Bombay Presidency - Section

Section 304 in The Bombay Provincial Municipal Corporations Act, 1949

304. Effect of order for demolition of obstructive building. - (1) If, before the expiration of the period within which a building or part thereof in respect of which an order is made under section 303 is thereby required to be vacated, any owner or any person known to have an interest in such building or the site of the building makes to the Commissioner an offer for the sale of the building site or any interest therein to the Corporation at a price equal to the compensation to be assessed as provided in subsection (6), the Commissioner shall, upon obtaining the requisite sanction under section 77 accept the offer and shall, as soon as possible after obtaining possession, carry out the demolition.

(2)Upon payment of the price mentioned in sub-section (1), the said building and the site thereof to the extent of the interest acquired shall vest in the Corporation.
(3)If no such offer as is mentioned in sub-section (1) is made before the expiration of the said period, the owner of the building shall carry out the demolition provided for by the order before the expiration of six weeks from the last day of that period, or, if the building, or such part thereof as is required to be vacated, is not vacated until after that day, before the expiration of six weeks from the day on which it is vacated, or, in either case, before the expiration of such longer period as in the circumstances the Commissioner deems reasonable, and if the demolition is not so carried out the Commissioner shall [cause the building or part thereof to be vacated, if necessary, in the manner provided in section 388A and] take measures to carry out the demolition and sell the materials rendered available thereby.
(4)When any obstructive building or any part thereof is demolished either by the owner or by the Commissioner as provided for in sub-section (3), the Commissioner may at once take possession on behalf of the Corporation of the land occupied by and appurtenant to the said building or part thereof, and shall pay compensation as provided in sub-section (6).
(5)The provisions of sub-sections (2) and (3) of section 301 shall apply in relation to any expenses incurred by the Commissioner under sub-section (3) and to any surplus remaining in the hands of the Commissioner as they apply in relation to any expenses or surplus in a case where a building is demolished in pursuance of a demolition order made under section 300.
(6)The Compensation payable by the Commissioner for the building and the site thereof upon any sale effected under sub-section (1) and the compensation payable by the Commissioner under sub-section (4) shall be the market value of the land and the building demolished, at the date of the demolition order made under sub-section (2) of section 303.