Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0]

National Green Tribunal

Tribunal On Its Own Motion Regarding ... vs State Of Jharkhand Through Chief ... on 24 January, 2023

Item No.05                                                     Court No.1


         BEFORE THE NATIONAL GREEN TRIBUNAL
            EASTERN ZONE BENCH, KOLKATA
             (THROUGH PHYSICAL HEARING WITH HYBRID MODE)

                            M.A. No.38/2022/EZ
                                       In
                     Original Application No.50/2022/EZ


In the Matter of:-

Tribunal on its own motion
Reg: Frequent Accident Occurring
due to illegal coal mines in abandoned
coal mines in Dhanbad, Jharkhand
                                                               Applicant(s)
                                  Versus

1. Integrated Regional Office, MoEF & CC, Ranchi
   Through Senior Scientist,
   Bungalow No.A-2, Shyamali Colony
   Doranda, Ranchi, Jharkhand-834002

2. Central Pollution Control Board
   Through Senior Scientist,
   Parivesh Bhawan, East Arjun Nagar,
   Delhi-110032

3. Jharkhand State Pollution Control board,
   Through Senior Scientist,
   H.E.C. Durwa, Ranchi-834004

4. District Magistrate, Dhanbad,
   Station Road, Pandey Muhalla,
   Dhanbad, Jharkhand-826001

5. Director General of Mines Safety Dhanbad,
   Ministry of Labour and Employment,
   DGMS Head Office, Sardar Patel Nagar,
   Dhanbad, Jharkhand-826001

6. District Mining Officer, Dhanbad,
   Combined Building,
   P.O.+P.S. & District-Dhanbad

7. Superintendent of Police/Senior Superintendent of Police,
   NH 32, Near General Post Office,
   Kasturba Nagar, Dhanbad, Jharkhand-826001

                                                          Respondent(s)

Date of hearing: 24.01.2023



                                  1
 CORAM:      HON'BLE MR. JUSTICE B. AMIT STHALEKAR, JUDICIAL MEMBER
            HON'BLE PROF. A. SENTHIL VEL, EXPERT MEMBER


For Applicant(s)    : Suo Motu

For Respondent(s) : Mr. Apurba Ghosh, Adv. for R-1,
                    Mr. Surendra Kumar, Adv. for R-3,
                    Mr. Ashok Prasad, Adv. for R-5

                                      ORDER

1. The Original Application No. 50/2022/EZ was disposed of by this Tribunal vide its order dated 04.07.2022 with the following directions:-

"11. Considering the anomalies and non-compliance of the Mine Closure Plan noted by the Committee and the remedial action suggested by the Committee, we direct the Committee constituted by us to monitor the mining operations, so far as the implementation of Mine Closure Plan is concerned, at the sites in question in the present Original Application and to ensure strict compliance of the remedial measures suggested by the Committee within a time period of four months and file an affidavit of compliance by 11.11.2022. 12. With the aforesaid directions, the Original Application No. 50/2022/EZ is accordingly disposed of.
13. There shall be no order as to costs."

2. Since no compliance affidavit had been filed, the present M.A. No.38/2022/EZ was taken up suo motu.

3. An affidavit dated 14.01.2023 has been filed by Respondent No.1, MoEF & CC, Ranchi.

4. As regards delay in filing the compliance report has been satisfactorily explained which we accept.

2

5. It is stated that compliances of M/s BCCL and M/s ECL were observed to be different, and, therefore, have been filed with the affidavit in two different tables.

6. Table-A relates to the compliance report on the Remedial Measures/Action Plan to Prevent Illegal/Unauthorized Coal Mining from Coal Mines of CV Area, BCCL and reads as under:-

A. "Compliance Report on Remedial Measures/Action Plan to prevent ILLEGAL/Unauthorized Coal mining from Coal Mines of CV Area, BCCL.
Sl.N Remedial steps/action plan suggested by the Action Taken/Response Latest o. Hon'ble NGT and committee members to Submitted By PP (M/S observations/comp prevent illegal/unauthorized mining from BCCL) liance status coal mines based on site inspection on based on site 20.05.2022 inspection on 09.11.2022 and documents submitted by PP.
1. Progressive and final mine closure Plan has Mine closure guideline Being complied to be followed strictly ECL, BCCL: As came into force in August but further explained earlier accidents and death in 2009 and MCP's of two action needed.

