Bombay High Court
Disha Constructions vs Lok Constructions And 5 Ors on 22 April, 2019
Author: G.S. Patel
Bench: G.S. Patel
41-CHSCD1130-18+.DOC
Shephali
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
CHAMBER SUMMONS NO. 1130 OF 2018
IN
COMM EXECUTION APPLICATION NO. 1341 OF 2018
Disha Constructions ...Applicant
Versus
Lok Constructions & Ors ...Respondents
Mr Karl Tamboly, with Ms Swapna Roopwate, i/b Tushar Goradia, for the Applicant.
Ms Kajal Solanki, i/b Divya Shah Associates, for the Respondents.
CORAM: G.S. PATEL, J
DATED: 22nd April 2019
PC:-
1. An Affidavit of Disclosure by some of the Respondents has only just been served on the Applicant. The affidavit is to be filed in the Registry. Mr Tamboly for the Applicant will need time to take instructions. A response Affidavit by the Applicant is to be filed and served on or before 7th June 2019.
Page 1 of 222nd April 2019 ::: Uploaded on - 23/04/2019 ::: Downloaded on - 24/04/2019 02:01:22 ::: 41-CHSCD1130-18+.DOC
2. Respondent No. 4 was out of town. She is the mother of some of the individual Respondents. Time to file her Disclosure Affidavit is extended by one week from today.
3. List the matter on 17th June 2019.
4. Previous orders to continue until the next date.
(G. S. PATEL, J) Page 2 of 2 22nd April 2019 ::: Uploaded on - 23/04/2019 ::: Downloaded on - 24/04/2019 02:01:22 :::