Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 2, Cited by 0]

Delhi District Court

Nirula Corner House Pvt. Ltd vs Moolchand Khairatiram Hospital on 2 August, 2018

             IN THE COURT OF SHRI GIRISH KATHPALIA, 
                    DISTRICT & SESSIONS JUDGE
              SOUTH EAST : SAKET COURT, NEW DELHI.
ARBITRATION No. 423/2016

NIRULA CORNER HOUSE PVT. LTD.
10185 C, ARYA SAMAJ ROAD,
KAROL BAGH, NEW DELHI 110005                                            
                                                                            ....PETITIONER

                                          VERSUS

MOOLCHAND KHAIRATIRAM HOSPITAL
& AYURVEDIC RESEARCH INSTITUTE,
LAJPAT NAGAR­III, NEW DELHI 110024

                                                                           ...RESPONDENT

Date of filing  : 19.11.2016 First date before this court : 01.06.2017 Arguments concluded on : 30.07.2018 Date of Decision :  02.08.2018 Appearance:  Shri Ayush Negi, counsel for appellant Shri Shaurya Sahay, counsel for respondent J U D G M E N T 

1.  By   way   of   this   appeal   brought   under   the   provisions   of Section   37   (2)   (a)   of   the  Arbitration   &   Conciliation   Act  1996,   the appellant  has  challenged  order  dated  19.09.2016 whereby  the  learned Sole Arbitrator terminated the arbitral proceedings under Section 16 of the Act.   I have heard learned  counsel for both sides and perused the original record of the arbitral proceedings.

Arbitration No. 423/2016  Page 1 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital  

2.  In earlier proceedings between parties to this appeal, vide order dated 09.12.2015 in ARB. P. 516/2015, the Hon'ble Single Judge of the Delhi High Court recorded that in terms with a valid arbitration agreement between the parties, each side had nominated an arbitrator but despite seven meetings, the arbitrators could not agree on the name of an umpire, so both sides had consented for termination of mandate of those two   arbitrators   and   appointment   of   sole   arbitrator   by   the   court. Accordingly, with consent of both sides, the Hon'ble Single Judge of the Delhi High Court terminated mandate of both arbitrators appointed by the parties and appointed the learned  Senior Advocate as sole arbitrator.

3.  The present appellant filed claim petition before the learned sole arbitrator, which was   followed by respondent's application under Section 16 of  the  Arbitration & Conciliation  Act  contending that the claims raised by the present appellant are not arbitrable disputes.   The present appellant filed reply, which followed a rejoinder from the present respondent   and   after   hearing   both   sides,   the    learned  sole   arbitrator passed   the  impugned   order,  thereby   allowing   the   application   of   the appellant and terminating the proceedings under Section 16 of the Act. Hence, the present appeal.

4.  Briefly stated, case set up by the present appellant in its claim petition before the  learned sole arbitrator was as follows.

Arbitration No. 423/2016  Page 2 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital   4.1  Parties   to   this   appeal   entered   into   an   agreement   dated 31.03.2009   whereby   the   respondent,   engaged   in   running   a   hospital, allowed the appellant to run a cafeteria in the said hospital premises for a period of 9 years with effect from 01.04.2009.     However, in the said agreement, period thereof was stipulated to be a period of two years from 01.04.2009 to 31.03.2011 and it was also agreed that the said agreement would be valid for initial period of two years or till relocation of the cafeteria to the new block of the hospital whichever was later.   Parties had also agreed that after relocation, the agreement would be renewed for a further period of 7 years from 01.04.2011 to 31.03.2018.

4.2  On the basis of the said agreement, the appellant spent Rs. 25,00,000/­ approximately for necessary interiors, kitchen and ambiance required   to   run   and   operate   a   cafeteria   after   obtaining   necessary approvals from various departments.

4.3  Since by 31.03.2011, new block of respondent hospital was not ready, by mutual consent, agreement dated 31.03.2009 was renewed vide letter dated 02.04.2011 for a period of one year till 31.03.2012.

4.4 The agreement dated 31.03.2009 was further renewed vide agreement dated 21.09.2012 for a period of two years from 01.04.2012 to 31.03.2014 and the appellant incurred an additional expenditure of Rs. 2,00,000/­ on renovation of cafeteria.

Arbitration No. 423/2016  Page 3 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital   4.5  Ever since the month of March 2014, appellant remained in touch with the respondent for renewal of the agreement but respondent neither acceded to the requests of the appellant nor showed any sign of discontinuance of the agreement.     Appellant continued to operate its cafeteria from the said premises in the hospital run by the respondent and continued to pay commission and dues in time to the respondent as per their agreement.

4.6  But   on   03.05.2014,   the   appellant   was   informed   by   its employees   that   respondent   had   engaged   musclemen   who   were   not allowing the employees of appellant to enter the cafeteria and they had forcibly removed all goods, equipments and other material out of the cafeteria.

4.7 The  appellant   lodged   police  complaints   dated   05.05.2014 and 05.06.2014 but to no avail.   The respondent got issued a frivolous legal notice dated 12.05.2014 to which the appellant sent reply dated 22.05.2014.     The respondent again got issued notice dated 02.06.2014 to which the appellant sent reply dated 07.06.2014.

