       upon the respondent for last 11 months of the extended period and
       during the relevant period which forms subject matter of dispute
       there was an entrustment of 3.8% of the materials for handling. It
       cannot be said that such interpretation is perverse and contrary to
       law."

       77. Mr. Kundu has submittred that while interpreting the terms of

the contract the learned Arbitral Tribunal has taken into consideration all

the relevant clauses and has interpreted the said terms with which Justice

Tandon has concerned.
                                       37



       78. The award can be interfered only on the limited grounds as

envisaged under the Act. Moreover, when the view taken by the arbitrator is

a possible view the court in deciding an application for setting aside the

award shall not interfere with such a view. Once the interpretation given by

the arbitrators are backed by logic and are reasonable the same is required

to be upheld as held in:


         i)   MMTC Ltd. v. Vedanta Ltd. reported in 2019(4) SCC 163

         paragraph 14


         ii) UHL Power Company Ltd. v. Stae of Himachal Pradesh

         reported at 2022(4) SCC 116 paragraphs 18 and 22.


       79. Mr. Kundu has submitted that in the instant case the arbitral

tribunal has taken an overall view of the terms and conditions of the

contract and not any particular clauses as an exclusionary clause as it

would render the contract ineffective and such an interpretation has been

accepted by the Hon'ble supreme Court in Welspun Specialty Solutions

Ltd. v. ONGC reported in 2022(2) SCC 382 paragraph 11.


       80. It is submitted that in absence of any perversity in its reasoning

an award cannot be set aside as observed in Dyna Technologies Pvt. Ltd.

v. Crompton Greaves Ltd. reported in 2019(20)SCC 1 (paragraphs 24 , 25,

34, 35 and 37).


       81. Moreover in deciding an application for setting aside of the award

the court is not exercising its appellate jurisdiction and unless the award is
                                         38



perverse and contrary to the evidence on record the award is required to be

upheld as held in Parsa Kente Collieries Ltd. v. Rajasthan Rajya Bidyut

Utpadan Nigam Ltd. reported in 2019(7) SCC 236.


       82. Mr. Kundu has referred to the decision of the Hon'ble Supreme

court in Punjab Sikh Regular Motor Service, Moudhapara v. The

Regional Transport Authority, Raipur and Ors. reported in AIR 1966

SC 1318 and Sub-Committee of Judicial Accountability and Ors. vs.

Union of India (UOI) & Ors., reported in AIR 1992 SC 320 at 352 to show

that the enabling words are construed as compulsory whenever the object of

the power is to effectuate a legal right.


       83. Even if the words used in the statute are prima facie enabling,

the Courts will readily infer a duty to exercise power which is invested in aid

of enforcement of a right of public or private citizen as observed in L. Hirday

Narain vs. Income Tax Officer, Bareilly reported in AIR 1971 SC 33 at

36; (1970) 2 SCC 355 (Paragraphs 13,14)


       84. The aforesaid judgements, therefore, clearly lays down the law

that an enabling statute/clause does not give a discretionary power to the

authority rather an enabling statute/clause makes it mandatory to ensure

that the clause is of enabling nature invested in aid of enforcement of a right

to public or a private citizen.


       85. In the instant case HTC indeed had a legal right to expect that

SAIL would adhere to its assurance/promise to enable and ensure that

5,10,000 MT of materials would be handled by HTC and for that purpose the
                                        39



"Instructions to Tenderers" was worded differently from the NIT with a view

to incorporate such promise so that donee of the enabling provisions may

exercise or effectuate its right.


       86. In other words, by using the word "enabling" in the "Instructions

to Tenderers" in clause 4 thereof, SAIL was indeed liable by virtue of the

doctrine of promissory estoppel to ensure that HTC was entitled to handle

5,10,000 MT of material in the manner elaborately stated in the various

schedules regarding operation and rates which was a part of the contract

and HTC thus had a legitimate expectation to the same. This expectation

can neither be contrary to the public policy nor perverse and the arbitral

tribunal in coming to a finding that SAIL was required to offer 73% of the

expected quantity on the basis of calculation, which has not been challenged

by SAIL, cannot be said to have committed any error beyond its jurisdiction

or having made out a new clause or re-writing the contract between the

parties warranting interference by this Court under section 34 or 37 of the

1996 Act.

                          Analysis and Reasoning


       87. In the application for setting aside of the award, the appellant

had raised the contentions that:

            (i) The arbitrators had not considered the prohibitory and "no
            guarantee clauses"; and

            (ii) The arbitrators had interpreted the contract by going
            beyond the terms of the contract which he was not entitled to
            do.
                                        40



       88. As a matter of law, if the arbitrator had indeed not considered the

prohibitory and no-guarantee clauses, it may be successfully contended that

the arbitrator failed to consider a relevant material that was needed to be

considered and thus the award could be set aside on the ground of illegality.

Further if it is found, in spite of the big leeway given to the remit of the

arbitrator, that the arbitrator did indeed go beyond the terms of the

contract, it could be said that the arbitrator had misdirected himself and the

award could be set aside on the count on the ground of arbitrariness (see

Steel Authority of India Ltd. v. J.C. Budharaja, government and Mining

Contractor, (1999) 8 SCC 122). However, if it is found that a clause or fact

situation was capable of being interpreted in two ways and the arbitrator

had taken a view that was a possible one, if not a plausible one, the setting

aside courts would veer on the side of caution and give the benefit of the

doubt to the arbitrator since in such a circumstance it would not be possible

to say that the arbitrator travelled outside his jurisdiction.


       89. For deciding the issues relevant in this appeal it is to be seen if

the arbitrator has looked into the contract and considered all the relevant

clauses of the contract between the parties. Clause 11.1 of the Instruction

to tenderer makes it clear that the advertisement for tender, instructions to

terderers, terms and conditions of the contract along with all enclosures and

the letters exchanged between the parties shall form part of the contract. In

the document titled 'Invitation to Tender' Clause 2 and Clause 4 speaks of

the estimated quantities proposed to be handled by the respondent during

the first year of operation of the contract based on the calculation of the
                                        41



sales plan. An applicant was required to be capable of handling this volume

in order to be eligible for the tender process.    Clause 5    is a clarificatory

clause clarifying that clause 4 was for the purpose of finding out the value of

the tender and the appellant was in no way responsible if the actual quantity

of work differed from the estimated quantity. Clause 6.2 of the terms and

conditions contained the rates of the estimated value that the respondent

could expect to be handling. As against this, Clause 8.3 of the General

Terms and conditions (referred to as the "prohibitory clause") and Clause 8.7

of the General Terms and conditions (referred to as the "non-guarantee

clause") provides that the respondent could not claim against the appellant

if the appellant was not able to provide a definite volume of work in

accordance with the estimated quantity referred to earlier.


       90. The Arbitral Tribunal rationalised its decision for accepting

"expected quantities" in place of "estimated quantities" in paragraphs 6.8

and 6.9. It states:


          6.8 Clause-5 of the Invitation to Tender on which reliance has been
          placed by SAIL provides as follows:-

          "The estimated quantities for the first year of operation of the
          contracts are only for the purpose of finding out the value of the
          tender" and SAIL is no way liable if the actual quantity of work
          differs from the estimated quantity indicated above.

          In our view it cannot be disputed that the contract would be for
          a large assignment having regard to number of workers,
          number of equipments and expected quantities of materials.
          Moreover, Clause 2.2 of Invitation to Tender states that
                                 42



"Tenderers   should   be   of    sound financial   standing   and
experience." Clause 6 of the Invitation to Tender provides that
"by submitting a quotation the Tenderer shall be deemed to
have fully familiarised himself with all requisite data including
those indicated above and contained in Clause-4 of Invitation to
Tender and Clause 4 of Instructions to Tenderers including
terms and conditions of the Contract and have fully satisfied
himself/itself of his/its capabilities to undertake and perform
the jobs to the satisfaction of SAIL. In our opinion this
requirement cannot be an one way traffic. A contractor having
made all arrangements as required by SAIL to execute the work
cannot be denied materials sufficient for utilisation of all such
equipments and the work force. matter of fact under Clause-9 of
the Instructions to Tenderers a declaration has to be made by
each Tenderer to the effect that he has successfully carried out
large assignment of iron and steel handling of this nature and
has   adequate    organisation,      resources   and   experienced
personnel to handle the type and magnitude of the subject
tender. It is, therefore, clear that SAIL represented that the
contractor would be required to handle at least 5,10,000 MT as
mentioned in clause 4 of the Invitation to Tender and clause 4
of Instructions to Tenderers as aforesaid.

The aforesaid clauses of the Invitation to Tender and Instruction
to Tenderers make it clear that the estimated quantity proposed
to be handled in the first year expected to be 5,10,000 MT and
under clause 6 of the Invitation to Tender the contractor must be
capable of performing the job i.e. handling of 5,10,000 MT of
materials per annum. The contractor would not be eligible even
to submit a tender if it is not capable of performing the job of
handling 5,10,000 MT materials. It must have equipments and
work force and financial resources to cope with the assignment
of handling 5,10,000 MT of materials per annum.
                              43



SAIL have sought to urge with reference to Clause 5 of the
Invitation to Tender which has been reproduced hereinbefore
that the estimated quantities for the 1st year of operation of the
contract are only for the purpose of finding out the value of the
tender and SAIL is no way liable if the actual quantity of work
differs from the aforesaid estimated quantity of 5,10,000 MT.
According to SAIL finding out of the value of the tender is the
sole object for specifying the estimated quantities for the first
year of operation but the records do not say for what purpose it
is necessary to find out the value of the tender. The
implementation of tender is based on the expected quantities of
the materials to be handled by the contractor.

