Union of India - Subsection

Section 33(7) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

(7)The generating company or the transmission licensee, as the case may be, shall submit the details of proposed capital expenditure five years before the completion of useful life of the project along with justification and proposed life extension. The Commission based on prudence check of such submissions shall approve the depreciation on capital expenditure.