Gopinathpur could have been avoided if operating mines of Patch 'C' working Project Proponent (JPP) had followed the Cluster XVI of BCCL has at Mine Closure Plan and backfilled the been prepared and BasantimataDahib exposed final coal face/highwall. Coal mines approved by BCCL ari was fenced by have their Progressive and Final closure Plan Board: single row barbed approved by Coal controller (under Ministry 1. DahibariBasantimata wire fencing. The of coal, Govt. of India) or their Company OCP patch C quarry Board. It was informed that ECL and BCCL 2. Basantimata Colliery floor was partially board had been delegated the power to Activities mentioned in waterlogged. At approve the Mine Closure Plan. In the mine Approved Mine Closure places the fencing Closure plan there are steps Plan of Basantimata was found given/procedure enumerated so that step by Colliery damaged. step mine is closed in a scientific/systematic &DahibariBasantimata Accompanying way for e.g. For opencast (o/c) mine OCP are being taken. officials (PP) backfilling of excavated/open pit, dozing and Third party audit by informed that the levelling the area of natural elevation, IIEST Shibpur (MoC fencing was developing grassing vegetation and greenbelt certified agency) and completely made on the dumps, levelled area, etc. Sometimes inspection by officials of around the patch pits are partly filled and partly left for CCO has been done to C opencast rainwater harvesting, groundwater recharge, verify the MCP activities workings but it etc. Overall, the aim is to either return the undertaken, found was damaged at land in the way it was in earlier (premining) satisfactorily as per places by days (agriculture land, forest land) or to provisions mentioned in miscreants. Two return to local community in a more better approved MCP and lines of fencing way (in the way of ponds, agriculture land, recommended was not found at etc.) reimbursement of any place around For u/g mine: All entries/openings to Rs.4.10 cr approx. for the mine nor any underground workings of DBOCP & Rs.1.53 cr fence found in abandoned/closed/discontinued approx. for Basantimata between two lines mine/workings shall be effectively sealed off UG. Further in this, for of fencing that or filled upto ground level to prevent entry of DBOCP has been may act as persons through them. released from CCO and deterrent for illegal Implementation/Execution of Mine rest will be released. miners. Patch C Closure activities as per the approved working has been Mine Closure Plan is the responsibilities of In progressive operation temporarily Mining Companies (in this case M/s ECL, of mines, sealing of discointinued due M/s BCCL). However, there is a need of incline/shaft is not to unavailability of supervision by Government regulatory usually done. further land and is agencies. In the case of non-coal major Both pit (3&4) of closed situated just 3 minerals (Iron ore, Bauxite, Manganese, Chanch UG colliery has adjacent to the Limestone, etc.) there is Indian Bureau of ben sealed and fenced. present opencast Mines that approves the Mine Plan and Mine workings. Closure Plan and also supervises/ensure the Further, recommendation activities are done in the mines are as per No. K of NGT clearly In the mine, the plan. Because there is one (very states mine workings were important) aspect to Mine Closure and that is face/highwall could not previously being the coal/minerals conservation aspect. For advance due to made by non-coal major minerals, Indian Bureau of unavailability of land underground Mines-IBM ensures that all mineral that is and chances of illegal through numbers technically and safely possible to be mining increases as coal of inclines. Most of excavated is taken out of the mine before companies could not go the incline entries mine closure. Since coal/mineral left behind for backfilling as mine have been in mine can be national loss (It is really has to further advance excavated in tough to search for a mineral, open a mine, and exploit the coal opencast mining run it profitably so leaving behind the further, follow up with and presently mineral/coal haphazardly is not at all local have no existence. sustainable). administration/District Rest of the incline officials can help the coal entries to the During inspection in the coal mines the companies in acquiring underground mine closure plan implementation was the land is to be made. In workings were not found satisfactory. this, help from district sealed at surface administration are being by dumping sought on for overburden.

                                                acquirement of land for        Presently       there
                                                Mining Purpose. Coal           was                no
                                                Production from Patch-C        underground
                                                of BasantimataDahibari         working in the
                                                Colliery      has      been    mine      and      all
                                                temporarily stopped due        scams were being
                                                to non-availability of land    extracted          by
                                                and the mine void filling      opencast       mining
                                                in case of Patch -C could      only.
                                                not be taken under Mine
                                                Closure activity as the        Adequate display
                                                patch        is      under     boards           for
                                                development stage and          preventing illegal
                                                there is no De-coaled          entry to the mine
                                                area under Patch-C for         were placed near
                                                backfilling       as     per   common approach
                                                approved Mine closure          points to the mine.
                                                Plan.                          Howevercheckpost
                                                                               s were not found
                                                Approximately 800m of          appropriate. There
                                                Fencing work around the        were no barriers
                                                Patch-C was done and           for entry there.
                                                nearly 100m of fencing         One line of fencing
                                                was     damaged      by        was also found
                                                miscreant for which FIR        damaged at some
                                                has been lodged.               places.        One
                                                                               display board was
                                                LOA for another proposal       observed there.
                                                for 1000m of fencing
                                                around Patch C has been        Two check posts
                                                done for dual fencing as       with       security
                                                recommended           by       guard         were
                                                committee.                     provided in the
                                                                               mine to monitor
                                                MCSR has been prepared         and        prevent
                                                for mines which are            unauthorized
                                                inoperative before issue       entry   into   the
                                                of     Mine       Closure      mine.
                                                Guidelines on 27th Aug
                                                2009, the provisions are       The
                                                being     complied     by      abandoned/disco
                                                submitting Form-I/AMP          ntinued mines in
                                                as       per      CMR-6,       CV area of M/s