In the context of the facts and circumstances of the case
expectation must be based on certain objective facts. Concise
Oxford Dictionary says that 'expect' means what is regarded as
likely. It is highly probable depending on the facts and
circumstances of the case. If the word 'estimate' is considered,
it means approximate judgement of number, amount etc. (see
Concise Oxford Dictionary, 7th Edition). It cannot be arbitrary.
The estimate is made by the technical experts which forms the
bed-rock upon which the entire tender or contract is based.

6.9 A few other facts having relevant bearing on the issues
have to be mentioned. Firstly the rates quoted by the Tenderer
must depend on the quantity of materials which are required to
be handled by a contractor. The rates could only be quoted on
the basis of materials to be supplied by SAIL. There must be
some factual basis regarding work force and materials which
would enable the contractor to submit rate for several
components of the jobs involved. A rate offered by a contractor
has to be based and calculated on the quantities of materials to
be handled. Once the quantum is fixed for the purpose of
                                      44



         quoting the rate of different jobs pertaining to receipt and
         delivery of materials, it cannot be changed to the detriment of
         the contractor. More the materials to be handled lesser would
         be the rate."

       91. The respondent had claimed successfully before the arbitrator

that the terms of the contract indicating the estimated value of work that

could be handled by the respondent could be acted on in case of its breach

since the prohibitory and the no-guarantee clauses may be construed as a

bar to claim the exact estimated quantity of the work but could not be

construed as a bar to at least claim a minimum quantity known to the

commercial workings of the parties of any similar nature of work in order to

offset the fixed costs that the respondent had to bear for maintaining

equipments, labour charge and other costs that would be incurred by it

during the term of the contract.      The arbitrator had agreed with the

respondent's contention and held that the respondent was entitled to claim

this minimum quantity of work.


       92. In the instant case, the Arbitral Tribunal has considered and

construed the relevant clauses as would appear from its findings in

paragraphs 6.16 to 7.5. For the sake of convenience the said paragraphs

are reproduced below:


         "6.16 It is the contention of HTC that according to sale

         performance (i.e. delivery factor) it has been proved beyond doubt

         the pattern of quantum of handling materials of subject stock-yard

         in the past 10 years. It gives a firm indication about the certainty
                                45



of   receipt   of   similar   quantities   in   accordance   with   sales

performance. It is also the contention that the commercial

document or immediate past records could definitely be relied

upon by any participating intending bidder who was entitled to

presume that the estimated or proposed quantities contained in

clause 4 was not illusory or the same should not or could not be

taken into account by the Tenderers for quoting their rates. It has

been contended, by HTC in our view rightly, that the main

commercial purpose of the contract was not for evaluation but for

performance and a contractor is entitled to proceed relying on the

representation made regarding the quantity of the materials to be

handled and for that purpose tenderer made all arrangements

including infrastructure etc. in accordance with the requirements

of the contract. Mere omission to mention specific quantity does

not mean that the contract cannot be harmoniously construed. If

the contractor does not rely on the contractual stipulations, then

no offer could have been made and any contract based on without

having specific quantity be it minimum or maximum would not be

capable of execution at all.


6.17 Having regard to the facts and circumstances of this case as

narrated herein before we are of the view that commercial working

of any similar nature of work has to provide for a certain minimum

quantity of goods to be handled since the fixed costs would be too

high if very little quantity of goods are allowed to be handled. In
                             46



such circumstances it would not be possible for anyone to submit

a bonafide tender and enter into a contract unless a reasonable

and harmonious construction of the contract is made by the

Tribunal. If the Claimant have found that the rates quoted by the

HTC were not viable and recklessly quoted, in that event it ought

not to have accepted the said rates. But on the contrary it has

been admitted that SAIL has internally assessed the rates quoted

by HTC as reasonable and thereafter decided to award the contract

to HTC.


6.18 We are of the view that unless a minimum quantity is known

and ascertained it would be impossible for the contractor to quote

the rates. The contract may also be void for uncertainty. For 11

months (January, 1999 to November, 1999) there was no supply of

materials at all either by way of receipt or delivery. SAIL may not

have guaranteed 510000 MT but that does not mean that month

after month there would be no supply at all. Further we do not

think that the parties ever agreed that total quantity being

supplied between May, 1998 to March, 1999 would be 3.80% of

the estimated quantity. The Court always endeavours to uphold a

contractual document. Even if HTC is not entitled to 510000 MT

annually, it must have obtained a reasonable quantity to recoup

the fixed costs, labour costs and also retain profit of at least 15%

as provided in the contract itself. If there is any ambiguity

regarding a term relating to quantity, an obligation may have to be
                              47



implied to uphold the contract and to do justice to the parties on a

true reading and construction of the contract. In the light of all the

documents and surrounding circumstance, we have to consider a

reasonable and equitable way to resolve the disputes.


6.19 We do not support the stand taken by SAIL. They ought to

have fairly stated that to work out the instant contract at least a

particular quantity of materials have to be supplied to the

contractor having regard to the magnitude of the investment made

in equipment, work force, infrastructure. It is surprising that SAIL

having knowledge and notice of rapid diminishing curve of supply,

extended the term of the contract for one year and for eleven

months of the extended period there was no supply of material at

all. SAIL ought to have allowed the contract to expire. It appears

that SAIL had been trying to abolish the subject stock-yard due to

ongoing litigation with approximately 560 contract labourers but

the Government have turned down the prayer of SAIL for

redeployment of its surplus labourers working at the said stock-

yards and no Court had allowed the prayer of SAIL to close down

the subject stock-yards. It was also within the knowledge of SAIL

that since 1981 and onwards there was a decrease in the export

from Kolkata Port, as a result, handling of materials from the

stock-yard was on the down-ward trend. Handling of materials by

manual labourers were increasingly being replaced by mechanised

equipments and by cranes. In this context letter dated 13th
                            48



February, 1989 of A.K. Das Gupta, Zonal Manager of SAIL and

letter dated 18th August, 1989 of the then General Manager of

SAIL are relevant (Vol. 1A PP 111 and127). In the first letter

addressed to the Joint Labour Commissioners it has been said that

there would not be any requirement of manual labours for

handling of steel materials under the head of export and import. In

the second letter addressed to the Labour Minister, it is said that

there being surplus labour to the Steel Plants, it was necessary to

redeployment of surplus personnel from Steel Plants. It was

categorically said SAIL was not in a position to add any more man-

power. However, in spite of the said information being in their

possession SAIL did not feel it necessary to reduce the number of

workers at the said stock-yards. On the other hand SAIL invited

the tender by giving a stipulation and/or promise of handling of

approximately 5,10,000 MT of materials and entered into the

instant contract promising supply of assured quantity of materials.


6.20 It may be true that due to change in the market condition or

trend and the mode of disposal of the materials has contributed to

the drastic reduction in the quantity of supply of materials to HTC

for being handled. It would be evident from the judgement dated

25th April, 1996 in F.M.A.T. No. 1460 of 1994 that the High Court

had directed SAIL "that any tender which is accepted by SAIL in

respect of the stock-yards in question must not in any way affect

the interim order passed by the Appellate Court or the Supreme
                              49



Court and the Tenderers should be put on notice by SAIL before

acceptance of the tender."


6.21 After the application of SAIL to close down the stock-yard was

rejected by the Division Bench of the High Court, the SAIL had

unilaterally taken decision not to despatch any materials to the

stock-yard and on the other hand invoked Section 21(4) of the

Contract Labour (Regulation and Abolition) Act on the ground that

the HTC had failed to perform its obligations. We do not appreciate

the stand of SAIL. When for continuous 11 months not a single

gram of materials was given, no question of performance of

contract could arise. There was nothing to perform, nonetheless

contract was extended by one year more.


6.22 SAIL said there is a change in the policy decision of SAIL in

attempting to close down the stock-yard and shifting the entire

work to elsewhere (Dankuni Stock-yard) the result was that the

contractor was not supplied with agreed material month after

month which otherwise would have been given to the subject

stock-yards. The contract was not subject to any change of policy.

It is well settled that no term of a contract can be altered by reason

of a unilateral decision of the contracting party. The terms of the

contract can only be altered by consent of both the parties. After

SAIL had decided to alter its policy and go for direct sell HTC is not

to suffer therefor. It has been contended that the customers of

SAIL were more interested in taking direct delivery and not
                              50



through stock-yards. This contention has no bearing on the issue

whether or not the customers of SAIL wanted to take delivery of

goods directly or through stock-yard does not concern the

contractor. Our attention has been drawn to a decision of the

Supreme Court in the case of Thawards Dheriumal & Anr. -v-

Union of India reported in AIR 1955 SC 468 where the Supreme

Court has held that "a party having contracted he cannot go back

on his agreement simply because it does not suit him to abide by it

and the party can be held responsible for damages occasioned by

breach of the contract." Our attention has also been drawn to

another decision of the Supreme Court in the case of M/s. Alapi

Porshad and Sons Ltd. - v- Union of India reported in AIR 1960

SC 588 where the Supreme Court held that "there is no general

liberty reserved to the Court to absolve a party from the liability to

perform his part of the contract merely because on account of a

uncontemplated term or event the purpose of the contract may

become onerous." (emphasis supplied)


6.23 A contention was raised that HTC was not capable of

performing its obligation which is not borne from records and no

such allegation was made earlier. For eleven months at a stretch

not a single gram of material was given to HTC, no question of

non- performance therefore arises. There is no contemporaneous

correspondence or complaint stating that HTC was unable to
                              51



discharge its obligations. On the contrary SAIL, by not supplying

material as assured, failed to discharge its obligation.


