Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 13, Cited by 2]

National Green Tribunal

Ajay Jayvatrao Bhosale vs Union Of India Through The Secretary on 1 December, 2022

Item No. 4                                                   (Pune Bench)

                BEFORE THE NATIONAL GREEN TRIBUNAL
                    WESTERN ZONE BENCH, PUNE

                          (By Video Conferencing)

                    Original Application No. 63/2019(WZ)
                   (I.A. No. 100/2019 & I.A. No. 86/2021)


Mr. Ajay Jayvantrao Bhosale
                                                                  .....Applicant
                                    Versus

Union of India through MoEF&CC & Ors.
                                                              ....Respondent(s)
Date of hearing:   01.12.2022

CORAM: HON'BLE MR. JUSTICE DINESH KUMAR SINGH, JUDICIAL MEMBER
       HON'BLE DR. VIJAY KULKARNI, EXPERT MEMBER


Applicant          :     Mr. Nitin Lonkar, Advocate
Respondent(s)      :     Ms. Manasi Joshi, Advocate for R-1, 6 & 7
                         Mr. Aniruddha Kulkarni, Advocate for R-3 to 5
                         Mr. S. Swaminathan, Advocate for R-8 & 9/PCMC
                         Mr. Saket Mone along-with Mr. Abhishek Salian,
                         Advocates for R-11/PP


                                  ORDER

1. Today this matter is listed on the issue of limitation against which objection has been filed by the learned Counsel for the Applicant.

2. Heard the arguments of learned Counsel for the Applicant Mr. Nitin Lonkar and learned Counsel for Respondent No. 11/Project Proponent- Mr. Saket Mone along-with learned Counsel Mr. Abhishek Salian. I.A. No. 86/2021(WZ)

3. This I.A. has been filed by the Respondent No. 11/Project Proponent (PP), praying for dismissal of the Original Application No. 63/2019(WZ). The main ground which has been set up in this application is that Original Application is time barred, therefore, it requires to be dismissed at the threshold itself. The core issue raised by the Applicant is Page 1 of 10 that the Respondent No. 11 did not obtain prior Environmental Clearance (EC) with respect to the project in question.

4. As per the Project Proponent (PP), he commenced the construction and excavation in the year, 2012, therefore, the cause of action in respect of the alleged construction first arose in the year, 2012 which is well over 07 years from the date of the filing of the present Original Application.

5. The Sections 14 and 15 of the National Green Tribunal Act, 2010 provide for 06 months from the date when the cause of action first arose within which the Original Application ought to have filed. Therefore, if the 06 months period is calculated from the year 2012, it would expire in the year 2013 and as regards Section 15, it provides for 05 years period from the date of cause of action first arose, which too would expire in the year, 2017, while the Original Application has been filed on 14.08.2019.

6. The learned Counsel for the Respondent No. 11 has drawn our attention to para no. 40 of the main petition, where-in it is stated by the Applicant that the Project Proponent carried out illegal construction on 0 sq. mtrs. to 18500 sq. mtrs. vide sanction dated 24.11.2016.

7. As per the Applicant in O.A., the Project Proponent had intention to go on beyond 36,500 sq. mtrs. vide sanction dated 31.03.2018. The civil construction activity is recurring process. The Project Proponent/Respondent No. 11 has increased the project capacity from 0 sq. mtrs to 18500 sq. mtrs. from 2011 to 19.05.2018, therefore, it is nothing but a recurring cause of action for building construction activity.

8. The Applicant in Original Application had obtained information through online search and under RTI Act from 2017 to 18.05.2018 and thereafter had sent legal notice through Counsel to the Respondents inviting their attention towards the violations committed by the Project Page 2 of 10 Proponent. Therefore, the cause of action first arose on 15.06.2019 when SEIAA issued a Show Cause Notice to the Project Proponent.

9. Therefore, 06 months period from 15.06.2019 should be counted, which would end on 14.12.2019, while the present application has been filed on 14.08.2019, therefore, it is within time.