                                            4
     submission of AMP as         BCCL, situated in
    per CMR-61 under CMR         the       state    of
    1957. The list of mines is   Jharkhand         are
    as follows:                  Chanch
    1. Chanch             UG-    underground
       inoperative,    Form-I    colliery,     Laikdih
       submitted           on    deep underground
       24.10.2016. Pit no.       mine and New
       3&4 has been sealed.      Laikdih OCP.
    2. New Laikdih       OCP-
       inoperative,      AMP     The two vertical
       submitted           on    shafts, Pit 3 & Pit
       27.07.2000.               4      of     Chanch
    3. Laikdih    Deep    UG-    underground
       inoperative,    Form-I    colliery have been
       submitted           on    sealed          from
       24.10.2016, Pit no.1 &    surface by RCC
       2 sealed                  and      also   kept
                                 fenced by barbed
                                 wire.

                                 Two out of three
                                 vertical shafts of
                                 Laikdih       deep
                                 underground mine
                                 were fenced all
                                 around by brick
                                 cement boundary
                                 wall of 3m height
                                 and      one      is
                                 completely sealed
                                 with GI sheet from
                                 which       regular
                                 pumping        was
                                 being done for
                                 domestic purpose.
                                 Management
                                 reported that the
                                 process           of
                                 complete sealing of
                                 the
                                 abandoned/disco
                                 ntinued pits i.e.
                                 two pits of Laikdih
                                 deep underground
                                 mine     was     on
                                 process.

                                 New Laikdih OCP
                                 had almost been
                                 backfilled     upto
                                 and           above
                                 surrounding
                                 ground level. The
                                 excavated      area
                                 not yet backfilled
                                 was          partilly
                                 waterlogged and
                                 exposed coal seam
                                 was not visible
                                 there. Part of the
                                 discontinued
                                 opencast workings
                                 of New Laikdih
                                 OCP, CV Area,
                                 M/s BCCL which
                                 was      not     yet


5
                                                                                      reclaimed         by
                                                                                     backfilling or by
                                                                                     any other means
                                                                                     was      not    kept
                                                                                     securely     fenced.
                                                                                     Management has
                                                                                     been        suitably
                                                                                     addressed       vide
                                                                                     letter       no.901
                                                                                     dated 30.11.2022
                                                                                     for       immediate
                                                                                     compliance.

                                                                                     With respect to
                                                                                     mine       closure
                                                                                     plan,    PP    has
                                                                                     assured          to
                                                                                     comply as per
                                                                                     the      approved
                                                                                     mine       closure
                                                                                     plan.
2.   The officials of Coal Controller of India,      Third party audit by            Committee
     Ministry of Coal, Govt. of India and Director   IIEST     Shibpur     (MoC      members have no
     level officers of BCCL/ECL would check the      certified agency) and           information
     status of implementation of Mine Closure        audit by officials of CCO       whether       NGT
     Plan/Progressive Mine closure plan of all the   has been done to verify         order    in    this
     Mines of BCCL and ECL in Dhanbad District       the      MCP      activities    matter and report
     and ensure that Mine closure activities are     undertaken,          found      of NGT constituted
     being carried out in an appropriate manner.     satisfactorily    as    per     committee
                                                     provisions mentioned in         members       have
                                                     approved       MCP     and      been shared with
                                                     recommended                     Coal controller of
                                                     reimbursement              of   India, and Director
                                                     Rs.4.10 cr approx. for          level officers of
                                                     DBOCP & Rs.1.53 cr              BCCL.
                                                     approx. for Basantimata.
                                                     Further     in this,     an
                                                     amount        of   Rs.2.04
                                                     crapprox. of DBOCP has
                                                     been released from CCO
                                                     and rest will be released.
3.   Mining authorities (M/s ECL, M/s BCCL)          The list of Discontinued        Being complied.
     should provide the list of all the abandoned    Mines and abandoned
     as well as discontinued mine working in the     Mines under Cluster XVI,        Notice         of
     area. It should be ensured by the mining        CV area is as below:-           abandonment    of
     authorities that the notice of abandonment,       1. Chanch             UG-     Chanch UG mine,
     closure or discontinuance of all such mines          inoperative                New Laikdih OCP
     are given to the Chief Inspector (DGMS) as        2. New Laikdih OCP-           mine and Laikdih
     well as the district administration as per           inoperative                Deep UG mine had
     rule.                                             3. Laikdih Deep UG-           been submitted to
                                                          inoperative                DGMS.
     It should be ensured by the lease holder or       4. Basantimata        UG-
     the owner of the mine that no mine should be         Production                 Basantimata UG
     discontinued or abandoned in violation of the        suspended                  mine has been
     existing safety precaution as per CMR 2017.     It has been ensured that        amalgamated with
                                                     no mine of Cluster XVI          Dahibari mine and
                                                     has been discontinued or        presently    being
                                                     abandoned in violation of       worked by only
                                                     the      existing    safety     opencast mining.
                                                     precaution as per CMR
                                                     2017.
4.   Fencing around mines can be done in two         Approximately 800m of           Partially
     rows- ie. In between two rows of barbed         Fencing work around the         complied. Patch
     wire fencing a trench (width 1m, depth 2m)      Patch-C was done and            'C'   working  at
     can     be    made     that      shall make     nearly 100m of fencing          BasantimataDahib
     illegal/unauthorized mining and manual          was       damaged         by    ari was fenced by
     transportation of coal difficult. However, as   miscreant for which FIR         single row barbed