6.24 Having considered the facts and circumstances of the case in

detail we are of the view that the stipulation regarding the quantity

in clause 4 of Invitation to Tender and clause 4 of the Instructions

to Tenderer cannot be held to be only an estimate not amounting

to any assurance of, if not definite, but reasonable volume for

meaningful performance of work, with equipment, work force and

infrastructure. The quantity must be reasonable having regard to

the various requirements which had to be complied with by the

contractor regarding the equipments, labour force and other

infrastructure etc. The submissions made with reference to the

different documents which we have mentioned earlier cannot in

our view lead to the conclusion that no specific quantity was

agreed to be supplied to HTC. This cannot be the intention of the

contract. SAIL could not resile from the contractual commitment

regarding expected supply of the quantities on the basis of which

HTC had quoted its rates and maintained more than sufficient men

and machinery for handling of those materials in performance of

the contract. For eleven months there was nothing to be performed

at all. No quotation could have been accepted by SAIL if no specific

quantity to be handled by the HTC was mentioned for all purposes

of execution of the contract. HTC has shown its readiness in

complying with the provisions of the contract. They have quoted
                              52



rates on the basis of the quantities proposed or expected to be

handled, bought and brought the equipment as mentioned,

retained the labour force over and above its requirement. In such

circumstances reasonable construction of the contract has to be

made. It cannot be disputed that for construction of contract

intention of the parties has to be gathered from the words used in

the agreement. It cannot be said that since contract does not

mention specific quantity, the Court cannot supply any omission

in the contract. But it is not a question of omission in the contract,

it is a question of interpretation and harmonisation between the

different parts of the contract which would be liable for execution

by both the parties. It is pertinent to mention that in the 1st

arbitration the Learned Single Judge of the High Court observed

that "it was specifically indicated that HTC was required to handle

5,10,000 MT. Hence HTC was obliged to keep infrastructure for the

above quantity ready for the entire contractual period being its

men or by it machinery.' Stipulation in the contract to such extent

should be given a harmonious construction along with all the

terms and conditions including notice for inviting tender. The

Learned Judge also dealt with the contention regarding change of

policy. The Learned Judge held that after the allotment of the work

and after the contract was entered into, SAIL changed its policy

which resulted in substantial decrease of work." It is not the case

where SAIL did not allot the work because of the inability of HTC to
                             53



handle such work. If it had been so the contract would not have

been allowed by SAIL to be continued for the entire contractual

period and may be after the extended period according to HTC.

However whether such change in policy was an inevitable fact or

whether such change in policy could be considered as a breach on

the part of SAIL under the contract was a matter to be gone into by

the Tribunal. In the instant case the Tribunal came to a finding

that SAIL was responsible for such breach and awarded damages

in favour of HTC."


7. It is evident from the facts stated hereinabove that continuously

for 11 months no material at all was provided to HTC and prior to

that also insignificant quantity was supplied by SAIL. This could

not have been the intention of the contracting parties having

regard to the magnitude of involvement of men, equipments,

resources and overheads. When the job of HTC is to handle the

materials, can it be said that SAIL had no obligation whatsoever to

ever supply a reasonable quantity but even nil quantity would be

good enough in terms of the contract. We cannot accept this

extreme view propounded by SAIL. A handling contractor is not

expected to sit idle months after months incurring the fixed

overhead costs and cost of labour and equipments and suffering

loss. We are of the view that in the facts and circumstances of this

case SAIL has committed breach of the contract in not supplying a
                             54



reasonable quantity of materials and HTC is entitled to damages

therefore.


7.1 The question now is as to the determination of the reasonable

quantity of materials that HTC was entitled to handle (both receipt

and delivery) in the light of facts and circumstances and the

contract documents as aforesaid. During the period between 1st

May, 1998 and 22nd November, 1999 that is for nearly 18 months

HTC had been supplied only 30335 MT of steel materials as

against 796900 MT which was estimated and expected to be

handled during the said period by HTC in terms of Clause 4 of the

terms and conditions of the contract. Thus for the said 18 months

HTC did not get 766565 MT of materials (Expected 796.900 MT-

Actual receipt 30355 MT) which is equivalent to 96.20% of the

expected quantity. Again during the first half of the present

contract that is from 23rd November, 1996 till 30th November,

1998 HTC had handled approximately 54.86% of the estimated or

expected quantity as provided in Clause 4 of the tender/contract

document.


7.2 Our attention has been drawn to the fact that the earlier

arbitral proceeding which was initiated by HTC (Respondent

herein) against SAIL (Claimant herein) an award was passed by the

Learned Arbitral Tribunal holding that the Respondent (Claimant

therein) was entitled on year to year basis the entirety i.e. 100% of
                             55



the quantity which was specified in Clause 4 of the contract

document subject to 5% deviation therefrom.


7.3 We, however, propose to deal with the matter differently. Upon

a careful analysis of the contractual terms and conditions and on

perusal of all documents of both sides we have no hesitation in

holding that Claimant was obliged to provide the Respondent to

handle such quantity of materials which would have been

sufficient to compensate the Respondent because it had to incur

cost in keeping men and equipments and the infrastructure in

readiness throughout the term of the contract. That apart the

Respondent is also entitled to profit on such quantity of materials

which the Respondent was expected to handle. The main question

therefore is what is the quantity of materials which the Claimant

was obliged to provide to the Respondent for handling in terms of

the contract. There is no fool proof formula for determining such

quantum. However, we propose to base our judgement on the facts

and figures as brought to light.


7.4 Admittedly the Claimant has supplied 54.85% materials of the

estimated or expected quantity during the first 18 months of the

contract to the Respondent. Assuming that the Respondent is

entitled to 100% supply of the quantity which has been specified in

clause 4 of the contract document (which we term as 'notional

quantity) the average of the actual supply made during the first

half of the contract and the notional supply would, in our opinion,
                            56



be deemed to be the quantum of materials which at least the

Claimant was obliged to supply to the Respondent during the said

period. Accordingly, we hold that the average of 54.80% (actual

supply) and 100% (notional quantity) comes to 77.4% (rounded off

to 77%) is to be reckoned as actual percentage of the materials of

the expected or notional quantity which ought to have been

supplied by the Claimant to the Respondent. However, for the

period under reference i.e. 1st May, 1998 to 22nd November, 1999

the Respondent had already received 3.80% of such materials. The

same has to be deducted from the above and thus the applicable

percentage comes to 77% (-3.8%) = 73.20% (rounded off to 73%).

We, therefore, hold that SAIL had the obligation to provide the

Respondent with materials to be handled by HTC during the said

period i.e. 1st May, 1998 to 22nd November, 1999 at least 581737

MT being 73% of the expected or notional quantity of the material

as provided in clause 4 of the tender documents.


7.5 In the premises aforesaid we hold that the Claimant committed

breach of its obligation of providing reasonable quantity of

materials to be handled by HTC in performance of the contract and

we assess in the light of the surrounding circumstances including

contract documents and other evidence brought on record that

reasonable quantity would be 581737 MT for the period 1st May,

1998 to 22nd November, 1999. We answer the issues 1(a) and 1(b)

accordingly.
                                       57



       93. In an application for setting aside of the award under Section 34

of the Arbitration and Conciliation Act, 1996 it is now well settled by catena

of decisions that the Court does not act and function as a court of appeal

over the arbitral award and may interfere on merits limited to the grounds

mentioned in Section 34 (2) of the said Act. It is relevant to note that by way

of amendment in 2016 Sub-section (2A) has been inserted in Section 34

which provided that in case of domestic arbitration violation of public policy

of India would also include patent illegal ex facie must appear on the face of

the award. However, the ground of patent illegality would not be available in

the event an application for setting aside of the award is filed prior to

amendment in 2005 i.e. 23rd October, 2015 (See Ssangyong Engineering

and Construction Co. Ltd. vs. National Highways Authority of India

(NHAI) 2019(15) SCC 131). The application for setting aside of the award

was filed in June 2006. By way of clarification in the amendment it was

made clear that the award shall not be set aside merely on the ground of an

erroneous application of law or by re-appreciation of evidence which is

merely a reiteration of the earlier views expressed by the Hon'ble Supreme

Court that in deciding the application for setting aside the award the court is

not exercising its jurisdiction as an appellate authority and the powers of the

appellate court would not be available to a court deciding such an

application. The scope of jurisdiction under Section 34 and Section 37 of the

Act is not akin to normal appellate jurisdiction. The powers of the Court are

circumscribed by the limited grounds as mentioned in Section 34.           The

reason being that the arbitration proceedings are not considered and
                                        58



comparable to judicial proceedings before the Court and a party can opt for

an arbitration before any person who is not required to have a degree in law

or any prior legal experience.      Once the parties have consented to an

appointment of an arbitrator it should be presumed that they have bestowed

their faith and trust on the arbitrator and wanted a decision in an informal

manner.    This was recognised in Dyna Technologies Private Limited

(supra) in which it is observed: "The intention of the legislature to provide for

a default rule, should be given rational meaning in light of commercial

wisdom inherent in the choice of arbitration" and reiterated in K. Suguman

vs. Hindustan Corporation Limited 2020(12) SCC 539 at 540 in the

words: "When parties have chosen to avail an alternate mechanism for

dispute resolution, they must be left to reconcile themselves to the wisdom

of the decision of the arbitrator and the role of the court            should be

restricted to the bare minimum". In Vidya Drolia and Ors. v. Durga

Trading Corporation reported in 2021(2) SCC 1 it is stated:


          "Arbitration is a private dispute resolution mechanism whereby
          two or more parties agree to resolve their current or future
          disputes by an Arbitral Tribunal, as an alternative to
          adjudication by the Court or a public forum established by law.
          Parties by mutual agreement forgo their right in law to have
          their   disputes   adjudicated    in   the   courts/public   forum.
          Arbitration agreement gives contractual authority to the Arbitral
          Tribunal to adjudicate the disputes and bind the parties."