4.8  Since the agreement dated 31.03.2009 was to be extended till   31.03.2018   but   respondent   illegally   terminated   the   agreement   by forcibly dispossessing the appellant, the latter  suffered losses to the total Arbitration No. 423/2016  Page 4 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital   tune of Rs. 32,50,356/­ on different counts as enumerated  in para 21 of the claim petition.  

5.  In   its   application   under   Section   16   of   the  Arbitration   & Conciliation   Act,   the   present   respondent   contended   that   the  Hon'ble Delhi High Court  in order dated 09.12.2015 had granted liberty to the respondent to raise all pleas before the arbitrator including the plea that the present appellant's claims are not arbitrable.  It was further contended by   the  present   respondent   before   the  learned    sole   arbitrator   that  the allegations   of   the   present   appellant   related   mainly   to   preventing   the employees   of   the   appellant   from   entering   into   the   premises   of   the respondent and also preventing them from taking away their material, which would have a remedy before a civil court and not under arbitration since clause 3.2 of the agreement dated 21.09.2012 provided that any dispute arising in relation to the terms and conditions thereof would be submitted to the exclusive jurisdiction of the courts of Delhi.     It was further contended by the present respondent before the   learned    sole arbitrator that the arrangement dated 31.03.2009 had expired and was renewed for one year vide letter dated 02.04.2011 and thereafter a new arrangement dated 21.09.2012 was created for a period upto 31.03.2014, thus   all   arrangements   expired   by   efflux   of   time   and   there   was   no termination   of   any   agreement.       According   to   respondent,   the arrangement   between   the   parties   was   extended   vide   agreement   dated Arbitration No. 423/2016  Page 5 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital   21.09.2012 with revised terms for a period of two years with effect from 01.04.2012 and that agreement elapsed by efflux of time on 31.03.2014.

6.  In reply to application under Section 16 of the Arbitration & Conciliation Act, the present appellant stated that the liberty was granted by  the  Hon'ble   Single   Judge  of   the  Delhi  High  Court  in  order  dated 09.12.2015 in routine.  It was contended by the appellant that agreement dated   21.09.2012   was   in   continuance   of   the   first   agreement   dated 31.03.2009   and   the   same   has   to   be   read   in   the   light   of   all   earlier agreements between the parties.  It was contended that agreements dated 31.03.2009, 02.04.2011 and 21.09.2012 have to be read in continuance and   in   the   light   of   first   agreement   dated   31.03.2009   whereby   the respondent   had   agreed   for   entering   into   the   arrangement   for   a   total period of 9 years.  

7.  In   the  impugned   order,   the  learned    sole   arbitrator,   after analysis of rival pleas, took a view that claims of the present appellant were   for   breach   of   agreement   dated   31.03.2009   while   the   arbitration proceedings   were   commenced   on   the   basis   of   agreement   dated 21.09.2012 but agreement dated 21.09.2012 was not placed on record from which the appellant could show that there was any breach of any agreement or that the arbitration clause of the said agreement permitted the appellant to raise disputes pertaining to the earlier agreement dated 31.03.2009.     The  learned    arbitrator took a view that apparently, the Arbitration No. 423/2016  Page 6 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital   agreement   dated   21.09.2012   superseded   the   earlier   agreement   dated 31.03.2009   and   parties   did   not   place   on   record   the   agreement   dated 21.09.2012,   so   the   dispute   having   arisen   out   of   agreement   dated 31.03.2009 cannot be looked into.   Therefore, according to learned  sole arbitrator,   he   had   no   jurisdiction   and   as   such   proceedings   were terminated under Section 16 of the Act.

8.    During argument,  learned  counsel for both sides took me through   record   and   their   rival   contentions,   already   narrated   above. Learned  counsel for appellant argued that the learned  arbitrator arrived at wrong conclusion that agreement dated 21.09.2012 had superseded the agreement dated 31.03.2009.   It was argued that all agreements between the parties flowed from agreement dated 31.03.2009 and therefore, it was wrongly held that the disputes were not arbitrable.  It was also argued on behalf of appellant that since agreement dated 21.09.2012 was not on record of the  learned    arbitrator, it could not be recorded that the said agreement had superseded the agreement dated 31.03.2009.   Per contra, learned    counsel   for   respondent  supported   the  impugned   order, contending   that   even   according   to   the   claim   petition   filed   by   the appellant,   the   agreement   dated   31.03.2009   stood   expired   and   the agreement   dated   21.09.2012   was   a   fresh   agreement,   containing   fresh arbitration clause.   It was argued on behalf of respondent that it is the appellant   who   was   under   duty   to   place   on   record   agreement   dated 21.09.2012 but did not do so.  

Arbitration No. 423/2016  Page 7 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital  

9.  Against   the   above   backdrop   of   rival   contentions   I   have examined the original records of arbitration proceedings.