10. As per Respondent No. 11/Project Proponent (PP), the above contention of the Applicant in Original Application is absolutely false because the Applicant is trying to establish the date 19.05.2019 as the date, when the first cause of action arose on the basis of his having obtained information under RTI. It is further argued by the learned Counsel for the Respondent No. 11 that any person may move an RTI application on a particular date of his choice in order to create cause of action so as to bring it within the period of limitation in order to initiate legal proceedings, which cannot be allowed to happen because that is not the intent of law.

11. The learned Counsel for the Respondent No. 11 has placed reliance of the Judgment Jai Javan Jai Kisan and ors. v. Vidarbha Cricket Association and Ors. [MANU/GT/0006/2017], where-in relevant para no. 11 is as follows:-

"11. Conjoint reading of Section 14 and 15 of the National Green Tribunal Act reveals that essentially any application moved for claiming reliefs there-under must necessarily present a Civil case wherein substantial question relating to environment or environmental damage arising under the enactments specified in the Schedule-I of the Act (including accident occurring while handling any hazardous substance) is involved. We are, therefore, of the considered opinion that it is the substantial question relating to the environment or environmental damage as aforesaid which gives rise to the cause for an action under the provisions of National Green Tribunal Act, 2010. In the present case, the question raised is about restoration of the environmental damage on account of injury to it as a result of raising VCA Stadium without EC or consent to operate under the provisions of Schedule-I Acts viz Environment (Protection) Act, 1986, the Air (Prevention and Page 3 of 10 Control of Pollution) Act 1981 and Water (Prevention and Control of Pollution) Act 1974. As stated herein above, the causes of injury are insufficiency of Effluent Treatment Plant (ETP), open species, parking spaces and tree cover. These facts were very much manifest when the VCA stadium became functional in the year 2008. In our opinion, therefore, the cause of action for the present Application arose first when the VCA stadium became functional. There is nothing in the Application to state that these injuries stood compounded further to actuate the Applicants to initiate the action in the present case as framed."

12. Thereafter, the learned Counsel for the Respondent No. 11 has placed reliance on Graminee Environment Development Foundation v. Balaji Infrastructure Ltd. & Ors. [(2017) SCC Online NGT 1098], where-in relevant para nos. 11 to 13 are as follows:-

"11. Section 15 (3) of the NGT Act, 2010 in clear terms requires the Application for restitution of the property damaged to be made within the period of five (5) years from the date on which cause for such relief first arose, and provides for discretion to the Tribunal to condone delay for 'sufficient cause' if the application is filed within further period of sixty (60) days and no further. In the present case, the Applicant avers that the cause of action first arose on 24.2.2015, when the letter was addressed by the Member Secretary, Maharashtra Coastal Zone Management Authority (MCZMA) to the Collector, Raigad to take action in respect of the grievance made by the Applicant and yet no action was taken by the authorities. The Applicant has further revealed in her Application that she has been making several complaints to the Authorities about the said grievance, first such complaint being made on 15.9.2014 to the Divisional Commissioner, Konkan Division, Navi Mumbai. Reading of the letter dated 24.2.2015, Annexure ''I to the Application (Pg.81) reveals the nature of grievance made by the Applicant. In short, the Applicant was aggrieved by the alleged illegal blasting work, storage of minerals and reclamation by Dighi Port Ltd. Similarly, the grievance made with complaint dated 15.9.2014 is regarding alleged illegal work of reclamation of seashore and filling rocks at village Nanavali and intertidal land encroachment without EC by Dighi Port Ltd, and Balaji Infrastructure Ltd.

12. In our considered opinion, making of grievance of the kind in the present case by writing a letter cannot be constituted as 'cause of action' but the actual act or its consequence constitutes 'cause of action' in any case. In the present case, cause of action has arisen as a result of blasting work as well as dumping of rocks etc. by Dighi Port Ltd and its holding Company Balaji Infrastructure Ltd in the said land.