       94. This view has been reiterated in Konkan Railway Corporation

Ltd. v. Chenab Bridge Project Undertaking reported in 2023 INSC 742:

2023 SCC Online SC 1020.
                                        59



          95. In view of the nature of proceeding interference to an arbitral

award is extremely limited and would be justified only in cases of

commission of by an arbitrator misconduct which can find manifestation in

different forms including exercise of legal perversity by the arbitrator. (See K.

Sugumar (supra).      This insulation of an award acts as a guard-wall from an

assault on the award on the ground of misappreciation of evidence or

interpretation of the contract or application of erroneous legal principle. It is

for this protection and immunity that an award enjoys the courts have held

that :


         (i)     construction of the contract is primarily for an arbitrator to

                 decide unless the arbitrator contracts the contract in such a

                 way that it can be said to be something that no fair-minded

                 or reasonable person could do.       A possible view by the

                 arbitrator on facts has necessarily to pass muster as the

                 arbitrator is the ultimate master of the quantity and quality

                 of evidence to be relied upon when he delivers his arbitral

                 award (Per Justice M.R. Shah in Parsa Kenta Collieries

                 Ltd.(supra).


                 ii) Court should not interfere with an award merely because

                 an alternative view on facts and interpretation of contract

                 exists (Dyna Technologies (supra).


                 (iii) Unless the court comes to a conclusion that the

                 perversity of the award goes to the root of the matter without
                                        60



               there being a possibility of alternative interpretation which

               may sustain the arbitral award an arbitral award should not

               be interfered with in a casual and cavalier manner (Dyna

               Technologies (supra).


               (iv) It is well settled law that where two views are possible, the

               court cannot interfere if the plausible view taken by the

               arbitrator is supported by reasoning. In other words if there

               are two plausible interpretations of the terms and conditions

               of the contract, then no fault can be found, if the learned

               arbitrator proceeds to accept one interpretation as against

               the other. (Dyna Technologies (supra) followed in South

               East Asia Marine Engineering and Construction Ltd.

               (SEAMEC Ltd.) v. Oil India Limited; 2020(5) SCC 164 and

               UHL Power Company Ltd. (supra).


       96. In the instant case, the limited grounds of challenge was reading

into "reasonable quantity" in the "estimated quantity" and it is being argued

that by substituting or incorporating the said term by way of interpretation

in the original contract between the parties the contract has been rewritten

and a new contract has come into existence.


       97. We need to decide if the award is assailable within the limited

grounds under Section 34 of the 1996 Act prior to amendment in 2015. The

approach of the court in interfering with the award is limited and

circumscribed by the grounds mentioned in Section 34 of the 1996 Act.
                                       61



       98. There were various changes which were brought about in the

1996 Act from the 1940 Act. The purpose of the new Act was to have speedy

disposal through the forum of arbitration.


       99. Section 34 introduces itself by saying that the grounds

mentioned thereunder are the "only" grounds on which an arbitral award

may be set aside. However, apart from the grounds mentioned under S.34,

the Act also provides for other grounds as under S.13, S.16, S.75 and S.81

on the basis of which the award can be set aside.

       100. The grounds given under S.34(2)(a) are crisp and precise and lay

the law as it is without the inclusion of any open-ended expression which

otherwise would have given the courts an opportunity to widen their scope of

interference with the arbitral awards.       The only open-ended expression

which can be and has been of concern is the ground of public policy of India.

It has been under many cases defined as an unruly horse thus giving the

interpretation that it can never be defined or be a certain thing. However,

for the purpose of achieving the aim of the new Act, the Act of 1996 - the

legislature while drafting the Act limited the scope of public policy in its

explanation restricted it to:-

       a) Fraud

       b) Corruption

       c) S.75 or S.81 (confidentiality breach or admissibility of evidence)

       101. The scope of public policy was, however, widened after Supreme

Court in its decision of Oil & Natural Gas Corporation Ltd. v. Saw Pipes
                                           62



Ltd. (2003 (5) SCC 705) (also referred to as : "Saw Pipes Case") interpreted

it to include "patent illegality" in its definition.

        102. Interpretation of a contract is a matter for the arbitrator to

determine, even if it gives rise to determination of a question of law. It is a

settled law that interpretation of the contract and appreciation of the

evidence by the arbitral tribunal cannot be reopened by arguing that the

award is contrary to the contract. Arbitration is consensual and some

amount of laxity should be given while scrutinizing an award. A sense of

informality is attached to such proceeding. It cannot be scrutinized with an

Eagle's eye or eye of a needle and as an appellate authority. A possible view

by the arbitrator on facts has necessarily to pass muster as the arbitrator is

the ultimate master of the quantity and quality of evidence to be relied upon

when he delivers his arbitral award. Thus an award based on little evidence

or on evidence which does not measure up in quality to a trained legal mind

would not be held to be invalid on this score.

        103. Once it is found that the arbitrator's approach is not arbitrary

or capricious it has to be accepted. He is the last word on facts.         The

construction of the terms of the contract is primarily for an arbitrator to

decide unless the arbitrator construes the contract in such a way that it

could be said to be something that no fair minded or reasonable person

would do, of course, the arbitrator cannot wander outside the contract and

deals with the matters not forming the subject matter or allotted to him as in

that case he would commit jurisdictional error. (See Delhi Airport Metro

Express (P) Ltd. v. DMRC, 2022 (1) SCC 131)
                                        63



      104. In Delhi Development Authority v. R.S. Sharma, 2008(13)

SCC 80 the Hon'ble Supreme Court summarized the law thus:


"From the above decisions, the following principles emerge:


      (a) An Award, which is

      (i) Contrary to substantive provisions of law; or

      (ii) The provisions of the Arbitration and Conciliation Act, 1996; or

      (iii) Against the terms of the respective contract; or

      (iv) Patently illegal, or

      (v) Prejudicial to the rights of the parties, is open to interference by
      the Court under S.34(2) of the Act.

     (b) Award could be set aside if it is contrary to:

      (i) Fundamental policy of Indian Law; or

      (ii) The interest of India; or

      (iii) Justice or morality;

      (iv) The Award could also be set aside if it is so unfair and
      unreasonable that it shocks the conscience of the Court;

      (v) It is open to the Court to consider whether the Award is against
      the specific terms of contract and if so, interfere with it on the ground
      that it is patently illegal and opposed to the public policy of India."

      105. The Supreme Court in Mc Dermott International v. Burn

Standard Co. Ltd.; 2006 (11) SCC 181, has commented on the scope of

the powers of the arbitrator to interpret terms of the contract, and the
                                         64



permissible interference by the courts on the assessment of the arbitrator. It

was held:-


          "It is trite that the terms of the contract can be express or
          implied. The conduct of the parties would also be a relevant
          factor in the matter of construction of a contract.             The
          construction of the contract agreement, is within the jurisdiction
          of the arbitrators having regard to the wide nature, scope and
          ambit of the arbitration agreement and they cannot, be said to
          have misdirected themselves in passing the award by taking
          into consideration the conduct of the parties. It is also trite that
          correspondences exchanged by the parties are required to be
          taken into consideration for the purpose of construction of a
          contract.    Interpretation of a contract is a matter for the
          arbitrator to determine, even if it gives rise to determination of a
          question of law. The 1996 Act makes the provision for the
          supervisory role of courts, for the review of the arbitral award
          only to ensure fairness. Intervention of the Court is envisaged
          in few circumstances only, like, in case of fraud or bias by the
          arbitrator, violation of natural justice, etc. The court cannot
          correct the errors of the arbitrators. It can only quash the
          award leaving the parties free to begin the arbitration again if it
          is desired. So, the scheme of the provision aims at keeping the
          supervisory role of the court at minimum level and this can be
          justified as parties to the agreement make a conscious decision
          to exclude the court's jurisdiction by opting for arbitration as
          they prefer the expediency and finality offered by it."

       106. The Court will not judge the reasonableness of a particular

interpretation accorded by the arbitrator to the terms of the contract. Even

an error in interpretation, unless patently illegal, will only amount to an

error within the jurisdiction of the arbitrator.

       107. In KV Mohd. Zakir v. Regional Sports Centre reported at AIR

2009 SC (Supp) 2517 it held that the courts should not interfere unless

reasons given are outrageous in their defiance of logic or if the arbitrator has

acted beyond his/her jurisdiction.
                                         65



        108. In P.R. Shah Shares & Stock Brothers v. M/s. B.H.H.

Securities (P) Ltd.; 2012 (1) SCC 594 it is clearly stated that a court does

not sit in appeal over the award of an arbitral tribunal by re-assessing or re-

approaching the evidence. An award can be challenged only on the grounds

mentioned in S.34(2) of the Act.

        109. The decision of the Arbitral Tribunal in the instant case is a

possible view and an acceptable outcome which is clearly defensible in

respect of the facts and law.