                                                 6
      per DGMS Circular 11/1959, top of the              has been lodged.           wire fencing. The
     'abandoned quarries' shall be fenced by (i)                                   patch C quarry
     0.4m thick brick wall in lime/cement mortar        LOA for another proposal   floor was partially
     not less than 1.5m high with a parapet top or      for 1000m of fencing       waterlogged.       At
     (ii) 0.75m thick stone wall in lime/cement         around Patch C has been    places the fencing
     mortar not less than 1.5m high.                    done for dual fencing as   was           found
                                                        recommended           by   damaged.
     The fencing must also be maintained till the       committee.                 Accompanying
     whole area is completely reclaimed as per                                     officials informed
     rule. Necessary steps should be taken to                                      that the fencing
     ensure that no illegal mining is done in                                      was      completely
     abandoned or discontinued mine area by                                        made around the
     properly filling the exposed coal faces of the                                patch C opencast
     discontinued workings.                                                        workings but it
                                                                                   was damaged at
                                                                                   places            by
                                                                                   miscreants.      Two
                                                                                   lines of fencing
                                                                                   was not found at
                                                                                   any place around
                                                                                   the mine nor any
                                                                                   fence found in
                                                                                   between two lines
                                                                                   of fencing that
                                                                                   may       act      as
                                                                                   deterrent for illegal
                                                                                   miners. Patch C
                                                                                   working has been
                                                                                   temporarily
                                                                                   discontinued due
                                                                                   to unavailability of
                                                                                   further land and is
                                                                                   situated         just
                                                                                   adjacent in the
                                                                                   present opencast
                                                                                   workings.
5.   Number of checkpoints can be made around           Two check posts have       Being complied
     the mines especially at those places from          been      created    for   but         further
     where there are chances of unauthorised            monitoring unauthorized    action needed.
     entry of outsider for theft of coal and            entry in mine premise
     transport of theft coal from mine to outside. It   and coal theft.            Two check posts
     must be ensured that each of the                                              with       security
     abandoned/discontinued mine workings are           Internal security guards   guard         were
     provided with proper fencing and sufficient        are also deployed round    provided in the
     no. of display boards of adequate size at all      the clock for monitoring   mine to monitor
     common approach point with information             coal theft.                and        prevent
     about the date of discontinuance /                                            unauthorized
     abandonment stating that entering into the         The                        entry   into   the
     area by anyone is illegal as per rule (as          abandoned/Discontinued     mine.
     provided at Railway crossing).                     mine     workings    are
                                                        properly sealed off and    Adequate display
                                                        being    provided   with   boards           for
                                                        adequate fencing.          preventing illegal
                                                                                   entry to the mine
                                                                                   were placed near
                                                                                   common approach
                                                                                   points to the mine.
                                                                                   However       check
                                                                                   posts were not
                                                                                   found appropriate.
                                                                                   There were no
                                                                                   barriers for entry
                                                                                   there. One line of
                                                                                   fencing was also
                                                                                   found damaged at
                                                                                   some places. One
                                                                                   display board was