Page 4 of 10

13. A perusal of the Application gives some clue as to when such acts of blasting of hills and dumping of material excavated started. The Applicant has pleaded in her Application that Respondent No.1 encroached upon 3km of seashore of village Nanavali and without permission of any Govt. Authority dumped soil and rocks there. It is further pleaded that Respondent No.1 has been doing illegal activities of levelling, blasting, excavation of land, filling of land space with soil, dumping huge rocks and artificial land spaces without any permission; and in spite of such illegalities going on, Respondent Nos. 2 to 7- Govt. Authorities did nothing. The Applicant in her pleadings referred to EC granted in the name of Dighi Port Ltd on 30th September, 2005 for construction of Port at village Dighi, Taluka Shrivardhan, District Raigad and states that she does not challenge or dispute anything about such EC or any work at Dighi Port and her only grievance is that Respondent No.1 has encroached upon the property and extended various kinds of constructions beyond consented area. These facts as pleaded if read in conjunction with the plaint in Regular Civil Suit No.4 of 2009 filed by the Applicant in the Court of Civil Judge, Junior Division, Shrivardhan, do make sense as to when alleged activity had started. At para-7 of the said plaint, the Applicant has categorically stated that on 26.12.2008 the defendant (therein) i.e. Dighi Port Ltd came at the land adjacent to the house of the Applicant in order to make encroachment and reclaimed the land, and this highhanded activity of Dighi Port Ltd was resisted by the Applicant with objection that they cannot reclaim land by blasting the hills and dumping rocks at the said land. A clear fact emerges that the act of blasting the hill sides, dumping materials illegally and reclamation of land, first started in or about December, 2008. Thus, cause of action for the present Application clearly arose in or about December, 2008."

13. Based on the above provisions of law, it is vehemently argued by the learned Counsel for the Respondent No. 11/Project Proponent that the present application is time barred and needs to be dismissed on that ground alone.

14. During argument, the learned Counsel for the Applicant in Original Application has pointed out that he is relying on para no. 18.25 & 18.26 of the reply affidavit dated 26.10.2021, mentioned at page nos. 981 to 986 of the paper book, which are as follows:-

"18.25. I state that, this Hon-ble Tribunal in the matter of "Forward Foundation, A Charitable Trust and Ors. Vs. State of Karnataka and Ors. (OA No. 222/2014) Judgment dated Page 5 of 10 7th May, 2015", reported in 2015 SCC Online NGT 5 in dealing with the issue of limitation and cause of action has specifically held as follows-
"24. The expression 'cause of action' as normally understood in civil jurisprudence has to be examined with some distinction, while construing it in relation to the provisions of the NGT Act. Such 'cause of action' should essentially have nexus with the matters relating to environment. It should raise a substantial question of environment relating to the implementation of the statutes specified in Schedule I of the NGT Act. A 'cause of action' might arise during the chain of events, in establishment of a project but would not be construed as a 'cause of action' under the provisions of the Section 14 of the NGT Act, 2010 unless it has a direct nexus to environment or it gives rise to a substantial environmental dispute. For example, acquisition of land simplicitor or issuance of notification under the provisions of the land acquisition laws, would not be an event that would trigger the period of limitation under the provisions of the NGT Act, 'being cause of action first arose'. A dispute giving rise to a 'cause of action' must essentially be an environmental dispute and should relate to either one or more of the Acts stated in Schedule I to the NGT Act, 2010. If such dispute leading to 'cause of action' is alien to the question of environment or does not raise substantial question relating of environment, it would be incapable of triggering prescribed period of limitation under the NGT Act, 2010. [Ref Liverpool and London S.P. and I Asson. Ltd: v. M.V. Sea Success I and Anr., (2004) 9 SCC 512, J. Mehta v. Union of India, 2013 ALL (I) NGT REPORTER (2) Delhi, 106, Kehar Singh v. State of Haryana, 2013 ALL (I) NGT REPORTER (DELHI) 556, Goa Foundation v. Union of India, 2013 ALL (I) NGT REPORTER DELHI 234].
25. In contradistinction to 'cause of action first arose', there could be 'continuing cause of action', 'recurring cause of action' or 'successive cause of action'. These diverse connotations with reference to cause of action are not synonymous. They certainly have a distinct and different meaning in law, 'Cause of action first arose' would refer to a definite point of time when requisite ingredients constituting that 'cause of action' were complete, providing applicant right to invoke the jurisdiction of the Court or the Tribunal. The Right to Sue' or 'right to take action' would be subsequent to an accrual of such right. The concept of continuing wrong which would be the foundation of continuous cause of action has been accepted by the Hon'ble Supreme Court in the case of Bal Krishna Savalram Pujari & Ors. v. Sh. Dayaneshwar Maharaj Sansthan & Ors., AIR 1959 SC 798.
18.26 Further I state that, the Forward Foundation Judgment was challenged before the FIon'b1e Supreme Court in the matter of Mantri Technoze Pvt. Ltd. Vs. Forward Foundation, Civil Appeal No. 5016/2016 reported in (2019) 18 SCC 494 has specifically held vide judgment dated 5th March, 2019 and has confirmed the said judgment Page 6 of 10 of Forward Foundation and even the Review petition of the same has been dismissed vide order dated 06/08/2019 and has thus become final and binding.
"In fact, in the original application before the Tribunal there was no mention of the provision under which it was being filed. It is well settled principal of law that non- mention of or erroneous mention of the provision of law would not be of any relevance, if the Court had the requisite jurisdiction to pass an order. It would be mere irregularity and would not vitiate the application or the judicial order of the Tribunal"