        110. In Associate Engineering Builders v. Delhi Development

Authority reported in 2015(3) SCC 49 the Supreme Court has laid down

the principle on which an award can be held to be perverse. The Apex Court

held:

          "32. A good working test of perversity is contained in two
          judgments. In Excise and Taxation Officer-cum- Assessing
          Authority v. Gopi Nath & Sons [1992 Supp (2) SCC 312], it was
          held: (SCC p. 317, "7. ... It is, no doubt, true that if a finding of
          fact is para 7) arrived at by ignoring or excluding relevant
          material or by taking into consideration irrelevant material or if
          the finding so outrageously defies logic as to suffer from the
          vice of irrationality incurring the blame of being perverse, then,
          the finding is rendered infirm in law."
          In Kuldeep Singh v. Commr. of Police [(1999) 2 SCC 10: 1999
          SCC (L&S) 429], it was held: (SCC p. 14, para 10)
          "10. A broad distinction has, therefore, to be maintained
          between the decisions which are perverse and those which are
          not. If a decision is arrived at on no evidence or evidence which
          is thoroughly unreliable and no reasonable person would act
          upon it, the order would be perverse. But if there is some
                                        66



          evidence on record which is acceptable and which could be
          relied upon, howsoever compendious it may be, the conclusions
          would not be treated as perverse and the findings would not be
          interfered with.
          33. It must clearly be understood that when a court is applying
          the "public policy" test to an arbitration award, it does not act
          as a court of appeal and consequently errors of fact cannot be
          corrected. A possible view by the arbitrator on facts has
          necessarily to pass muster as the arbitrator is the ultimate
          master of the quantity and quality of evidence to be relied upon
          when he delivers his arbitral award. Thus an award based on
          little evidence or on evidence which does not measure up in
          quality to a trained legal mind would not be held to be invalid
          on this score."



       111. Once it is found that the arbitrators' approach is not arbitrary

or capricious then he is the last word on facts.

       112. Reasonableness of the decision cannot be a matter of judicial

review in deciding an application for setting aside and award.

       113. Once the arbitrator has come to a finding the Court should not

interfere with the award unless reasons given are outrageous in their

defiance of logic or if the arbitrator has acted beyond his jurisdiction.

Moreover, the Court does not sit in appeal over the award of the arbitral

tribunal by re-assessing, re-approaching or re-appreciating the evidence. It

is well settled that the Court does not sit in appeal over an award. It is not

for this Court to reassess the evidence on record. It is also not for this Court

to weigh the quality and quantity of the evidence put forward before the

Arbitration. In Ravindra Kumar Gupta & Co. v. Union of India reported
                                         67



at 2010 (1) SCC 409 it is reiterated that reappraisal of evidence by the

Court is not permissible.         Where the reasons have been given by the

arbitrator   in   making    the    award     the   court   cannot   examine   the

reasonableness of the reasons. If the parties have selected their own forum,

the deciding forum must be conceded the power of appraisement of

evidence.    The arbitrator is the sole judge of the quality as well as the

quantity of evidence and it will not be for the court to take upon itself the

task of being a Judge on the evidence before the arbitrator. The award can

be challenged only on the ground mentioned in Section 34(2) of the Act.

       114. An erroneous application of the law by itself is not a ground to

challenge an award under Section 34 of the Arbitration and Conciliation Act.

For an award to be set aside there must be a patent illegality, an error which

goes to the very root of the matter and affects the jurisdiction of the

arbitrator in deciding a dispute. If the arbitrator lacks the authority to

decide the dispute the award is a nullity. If the disputes are by nature non-

arbitrable the assumption of jurisdiction would be an illegality.

       115. The judgment in Associate Builders (supra), which was passed

in relation to a domestic award also recognized and reaffirmed the settled

law that where a cause or matters in differences are referred to an arbitrator,

whether lawyer or layman, he is considered to be the sole and final judge of

all questions of law and of fact obviously with the limited grounds of

interference, namely, if it is opposed to fundamental policy of Indian Law,

interest of India, justice or morality and patent illegality.
                                         68



       116. A patent illegality would mean an illegality which goes to the

root of the matter and not a mere erroneous application of the law is the

view in Associated Builders (supra) which was reiterated in SSangyong

Engineering & Construction Company Ltd. v. National Highway

Authority of India, reported in 2019(15) SCC 131 in paragraphs 37, 39,

40 and 41 of the said report which reads:


         "37. Insofar as domestic awards made in India are concerned,
         an additional ground is now available Under Sub-section (2A),
         added by the Amendment Act, 2015, to Section 34. Here, there
         must be patent illegality appearing on the face of the award,
         which refers to such illegality as goes to the root of the matter
         but which does not amount to mere erroneous application of the
         law. In short, what is not subsumed within "the fundamental
         policy of Indian law", namely, the contravention of a statute not
         linked to public policy or public interest, cannot be brought in by
         the backdoor when it comes to setting aside an award on the
         ground of patent illegality.

         39. To elucidate, paragraph 42.1 of Associate Builders (supra),
         namely, a mere contravention of the substantive law of India,
         by itself, is no longer a ground available to set aside an arbitral
         award. Paragraph 42.2 of Associate Builders (supra), however,
         would remain, for if an arbitrator gives no reasons for an award
         and contravenes Section 31(3) of the 1996 Act, that would
         certainly amount to a patent illegality on the face of the award.

         40. The change made in Section 28(3) by the Amendment Act
         really follows what is stated in paragraphs 42.3 to 45 in
         Associate Builders (supra), namely, that the construction of the
         terms of a contract is primarily for an arbitrator to decide,
         unless the arbitrator construes the contract in a manner that no
                                       69



         fair-minded or reasonable person would; in short, that the
         arbitrator's view is not even a possible view to take. Also, if the
         arbitrator wanders outside the contract and deals with matters
         not allotted to him, he commits an error of jurisdiction. This
         ground of challenge will now fall within the new ground added
         Under Section 34(2A).

         41. What is important to note is that a decision which is
         perverse, as understood in paragraphs 31 and 32 of Associate
         Builders (supra), while no longer being a ground for challenge
         under "public policy of India", would certainly amount to a
         patent illegality appearing on the face of the award. Thus, a
         finding based on no evidence at all or an award which ignores
         vital evidence in arriving at its decision would be perverse and
         liable to be set aside on the ground of patent illegality.
         Additionally, a finding based on documents taken behind the
         back of the parties by the arbitrator would also qualify as a
         decision based on no evidence inasmuch as such decision is not
         based on evidence led by the parties, and therefore, would also
         have to be characterised as perverse."

       117. We are unable to accept the said submission on behalf of the

appellant that it is assailable under Section 34(2)(a)(iv). The tender inviting

bid was not for a fun or humour.       SAIL had expended huge amount in

floating a tender inviting bidders for to act as handling contractor. In this

regard the observation of the Arbitral Tribunal in paragraph 6.10 and 6.11

are apposite:


         "6.10. In our view in a large assignment like the present one
         materials to be handled could not have been approximately 55% or
         4% of the expected quantities. Sudden fall of the supply of materials
         has not been justified by SAIL excepting taking shelter behind the
                                        70



         clauses which say that no guarantee was given regarding the
         quantities to be supplied or SAIL is not responsible for actual short
         fall of estimated quantifies on the basis whereof the contract was
         arrived at.

         6.11. Another factor is to be taken into account. It is on record that
         the Tender Committee took into account the schedule of operations
         evaluating the quotations of the Tenderers. From the schedule of
         operations annexed to the statement of claim, it is clear that the
         materials which were to be received at the stockyard would
         aggregate at least 2,56,000/- MT per annum.        Similarly the said
         schedule of operations relating to delivery (annexed to the Statement
         of claim) shows that the aggregate amount of delivery mentioned is
         2,55,000/- MT. The pattern of the quantum of handling materials in
         the past shows that the same stockyard had handled more than
         21250 MT. (separately receipt and delivery) of materials per month.
         As a matter of fact the contractor who was operating just before the
         present contract was awarded to HTC obtained the following
         quantities of materials.

         Statement of Receipt & Delivery A/C: Paharpur and Coal Berth
         Stockyard, Financial Year 1996-97 handled by Bardhan & Co.
         (Handling Contractor) Private Ltd.

Month                       Receipt (in M.T.)        Delivery (in M.T.)

April, 1996                 24580                    16127

May, 1996                   16188                    16127

June, 1996                  21282                    28180

July, 1996                  21235                    19566

August, 1996                16694                    13167
                                      71



September, 1996            16864                       13064

October, 1996              19322                       14453

Upto    22nd    November, 13383                        6856
1996

TOTAL                      159548                      125854




          Average quantities handled:-

          20586 M.T. (Receipt) 16239 M.T. (Delivery)

          It may be mentioned that for the financial year 1995-96 Bardhan &
          Co. (Handling Contractors) Pvt. Ltd. received 250142 MT. and
          delivery 247710 MT. Average quantities handled during the
          aforesaid period are 20854 MT (Receipt) and 20642 MT (Delivery).

        118. The phrase "implied term" can be said to denote a term inherent

in the nature of the contract which the law will imply in every case unless

the parties agree to vary or exclude it. (See Sterling Engineering Co. V.

Patchett (1955) AC. 534 at p. 547 per Lord Reid).


        119. If all the documents are read as a whole it can be reasonably

inferred that the contract documents are capable creating a reasonable and

legitimate expectation in the mind of the contractor to receive if not the

entirety of the estimated amount but a reasonable quantity which would

enable a contractor to earn a profit of 15%. "Oh yes" could be anybody's

reaction on reading the contract documents of a reasonable quantity. This

expectedly could be the reaction in a commercial transaction of this nature.

The court is usually not required to examine the merits of the interpretation
                                          72



provided in the award by the arbitrator, if it comes to a conclusion that such

an interpretation was reasonably possible [See South East Asia Marine

Engineering & Construction Ltd. (supra)].


