Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 5, Cited by 0]

Bangalore District Court

M/S Ssjv Project Pvt. Ltd vs M/S Sathyanarayana Raju And Co on 10 April, 2017

IN THE COURT OF THE XLI ADDL.CITY CIVIL JUDGE
          AT BANGALORE [CCH.No.42]

       PRESENT: SRI.BASAVARAJ B.COM., LL.M.
               XLI Addl. City Civil Judge

       Dated this the 10th day of April 2017

               O.S.No.39/2013
PLAINTIFF :       M/s SSJV Project Pvt. Ltd.
                  Having its registered office at
                  "Vainetheya', No.64, Terrace Floor
                  1st Main, ST Bed
                  Koramangala
                  Bangalore-560 034
                  Represented by its Director
                  Sri.Somashekar Salimath

                  (By Sri.S.J., Advocate)


                    V/s.

DEFENDANTS :      1. M/s Sathyanarayana Raju and Co.
                     Engineers and Contractors
                     D.No.51-8-40, Plot No.5
                     Behind BOC Limited
                     Seethammadhara
                     Vishakapatnam-530 013
                     Andhra Pradesh
                     Rep. by its Managing Partner
                     Sri.S.Sathyanarayana Raju

                  2. S.Sathyanarayana raju
                     Managing Partner
                     M/s Sathyanarayana Raju and Co.
                     D.No.51-8--40, Plot No.5
                     Behind BOC Limited
                               2      OS No.39/2013 & OS.145/2013



                          Seethammadhara
                          Vishakapatnam-530 013
                          Andhra Pradesh

                       3. S.Sitarama Raju
                          Managing Partner
                          S/o Late Shri.Atchutarama Raju
                          Flat No.102, Venu Vihar
                          Apartments
                          Balaji Hills, Vishakapatnam
                          Andhra Pradesh

                      (By Sri.C.M.R., Advocate)


Date of Institution of the Suit:            02.01.2013
Nature of the suit
(Suit on Pronote, suit for                  Recovery of Money
declaration & possession, suit
for injunction)
Date of commencement of                     05.11.2015
recording of evidence:
Date on which the Judgment                  10.04.2017
was pronounced:
Total Duration:                    Year/s    Month/s     Day/s
                                     04        03         08

                  O.S.No.145/2013
PLAINTIFF :           M/s S.Satyanarayuana Raju & Co.
                      Engineers & Contractors
                      Door No.51-8-40, Behind BOC Ltd.
                      Seethammadhara
                      Visakhapatnam-530 013
                      By Sri.Sagiraju Sathyanarayana Raju
                      Managing Director
                      Through its Power of Attorney holder
                      Sri.K.Sreenivasa Rao
                      Flat No.501, Teja Residency
                                   3     OS No.39/2013 & OS.145/2013



                        Vaibhav Nagar, Kommadi
                        Madhurawada
                        Visakhapatnam-530 041

                        (By Sri.M.R.M, Advocate)


                           V/s.

  DEFENDANTS :           1. M/s SSJV Projects Pvt. Ltd.
                            Regd. Office at 12th Floor,
                            S.N.Towers, 25/2, M.G.Road
                            Bangalore-560 001

                         2. SSJV-ZVS Joint Venture
                            "Vainateya", NKo.64, Terrace Floor
                            1st Main, ST Bed, Koramangala
                            Bangalore-560 034

                        (D1 & D2 By Sri.A.A., Advocate)


  Date of Institution of the Suit:             02.01.2013
  Nature of the suit
  (Suit on Pronote, suit for                   Recovery of Money
  declaration & possession, suit
  for injunction)
  Date of commencement of                      11.06.2017
  recording of evidence:
  Date on which the Judgment                   10.04.2017
  was pronounced:
  Total Duration:                     Year/s    Month/s     Day/s
                                        04        03         08

                    COMMON JUDGMENT

     After hearing the arguments on main suit, it is came to

the knowledge that both the suits are arising out of the
                                4        OS No.39/2013 & OS.145/2013



closing of work construction barrage and desilting chamber

package for Tapovan Vishnugad Hydro Electric Project dated

22.01.2007 and hence the OS.145/2013 is clubbed with

OS.39/2013. Hence, taken for common Judgment.



      2.   The plaintiff of OS.39/2013 filed the suit for the

recovery of Rs.6,05,61,574/- from the defendants with

interest at 18% per annum from the date of suit till date of

realization, to award costs of the suit and to pass such other

reliefs.



      3.   The plaint averments in OS.39/2013 in brief is

that the plaintiff is a company incorporated under the

provisions of Companies Act, 1956. The plaintiff is a reputed

construction   company      carrying    on    the   business     of

construction   of   dams,    tunnels,     canals,    roads     and

infrastructure development. The plaintiff along with its Joint

Venture entity M/s Zarubezh Vodstory (ZVS), a Company

incorporated under laws of Russia, formed Joint Venture in

the name and style of SSJV-ZVS-JV.           The purpose of the
                               5      OS No.39/2013 & OS.145/2013



Joint Venture was for construction of barrage and desilting

package for Tapovan - Vishnugad Hydro Electrical Power

Project of National Thermal Power Corporation Limited

(NTPC).

     The SSJV-ZVS-JV was awarded the contract by M/s

NTPC for the construction of barrage and desilting chamber

package for Tapovan - Vishnugad Hydro Electric Power

Project. The defendants represented to the plaintiff that they

have experience and expertise in the area of construction and

induced the plaintiff to issue work order. The work order laid

down the terms and conditions and scope of work of the

defendant No.1.       The scope of work of defendant No.1

included construction of barrage and desilting chamber

package for Tapovan - Vishnugad Hydro Electric Power

Project (4x130 MW).

     In furtherance of the work order dated 22.01.2007 the

principal employer SSJV-ZVS-JV issued another work order

dated 22.01.2007 agreeing to fund the cost of machinery,

equipment and vehicles etc.
                                6      OS No.39/2013 & OS.145/2013



      As per clause 2 of the work order dated 22.01.2007, the

defendant No.1 was to execute the work strictly in accordance

with the drawings and specifications laid down in the

agreement between SSJV-ZVS and NTPC for the project. The

defendant No.1 had to carry out their scope of work under

oval guidance, survey and technical supervision and strictly

with respect to the terms and conditions of the contract

agreement of NTPC.     All other terms and conditions of the

contract agreement the plaintiff had executed with NTPC was

applicable to the defendant No.1 in respect of performance of

the work and payments.

      The plaintiff had agreed to pay mobilization advance of

Rs.100 lakhs for making arrangements of accommodation,

labour, transportation of machinery etc. and interests at the

rate of 12% was levied till the said advance was recovered

from the bills.

      The defendant No.1 as per clause 18 of the work order

dated 22.1.2007 had agreed to indemnify the plaintiff against

all liabilities that may incur to any other person, all claims,

demands, proceedings, damages, cost and expenses made
                                  7         OS No.39/2013 & OS.145/2013



against or incurred by the plaintiff by reason of any breach of

the terms of the defendant No.1 or his personal.

     During the execution of the work order, SSJV-ZVS-JV

vide letter dated 31.3.2008 had brought to the attention of

the defendant No.1 regarding false reporting and negligence

at work site.    SSJV-ZVS-JV had informed that the quantity

which the defendant No.1 was excavating in desilting area

was not matching to their actual survey data, and in addition

the staffs of defendant No.1 were giving false reporting on

quantity.       During   the   execution    of   work   order    joint

measurement of works with the SSJV-ZVS-JV was conducted

and it was noticed that defendant No.1 with a malafide

intention, had billed extra quantities of works to the total

extent of 33,920.083 cubic meters on the monthly bills.

