Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 1, Cited by 0]

Kerala High Court

J.J. Agencies (P) Ltd vs The Kerala State Electricity Board on 15 March, 2012

Author: B.P.Ray

Bench: B.P.Ray

       

  

  

 
 
                   IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                        PRESENT:

                        THE HONOURABLE MR.JUSTICE B.P.RAY

      THURSDAY, THE 15TH DAY OF MARCH 2012/25TH PHALGUNA 1933

                                WP(C).No. 27641 of 2006 (N)
                                   ---------------------------

    PETITIONER(S):
    ------------------------

       J.J. AGENCIES (P) LTD.,
       HOTEL GAYATHRI INTERNATIONAL, ARAYEDATHUPALAM,
       MAVOOR ROAD, CALICUT-4, REPRESENTED BY ITS
       DIRECTOR A.M.GOPALAN, S/O. CHATHU.

       BY ADVS.SRI.K.S.BABU
                    SMT.SUDHA
                    SRI.P.PRIJITH
                    SRI.BINU B.SAMUEL
                    SMT.C.SEENA

    RESPONDENT(S):
    ---------------------------

    1. THE KERALA STATE ELECTRICITY BOARD,
        REPRESENTED BY ITS SECRETEARY, VYDHYUTHI BHAVAN,
        PATTOM, TRIVANDRUM.

    2. THE ASSISTANT ENGINEER,
        ELECTRICAL SECTION, POTTAMMEL, KOZHIKODE.

    3. THE SENIOR SUPERINTENDENT,
        ELECTRICAL MAJOR SECTION, POTTAMMEL, KOZHIKODE.

    4. THE EXECUTIVE ENGINEER,
        KERALA STATE ELECTRICITY BOARD (POTTAMMEL),
        VYDHYUTHI BHAVAN, GANDHI ROAD, KOZHIKODE.

       BY ADV. SMT.P.K.RADHIKA, SC, KSEB
       BY ADV. SRI.JOSE J.MATHEIKEL, SC, KSEB


     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
    15-03-2012, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

Kss

WPC.NO.27641/2006 N


                                     APPENDIX


PETITIONER'S EXHIBITS:


P1:   COPY OF THE DEMAND NOTICE-CUM-DISCONNECTION NOTICE UNDER
      SECTION 24 (1) OF THE INDIAN ELECTRICITY ACT.


P2:   COPY OF THE COMMUNICATION ISSUED FROM THE REGIONAL AUDIT
      OFFICE OF THE 1ST RESPONDENT DTD. 27/07/06.


P3:   COPY OF THE LETTER SUBMITTED BY THE PETITIONER BEFORE THE
      4TH RESPONDENT DTD. 5/10/06.




RESPONDENT'S EXHIBITS:               N I L




                                                     /TRUE COPY/




                                                     P.A.TO JUDGE

Kss



                                      B.P.RAY, J.
                - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
                          W.P.(C)No.27641 OF 2006
                - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
                Dated this the 15th day of March, 2012

                                     JUDGMENT

Petitioner has filed this writ petition with the following prayers:

(a) issue a writ of certiorari or other appropraite writ, order or direction to call for the records leading to Ext.P1 and quash the same as it is illegal and unsustainable.
(b) declare that the demand made under Ext.P1 is illegal and unsustainable.

2. Heard the learned counsel for the petitioner and the learned Standing Counsel appearing for the Kerala State Electricity Board.

3. The issue involved in this case is squarely covered by the decision in Executive Engineer and another v. Sitaram Rice Mill reported in (2010 (4) KHC 1) wherein the Apex Court in paragraphs 44 and 46 held as follows:

"44. Minimum energy charges are to be levied with reference to 'contract demand' at the rate prescribed under the terms and conditions. These clauses of the agreement clearly show that the charges for consumption of electricity are directly relatable to the sanctioned/connected load and also the load consumed at a given point of time if it is in excess of the sanctioned/connected load. The respondent could consume electricity upto 110 KVA but if the connected load exceeded that higher limit, the category of the respondent itself could stand changed from 'medium industry' which will be governed by a higher tariff.
45. xxxxx
46. On the cumulative reading of the terms and conditions of supply, the contract executed between the parties and the W.P.(C)No.27641 OF 2006 :: 2 ::
provisions of the 2003 Act, we have no hesitation in holding that consumption of electricity in excess of the sanctioned/connected load shall be an 'unauthorised use' of electricity in terms of Section 126 of the 2003 Act. This, we also say for the reason that overdrawal of electricity amounts to breach of the terms and conditions of the contract and the statutory conditions, besides such overdrawal being prejudicial to the public at large, as it is likely to throw out of gear the entire supply system, undermining its efficiency, efficacy and even increasing voltage fluctuations. In somewhat similar circumstances, where the consumer had been found to be drawing electricity in excess of contracted load and the general conditions of supply of electricity energy by the Board and Clause 31(f) of the same empowered the Board to disconnect supply and even levy higher charges as per the tariff applicable, this Court held that such higher tariff charges could be recovered. While noticing the prejudice caused, the Court in the case Bhilari Rerollers and others v. M.P.Electricity Board and others (2003 KHC 1521 : 2003 (7) SCC 185 : JT 2003 (7) SC
215), held as under:
"21. The respondent Board, therefore, is entitled to raise the demand under challenge since such right has been specifically provided for and is part of the conditions for supply and particularly when such drawal of extra load in excess of the contracted load is bound to throw out of gear the entire supply system undermining its efficiency, efficacy not only causing stress on the installations of the Board but considerably affect other consumers who will experience voltage fluctuations. Consequently, we see no merit in the challenge made on behalf of the appellants. The appeals, therefore, fail and shall stand dismissed but with no costs."

4. In that view of the authoritative pronouncement of the Apex Court, I set aside the order of the assessing authority as well as the appellate authority and remit the matter to the assessing officer to dispose W.P.(C)No.27641 OF 2006 :: 3 ::

of the same in accordance with the judgment referred above. Learned counsel for the petitioner submits that no penalty can be levied under Section 126 of the Electricity Act, 2003. The assessing authority, while considering the matter, shall take into consideration all the observations of the State Electricity Regulatory Commission in D.P.75/2009 dated 19.1.2010 and the judgment of the Apex Court and decide the question afresh after giving the petitioner an opportunity of being heard. The entire exercise shall be completed within a period of two months from the date of receipt of a copy of this judgment subject to the condition that, as agreed, the petitioner deposits 50% of the demand within one month. Since, it is submitted that the petitioner has paid more than 50% of the demand, no further amount need be paid. In order to avoid delay, let the petitioner appear before the authority along with a copy of this judgment on 23.4.2012. It is open to the petitioner to raise all relevant points before the assessing authority, if so advised.

Writ petition is disposed of as above.

B.P.RAY, JUDGE jes