       120. The thumb rule as to the interpretation of a contract is that the

document forming a written contract should be read as a whole and so far

as possible as mutually explanatory.          The terms and conditions clearly

stipulate that the contractor would be entitled to 15% profit and that is

possible only when a reasonable quantity is handled by the contractor. The

construction of the documents cannot lead to an inference that the quantity

will be nil for the entire duration of the contract. SAIL had the option not to

renew the contract after two years. The learned Arbitral Tribunal consisting

of three retired experienced judges of this Court had interpreted the contract

and arrived at a conclusion that the relevant clauses to which reference have

been made earlier are to be construed in a commercial manner as any other

interpretation would cause hardship,          lead to absurdity and made the

contract nugatory. While the words "estimated quantity" with "no guarantee

clause" may lead to inference that the contractor may not have any claim in

the event of short supply but this cannot lead to an inference of no supply.

The   contractor   for   the   purpose   of performing   and   discharging   its

responsibilities are required to incur substantial expenses as failure to

perform the contract would entail serious consequences as provided in

clause 4.8 of the contract document. It required a continued presence of

man, material and infrastructure. The contractor is supposed to be ready

with its men, material, workforce and equipment for due performance of the
                                       73



contract. If the interpretation of SAIL with regard to the contract is accepted

then it would mean that SAIL would have no obligation at all to supply any

quantity although SAIL would expect the contractor to keep its labour,

equipment, infrastructure ready throughout the life of the contract which

would result in colossal loss for the contractor which the parties have never

intended at the time of making the contract. The requirement of supply of a

reasonable quantity is implicit in the contract. It is so obvious that it goes

without saying that the parties intended to supply reasonable quantity. Any

other interpretation would make the contract onerous. The contract does

not make any business sense without the term "reasonable" as interpreted

by the Arbitral Tribunal to give it a business efficacy.       To borrow the

language of Mackinnon L.J. in Shirlaw v. Southern Founderies Ltd.

[1939] 2 K.B. 226 at 227:


         "Prima facie that which in any contract is left to be implied and need
         not be expressed is something so obvious that it goes without
         saying; so that, if while the parties were making their bargain, an
         officious bystander were to suggest some express provision for it in
         the agreement, they would testily suppress him with a common 'oh,
         of course'."

         As pithly put by Diplock L.J. in Hongkong Fir Shipping v.
         Kawasaki Kisen Kaisha [1962] 2 Q.B. 26 at p. 69: "It goes
         without saying".

         This has been justified, in relation to business contracts, on the
         ground that the law desires to give such business efficacy to a
         transaction as must have been intended at all events by both
                                        74



           parties who are businessmen, and this can only be does by
           allowing such terms. [See The Moorcock (1889) 14 P.D. 64].

           Brown L. J. in The Moorcock (supra) sums up the position:

           "....In business transactions such as this, what the law desires to
           effect by the implication is to give such business efficacy to the
           transaction as must have been intended at all events by both parties
           who are businessmen; not to impose on one side all the perils of the
           transaction, or to emancipate one side from all the chances of
           failure, but to make each party promise in law as much, at all
           events, as it must have been in the contemplation of both parties
           that he should be responsible for in respect of those perils or
           chances."

       121. This has been followed in Satya Jain v. Anis Ahmed Rushdie,

2013(8) SCC 131, Nabhi Power Ltd. (supra) and Adani Power (supra).

The Arbitral Tribunal in fact in fact, has considered the aforesaid principles

in paragraphs 6.16, 6,18, 6.24 and 7 in particular.


       122. The said interpretation does not make any commercial sense at

all. Moreover, business efficacy test requires that a term can only be implied

if it is necessary to give business efficacy to the contract to avoid such a

failure of consideration that the parties cannot as reasonable businessmen

have intended and for that purpose the most limited term should be implied

- the bare minimum to achieve this goal (Per Ranjon Gogoi, J. in Satya Jain

(supra).


       123. The jurisdiction of the court under section 37 of the Act, as

clarified in MMTC (supra) and reiterated in Konkan Railway Corporation
                                       75



Ltd. (supra) is akin to the jurisdiction of the court under Section 34 of the

Act. The scope of interference by a court in an appeal under Section 37 of

the Act, in examining an order setting aside or refusing to set aside an

award, is restricted and subject to the same grounds as the challenge under

Section 34 of the Act. The jurisdiction under Section 34 of the Act is

exercised only to see if the Arbitral Tribunal's view is perverse or manifestly

arbitrary. (See Konkan Railways Corporation Ltd. (supra) The views

expressed by the tribunal was accepted by Justice Tandon.


       124. I am convinced that the interpretation of the Arbitral Tribunal

was clearly a possible and plausible view and rightly accepted by the learned

Single Judge. The views of the Tribunal was "reasonable and fair minded" in

approach.


       125. The learned Single Judge has rightly accepted such findings of

the Arbitral Tribunal to be fair, plausible and reasonable.


       126. The award is upheld. The appeal and the application stand

dismissed. However, there shall be no order as to costs.


                                            (Soumen Sen, J.)



Ravi Krishan Kapur, J.:

1. I have read the draft judgment of my Learned Brother. With utmost respect, I find myself unable to agree with my Learned Brother and therefore, I am writing this separate judgment.

76

2. This appeal arises from a judgment dated 25th April, 2016 dismissing an application under section 34 of the Arbitration and Conciliation Act, 1996 (the Act).

3. The disputes between the parties arise out of a contract for handling iron and steel materials at the appellant's stock yard and office located at Paharpur, 20, Coal Berth and DP-II siding at the Calcutta branch respectively.

4. Clause 11.1 of the Instructions to the Tender is as follows:-

(i) The advertisement for tender.
(ii) Instructions to tenderers,
(iii) Terms and conditions of contract along with all its enclosures etc. and any other letters exchanged with the successful tenderer shall form part of the contract.

5. Salient clauses of the contract inter alia provide as follows:

CLAUSE-4:
The estimated quantities proposed to be handled during the first year of operation of the contract are expected to be as under (calculation based on sales plan) Receipt Delivery Pig Iron: 5000 M.T 5000 M.T Tool: 2,50,000 M.T 2,50,000 M.T Total 2,55,000 M.T 2,55,000 M.T CLAUSE-5 "The estimated quantities for the first year of operation of the contract are only for the purpose of finding out the value of the tender & SAIL is in no way liable if the actual quantity of work differs from estimated quantity indicated above".
77
CLAUSE-8.3 The mere mention of any item or work in the contract does not by itself confer the right upon the contractor to demand that item of work at all times.
CLAUSE-8.7 The company gives no guarantee about the definite volume of work to be entrusted with the contractor at any time or even throughout the tenure of the contract.

6. The claim for damages by the claimant was on the ground that there was a shortfall in providing materials by the appellant at the stock yard between the period 1 May, 1998 and 22 November, 1999 (18 months 22 days). It is contended that during this period the appellant had only made available 30,335 MT of materials. On behalf of the appellant it is contended that there is no question of shortfall as the contract between the parties does not provide for any minimum quantity of materials which the appellant is obliged to provide under the contract.

7. The Arbitral Tribunal passed an award dated 17 March, 2006 (the award) and implied a condition to the effect that the appellant would make available to the respondent for handling (receiving and delivery) a reasonable quantity of materials per year for the remaining two years of the contract. In this context, Clause 6.24 of the award is as follows:

6.24 Having considered the facts and circumstances of the case in detail we are of the view that the stipulation regarding the quantity in clause 4 Invitation to Tender and clause 4 of the Instructions to Tenderer cannot be held to be only an estimate not amounting to any assurance of, if not definite, but reasonable volume for meaningful performance of work, with equipment, work force and infrastructure.

The quantity must be reasonable having regard to the various 78 requirements which had to be complied with by the contractor regarding the equipments, labour force and other infrastructure etc. The submissions made with reference to the different documents which we have mentioned earlier cannot in our view lead to the conclusion that no specific quantity was agreed to be supplied to HTC. This cannot be the intention of the contract. SAIL could not resile from the contractual commitment regarding expected supply of the quantities on the basis of which HTC had quoted its rates and maintained more than sufficient men and machinery for handling of those materials in performance of the contract. For eleven months there was nothing to be performed at all. No quotation could have been accepted by SAIL if no specific quantity to be handled by the HTC was mentioned for all purposes of execution of the contract. HTC has shown its readiness in complying with the provisions of the contract. They have quoted rates on the basis of the quantities proposed or expected to be handled, bought and brought the equipment as mentioned, retained the labour force over and above its requirement. In such circumstances a reasonable construction of the contract has to be made. It cannot be disputed that for construction of contract intention of the parties has to be gathered from the words used in the agreement. It cannot be said that since contract does not mention specific quantity, the Court cannot supply any omission in the contract. But it is not a question of omission in the contract, it is a question of interpretation and harmonisation between the different parts of the contract which would be liable for execution by both the parties. It is pertinent to mention that in the 1st arbitration the Learned Single Judge of the High court observed that "it was specifically indicated that HTC was required to handle 5,10,000 MT. Hence HTC was obliged to keep infrastructure for the above quantity ready for the entire contractual period being its men or by it machinery.' Stipulation in the contract to such extent should be given a harmonious construction along with all the terms and conditions including notice for inviting tender. The Learned Judge also dealt with the contention regarding change of policy. The Learned Judge held that "after the allotment of the work and after the contract was entered into, SAIL changed its policy which resulted in substantial decrease of work." It is not the case where SAIL did not allot the work because of the inability of HTC to handle such work. If it had been so the contract would not have been allowed by SAIL to be continued for the entire contractual period and may be after the extended period according to HTC. However whether such change in policy was an inevitable fact or whether such change in policy could be considered as a breach on the part of SAIL under the contract was a matter to be gone into by the Tribunal. In the instant case the Tribunal came to a finding that SAIL was responsible for such breach and awarded damages in favour of HTC."