Apart from this, defendant No.1 had also billed fictitious bills

as if they had executed the works. This was encapsulated in

the letter dated 31.3.2008.

     In addition, the defendant No.1 during the course of

execution of work order had illegally shifted sand from the

project site of the above mentioned work order and sold the
                                 8     OS No.39/2013 & OS.145/2013



same to the third parties on many occasions. The quantity of

sand misused by the defendant No.1 was to the extent of

2,884 cubic meters and made money from the illegal shifting

and selling of sand. The same was also brought to the notice

of defendant No.1 vide letter dated 25.2.2009 sent by SSJV-

ZVS-JV.

       The plaintiff had provided a vehicle and equipment to

the defendant and further all the running cost, RTO fees,

maintenance etc. were borne by the plaintiff itself and this

was decided as per the work order. However, the defendant

No.1 had not paid the vehicle taxes during the course of

execution of works. But as the same were demanded by the

concerned RTO and the principal employer, SSJV-ZVS-JV the

plaintiff was constrained to pay the vehicle tax payment to the

RTO.    The principal employer SSJV-ZVS-JV had also paid

part of the taxes to the RTO.

       Inspite of their repeated requests to complete the work

order, the defendant No.1 expressed inability to continue the

work. In view of the same, the principal employer, SSJV-ZVS-

JV and defendant No.1 mutually agreed to cancel the work
                                9       OS No.39/2013 & OS.145/2013



order.   The defendant No.1 vide letter dated 15.7.2009

addressed to SSJV-ZVS-JV accepted that they could not

execute the work as per the time schedule and handed over

the plant and machinery along with the list of inventories.

     SSJV-ZVS-JV acknowledged the receipt of inventories

and valuation arrived by the defendant No.1 and thereafter

the plaintiff took over the work of defendant No.1.           The

plaintiff upon taking over the work of defendant No.1,

prepared final settlement of accounts and the same was also

acknowledged by the defendant No.1.

     As on the date of final settlement of accounts i.e. on

28.12.2009 the defendant No.1 was due to the plaintiff an

amount of Rs.3,15,35,313/-only.       The said amounts were

calculated as the net debit balance in the books of accounts

of the plaintiff before adjustment as on 28.12.2009.

     After taking over the work order and after adjustment of

their books of account, it is noticed that since the defendant

No.1 had billed extra quantities of works to the total extent of

33,920.083 cubic meters on their monthly bills and had also

billed fictitious bills as if they had executed the works, which
                                 10      OS No.39/2013 & OS.145/2013



was brought to the notice of the defendant No.1 vide letter

dated 31.3.208. The plaintiff is entitled to receive back the

payments made to the defendant No.1 i.e. the excess payment

plus interest.

       They are entitled to receive the cost of sand plus interest

on that amount, which the defendant No.1 had illegally

shifted sand from the project site and sold the same to the

third parties to the extent of 2,884 cubic meters. The plaintiff

is further entitled to receive payment made towards vehicle

and equipment cost, running cost, RTO fees, maintenance

etc.

       The plaintiffs are entitled to and the defendant No.1 is

due and liable to pay the following amount as explained in

the table below:



                       Amount to
                                     Interest on
                       be payable
Sl.                                  the amount
        Particulars       by the                        Total
No.                                   payable @
                        contractor
                                      18% p.a.
                           (Rs).
1      Amount          3,15,35,313   1,68,73,552     4,84,08,865
       payable as
       per the
       settlement
                                11      OS No.39/2013 & OS.145/2013



     dated
     28.12.2009
2    Extra             36,03,822      22,43,193       58,52,015
     quantities
     billed
3    Sand theft        21,63,000      14,82,692       36,45,692

4    Vehicle taxes     16,35,019      10,19,983       26,55,002

     Grand Total     3,89,37,154    2,16,24,420     6,05,61,574



     Defendant No.1 was unable to complete the project in

time, caused delay in completion of the project, despite

several requests and reminders, failed to pay the amount,

which is legally due and liable to be paid to the plaintiff. The

defendant No.1 has been evading payment by one or the other

pretext and has been postponing the payment date.

     When such being the case, the plaintiff was shocked

and surprised by the legal notice dated 7.12.2012 issued by

the defendant No.1 calling upon the plaintiff to make payment

of Rs.1,12,69,778/- including an amount of Rs.73,73,102

alleged to be due to the plaintiff plus 38,95,675/- interests at

the rate of 18% from 28.12.2009 till the date of the legal

notice.
                                   12     OS No.39/2013 & OS.145/2013



        The plaintiff issued reply to the legal notice of the

plaintiff on 21.12.2012 narrating the true and correct facts

and called upon the defendant No.1 to pay Rs.6,29,80,880/-

legally due and liable to be paid by the defendant No.1.

        The defendants No.2 and 3 are the Managing Partners

of the defendant No.1 and they are responsible for the day to

day affairs of the defendant No.1. Hence, the defendants No.2

and 3 are jointly and severally responsible to pay the

amounts due to the plaintiff. The plaintiff is represented by

its Director in the present suit. Hence, prayed to decree the

suit.



        4.   In   response   to    the   summons     issued,    the

defendants No.1 to 3 appeared before the court through their

counsel and filed written statement contending that without

joining plaintiff's principal employer viz. SSJV-ZVS-JV as a

party to the suit, plaintiff is not supposed to mention

regarding work order assigned by SSJV-ZVS-JV.            It can be

inferred that SSJV-ZVS-JV has no dispute or claim.             Both

the parties as per the settlement terms (letter dated
                                13      OS No.39/2013 & OS.145/2013



28.12.2009) have mutually agreed to close the work order

after considering and taking into account all the stocks, camp

accommodation, machineries, advance settlement etc. the

final settlement was arrived and therefore the allegation that

fictitious bills were raised by the defendants is false,

malicious and mischievous. The defendants strongly contend

and dispute the veracity of the calculations and method

adopted in arriving the net debt balance in the books of

accounts of the plaintiff. In fact the plaintiff is due a sum of

Rs.73,73,102/ to the defendants which sum the defendants

had to pay to their creditors. Plaintiff is obliged to pay the

said sum to the defendants as per the agreement at the time

of closing of work orders.   The settlement amount includes

the liability of the defendants to the creditors. This liability

has been taken over by the plaintiff for payment.             For

recovery of the said amount numbers of requests were made

by means of letters, e-mails etc. for which no reply was

received from the plaintiff.        This correspondence      was

produced as documents in case No.145/2013 filed by the

defendants for recovery of the said amount.          On getting
                               14      OS No.39/2013 & OS.145/2013



response from the plaintiff the defendant No.1 has caused a

legal notice dated 7.12.2012 to the plaintiff and its employer.

To the surprise the defendant, the plaintiff instead of

honouring of the commitment has caused a reply notice dated

21.12.2012 making wild allegations and fictitious claims.

     On receipt of the reply legal notice and finding that no

proper response forth coming from the plaintiff the defendant

No.1 has filed a suit on 2.1.2013 in the City Civil Court,

Bangalore for recovery of the said amount of Rs.73,73,102/-.

The plaintiff has not made any claim regarding the suit claim

at any time. It is only in the reply notice dated 21.12.2012 to

the legal notice dated 7.12.2012 caused by the defendants.

