State of Jharkhand - Section

Section 19 in Jharkhand Industrial Area Development Authority Regulations, 2016

19. Timelines For Construction of Factory/shed.

- i. The allottee shall start construction as per the approved plan within 6 (six) months, extendable to a maximum period of another six months, under extraordinary circumstances, with prior approval of the Chief Executive Officer of the region from the date of taking physical possession of the allotted plot. In the event of failure on the part of allottee to do so, late action charges shall be recovered @ 1.00 per sq. ft. per month from the last date of extended period.ii. Jharkhand Industrial Area Development Authority shall organize annual inspection of all allotted plots to ensure its utilization. Detailed information compiled by the inspection team will be placed on the Website. The case of enterprises not utilizing the plot or inadequately utilizing the plot for the purpose, for which the allotment was made, Chief Executive Officer of the region shall take action for cancellation of allotment order of land or penalty equal to land premium or forfeiture of amount deposited by the entrepreneur towards land premium and other charges . After allotment and taking over possession thereof if a fully functional industry is not set up by the allottee within the stipulated period (two years for micro and small enterprises and five years for other enterprises) the allotment of land shall be cancelled and possession taken by Jharkhand Industrial Area Development Authority.