10.  The   record   of   arbitration   proceedings   bear   at   page   80 thereof,   a   copy   of   notice   dated   10.06.2014   addressed   to   the   present appellant, whereby the present respondent nominated Shri Gian Chand as arbitrator in accordance with clause 3.1 and 3.2 of agreement dated 21.09.2012.       In   response,   the   present   appellant   vide   reply   dated 16.06.2014  (page 82 of arbitral record) nominated Shri T.S. Ahuja as arbitrator   on   its   behalf   under   the   same   clause   no.   3.1   and   3.2   of agreement   dated   21.09.2012.       Admittedly,   when   the   two   arbitrators could not agree on the name of umpire, the present appellant approached the Hon'ble Delhi High Court and vide order dated 09.12.2015, learned sole arbitrator was appointed.   It cannot be denied that appointment of the  learned Sole Arbitrator was under agreement dated 21.09.2012.    It also   cannot   be   denied   that   agreement   dated   21.09.2012   contained   a specific arbitration clause.

11.  The disputes under reference arise out of the alleged breach of agreement dated 31.03.2009 since according to the present appellant also,   the   space   for   cafeteria   allowed   to   the   present   appellant   by   the present respondent for a period of 9 years was under agreement dated 31.03.2009.       It   cannot   be   disputed   that   the   dispute   under   reference pertained strictly to the agreement dated 31.03.2009.   

Arbitration No. 423/2016  Page 8 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital  

12.  In   application   under   Section   16   of   the  Arbitration   & Conciliation   Act,   the   present   respondent   specifically   pleaded   that agreement   dated   31.03.2009     had   expired   by   efflux   of   time     and agreement dated 21.09.2012 was a fresh arrangement.     In reply to the said application, the present appellant disputed that contention, pleading that agreement dated 21.09.2012 was in continuation of agreement dated 31.03.2009.   That being so, it was incumbent upon the present appellant to   place   on   record   of  learned    arbitrator   a   copy   of   agreement   dated 21.09.2012, but the same was not done.  Since, as mentioned above, the agreement dated 21.09.2012 contained an arbitration clause under which the arbitral proceedings had been commenced by the present appellant, a copy of the said agreement ought to have been placed on record by the present   appellant   to   establish   that   the   disputes   under   reference   were arbitrable under the said arbitration agreement.   

13.  I have also examined the agreement dated 31.03.2009, copy whereof   is   at   page   64   of   the   arbitral   record.       Clause   17   of   the Commercial part of agreement dated 31.03.2009 is the arbitration clause. But  as mentioned above, it is not this clause which was invoked for initiation of arbitration.    As mentioned above, arbitration was initiated on   the   basis   of   clause   3.1   and   3.2   of   agreement   dated   21.09.2012. Further,   according   to   clause   1   of   the   Commercial   part   of   agreement dated   31.03.2009,   renewal   of   the   arrangement   for   a   period   from Arbitration No. 423/2016  Page 9 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital   01.04.2011 to 31.03.2018 was subject to relocation of the cafeteria to the new building of the hospital.   Even according to the present appellant, no relocation of the cafeteria took place.  That being so, it cannot be said that agreement dated 31.03.2009 could have continued to survive after 31.03.2011   automatically.       It   is   for   this   reason   that   by   letter   dated 02.04.2011, the engagement was continued for a period of one year till 30.03.2012.

14.  Respondent's   letter   dated   02.04.2011   at   page   72   of   the arbitral record also has been perused by me.   The said letter is of hardly three   sentences,   holding   that   the   agreement   dated   31.03.2009   stood extended for one year on same terms and conditions.     As mentioned above, in agreement dated 21.09.2012, there was a specific arbitration clause no. 3.1 and 3.2 and  it was not a short and crisp  extension of agreement dated 31.03.2009 similar to letter dated 02.04.2011.   Had the agreement   dated   21.09.2012  been   in  continuation   of   agreement   dated 31.03.2009,   it   would   have   been   in   the   form   of   a   short   and   crisp extension/renewal   letter,   and   not   an   agreement   containing   fresh arbitration clauses. Therefore, the view taken by the  learned    arbitrator that agreement dated 21.09.2012 was not in continuance of agreement dated 31.03.2009  was sound and sustainable.   Consequently, the view of the learned  arbitrator that the disputes pertaining to agreement dated 31.03.2009 could not be held to be arbitrable under the agreement dated Arbitration No. 423/2016  Page 10 of 11 pages Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital   21.09.2012   was   sound   and   sustainable.       I   am   unable   to   find   any infirmity in the impugned order.

15.  In view of above discussion, the impugned order is upheld and the present appeal is dismissed.

16.  File be consigned to records. 





Announced in the open court on                                                                 
this 02nd day of August 2018                                     (GIRISH KATHPALIA)
                                                             District & Sessions Judge
                              Digitally signed
                                                                  South East, Saket Courts
                              by GIRISH
                   
   GIRISH                                                        New Delhi 02.08.2018 (a)
                              KATHPALIA
   KATHPALIA Date:
                        2018.08.03
                        12:51:35 +0530




Arbitration No. 423/2016                                                    Page 11 of 11 pages

Nirula Corner House Pvt. Ltd. vs Moolchand Khairatiram Hospital