                                                    7
                                                                                      observed there.
6.   Round the clock rounds by CISF/internal           A Central Control rooms       Being complied
     security of coal companies by mobile              have been established in      but         further
     vehicles. This inspecting CISF officials and      CV Area. Round the clock      action     needed.
     internal security members should be               monitoring is being done      Reply of PP is as
     connected directly to local police control room   by CISF and Security          given in adjacent
     so that they can report/ask for help, etc.        team     of    companies.     column. Better co-
                                                       Connection with Local         ordination       and
                                                       police control room has       connectivity       is
                                                       been also established for     required between
                                                       report & help.                internal    security
                                                                                     members and coal
                                                                                     police central room
                                                                                     to    stop    illegal
                                                                                     mining.
7.   Installation of CCTV cameras in and around        CCTV       camera      has    Being complied
     the mines that can aid in identification of       already been installed in     but         further
     persons engaged in illegal/un-authorised          Mine       premises      of   action needed.
     mining. They should be connected with             BasantimataDahibari
     common control room having access to CISF.        Colliery for surveillance     Two             CCTV
     Internal security in-charge, local police and     of    coal    theft    and    cameras          were
     other key person who can take action.             monitoring of persons         installed in the
                                                       engaged in illegal/un-        mine to cover the
                                                       authorised          mining.   patch C workings.
                                                       Connectivity of the same      The
                                                       has been established to       surveillance/contr
                                                       central control room and      ol     room       was
                                                       CISF, Internal security in-   established          in
                                                       charge. However local         Area office and
                                                       villagers have tried to       was accessible to
                                                       damage       the     CCTV     CISF and internal
                                                       installed for which FIR       security.           As
                                                       has been lodged to local      informed       during
                                                       police station.               inspection       there
                                                                                     was fifteen days
                                                                                     backup of the CC-
                                                                                     TV footage. There
                                                                                     was no power
                                                                                     back up facility of
                                                                                     operation of the
                                                                                     installed      CC-TV
                                                                                     during         power
                                                                                     failure.
                                                                                     Local police has
                                                                                     no access to this
                                                                                     control room.
8.   Drones can be utilised for tracing illegal/un-    Proposal for utilization of   No drones has
     authorised mining that may be going on in         Drones      for     tracing   been utilized for
     the project/area and also for action by           illegal/un-authorized         tracing illegal/un-
     internal security/CISF and Local Police           mining has been sent to       authorized mining
     administration.                                   BCCL HQ                       that may be going
                                                                                     on          in     the
                                                                                     project/area and
                                                                                     also for action by
                                                                                     internal
                                                                                     security/CISF and
                                                                                     Local           Police
                                                                                     administration.
9.   All the above arrangements would be futile if     Information of illegal coal   Being complied.

local Police department do not take strict mining under leasehold 1. Total FIR on action against the identified or caught illegal is being reported to Local illegal mining mines. Strict action/Punishment can only Police Station and (till Nov. deter the illegal/un-authorised miners to subsequently FIR are 2022): 347 leave this unlawful job. Proper FIRs should being lodged for the 2. 178 arrested be done and illegal/un-authorised miners be same to the Local Police 3. Around brought to justice/punishment may be given administration. 48000 ton as per the law, then only fear of law can be and 300 jute 8 penetrated among illegal/un-authorised bags filled miners. with coal recovered.

4. Dedicated force provided by DIG for raid.

5. Special drives are conducted every month for minimum of 10 days.

6. Monthly meeting of mining task force for better coordination and resolution of any pending issues.

                                                                                        The above data is
                                                                                        for       Dhanbad
                                                                                        District       from
                                                                                        January 2022 to
                                                                                        November 2022.
10.   Alternate occupation / employment / means         Skill       development        Partially
      of livelihood can be given to illegal/un-         programmes are being           complied.
      authorised miners so that if they leave the       taken under CSR from           Involvement          of
      work of illegal mining they can sustain their     BCCL HQ for people             local people by PP
      and their family's life. Skill development        residing near the Mine         for              skill
      programmes can be done/ initiated for local       area.                          development was
      villagers around the mines area in the field                                     not            found
      of textile, handloom making, tailoring, candle                                   satisfactory.

making, food processing, phenyl and liquid soap making, mobile and laptop repair works, other electrical and electronic repair works etc. Mine management can initiate the above skill development programmes in a vigorous manner and also make propaganda about it (door to door campaign, pamphlet distribution/pasting, newspaper advertisement can be done). District Mineral fund can also be utilised for such skill development program. Villagers can also be encouraged to do farming/agriculture -

Multiple crop forming can be encouraged.

Water can be provided by BCCL/ECL mines management (Many of the abandoned mines work as water storage in the area).

11. At some mines it was observed that mine Help from district face/highwall could not advance due to administration are being unavailability of land. Though the adjacent sought on for acquisition land (adjacent to coal faces) are in the lease of land for Mining area but due to land acquisition problems Purpose. Coal Production coal companies/projects are unable to from Patch-C of acquire their lands. At these places local BasantimataDahibari administration/District officials can help the Colliery has been coal companies in acquiring the land. When temporarily stopped due the coal face advances and legal mining by to non-availability of coal companies are ongoing there is little land. chance of illegal mining. But as the coal face advance stops and mine patch is discontinued / temporarily stopped due to further land acquisition, a chance is given for 9 illegal mining (At that position coal companies could not go for backfilling as mine has to further advance and exploit the coal further). Coal companies can prepare and hand over the list of those mine (mine patches where coal face advance has been temporarily stopped due to land acquisition problems) to District administration. District admin. should co-operate with coal projects/companies to expedite the process of land acquisition.

12. Internal calculation/comparison of Records are being Being complied.

production, dispatch and reserve depletion of maintained in the form of coal by coal companies. A register can be Daily Production Report made for comparison purpose that may be as per Yellow Book. signed daily by Geologist, Mines Manager, Surveyor, Project Officer and General Manager of the Mines/Area of the coal companies.