     In order to pay to their creditors, the defendants have

accepted another work order No.SSJV/SORANG/WO/2009-

10/01 dated 10.4.2009 regarding roads to job facilities and

roads to project colony works.       As mutually agreed for

adjustment; a sum of Rs.3,15,32,282/- has been adjusted

towards the debit balance of Rs.3,15,32,313/-.       Hence, no

amount is due to the plaintiff by the defendants.             As

submitted in the previous paras the plaintiff in turn is due a
                                  15     OS No.39/2013 & OS.145/2013



sum of Rs.73,73,102/.     On the following grounds based on

legal and material facts the suit deserves dismissal in limine.

        a) The plaintiff's claim is based only on
           mutual agreement letter dated 28.12.2009.
           The claim is not tenable as in the said
           letter at para 4 "It is further agreed that
           they shall not be any claim whatsoever
           nature from either parties in respect of the
           subject work". Hence, there is no cause of
           action for the suit as alleged by the plaintiff
           that   the    cause    of   action   arose   on
           28.12.2009.
        b) There is no demand from the plaintiff for
           the said sum of suit claim (so called due) at
           any time. A reply notice to the legal notice
           caused by the defendant will not create any
           cause of action.
        c) The claim regarding the alleged theft of the
           sand, extra quantity billed or based on
           letters dated 31.3.2008 and 25.2.2009,
           which is included in the suit claim is
           barred by limitation as the suit is filed on
           2.1.2013.
        d) The suit also fails on the ground of non-
           joinder of parties.
                                   16      OS No.39/2013 & OS.145/2013



            e) The plaintiff did not disclose in the plaint
              about the adjustments made with respect
              to the work undertaken by defendants
              against    work   order   No.SSJV/SORANG/
              WO/ 2009-10/01 dated 10.4.2009.
       Hence, prayed to dismiss the suit.



       5.     The plaintiff of OS.145/2013 file the suit for the

recovery of Rs.1,12,69,778/- from the defendants with

interest at 18% per annum from the date of suit till date of

realization, to award costs of the suit and to pass such other

relief's.



       6.     The plaint averments in OS.145/2013 in brief is

that the plaintiff is a Registered Partnership Firm engaged in

the business of execution of Civil Engineering Construction

Work contracts.         The defendants had awarded the work of

"Construction of Barrage and Desilting Chamber Package for

Tapovan Vishnugad Hydro Electric Project" to the plaintiff

dated 22.01.2007.         The defendant has agreed to mobilize

certain vehicles, equipment and machinery on the basis of
                               17      OS No.39/2013 & OS.145/2013



financing the cost of equipment and the same will be treated

as advance in the books of account on recoverable from

plaintiff's running account bills with interest @ 12% p.a. vide

agreement executed on 24.01.2007 by defendant No.2 and

the plaintiff.   Whereas the defendants has also awarded

another work of "Execution of Work of Roads to Job facilities,

roads to project colony and road widening works for SORANG

Hydro Electric Project in the state of Himachal Pradesh. The

defendant and the plaintiff have mutually agreed to close the

work of construction of Barrage & Desilting Chamber package

for Tapovan Vishnugad Hydro Electric Project (4 x 130 MW)

and reduced the same in writing vide letter dated 28.12.2009.

It was agreed to take over the Vehicles, Equipment and

machinery on 'as is where is' basis along with Operators,

Mechanical staff and technical supervisors including some of

the regular technical staff of the plaintiff.      It was also

mutually agreed that defendants shall take over all the

materials like sand, boulders etc. and also the store stock,

complying accommodation of the plaintiff and give due credit

the same. The defendants and the plaintiff have jointly
                                  18       OS No.39/2013 & OS.145/2013



identified the liability to creditors of the plaintiff to the tune of

Rs.73,73,102/- up to 30.06.2009. For the defendant to take

over the same to make the payment and added the said

Rs.73,73,102/- to overall liability of the plaintiff for the above

work order, thus finally arriving at Rs.3,15,33,313/-. As the

defendants have to pay an amount of Rs.3,15,33,282/- to the

plaintiff in respect of works executed under the work order

dated 10.04.2009 for which the defendants has deducted TD

from the gross bills, paid to the credit of central government

and issued TDS certificates also to the plaintiff and while

finalizing the closing of the work order No.SSJV/BNG/2006-

07 dated 22.01.2007, it was mutually agreed by the

defendants and the plaintiff that both the amounts will be set

off against each other. As per the settlement agreement dated

28.12.2009 the defendants has agreed to pay the creditors of

the plaintiff to the tune of Rs.73,73,102/ but failed to honor

its commitment of paying to the creditors.            That as the

pressure from the creditors was mounting the plaintiff had to

undertake another work with L&T JV in the same area and

cleared off the dues on its own.       Thus the defendants has
                              19       OS No.39/2013 & OS.145/2013



become liable to pay the amount of Rs.73,73,102/- to the

plaintiff.     The    work    under      the    Work      Order

No.SSJV/BNG/206-07 dated 22.01.2007 was stopped in the

month of June, 2009 and as plaintiff and the defendants have

mutually agreed to close the work under a settlement

agreement dated 28.12.2009. Inspite of several oral, written

and electronic mail requests by the plaintiff for release of

payment of its legitimate due acknowledgements from both

defendants for having received the legal notice.            The

defendants for once have acknowledged the receipt of the

legal notice and sent a reply notice through their counsel on

21.1.2012. In the said reply notice, the defendant instead of

accepting its liability as agreed vide settlement agreement

dated 28.12.2009, has made untenable, baseless, fictitious

and    imaginary   counter   claims   against    the   plaintiff,

conveniently avoided the mentioning of the due amount of

Rs.3,15,33,282/- to the plaintiff for the work executed under

the work order dated 10.04.2009 for the work of "Execution of

works of Roads to Job facilities, roads to project colony and

road widening works for SORANG Hydro Electric Project in
                                20     OS No.39/2013 & OS.145/2013



the state of Himachal Pradesh' for which TDS has been

deducted from the Bills and paid to the credit of central

government. The plaintiff having not received the due amount

from the amount of Rs.73,73,102/ the defendants has

released the payment nor acknowledge the receipt request

letters.

      i) Letter dated 15.10.2011
      ii) Gentle Reminder letter dated 14.11.2011
      iii) Letter dated 15.10.2012
      iv) Letter dated 05.11.2012
      v) E-mail of letter dated 05.11.2012


      The plaintiff has made several oral requests to the

defendants and always it was assured that the payment will

be released shortly, but so far nothing materialized.      After

observing the continued studied silence from the defendants,

the plaintiff has got issued a legal lawyer's notice on

07.12.2012 demanding release of its legitimate and genuine

due amount of Rs.73,73,102/- along with interest at 18%

from the date of settlement agreement.       The original legal

notice dated 07.12.2012 was sent to both defendants by
                                21         OS No.39/2013 & OS.145/2013



RPAD.     The plaintiff's counsel has received the postal

defendants, preferred this plaint for recovery of its legitimate

and genuine due amount of Rs.73,73,102/- along with

interest at 18% p.a. from the date of settlement agreement i.e.

28.12.2009. The plaintiff felt that no purpose will be served

in giving reply to the said reply legal notice and also keeping

in view the limitation period for filing suit, the plaintiff

preferred not to reply. Hence, prayed to decree the suit.