79

8. A reasonable quantity was assessed by the Arbitral Tribunal at 6,12,072 MT for the period from 1st April, 1998 to 26th November, 1999 being 77% of the expected quantity for the first year as stipulated in clause 4 taken to be 7,96,900 MT. The relevant portion of the award is as follows:

7.1 The question now is as to the determination of the reasonable quantity of materials that HTC was entitled to handle (both receipt and delivery) in the light of facts and circumstances and the contract documents as aforesaid. During the period between 1st May, 1998 and 22nd November, 1999 that is for nearly 18 months HTC had been supplied only 30335 MT of steel materials as against 796900 MT which was estimated and expected to be handled during the said period by HTC in terms of Clause 4 of the terms and conditions of the contract. Thus for the said 18 months HTC did not get 766565 MT of materials (Expected 796.900 MT- Actual receipt 30355 MT) which is equivalent to 69.20% of the expected quantity. Again during the first half of the present contract that is from 23rdNovember, 1998 HTC had handled approximately 54.86% of the estimated or expected quantity as provided in Clause 4 of the tender/contract document.
7.2 Our attention has been drawn to the fact that the earlier arbitral proceedings which was initiated by HTC against SAIL an award was passed by the Learned Arbitral Tribunal holding that the respondent was entitled on year to year basis the entirety i.e. 100% of the quantity which was specified in clause 4 of the contract document subject to 5% deviation therefrom.
7.5 In the premises aforesaid we hold that the claimant committed breach of its obligation of providing reasonable quantity of materials to be handled by HTC in performance of the contract and we assess in the light of the surrounding circumstances including contract documents and other evidence brought on record that reasonable quantity would be 581737 MT for the period 1st May, 1998 to 22nd November, 1999. We answer issues 1(a) and 1(b) accordingly.

9. Thereafter, the Arbitral Tribunal fixed the profit of the respondent @ 15% of the total price amount payable for receiving and delivery namely Rs.490/- for 2(two) MT (Rs.265/- + Rs.225/-) which is Rs.73.5/2=Rs.36.75/- per MT. The Arbitral Tribunal held as follows: 80

19.1) Issue No.5 deals with the counter claim arising out of the failure of SAIL to provide entirety of expected quantity of materials. The respondent HTC has claimed on account of shortfall quantities of materials relating to Group-A and Group-B both for receipt and delivery by taking into account handling charges at Rs.9,00,31,650.00. We have under issue Nos. 1(a) and 1(b) discussed in detail the question as to the obligation of SAIL to provide HTC with reasonable quantity of materials to compensate the loss of profit or any other loss, if any, connected with handling job. In our considered view the reasonable quantity of materials which ought to have been given to HTC by SAIL would be 581737 MT for the period 1st May, 1998 to 22nd November, 1999 as against the claim of respondent of 796900 MT. Thus, the claimant has filed to provide the respondent at least 581737 MT of materials being 73% of the expected or estimated quantity of 796900 MT in terms of clause 4 of the contract document.

10. In effect, the Arbitral Tribunal implied a term of minimum guarantee of a reasonable quantity into the contract i.e. 6,12,072 MT - 30,335 MT aggregating to 5,81,737 MT x Rs.36.75 per MT amounting to Rs.2,13,78,834.75/-.

11. It is contended by the appellant that in passing the award the Arbitral Tribunal erred in implying such a term the effect of which was to contradict the express terms of the contract. The condition for implying a term is also contradictory to clause 5 of the Invitation to Tender and clause 8.7 of the Terms and Condition of the Contract. The Arbitral Tribunal also formulated new disputes which were not referred to arbitration namely that the claimant would be entitled to a reasonable quantity for handling the materials. Consequently, the Arbitral Tribunal erred in awarding compensation @ 15% plus the costs involved in earning such profits. The assessment of the quantity of 5,81,737 MT was arbitrary, unreasonable and perverse. The award 81 is also contrary to public policy as well as in excess of jurisdiction. Hence, the entire award is vitiated and is liable to be set aside inter alia under section 34(2)(a)(iv) of the Act. In support of their contentions, the appellant placed reliance on B.P. Refinery (Westernport) Proprietary Limited vs. The President Councilors and Ratepayers of the Shire of Hastings (1977) 52 A.L.J.R 20, Nabha Power Ltd. v. Punjab SPCL (2018) 11 SCC 508, Adani Power (Mundra) Limited v. Gujrat Electricity Regulatory Commission (2019) 19 SCC 9, State of Chhattisgarh and Anr. v. SAL Udyog Private Limited (2022) SCC 275, Boozallen and Hamilton Inc. v. SBI Home Finance Limited and Others (2011) 5 SCC 532, South East Asia Marine Engineering and Constructions Limited (SEAMEC Limited) v. Oil India Ltd. (2020) 5 SCC 164, Hindustan Zinc Ltd. v. Friends Coal Carbonisation, (2006) 4 SCC 445, Delhi Airport Metro Express (P) Ltd. v. DMRC, (2022) 1 SCC 131) and Ssangyong Engineering and Construction Company Limited v. National Highways Authority of India (NHAI) (2019) 15 SCC 131.

12. On behalf of the respondent, it is submitted that there are no grounds made out warranting any interference with the award. The award is adequately reasoned and all issues raised by the parties have been dealt with by the Arbitral Tribunal. The Arbitral Tribunal has given a reasonable and plausible interpretation to the contract which cannot be described as perverse. The respondent was required to maintain infrastructure, materials, labourers etc. throughout the period of contract and was not given any materials for the last 11 months of the 82 contract. In this background, there are no grounds which warrant interference with the impugned order or the impugned award and the appeal should be dismissed.

13. Section 9 of the Indian Contract Act, 1872 provides as follows:

Promises, express and implied.--In so far as the proposal or acceptance of any promise is made in words, the promise is said to be express. In so far as such proposal or acceptance is made otherwise than in words, the promise is said to be implied.

14. A contract may be expressed or implied. The question whether a contract is express or implied is one of inference to be borne from the facts and circumstances of each case. In certain circumstances, the Court imports into the contract a term to give effect to the intention, the presumed intention of the parties. The underlying reasoning being that a Court is not making a new contract for the parties but is implementing their intentions because this is something as reasonable parties they must have intended. The test is a strict test. The touchstone for implying a term is not only reasonableness but also necessity. A contract can only be implied when there is meeting of minds. As held by Lord Atkin in Bell vs. Lever Brothers [1932] AC 161:

"Nothing is more dangerous to allow oneself the liberty to construct for the parties contracts which they have not in terms made by importing implications which would appear to make the contract more businesslike or more just. The implications to be made are to be no more than are 'necessary' for giving business efficacy to the transaction... a condition should not be implied unless the new state of facts makes the contract something different in kind from the contract in the original state of facts."
83

15. The crux of the dispute even in the narrow and circumspect jurisdiction of the Act is whether in the facts and circumstances of this case the Arbitral Tribunal could have implied a term of minimum guarantee in the contract. In Philips Electronique Grand Public Sa and Anr. v. British Sky Broadcasting Ltd. (1995) EMLR at Page 481 it has been held as follows:

The Courts' usual role in contractual interpretation is, by resolving ambiguities or reconciling apparent inconsistencies, to attribute the true meaning to the language in which the parties themselves have expressed their contract. The implication of contract terms involves a different and altogether more ambitious undertaking: the interpolation of terms to deal with matters for which, ex hypothesi, the parties themselves have made no provision. It is because the implication of terms is so potentially instrusive that the law imposes strict constraints on the exercise of this extraordinary power.

16. In Deviprasad Khandelwal v. Union of India, AIR 1969 Bom 163 it has been held as follows:

12. It is a matter of a common experience that no perfect contract can be made, because the parties to it may not at the stage of making it, envisage or provide for all the contingencies that may arise. Several times the parties to a contract may either through forgetfulness or through bad drafting fail to incorporate into the contract terms which, had they adverted to the situation, they would certainly have inserted to complete the contract. In such cases, in order to give efficacy to the contract, the Court will imply into a contract terms which the parties have not themselves expressly inserted. It is true that it is not the function of the Court to make contracts for the parties, but only to interpret contracts already made. Nevertheless, in certain circumstances, the Court will imply terms. Such terms should neither be contrary to, nor inconsistent with the express terms of the contract contained in the terms and conditions of agreement.

17. In Nabha Power Ltd. v. Punjab SPCL, (2018) 11 SCC 508 it has been held as follows:

84

49. We now proceed to apply the aforesaid principles which have evolved for interpreting the terms of a commercial contract in question.

Parties indulging in commerce act in a commercial sense. It is this ground rule which is the basis of The Moorcock [The Moorcock, (1889) LR 14 PD 64 (CA)] test of giving "business efficacy" to the transaction, as must have been intended at all events by both business parties. The development of law saw the "five condition test" for an implied condition to be read into the contract including the "business efficacy"

test. It also sought to incorporate "the Officious Bystander Test"

[Shirlaw v. Southern Foundries (1926) Ltd. [Shirlaw v. Southern Foundries (1926) Ltd., (1939) 2 KB 206 : (1939) 2 All ER 113 (CA)] ]. This test has been set out in B.P. Refinery (Westernport) Proprietary Ltd. v. Shire of Hastings [B.P. Refinery (Westernport) Proprietary Ltd. v. Shire of Hastings, 1977 UKPC 13 : (1977) 180 CLR 266 (Aus)] requiring the requisite conditions to be satisfied: (1) reasonable and equitable; (2) necessary to give business efficacy to the contract; (3) it goes without saying i.e. the Officious Bystander Test; (4) capable of clear expression; and (5) must not contradict any express term of the contract. The same penta-principles find reference also in Investors Compensation Scheme Ltd. v. West Bromwich Building Society [Investors Compensation Scheme Ltd. v. West Bromwich Building Society, (1998) 1 WLR 896 : (1998) 1 All ER 98 (HL)] and Attorney General of Belize v. Belize Telecom Ltd. [Attorney General of Belize v. Belize Telecom Ltd., (2009) 1 WLR 1988 (PC)] Needless to say that the application of these principles would not be to substitute this Court's own view of the presumed understanding of commercial terms by the parties if the terms are explicit in their expression. The explicit terms of a contract are always the final word with regard to the intention of the parties. The multi-clause contract inter se the parties has, thus, to be understood and interpreted in a manner that any view, on a particular clause of the contract, should not do violence to another part of the contract.

