[Cites 0, Cited by 0]
[Entire Act]
State of Tamilnadu - Section
Section 5 in Central Electricity Regulatory Commission (Standards of Performance of Inter-State Transmission Licensees) Regulations, 2012
5. Standards of Performance.
| SI. No. | Transmission Elements | Availability (% of time) |
| (i) | AC Transmission line | 90 |
| (ii) | ICTs | 90 |
| (iii) | Reactors | 90 |
| (iv) | Static VAR Compensator | 90 |
| (v) | Series Compensator | 90 |
| (vi) | HVDC (Back-to-back Stations and bi-pole links) | 85 |
| SI. No. | Types of failures | Restoration Time (Days) |
| 1. | Insulator failure | |
| Plain Terrain | 1 | |
| Hilly Terrain | 2 | |
| 2. | Tower after collapse by Emergency RestorationSystem (ERS) | 12 |
| 3. | Tower after collapse | |
| Plain Terrain | 30 | |
| River Bed | 50 | |
| Hilly Terrain | 50 | |
| 4. | Snapping of phase conductor | |
| Plain Terrain | 2 | |
| Hilly Terrain | 3 | |
| 5. | Failure of earth wire | |
| Plain Terrain | 2 | |
| Hilly Terrain | 3 | |
| 6. | Failure of Inter Connecting Transformers (ICTs) | |
| Restoration of the failed ICT | 120 | |
| 7. | Failure of Reactors | |
| Restoration of the failed reactor | 120 |