     7.    Upon service of summons, defendants No.1 and 2

appeared before the court through their counsel and filed

written statement contending that SSJV-ZVS-JV was awarded

the contract by M/s NTPC for the construction of barrage and

distilling chamber package for Tapovan-Vishnugad Hydro

Electric Power Project.    The plaintiffs represented to the

defendants that they have experience and expertise in the

area of construction and induced the defendants to issue a

work order.    The scope of work of the plaintiff included

construction of Barrage and Distilling Chamber package for

Tapovan-Vishnugad     Hydro    Electric     Power    Project   (2   x
                               22      OS No.39/2013 & OS.145/2013



130MW). In furtherance of the work order dated 22.01.2007,

the principal employer SSJV-ZVS-JV issued another work

order dated 22.01.2007 agreeing to fund cost of machinery,

equipment and vehicles etc.     As per clause-2 of the work

order dated 22.01.2007 the plaintiff executed the work strictly

in accordance with the drawings and specifications laid down

in the agreement between SSJV-ZVS and NTPC for the

project.   The plaintiff had to carry out their scope of work

under overall guidance, technical supervision and strictly

with the respect terms and conditions of the contract

agreement the defendant had executed the NPTC was

applicable to the plaintiff in respect of performance of the

work and payments.       The defendant had agreed to pay

mobilization of Rs.100/ lakhs for making of arrangements of

accommodation, labour, transportation of machinery, etc.

and interest at the rate of 12%, which was levied till the said

advance was recovered from the bills.    During the execution

of the work order, SSJV-ZVS-JV vide letter dated 31.03.2008

had brought to the attention of the plaintiff regarding false

reporting and negligence at work site.      SSJV-ZVS-JV had
                                23      OS No.39/2013 & OS.145/2013



informed that the quantity which the plaintiff was excavating

in distilling area was not matching to their actual survey

data, in addition, the staffs of the plaintiff were giving false

reporting on quantity.   During the execution of work order

joint measurement of works with the SSJV-ZVS-JV was

conducted and it was noticed that plaintiff had also raised

fictitious bills as if they had executed the works. This work

encapsulated in the letter dated 31.03.2008.        In addition,

plaintiff during the course of execution of work order, had

illegally shifted sand from the project site of the above

mentioned work order sold the same to the third parties on

many occasions.    The quantity of the said misused by the

plaintiff was to the extent of 2,884 cubic meters and made

money from the illegal shifting of sand. The same was also

brought to the notice of the plaintiff vide letter dated

25.02.2009 sent by SSJV-ZVS-JV.           The defendant had

provided a vehicle and equipment to the plaintiff and further

all running cost, RTO fees, maintenance, etc. were borne by

the defendant itself and this was decided as per the work

order. However, the plaintiff had not paid the vehicle taxes
                                 24     OS No.39/2013 & OS.145/2013



during the course of execution of works.      But as the same

demanded by the concerned RTO and the principal employer,

SSJV-ZVS-JV.     The defendant was constrained to pay the

vehicle tax payment to the RTO.       Inspite of their repeated

requests to complete the work order, the plaintiff expressed

their inability to continue work.    In view of the same, the

principal employer, SSJV-ZVS-JV and the plaintiff was

constrained to pay the vehicle tax payment to the RTO. The

principal employer SSJV-ZVS-JV and also paid part of the

taxes to the RTO.        Inspite of their repeated requests to

complete the work order, the plaintiff expressed their inability

to continue the work.        In view of the same, principal

employer, defendant and the plaintiff mutually agreed to

cancel work order. The plaintiff vide letter dated 15.07.2009

addressed to SSJV-ZVS-JV accepted that they could not

execute the work as per time schedule and handed over the

plant and machinery along with the list of inventories. SSJV-

ZVS-JV acknowledged the receipt of inventories and valuation

of the plaintiff and thereafter the defendant took over the

work of the plaintiff.    As on the date of final settlement of
                                    25      OS No.39/2013 & OS.145/2013



accounts i.e. on 28.12.2009 the plaintiff was due to the

defendant an amount of Rs.3,15,25,313/-. The said amounts

were calculated as the net debit balance in the books of

accounts of the plaintiff as on 28.12.2009.              As per the

averments made in the plaint and the documents referred by

the plaintiff, there seems to approbation and reprobation of

the averments and documents produced. A document dated

23.12.2009 wherein the plaintiff has sought his present case

on the settlement agreement. There is no due of any amount

to the plaintiff from the defendants. It is true to suggest that

defendants had awarded the work of "Construction of Barrage

and Desilting chamber Package for Tapovan Vishnugad Hydro

Electric    Project"   to    the    plaintiff    vide   work     order

No.SSJV/BNG/2006-07 dated 22.01.2007.                   It is true to

suggest that the defendants has also awarded another work

of "Execution of works of works to job facilities, roads to

project colony and road widening works for SORANG Hydro

Electric Project in the state of Himachal Pradesh vide Work

Order No.SSJV/SORANG/2009-10/01 dated 10.04.2009. As

per   the   settlement      agreement    dated     28.12.2009,    the
                                        26        OS No.39/2013 & OS.145/2013



defendants have agreed to pay to the creditors of the plaintiff

to the tune of Rs.73,73,102/ to the plaintiff.                Hence, prayed

to dismiss the suit.



     8.      On the basis of the pleadings of both the parties,

the following issues have been framed in both the suits as

under:

                          OS.39/2013

     1.     Whether      the       plaintiff    proves     that      the
           defendant No.1 is due of Rs.6,05,61,574/-
           towards     the         discharge     of     liability    as
           contended in para No.7 to 19 of the plaint?
     2. Whether the plaintiff is entitled to the reliefs
           sought for?
     3. What decree or order?

                          OS.145/2013

     1.    Whether     the        plaintiff    proves    that,      the
          defendants     had         awarded      the     work       of
          construction       of      Barrage      and      Desilting
          Chamber Package for Tapovan Vishnugad
          Hydro Electro Project" by work order dated
          22.01.2007 and the defendants had agreed to
          mobilize   certain        vehicles,    equipment          and
                          27      OS No.39/2013 & OS.145/2013



  machinery on the basis of financing the cost
  of equipment and the same was to be treated
  as   advance    in   the    books   of   account
  recoverable from plaintiff's running account
  bills with interest at 12% per annum vide
  agreement dated 24.1.2007?

2. Whether the defendants prove that, the
  excavating in distilling area made by the
  plaintiff was not matching with the actual
  survey data and the staff of the plaintiff were
  giving false   report on quantity and the
  plaintiff had illegally shifted sand from the
  project site and had sold it to third parties on
  many occasions and the plaintiff had made
  money out of illegally shifting of 2,884 cubic
  meters of sand?

3. Whether the plaintiff proves that, it was
  agreed that the vehicles, equipment and
  machinery on "as is where is" basis along
  with    operators,   mechanical      staff   and
  technical supervisors was agreed to be taken
  over by the plaintiff and the defendant had to
  take sand boulders etc., and also the store
  stock camping and accommodation of the
  plaintiff and give due credit to the same?
                                    28      OS No.39/2013 & OS.145/2013



      4. Whether the plaintiff is entitled to recover an
           amount     of   Rs.1,12,69,778/-      from    the
           defendants with interest at 18% per annum,
           from the date of suit till realization?
      5. What Decree or Order?




      9.      In OS.39/2013 the Director of Plaintiff Company

examined himself as PW1 and got marked 5 documents at

Ex.P.1 to P.5.      The defendant examined its power of attorney

holder as DW1 and got marked sixteen documents at Ex.D.1

to D.16. After clubbing of both the suits these witnesses and

documents of the plaintiff and defendant are continued as it

is.



      10.     In OS.145/2013 the power of attorney holder of

plaintiff firm examined himself as P.W.1 and got marked

eighteen documents at Exs.P.1 to P.18. After clubbing this

evidence of PW1 is treated as further examination in chief of

DW1 and these Ex.P.1 to 18 are renumbered as Ex.D.6 to

Ex.D.23. The defendant No.1 Company examined its Director

as DW1 and got marked 5 documents at Ex.D.1 to D.5 and
                                29       OS No.39/2013 & OS.145/2013



examined one witness as DW 2. After clubbing this evidence

of DW 1 is treated as further examination in chief of PW1 and

these Ex.D1 to 5 are renumbered as Ex.P.6 to 10 and the

evidence of the DW2 is renumbered as P.W.2.



     11.    Heard the arguments and perused the records of

the case.