       Sl.     Present      Broken    Total   Pro
       No.     reserve       Coal      coal   duc
                of coal    (blasted      in   tion
              in-situ in    and in    mines    fro
                 mine      dumps)       (C)     m
               (Proven        (B)             min
              Reserve)                         es
                  (A)                          (D)




Above format can be improvised. Aim should be that all senior officers and Government statutory bodies should know the Reserve, Production, Despatch of coal from mines real time. Any shortages can be highlighted soon. Thus with the aid of above viz., proper mine closure making arrangements in and around the mine to make illegal/ unlawful mining extremely difficult, identification, catching of illegal/ un-authorised miners, punishing illegal/un-authorised miners through law, providing alternative livelihood to local villagers, etc. illegal mining and accidents thereof can be reduced and eliminated."

7. Table-B relates to the compliance report on the Remedial Measures/Action Plan to Prevent Illegal/Unauthorized Coal Mining from Coal Mines of MUGMA Area, ECL and reads as under:-

B. Compliance report on Remedial measures/Action plan Suggested by the Hon'ble NGT committee to prevent ILLEGAL/Unauthorized Coal mining from Coal Mines of MUGMA Area, ECL.
S. Remedial Steps/action plan Action Taken/Response Latest No. suggested by the Hon'ble NGT and submitted by PP (M/s ECL) observations/comp committee members to prevent liance status illegal/unauthorized mining from based on site coal mines based on site inspection inspection on on 20.05.2022 10.11.2022 and documents submitted by PP.
A Steps to be taken by coal companies M/s. ECL, 10 Progressive and final mine closure plan Gopinathpur: Gopinathpur Gopinathpur:
has to be followed strictly by ECL, colliery is a discontinued OC Being complied: BCCL: As explained earlier accidents patch. A copy of the letter of The discontinued and death in Gopinathpur could have discontinuation addressed to part of the been avoided if project proponent (JPP) DGMS, Dhanbad dated Gopinathpur had followed the Mine Closure Plan and 20.01.2020 is enclosed for Colliery was backfilled the exposed final coal kind reference. partially back filled face/highwall. Coal mines have their The Progressive Mine Closure and waterlogged. progressive and final closure plan Plan for Gopiathpur Colliery The exposed approved by Coal controller (under was prepared by CPDIL, RI 1 Gopinathpur seam Ministry of coal, Govt. of India) or their and duly approved by the ECL in quarry face has Company board. It was informed that Board in 2013. completely been ECL and BCCL board had been The compliance status as per covered by back delegated the power to approve the Mine the approved MCP is tabulated filling and the Closure Plan. In the mine Closure plan as follows: quarry was there are steps given/procedure Paramet As per Actual waterlogged upto enumerated so that step by step mine is ers be MCP impleme about 8m from the closed in a scientific/systematic way for followe ntation surface (see photos e.g. for opencast (o/c) mine bakfilling of d 3,4,5,6). excavated/open pit, dozing and levelling the area of natural elevation, developing Total 34 24 Barbed wire fencing grassing vegetation and greenbelt on the mined was done all dumps, leveled area, etc. sometimes pits out area around the are partly filled and partly left for (Ha) discontinued rainwater harvesting, groundwater Total 24 18 quarry. In the river recharge, etc. Overall, the aim is to Backfill side two line of either return the land in the way it was ed area barbed wire fancing in earlier (premining) days (agriculture (Ha) was done around land, forest land) or to return to local Balance 10 6 the quarry with community in amore better way (in the left trench in between way of ponds, agriculture land, etc.) mined (see photos For u/g mine: All entries/openings to out area 3,4,5,6,7,8) underground workings of (Ha) abandoned/closed/discontinued which mine/workings shall e effectively sealed will not off or filled upto grond level to prevent be entry of persons through them. backfille Implementation/Execution of Mine d Closure activities as per the approved Mine Closure plan is the Plantation has been done by responsibilities of Mining Companies (in the Forest Dept., Dhanbad in this case M/s ECL, M/s BCCL). over 8.5 Ha land over OB However, there is a need of supervision dumps and backfilled area, by Government regulatory agencies. In duly shown in enclosed plan. the case of non-coal major minerals (Iron The total land excavated i.e. ore, Bauxite, Manganese, Limestone, 24 Ha as against 24 Ha as etc.) there is Indian Bureau of Mines that per MCP is due to delay and approves the Mine plan and Mine issues arising in acquiring Closure plan and also land. However, a comparison supervises/ensure the activities are between the mine closure done in the mines are as per the plan. activities as per MCP and Because there is one (very important) actual activities carried out in aspect to Mine Closure and that is the mine shows that the the coal/minerals conservation implementation of the mine aspect. For non-coal major minerals, closure activities is in Indian Bureau of Mines-IBM ensures proportion and as per the that all mineral that is technically and MCP. Whereas, in the safely possible to be excavated is taken approved MCP it was out of the mine before mine closure. proposed to backfill 70.50% of Since coal/mineral left behind in mine the total excavated area, in can be national loss (It is really tough to actual, Gopinathpur colliery search for a mineral, open a mine, run it has backfilled 75% of the total profitably so leaving behind the actual excavated area.
mineral/coal haphazardly is not at all As per the approved MCP, it sustainable.) has been proposed that the remaining void shall be During inspection in the coal mines backfilled by brining OB from 11 the mine closure plan future OC patch, likely to come implementation was not found up in the vicinity. However, no satisfactory. new OC patches have come up since its discontinuance and due to the unavailability of OB, a void of about 6 Ha was left to be filled as and when OB will be available. However, in the present situation it is proposed to fill this void by suitable material.
Based on the above tabulated figures and subsequent facts, it is evident that Gopinathpur Colliery has duly complied in implementing the progressive mine closure activities as per the approved MCP.
Recently, in June 2022 CMPDIL, RI 1 has conducted an inspection regarding implementation of progressive mine closure activities of Gopinathpur Colliery as per the approved MCPO for the period between 2013-14 to 2017-18. The Audit report has been prepared by CMPDL and submitted to the Coal Controller by ECL. Copy of the report is enclosed for kind reference. Plan enclosed showing backfilled, excavated, void, plantation area, etc for reference.
Annexure (A1) Plan showing Backfilling Annexure (C2) Letter of discontinuance Annexure (A2) Audit report of CMPDL regarding MCP activities.
Kapasara:
Kapasara colliery is an active OC patch. The Progressive Mine Closure Plan was Kapasara: Being approved by the ECL Board in complied but 2013. The compliance status further action as per the approved MCP is need. South side tabulated as follows: and west side of the Parameters to be followed As quarry has been per MCP Actual fenced by barbed implementation. Total mined wire and cement out area (Ha) 11 8. Total pole ( see photos Backfilled area (Ha) 8. 12.13,16).
                                    Balance left mined out area
                                    (Ha) which will not be               The quarry was
                                    backfilled 30                        waterlogged up to
                                    Evidently, from the above            about 45-50m from
                                    table, it is clear that Kapasara     the surface (see
                                    OC has implemented mine              photos 12.13).
                                    closure activities as per the        Extraction       of
                                    approved MCP.                        overburden     and
                                    Subsequently, expansion of           formation        of
                                    Kapasara OC was approved             benches          in