18. In Adani Power (Mundra) Ltd. v. Gujarat ERC, (2019) 19 SCC 9 it has been held as follows:

24. It could thus be seen that it is more than well settled that the clauses in the agreement ought to be given the plain, literal and grammatical meaning of the expression used in the same. No doubt, that the courts will also try to gather as to what intention the parties wanted to give them. The principle of business efficacy could be invoked only if by a plain literal interpretation of the term in the agreement or the contract, it is not possible to achieve the result or the consequence intended by the parties acting as prudent businessmen. This test requires that a term can only be implied, if it is necessary to give 85 business efficacy to the contract, to avoid such a failure of consideration that the parties cannot as reasonable businessmen have intended. If the contract makes business sense without the term, the Courts will not imply the same. It is amply clear that Courts can imply a clause only if it is found that the plain and literal meaning given to the expression used in the terms is not in a position to make out the intention of the parties. Reading an unexpressed term in an agreement would be justified on the basis that such a term was always and obviously intended by and between the parties thereto. An unexpressed term can be implied if and only if the court finds that the parties must have intended that term to form part of their contract. It is not enough for the Court to find that such a term would have been adopted by the parties as reasonable men if it had been suggested to them. It must have been a term that went without saying, a term necessary to give business efficacy to the contract, a term which, although tacit, forms part of the contract. As held in Nabha Power Ltd. [Nabha Power Ltd. v. Punjab SPCL, (2018) 11 SCC 508 : (2018) 5 SCC (Civ) 1] , for invoking the business efficacy test and carving out an implied condition, not expressly found in the language of the contract, the following five conditions will have to be satisfied: (SCC p. 540, para 49) (1) Reasonable and equitable;

(2) Necessary to give business efficacy to the contract; (3) It goes without saying i.e. the Officious Bystander Test; (4) Capable of clear expression; and (5) Must not contradict any express term of the contract.

19. It is a cardinal rule that no term can be implied into a contract, if it contradicts or is inconsistent with an express term of the contract. A Court or Arbitral Tribunal will not improve the contract which the parties have made for themselves, however desirable the improvement might be. Neither does the Court imply terms based on its idea of what it thinks ought to be the contractual relationship between the parties. On a combined reading of Clauses 4 and 5 of the Invitation to Tender and Clauses 8.3 and 8.7 of the General Clauses, the parties at the time of entering into of the contract only provided for an estimate quantity for the first year of operations. In fact, on a plain reading of 86 clauses 8.3 and 8.7 above any minimum guarantee about the definite volume of the work during any time of the contract or even throughout the tenure of the contract was deliberately excluded and expressly prohibited. In such circumstances, there could be no question of any minimum quantity being guaranteed under the contract. It is obvious that there was no meeting of minds of the parties at the time of entering into the contract insofar as any minimum guarantee for the volume of the work was concerned. Any other interpretation would contradict the express terms of the contract. Trollope & Colls Ltd. vs. North West Metropolitan Regional Hospital Board (1973) 1 WLR 601, Naihati Jute Mills Ltd. vs. Khyaliram Jagannath AIR 1968 SC 522 and Food Corporation of India vs. Chandu Construction and Anr (2007) 4 SCC 697.

20. It is also not permissible for the Court to make a new contract, however reasonable, which the parties have not made themselves. A term cannot be implied simply because it is reasonable to do so or that it would make the performance of the contract more just, convenient or beneficial to one party. The subject contract had been entered into in detail and was a carefully drafted commercial contract. Accordingly, implying a term of minimum guarantee by the Arbitral Tribunal has resulted in re-writing the contract. The professed object of the Court or the Arbitral Tribunal in interpreting the contract is to discover the mutual intention of the parties and not to re-write the same. It is not the intent of a single party which is to be taken into 87 consideration but the joint intention of the both parties which can only be discovered from the terms of the contract. The contract was a business transaction which both parties had consciously undertaken. The parties at the time of entering into the contract were best placed to judge and protect their interests in the bargaining process. Freedom of contract is the general rule. There is nothing obvious about the implied term which must be incorporated by necessary implication without which the whole contract would become meaningless. Consequently, resort to the principle of business efficacy to read an implied term into the contract was wholly unfair and unreasonable. [Satya Jain (Dead) Through Lrs. & Ors. v. Anis Ahmed Rushdie (Dead) Through Lrs. & Ors. (2013) 8 SCC 131].

21. For the above reasons, the implied term as to minimum guarantee and a reasonable quantity by the Arbitral Tribunal is patently illegal. The language of clauses 4, 5, 8.3 and 8.7 were explicit, clear and unambiguous. There was no scope for drawing upon hypothetical considerations or supposed intentions of the parties. It was not open to the Arbitral Tribunal to ignore the express terms of the contract which were binding on the contracting parties. There is no discretion in a Court on the Arbitral Tribunal to make a new contract for the parties. In fact, it would be contrary to law to impose on the appellant an obligation of minimum guarantee which they were not contractually obliged to perform. A fundamental addition or alteration of a contract can never by foisted upon an unwilling party, nor can a 88 party to an agreement be liable to perform a bargain not entered into with the other party. Upon incorporation of the implied term in the contract by the Arbitral Tribunal, clause 5 of the Invitation to Tender and Clause 8.7 of the terms and conditions of the contract were modified to read as follows:

Clause 5: the estimated quantities for the first year of operation of contract are only for the purpose of finding out the value of the tender & SAIL is in no way liable if the actual quantity of work differs from estimated quantity indicated above. But the company (SAIL) would be liable if a reasonable quantity of work is not provided to the contractor throughout the tenure of the contract.
Clause 8.7: The company gives no guarantee about the definite volume of work to be entrusted with the contractor at any time or even throughout of tenure of the contract. But a reasonable volume of work is guaranteed by the company during the tenure of the contract.

22. In passing the award, the Arbitral Tribunal has also acted in manifest disregard to the terms of the contract and in excess of jurisdiction. The interpretation of the Arbitral Tribunal cannot be said to be a possible one as it would defeat the explicit terms and purpose of the contract [South East Asia Marine Engineering & Constructions Ltd v. Oil India Ltd (2020) 5 SCC 164]. The construction of the contract by the Arbitral Tribunal is neither reasonable nor plausible but manifestly arbitrary and patently illegal. The quantity claimed by the respondent in their pleading was for a specific quantity calculated on the basis of clause 4 for the 2nd and 3rd years. The Arbitral Tribunal has also made out a new case beyond the pleadings of the respondent. In view of the fact that the Arbitral Tribunal erred in implying a term as to guarantee 89 of a reasonable quantity to be incorporated into the contract, the remaining portion of the award in respect of assessment damages on the basis of net profit is against all notions of justice and liable to be set aside inter alia under sections 34(2a)(iv) and 34(2b)(ii) of the Act.

23. In Union of India and Ors. v. Bharat Enterprise 2023 SCC OnLine 369 it has been held that:

The Arbitrator comes on the scene as a result of the agreement between the parties. Not unnaturally, the fundamental and primary foundation for the Arbitrator to settle the dispute is the contract between the parties. An Arbitrator is a creature, in other words, of the parties and the contract. It is elementary that as Arbitrator he cannot stray outside the contours of the contract. He is bound to act within its confines. A disregard of the specific provisions of the contract would incur the wrath of the Award being imperilled. This position cannot be in the region of dispute.

24. The impugned order refers to numerous authorities under section 34 of the Act without adverting to the facts of this case. The mere mentioning of clause 4, 5, 8.3 and 8.7 in the impugned order without any discussion or relevancy of the same is ex facie erroneous. In passing the impugned order, the Learned Judge has failed to appreciate the scope, purport and ambit of clauses 4, 5, 8.3 and 8.7 or even discuss the same. The finding in the impugned order that "this is not certainly a case where the Arbitral Tribunal have incorporated the implied term into the contract which is inconsistent and repugnant to the express terms" is a conclusion bereft of any reasoning. For the above reasons, even in view of the extremely limited jurisdiction under the Act and the respect for party autonomy, the impugned order and the award are unsustainable and set aside. (Hindustan Zinc Ltd. v. 90 Friends Coal Carbonisation, (2006) 4 SCC 445, Ssangyong Engineering and Construction Company Limited v. National Highways Authority of India (NHAI), (2019) 15 SCC 131, Delhi Airport Metro Express (P) Ltd. v. DMRC, (2022) 1 SCC 131) and State of Chhattisgarh v. SAL Udyog (P) Ltd., (2022) 2 SCC 275.

25. For the above reasons, the appeal succeeds APO 356 of 2016 stands allowed.

(Ravi Krishan Kapur J.) Later, the Court:

In view of the difference of opinion the matter shall be placed before the Hon'ble the Chief Justice under Clause 36 of the Letters Patent.
(Ravi Krishan Kapur, J.)                               (Soumen Sen, J.)