     12.    My findings to the above issues in OS              No.

39/2013 are as under:

            Issue No.1 - Partly in the affirmative

            Issue No.2 - Partly in the affirmative

            Issue No.3 - As per the final order, for the following:


     13.    My findings to the above issues in OS No.

145/2013 are as under:

            Issue No.1 - Redundant

            Issue No.2 - Do not arise for consideration

            Issue No.3 - In the negative

            Issue No.4 - In the negative
                               30      OS No.39/2013 & OS.145/2013



           Issue No.5 - As per the final order, for the following



                        REASONS


     14.   ISSUE No.1 of OS.39/2013 and Issue Nos.1 to 3

of OS.145/2013:- Since these issues are interconnected with

each other hence to avoid repetition of facts and evidence they

are taken up together for common discussion.



     15.   The plaintiff of OS.39/2013 and defendant No.1 of

OS.145/2013 are one and the same and for the sake of

convenience in the judgment they will be referred as M/s

SSJV Projects Pvt. Ltd. The defendant No.1 of OS.39/2013

and the plaintiff of OS.145/2013 are one and the same and

for the sake of convenience in the judgment they will be

referred as M/s Sathyanarayana Raju and Co. After clubbing

of both the suits the witnesses and the exhibits are

renumbered as stated supra in Para No. 9 & 10.



     16.   It is admitted fact that the SSJV and ZVS Joint

Venture was awarded the contract by M/s NTPC for the
                                31      OS No.39/2013 & OS.145/2013



construction of 'barrage and desilting Chamber Package for

Tapovan - Vishnugad Hydro Electric Power Project'. It is

admitted fact that the SSJV - ZVS - JV in turn issued work

order for construction of 'barrage and desilting Chamber

Package for Tapovan - Vishnugad Hydro Electric Power

Project' in favour of the M/s Sathyanarayana Raju and

company    with the work orders both are dated 22.01.2007

agreeing to fund the cost of machinery, equipment and

vehicles etc. The Ex.P.1 & 2 shows the same. It is admitted

fact that as per the final settlement of the accounts as per

Ex.P.4 it was mutually agreed by the SSJV - ZVS - JV and

the M/s Sathyanarayana Raju and company to cancel the

work order and the M/s Sathyanarayana Raju and company

was due of Rs.3,15,35,313/ to the plaintiff. It is admitted fact

that the M/s SSJV Projects Pvt. Ltd. awarded another work of

'execution of work' of roads to job facilities, roads to project

colony and road widening works for SORANG Hydro Electric

Project in the state of Himachal Pradesh dated 22.01.2007.

The Ex.D.4 shows the same.
                              32      OS No.39/2013 & OS.145/2013



     17.     As per the M/s SSJV project Pvt. Ltd.       it has

found false reporting and negligence at the work sight and

with malafide intention had billed extra quantities of work,

illegally shifted the sand from project site and the M/s

Sathyanarayana Raju and company had not paid vehicle

taxes during the course of execution of work and inspite of

repeated request to complete the work order, the M/s

Sathyanarayana Raju and company expressed their inability

to continue the work and hence mutually agreed to cancel the

work order as per Ex.P.4. The M/s Sathyanarayana Raju and

company denied the reason for cancellation of work order and

admitted that mutual agreement to cancel the work order.

When both the parties are making their claims on the basis of

Ex.P.4, then for what reason the work order was cancelled

looses importance and hence it is immaterial to decide these

suits why the work orders both dated 22.1.2007 were

cancelled.



     18.     The plaintiff of OS.39/2013 claiming the said

Rs.3,15,35,313/- apart from Rs.36,03,822/- towards the
                               33        OS No.39/2013 & OS.145/2013



extra quantities billed, Rs.21,63,000/- towards sand theft

and   Rs.16,35,019/-    towards     vehicle   taxes   and   in   all

Rs.3,89,37,154/- with interest and the said table containing

those items reads thus:

                      Amount to
                                     Interest on
                      be payable
Sl.                                  the amount
       Particulars       by the                         Total
No.                                   payable @
                       contractor
                                      18% p.a.
                          (Rs).
1     Amount          3,15,35,313    1,68,73,552      4,84,08,865
      payable as
      per the
      settlement
      dated
      28.12.2009
2     Extra            36,03,822       22,43,193       58,52,015
      quantities
      billed
3     Sand theft       21,63,000       14,82,692       36,45,692

4     Vehicle taxes    16,35,019       10,19,983       26,55,002

      Grand Total     3,89,37,154    2,16,24,420      6,05,61,574



      19.   The plaintiff of OS.145/2013 claiming the amount

of Rs.73,73,102/- mentioned in Ex.P.4.
                                 34      OS No.39/2013 & OS.145/2013



     20.    As stated supra as both the plaintiffs claiming the

amount under the Ex.P.4, which is containing of two pages,

which reads thus :

        "The 1st page of Ex.P.4 reads thus:

           Sub:    Closing of the work of construction
                  barrage    and     desilting  chamber
                  package for Tapovan Vishnugad
                  Hydro Electric Projects awarded to you
                  vide work order dated 22.1.2007

        Dear Sir,

            Inspite of our repeated requests, you were not
        able to carry out the work awarded to you as per
        the program. You also expressed your inability to
        continue the work. Therefore, we mutually agreed
        to cancel the above work order on the following
        settlement terms:



            The final settlement of accounts shall be stand as

     follows:

      1)    It has been mutually agreed that the work awarded
            to the contractor shall be taken over the company
            w.e.f. 1.7.2009
      2)    That all the advance, work bills, claims etc. are to
            be accounted for upto 30th June 2009 for settlement
            of accounts.
                              35      OS No.39/2013 & OS.145/2013



   3)    It is agreed that the above amount covers all
         accounts and considerations and shall be treated
         as full and final settlement.
   4)    It is further agreed that there shall not be any claim
         of whatsoever nature from either parties in respect
         of the subject work.
   5)    The applicable TD will be deducted from your
         account for the bills receivable amount.

   The 2nd Page of Ex.P.4 reads thus:

Net debit balance in the books of SSJV         2,54,42,381.00
Projects Pvt. Ltd., before adjustment:

Add: Debit Balance transferred from              80,83,364.00
SSJV ZVS Joint Venture
                               Total           3,35,25,745.00

Less: this debit balance adjusted in the
following terms

c) Store stock of M/s S.S.N. Raju & Co.
   taken over by SSJV                            36,11,040.00

d) Camp accommodation taken over by              57,52,494.00
   SSJV

Net Credit balance                               93,63,534.00

Add: Liability of M/s S.S.N. Raju & Co.          73,73,102.00
as on 30.6.2009 related to project taken
over by SSJV Projects Pvt. Ltd.

Net debit balance in the books of SSJV         3,15,35,313.00
Projects Pvt. Ltd.

  For SSJV Projects Pvt. Ltd.,
  Sd/-
                                    36      OS No.39/2013 & OS.145/2013



       Authorized Signatory

       Accepted
       Sd/-
       M/s S.Sathyanarayana Raju & Co."