                                    12
                                               by       the     ECL     Board.     overburden      was
                                              Accordingly, revised mining         being carried out in
                                              plan and MCP have been              South-east corner of
                                              prepared by CMPDIL, RI-1 and        the     mine.     No
                                              duly approved by the ECL            working was being
                                              Board and submitted to              carried out beneath
                                              MoEFUCC.                            the high benches
                                              As per the revised MCP, he          (see photos 12.13)
                                              total quarry area is 55.65 Ha       As informed during
                                              against which about 23.80 Ha        inspection operation
                                              has been excavated to extract       in the mine had
                                              coal till date. Out of the total    been discontinued
                                              23.80 Ha of land broken for         in the mine since
                                              production of coal, 19.86 Ha        10.07.2022      and
                                              (approx.) has been backfilled.      again resumed on
                                              A total of 4.05 Ha of void area     05.09.2022.
                                              is left which is the active         In east side of the
                                              mining zone of Kapasara             quarry fencing and
                                              Colliery.    Concurrent    in-pit   check post were not
                                              backfilling is being carried out    yet provided.
                                              in the OC patch and current         In north side of the
                                              voids shall be backfilled after     mine, RCC brick
                                              decoaling of the area.              wall    was    being
                                              Kapasara colliery is an active      constructed.
                                              OC patch and all mine closure
                                              activities shall strictly be
                                              adhered to as per the MCP, as
                                              is the prevalent norm in the        With respect to
                                              mine.                               mine        closure
                                              Plan is enclosed to depict          plan,    PP     has
                                              progressive      mine    closure    assured to comply
                                              activities of the mine.             as     per      the
                                              Annexure (A4) Plan showing          approved      mine
                                              backfilling in Kapasara oc.         closure plan.
                                              UPDATED            COMPLIANCE
                                              STATUS:

                                              Fencing has been done all
                                              around the active void area.
                                              Photographs      attached     as
                                              Annexure 2. Annexure (A4).
                                              Plan showing backfilling in
                                              Kapasara oc.
The officials of Coal Controller of India,    The Coal Controller of India        Committee members
Ministry of Coal, Govt. of India and          (CCO) is the authority for          have no information
Director level officers of BCCL/ECL           checking the implementation         whether NGT order
would      check       the    status     of   status     of    mine    closure    in this matter and
implementation       of    Mine    Closure    activities as per approved          report      of   NGT
Plan/Progressive Mine closure plan of         MCP. However, CMPDIL is             constituted
all the Mines of BCCL and ECL in              deputed/authorized to inspect       committee member
Dhanbad District and ensure that Mine         and       audit    mines      for   have been shared
closure activities are being carried out in   implementation       of     mine    with Coal controller
an appropriate manner.                        closure activities. Recently, in    of     India,     and
                                              June, 2022 CMPDIL, RI-1 has         Director         level
                                              conducted       an    inspection    officers of ECL.
                                              regarding implementation of
                                              progressive      mine    closure
                                              activities    of    Gopinathpur
                                              Colliery as per the approved
                                              MCP for the period between
                                              2013-14 to 2017-18. The Audit
                                              report has been prepared by
                                              CMPDI and submitted to the
                                              Coal Controller by ECL.