The NGT Act being a beneficial legislation, the power bestowed upon the Tribunal would not be read narrowly. An interpretation which furthers the interests of environment must be given a broader reading. (See Kishsore Lal v. Chairman, Employees' State Insurance Corpn. (2007) 4 SCC 579, para 17). The existence of the Tribunal without its broad restorative powers under Section 15(1)(c) read with Section 20 of the Act, would render it ineffective and toothless, and shall betray the legislative intent in setting up a specialized Tribunal specifically to address environmental concerns. The Tribunal, specially constituted with Judicial Members as well as with Experts in the field of environment, has a legal obligation to provide for preventive and restorative measures in the interest of the environment"

"The Tribunal has also jurisdiction under Section 15(1)(a) of the Act to provide relief and compensation to the victims of pollution and other environmental damage arising under the enactments specified in Schedule I. Further, under Section 15(1)(b) and 15(1)(c) the Tribunal can provide for restitution of property damaged and for restitution of the environment for such area or areas as the Tribunal may think fit. It is noteworthy that Section 15(1)(b) & (c) have not been made relatable to Schedule I enactments of the Act. Rightly so, this grants a glimpse into the wide range of powers that the Tribunal has been cloaked with respect to restoration of the environment."
"Section 15(1)(c) of the Act is an entire island of power and jurisdiction read with Section 20 of the Act. The principles of sustainable development, precautionary principle and polluter pays, propounded by this Court by way of multiple judicial pronouncements, have now been embedded as a bedrock of environmental jurisprudence under the NGT Act. Therefore, wherever the environment and ecology are being compromised and jeopardized, the Tribunal can apply Section 20 for taking restorative measures in the interest of the environment."

15. The Applicant in Original Application has also placed reliance upon the important dates and events, which have been quoted by him in para Page 7 of 10 14 of the reply affidavit, mentioned at page nos. 926 to 928 of the paper book, which are as follows:-

"14. IMPORTANT DATES AND EVENTS:
I state that, the following events and dates are very important to understand the collusion between the Government Authorities and Respondent No. 11-PP and tactics, favouring practices adopted by the Joint Committee Members and Respondent No. 11-PP;
        "    Sr.                Events                             Date
             No.
               1.   1st Application for EC                     07.09.2013
               2.   1st Show Cause Notice by SEIAA &           30.08.2014
                    PS- DoE
               3.   1st Withdrawal Communication for SCN       10.03.2015
               4.   1st Consent to Establish                   10.03.2015
               5.   2nd Application for EC                     30.06.2016
               6.   2nd Consent to Establish                   12.10.2017
               7.   3rd Application for EC                     06.10.2018
               8.   Notice/Complaint of Original Applicant     19.05.2019
               9.   MPCB 1st Site Visit by Field Officer       10.06.2019
              10.   2nd Show Cause Notice by SEIAA &           15.06.2019
                    PS- DoE
              11.   MPCB 2nd Site Visit by SRO-2               27.06.2019
              12.   Filing of OA                               14.08.2019
              13.   First Order of NGT                         22.10.2019
              14.   Service to Joint Committee of SEIAA &      02.11.2019
                    MPCB
              15.   Personal hearing given to PP by PS-DoE     11.11.2019
              16.   2nd Withdrawal Communication for SCN       16.11.2019
              17.   Second Order of NGT                        10.12.2019         -- :
              18.   Joint Committee Visit to project site      15.12.2019
              19.   Architect Certificates prepared on         20.12.2019          I1