       21.    M/s Satyanarayana Raju and company in Para

No.12 of the written statement half heartedly          disputed the

Ex.P.4       as the veracity     of calculations and the method

adopted in arriving the net debt balance in the books of

accounts and it has not explained how the calculations and

method in preparing the Ex.P.4           is wrong and what is the

correct calculation.       So also during the course of cross

examination of        PW 1 it is not even suggested that the

veracity of calculations and the method adopted in arriving

the net debt balance is wrong and what is the correct

calculation. So in the circumstances it has to be held that

both the parties admit         the Ex.P.4. According to this there

was full and final settlement of the amount payable by the

M/s Sathyanarayana Raju and Co. to the M/s SSJV Projects

Pvt.   Ltd.     is   Rs.3,15,35,313/-.    With    respect   to   this

Rs.3,15,35,313/- is also concerned M/s Sathyanarayana
                                        37      OS No.39/2013 & OS.145/2013



Raju and Co. took contention since the M/s SSJV Projects

Pvt. Ltd. was due of Rs.3,15,35,313/-              to them with respect

to SORANG Hydro Electric Project and the same was adjusted

before     filing    of   these   suits.    This   contention    of   M/s

Sathyanarayana Raju and Co. shows that they have admitted

the claim of Rs.3,15,35,313/- made by the M/s SSJV Projects

Pvt. Ltd. This makes it very clear that M/s Sathyanarayana

Raju and Co. was liable to pay Rs.3,15,35,313/- to M/s SSJV

Projects Pvt. Ltd. with respect to the Ex.P.4.          Further, in this

regard M/s Sathyanarayana Raju and Co. produced Ex.D.5 to

D.8     which are RA Bill No.1 dated 30.5.2009, RA Bill No.2

dated      30.6.2009      and     RA    Bill   No.3   dated     31.7.2009

respectively        in all totally amounting to Rs.3,15,35,313/-,

which are with respect to the work order pertaining to

No.SSJV/SORANG/WO/2009-10/01. The M/s SSJV Project

Pvt. Ltd. admits the raising of bills by M/s Sathyanarayana

Raju and Co. with respect to the SORANG Project but it

disputes the liability of them with respect to the SORANG

Project.    If this amount is adjusted towards the amount of

Rs.3,15,35,313/- in Ex.P.4 then there will be correspondence
                                      38        OS No.39/2013 & OS.145/2013



between      the   M/S        SSJV   Project    Pvt.   Ltd.   and    M/s

Sathyanarayana        Raju     and Co. and definitely there will be

document with regard to the adjustment. No scrap of paper

is produced in order to show there was adjustment of

amount.       Hence      it     cannot    said      the    amount       of

Rs.3,15,35,313/- pertaining to SORANG Project was adjusted

towards the amount of           Rs.3,15,35,313/-       due by the M/s

Sathyanarayana Raju and Co. with                regard to the Tapovan

Vishnugad Project.


       22.   The learned Advocate appearing for the M/s

Sathyanarayana Raju and Co. vehemently argued and filed

the written arguments contending that since in Clause 4 of

Ex.P.4 it is stated that there shall not be any claim

whatsoever nature from either parties in respect of the

subject work and it was agreed that M/s SSJV Projects Pvt.

Ltd has agreed to taken vehicles, equipment and machinery

on "as is where is'' and        hence no amount is payable by M/s

Sathyanarayana Raju and Co. to the M/s SSJV Projects Pvt.

Ltd.
                                   39      OS No.39/2013 & OS.145/2013




       23.    With respect to the arguments of learned Advocate

for M/s Sathyanarayana Raju and Co. is concerned the

Ex.P.4, which is containing two pages has to be read together

and not each page separately. Taking into consideration of

the entire Ex.P.4 it can be made out that except payment of

Rs.3,15,35,313/- to be        paid by the M/s Sathyanarayana

Raju    and    Co.   no   any    amount    is   payable    by   M/s

Sathyanarayana Raju and Co. to M/s SSJV Projects Pvt. Ltd

and there is no such clause till Ex.P.4 the M/s SSJV Projects

Pvt. Ltd agreed to take vehicles, equipment and machinery

on "as is where is'' basis.


       24.    The learned       Advocate for appearing for the

Sathyanarayana Raju and Co. relied on the ruling reported

in AIR 1997 DELHI 355(Cofex Exports Ltd V/s Canara Bank)

wherein it is held that the defendant can plead adjustment

prior to the filing of the written statement and also relied

another ruling reported in AIR 1963 Punjab 479(Amarnath

V/s Produce Exchange Corporation Ltd., Calcutta.), wherein

it is held that two separate accounts being between the same
                                   40     OS No.39/2013 & OS.145/2013



parties in the same right could be set off or adjusted against

each other. As stated above though the M/s Sathyanarayana

Raju and company pleaded adjustment of Rs.3,15,35,313/-

before filing of the suit, but the same is not proved. Hence

these rulings are not helpful to the case of the M/s

Sathyanarayana Raju and Co.



     25.   Now,   it   is   to    be   seen   whether    the   M/s

Sathyanarayana Raju and Co. is liable to pay Rs.36,03,822/-

towards the extra quantities billed, Rs.21,63,000/- towards

sand theft and Rs.16,35,019/- towards vehicle taxes and in

all Rs.3,89,37,154/- with interest. The Ex.P.3, which is the

letter dated 15.7.2009 shows that the M/s Sathyanarayana

Raju and Co. handed over the plant and machinery to M/s

SSJV Projects Pvt. Ltd.          The Ex.P.5 is the letter dated

25.02.2009, which shows that the SSJV - ZVS- Joint Venture

written letter to the M/s Sathyanarayana Raju and Co.

regarding unauthorizing selling of sand from the Barrage site.

So, Ex.P.3 and P.5 are before entering into Ex.P.4. Hence, it

has to be held that taking into consideration of the return of
                                41      OS No.39/2013 & OS.145/2013



plan and machinery, unauthorised selling of sand and also

the vehicle taxes etc. the Ex.P.4 was entered between M/s

SSJV Projects Pvt. Ltd. and M/s Sathyanarayana Raju and

Co. If the M/s Sathyanarayana Raju and Co. is liable to pay

any amount with respect to the extra quantities billed, sand

theft and vehicles taxes, then the same would have been

mentioned in Ex.P.4. Hence, the M/s Sathyanarayana Raju

and Co. is not liable to pay the amount of Rs.36,03,822/-

towards the extra quantities billed, Rs.21,63,000/- towards

sand theft and Rs.16,35,019/- towards vehicle taxes and in

all Rs.3,89,37,154/- with interest to the M/s SSJV Projects

Pvt. Ltd.



      26.   As stated above M/s Sathyanarayana Raju and

Co. in OS.145/2013 claims Rs.73,73,102/- from SSJV

Projects Pvt. Ltd. stating that it has paid the said amount to

the creditors of M/s SSJV Projects and hence the SSJV

Projects Pvt. Ltd. is liable to pay the said amount. Firstly M/s

Sathyanarayana Raju and Co. relying on the Ex.P.4 claiming

that the SSJV Project Pvt. Ltd. is liable to pay Rs.73,73,102/-.
                                42      OS No.39/2013 & OS.145/2013



The Ex.D.9 is the list of sundry creditors, which shows the

amount of Rs.73,73,102/-.       Ex.D.10 is the list of sundry

creditors taken over by the SSJV Projects payment made. In

this regard the DW 1 deposed in his cross-examination as the

Ex.D.9 is not in the letter head of the company and it do not

contain the seal of the company and the Ex.D.10 is not

verified by the auditor and Ex.D.10 is not signed by M/s

SSJV Projects Pvt. Ltd. Ex.P.6(b) is said to be the signature of

the person on behalf of the SSJV Projects Pvt. Ltd. Ex.D.11

to D.14 are the letters of M/s Sathyanarayana Raju and Co.

dated 15.10.2011, 14.11.2011, 15.10.2012 and 05.11.2012

respectively calling upon the M/s SSJV Projects Pvt. Ltd. to

pay the amount of Rs.73,73,102/-. The Ex.D.15 - office copy

of   legal   notice   dated   07.12.2012    shows    that    M/s

Sathyanarayana Raju and Co. got issued legal notice through

their counsel calling upon the M/s SSJV Project Pvt. Ltd. to

pay the amount of Rs.73,73,102/-.          Ex.D.16 is the reply

given by M/s SSJV Projects Pvt. Ltd. dated 21.12.2012

denying the claim of Rs.73,73,102/- and contended that it is

the obligation and liability of the M/s Sathyanarayana Raju
                                      43              OS No.39/2013 & OS.145/2013



and Co. to the M/s SSJV Projects Pvt. Ltd. under the Ex.P.4.

In this regard, the said Srinivasa Rao deposed in the cross-

examination that he has also not produced the bills

pertaining to sundry creditors and he has not produced any

bills raised on the SSJV Projects Pvt. Ltd. pertaining to the

sundry creditors.        M/s Sathyanarayana Raju and Co. by

admitting Ex.P.4 admits the due of Rs.73,73,102/- to M/s

SSJV Projects Pvt. Ltd. M/s Sathyanarayana Raju and Co.

contending      that   the    amount           of     Rs.3,15,35,313/-       was

adjusted also shows the liability of it to pay the amount of

Rs.73,73,102/-. If really M/s SSJV Projects Pvt. Ltd. is liable

to pay the amount of Rs.73,73,102/-, then definitely the same

would    have     been       shown        in        Ex.P.4.    So,     the   M/s

Sathyanarayana Raju and Co. has not placed any acceptable

and cogent evidence to show that M/s SSJV Projects Pvt. Ltd.

is liable to pay Rs.73,73,102/- to it.



      27.    So, from the discussions made above, I am of the

opinion that M/s SSJV Project Pvt. Ltd. proved that                          M/s

Sathyanarayana         Raju     and        Co.         is     liable    to   pay
                                44      OS No.39/2013 & OS.145/2013



Rs.3,15,35,313/- to     it and failed to prove        that M/s

Satyanarayana Raju and Co. is liable to pay the remaining

amount of Rs.74,01,841/-. Since the M/s SSJV Projects Pvt.

Ltd. admits the awarding work of construction of Barrage and

Desilting Chamber Package for Tapovan Vishnugad Hydro

Electro Project" by work order dated 22.01.2007 and the

defendants had agreed to mobilize certain vehicles, equipment

and machinery on the basis of financing the cost of

equipment and the same was to be treated as advance in the

books of account recoverable from plaintiff's running account

bills with interest at 12% per annum vide agreement dated

24.1.2007   and hence the issue No.1 of OS.145/2013             is

answered as redundant and when the M/s SSJV Projects Pvt.

Ltd. and Sathyanarayana Raju and Co. entered into full and

final settlement as per Ex.P.4, then question of considering

that excavating in distilling area made by the plaintiff was not

matching with the actual survey data and the staff of the

plaintiff were giving false report on quantity and the plaintiff

had illegally shifted sand from the project site and had sold it

to third parties on many occasions and the plaintiff had made
                                  45     OS No.39/2013 & OS.145/2013



money out of illegally shifting of 2,884 cubic meters of sand

do not survive for consideration and M/s Sathyanarayana

Raju and Co. failed to prove that it was agreed that the

vehicles, equipment and machinery on "as is where is" basis

along    with   operators,   mechanical       staff   and    technical

supervisors was agreed to be taken over by it and the M/s

SSJV Project Pvt. Ltd. had to take sand boulders etc., and

also the store stock camping and accommodation of it and

give due credit to the same. Hence, Issue No.1 of OS.39/2013

is answered partly in the affirmative and Issue No.1 of

OS.145/2013 is answered as redundant and Issue No.2 of

OS.145/2013 is answered as do not arise for consideration

and Issue No.3 of OS.145/2013 is answered in the negative.



        28.   ISSUE No.2 of O.S. 39/2013 and ISSUE No.4 of

O.S. 145/2013: The Advocate for M/s Sathyanarayana Raju

and     Co.   submitted   that   admittedly     the   said   Tapovan

Vishnugad Project was granted by the NTPC to the SSJV &

ZVS Joint Venture, but this suit is only filed by the SSJV.

Hence, the suit is not maintainable.          Admittedly the NTPC
                                46      OS No.39/2013 & OS.145/2013



given the project to M/s SSJV Projects and ZVS Joint

Venture. The OS.39/2013 is for recovery of money. Hence, I

am of the opinion that the M/s SJV Projects Pvt. Ltd. can

maintain the suit against M/s Sathyanarayana Raju and Co.



     29.   The learned Advocate appearing for the M/s SSJV

Projects Pvt. Ltd. argued that it is came in the cross-

examination of DW1 that Sri.S.Sathyanarayana Raju, who is

the Managing Partner of M/s Sathyanarayana Raju and Co.

has got no obstacles to come to the Court and to give

evidence. But, M/s Sathyanarayana Raju and Co. examined

its power of attorney holder by name K.S.Srinivas Rao as

DW1, who cannot depose on behalf of M/s Sathyanarayana

Raju and Co. as he has no personal knowledge.



     30.   The learned Advocate appearing for the M/s SSJV

Projects Pvt. Ltd. has relied on the rulings reported in 2005(2)

SCC 217 (Janaki Vashdeo Bhojvani and another V/s

Indusind Bank Ltd. and others), 1986(2) WLN 713(Rajasthan

Shamboo dutt Shastri V/s State of Rajastan.), AIR 1988
                                47      OS No.39/2013 & OS.145/2013



Rajasthan      185(Ramprasad         V/s      Hari       Narain),

WP.No.20298/2014 (Nagarathnamurthy V/s S.Narayanappa

and others), Civil Appeal No.147-148 of 2001         (Man Kaur

dead by LRs V/s Hartar Singh Sangha and        Criminal Appeal

No.763 of 2007 (Omprakash V/s L.Sunitha and others).



     31.    The learned Advocate appearing for the M/s

Sathyanarayana Raju and Co. relied on the ruling reported in

AIR 2006 KAR 231 (Bhimappa and others V/s Allisab and

others), ILR 2015 KAR 635 (Sajedabanu V/s Alimabanu and

others) and ILR 2014 KAR 84 (R.Narasimha V/s S.P.Sridhar).



     32.    I have gone through the above rulings relied by

both the counsels with regard to the right of power of attorney

holder to depose on behalf of the party. In this regard, I would

like to rely on the ruling reported in 2005 KAR 4370(Kajudevi

and another V/s H.S.Rudrappa @ Rudy and others), wherein

his lordship held that the decision in the case of Janaki

Vashdeo Bhojwani cannot be accepted as binding precedent

or obiter-dicta in the facts and circumstances of the case. In
                                    48           OS No.39/2013 & OS.145/2013



the above said ruling reported in AIR 2006 KAR 231, wherein

it is held as under:

         "B)   Evidence     Act     (1     of     1872),    S.61
         Documentary evidence - Suit for declaration
         of title and possession - Tile of plaintiff
         required to be established by production of
         documentary evidence - Said evidence can
         be adduced by party or by his power of
         attorney holder - Evidence of a power of
         attorney holder can prove case of plaintiff.
               In a suit for declaration of title, the
         plaintiff has to establish his title.              Title
         cannot be established by his personal
         knowledge. It has to be established by
         producing documents under which he is
         claiming title, most of the time under a
         registered document. Insofar as documents
         are concerned S.61 of the Evidence Act
         mandates that the contents of documents
         may    be     proved     either    by     primary    or
         secondary      evidence.          Primary     evidence
         means the documentary evidence produced
         for inspection of the Court. Therefore, when
         a particular fact is to be established by
         production of documentary evidence there is
         no scope for leading oral evidence and there
                                  49       OS No.39/2013 & OS.145/2013



           is no scope for personal knowledge. What is
           to be produced is the primary evidence i.e.
           document itself. The said evidence can be
           adduced by the party or by his power of
           attorney holder. Production of the document,
           marking of the document is a physical act
           which    does   not    need    any       personal
           knowledge. Even proof of the document is
           by examining the persons who are well
           versed with the document or by examining
           the attesting witnesses or the executants of
           the document. Again the personal knowledge
           of the plaintiff has no role to play. In those
           circumstances it is open to the plaintiff to
           examine the power of          attorney    holder,
           produce the documents through the power of
           attorney holder, mark the same and examine
           witnesses to prove the said document if it is
           denied. Therefore, the contention that the
           evidence of a power of attorney holder can
           prove the case of the plaintiff in all cases is
           not correct."