              20.   Joint Committee Report filed to NGT        07.01.2020
              21.   Third Order of NGT issuing Notice 86       05.02.2020
                    Show cause to PP
              22.   Service to the Respondent No. 11-PP        15.02.2020
              23.   Grant of ex-post facto EC                  18.02.2020
              24.   Appeal No. 26/2020 filed on                19.03.2020
              25.   Fourth Order of NGT                        13.07.2020
              26.   Respondent No. 11-PP Reply Affidavit       24.09.2020
                    Sworn on
              27.   Respondent        No.      11-PP filed     24.09.2020
                                                                  IA No. 86/2020 sworn on
              28.   Fifth Order of NGT                         03.09.2021
              29.   Respondent       No.    11-PP filed      IA 06.10.2021
                                                                  No.
                    86/2020 filed on
              30.   Respondent No. 11-PP Corrected             09.10.2021
                    Reply Affidavit served on Original




                                                                             Page 8 of 10
                      Applicant                                                "

16. He has argued that in this case, there is recurring cause of action and therefore, the date which has stated in his application i.e.

15.06.2019, when the SEIAA issued a Show Cause Notice to the Project Proponent, should be treated to be the date of cause of action.

17. We have heard the arguments of the parties and perused the record and also have gone through the Judgments, which have been relied upon by both the parties, we find that as far as legal position is concerned, Sections 14 & 15 of the National Green Tribunal Act, 2010 provide as follows:-

"Section 14:- Tribunal to settle disputes.-
(1) .................................................................................... (2) ................................................................................... (3) No application for adjudication of dispute under this Section shall be entertained by the Tribunal unless it is made within a period of six months from the date on which the cause of action for such dispute first arose:
Provided that the Tribunal may, if it is satisfied that the applicant was prevented by sufficient cause from filing the application within the said period, allow it to be filed within a further period not exceeding sixty days." Section 15:- Relief, compensation and restitution -
(1) .................................................................................... (2) .................................................................................... (3) No application for grant of any compensation or relief or restitution of property or environment under this section shall be entertained by the Tribunal unless it is made within a period of five years from the date on which the cause for such compensation or relief first arose:
Provided that the Tribunal, may, if it is satisfied that the applicant was prevented by sufficient cause from filing the application within the said period, allow it to be filed within a further period not exceeding sixty days."

18. According to the Applicant in Original Application, as per his own pleadings which are stated in para no. 40, it is clear that construction of the project by the Project Proponent was started in the year 2011 and continued till 19.05.2018. He states that he had obtained information Page 9 of 10 through online search and under RTI from 2017 to 18.05.2018. Thereafter, he had sent legal notice through Counsel on 19.05.2019. According to him, the SEIAA had issued first Show Cause Notice on 15.06.2019. Therefore, that date should be taken to be the date of cause of action, which first arose.

19. We are not inclined to accept this argument because according to his pleading, he had full knowledge in the year 2011 itself when the construction had started. The pretext of having come to know about this project being constructed through RTI on a later date as stated above appears to be only in order to bring the present Original Application within limitation period. We agree with the learned Counsel for the Project Proponent (PP) that it is very easy for any person to use RTI to seek information for any project on any date chosen by him. We are of the considered opinion that such kind of practice cannot be allowed. We are not inclined to accept the argument made by the learned Counsel for the Applicant in Original Application and are convinced with the argument raised by the learned Counsel for the Respondent No. 11/Project Proponent. We find that this Original Application is time barred, hence this Original Application stands dismissed as time barred.

20. All connected I.A.s also stand disposed of.

21. Dinesh Kumar Singh, JM Dr. Vijay Kulkarni, EM December 01, 2022 Original Application No. 63/2019(WZ) (I.A. No. 100/2019 & I.A. No. 86/2021) P.Kr Page 10 of 10