     33.     From the above said rulings it is clear that their

lordships held that the power of attorney holder has got right
                               50     OS No.39/2013 & OS.145/2013



to give evidence on behalf of the party and if the power of

attorney holder does not have the personal knowledge about

the facts of the case, then his evidence cannot be accepted.

In the facts and circumstances of the case, the oral evidence

of power of attorney holder is formal one and the case can be

made out on the basis of the documents produced by both

the parties. Hence, the evidence of the said K.Srinivas Rao on

behalf of M/s Sathyanarayana Raju and Co. will no way effect

its case.



      34.   The learned Advocate appearing for M/s SSJV

Projects Pvt. Ltd. submits that the M/s Sathyanarayana Raju

and Co. represented by Sri.S.Sathyanarayana Raju filed

OS.No.145/2013 through his power of attorney holder

Sri.K.Srinivas Rao and the said K.Srinivas Rao deposed in

both the suits, but the M/s Sathyanarayana Raju and Co.

has not produced reconstituted partnership deed under

which the said Sathyanarayana Raju has got right to file

OS.No.145/2013 and authorized the said K.Srinivas Rao in

both the suits. M/s Sathyanarayana Raju and Co. in
                                     51        OS No.39/2013 & OS.145/2013



OS.39/2013 produced Ex.D.1, which is power of attorney,

which     shows      that    the   partners      by      name     Sagiraju

Sathyanarayana Raju and Sagiraju Seetharamraju authorized

said    K.Srinivas    Rao     to   depose     before     the    Court.   In

OS.145/2013 M/s Sathyanarayana Raju and Co. produced

Ex.D.17,     which     is     power      of   attorney     executed      by

S.Sathyanarayana Raju in favour of said K.Srinivas Rao to

depose in this suit.        The M/s SSJV Projects Pvt. Ltd. do not

dispute that M/s Sathyanarayana Raju and Co. is not a

registered partnership. Such being the case it goes without

saying that the one of the partner of M/s Sathyanarayana

Raju has got authority to file the suit and authorize the said

Srinivas Rao to depose before this court.



       35.   The learned Advocate appearing for the M/s

Sathyanarayana Raju and Co. relied on the ruling reported in

ILR 1992 KAR (Shivananjappa V/s Maralasiddappa and

Sons), wherein it is held that the suit filed by only one partner

in the name of the firm is maintainable. The OS.145/2013
                                   52      OS No.39/2013 & OS.145/2013



filed by Sagiraju Sathyanarayana Raju, who is the partner of

M/s Sathyanarayana Raju and Co. is maintainable.



     36.    In   view   of   my    findings   on    Issue   No.1   of

OS.39/2013 and issue No.1 to 3 of OS.145/2013 the plaintiff

of OS.No.39/2013 is entitled for the reliefs partly and the

plaintiff of OS.145/2013 is not entitled for the reliefs. Hence,

Issue No.2 of OS.39/2013 is answered partly in the

affirmative and Issue No.4 of OS.145/2013 is answered in the

negative.



     37.    ISSUE NO.3 of O.S. 39/2013 and Issue No.5

O.S.145/2013:- In the result, I proceed to pass the following:

                             ORDER

OS.39/2013 is partly decreed with costs. The defendants of OS.39/2013 are liable to pay Rs.3,15,35,313/- to the plaintiff with interest at the rate of 18% p.a. from the date of suit till the date of realization. 53 OS No.39/2013 & OS.145/2013

The suit of the plaintiff of OS.39/2013 with respect to the remaining amount of Rs.74,01,841/- is dismissed.

OS.145/2013 is dismissed with costs. Draw decree accordingly.

The original judgment has to be kept in OS.39/2013 and the copy of the same has to be kept in OS.145/2013.

(Dictated to the judgment writer directly on the computer, thereof, is corrected and then pronounced by me in the open court, on this the 10th day of April 2017).

( BASAVARAJ ) XLI ADDL.CITY CIVIL JUDGE BANGALORE ANNEXURE I. List of witnesses examined on behalf of plaintiff of OS.39/2013 and defendants of OS.145/2013:

P.W.1 Somashekhar Salimath P.W.2 Dayanand.K II. List of witnesses examined on behalf of defendant of OS.39/2013 and plaintiff of OS.145/2013:
D.W.1 K.Sreenivasa Rao 54 OS No.39/2013 & OS.145/2013 III. List of documents exhibited on behalf of plaintiff of OS.39/2013 and defendants of OS.145/2013:
Ex.P.1 C/c of work order dt.22.1.2007 Ex.P.2 C/c of another work order dt.22.1.2007 Ex.P.3 C/c of letter dt.15.7.2009 Ex.P.4 C/c of letter dt.28.12.2009 Ex.P.5 Another c/c of letter dt.25.2.2009 Ex.P.6 Power of Attorney Ex.P.7 Work order given by the defendant to the plaintiff Ex.P.8 Another agreement for procuring the machineries for the construction work Ex.P.9 Work order dated 10.04.2009 Ex.P.10 Settlement deed dated 28.12.2009 Ex.P.11 List of creditors of the plaintiff Ex.P.11(a) Signatures of the plaintiff and & (b) defendant Ex.P.12 to Office copies of original bills with 14 respect of 3rd work orders Ex.P.15 Office copy of the list of creditors to whom we have paid out of pocket Ex.P.16 Office copy of demand dated 55 OS No.39/2013 & OS.145/2013 05.11.2012 Ex.P.17 Another office copy of demand letter sent to the defendant dated 05.10.2012 Ex.P.18 Another office copy of demand letter sent to the defendant dated 15.11.2011 Ex.P.19 Another office copy of demand letter sent to the defendant dated 14.11.2011 Ex.P.20 Office copy of legal notice issued to the defendant Ex.P.21 & Two Postal acknowledgements 22 Ex.P.23 Reply given by the defendants dated 21.12.2012 IV. List of documents exhibited on behalf of defendant of OS.39/2013 and plaintiff of OS.145/2013:
Ex.D.1 Power of attorney dt.6.9.2013 Ex.D.2 Work order dt.22.1.2007 Ex.D.3 Work order dated 24.1.2007 Ex.D.4 Work order dt.10.4.2009 Ex.D.5 to 7 C/c of RA bills Ex.D.8 C/c of grant dt.28.12.2009 Ex.D.9 List of sundry creditors 56 OS No.39/2013 & OS.145/2013 E x.D.10 Payments made to sundry creditors Ex.D.11 to Letter to plaintiff requesting for 14 payment of suit claim in OS.145/2013 Ex.D.15 Legal notice dt.7.12.2012 Ex.D.16 Reply legal notice by plaintiff Ex.D.17 Office copy of work order dated 22.01.2007 Ex.D.18 Original additional work order dated 22.01.2007 Ex.D.19 Letter received from the plaintiff dated 15.07.2009 Ex.D.20 Original final settlement of accounts dated 28.12.2009 Ex.D.21 Office copy of the letter dated 25.02.2009 XLI ADDL.CITY CIVIL JUDGE BANGALORE 57 OS No.39/2013 & OS.145/2013