                                              UPDATED           COMPLIANCE
                                              STATUS:


                                              13
                                                   Progressive mine closure audit
                                                  (PMCA) report of Gopinathpur
                                                  colliery duly prepared and
                                                  submitted by CMPDL, RI 1 and
                                                  submitted to CCO.
                                                  Kapasara colliery
                                                  The Coal Controller of India
                                                  (CCO) is the authority for
                                                  checking the implementation
                                                  status     of    mine    closure
                                                  activities as per approved
                                                  MCP. However, CMPDIL is
                                                  deputed/authorized to inspect
                                                  and       audit     mines     for
                                                  implementation       of     mine
                                                  closure activities.

                                                  UPDATED            COMPLIANCE
                                                  STATUS:

                                                  Inspection of mine closure
                                                  activities as per MCP of
                                                  Kapasara colliery by CMPDIL
                                                  has been done on 13.09.2022
                                                  and the Progressive Mine
                                                  Closure Audit (PMCA) report is
                                                  under      preparation     for
                                                  submission to the CCO by
                                                  CMPDIL, RI 1

C   Mining authorities (M/s ECL, M/s BCCL)        There are no abandoned or             Being complied.
    should provide the list of all the            closed mines in Mugma Area,           Notices           of
    abandoned as well as discontinued mine        ECL. The list of discontinued         discontinuance    of
    working in the area. It should be ensured     mines are as follows:                 Mandman colliery,
    by the mining authorities that the notice          1. Mandman           Colliery    Gopianthpur
    of     abandonment,        closure      or              (letter                of   Colliery        and
    discontinuance of all such mines are                    discontinuation)            Shampur A colliery
    given to the Chief Inspector (DGMS) as                  enclosed                    have           been
    well as the district administration as per         2. Gopinathpur colliery (-       submitted         to
    rule.                                                   do-)                        DGMS.q
                                                       3. Shampur A Colliery (-
    It should be ensured by the lease holder                do-)
    or the owner of the mine that no mine                   Annexure            (C1)
    should be discontinued or abandoned in                  Mandman UG
    violation   of   the   existing   safety                Annexure            (C2)
precaution as per CMR 2017. Gopinathpur UG Annexure (C3) Shampur AUG UPDATED COMPLIANCE STATUS: -do-

D Fencing around mines can be done in Gopinathpur: Single row Gopinathpur:

two rows- ie. In between two rows of fencing has been provided all Being complied:
barbed wire fencing a trench (width 1m, around the void. It is proposed Barbed wire fencing depth 2m) can be made that shall make to fill the entire void within the was done all illegal/unauthorized mining and manual next two months. around the transportation of coal difficult. However, Annexure (D10 Photographs of discontinued as per DGMS Circular 11/1959, top of Fencing quarry. In the river the 'abandoned quarries' shall be fenced side two line of by (i) 0.4m thick brick wall in UPDATED COMPLIANCE barbed wire fencing lime/cement mortar not less than 1.5m STATUS: was done around high with a parapet top or (ii) 0.75m thick Although it was initially the quarry with stone wall in lime/cement mortar not less proposed to fill the void trench in between than 1.5m high. however the proposal could (see photos not be materialized due to 3,4,5,6,7,8) and a The fencing must also be maintained till unavailability of OB at trench between the whole area is completely reclaimed present. Therefore, as fencing was also as per rule. Necessary steps should be recommended fencing is being observed.
14
taken to ensure that no illegal mining is done in two rows of barbed done in abandoned or discontinued wire with trench of 1 m and mine area by properly filling the exposed depth 2 m in between the coal faces of the discontinued workings. rows to make illegal/unauthorized mining and manual transportation of coal difficult.
Photographs of fencing attached as Annexure-3. Kapasara: Being Kapasara: complied but The work for fencing of moving further action front of OCP by providing needed.
single row fencing of barbed wire in Kapasara OC has been South side and completed. This is as per west side of the DGMS circular No.11/1959. quarry has been Annexure(D2) Photographs of fenced by barbed Fencing wire and cement pole (see photos UPDATED COMPLIANCE 12,13,16).
                                                STATUS:                           In east side of the
                                                Work for providing single row     quarry fencing and
                                                fencing of barbed wire for        check post were not
                                                moving front of the OCP as per    yet provided.
                                                DGMS circular No.11/1959          In north side of the
                                                has been completed.               mine, RCC brick
                                                Annexure (4) Photographs of       wall    was    being
                                                Fencing                           constructed around
                                                                                  the         opencast
                                                                                  workings.


E   Number of checkpoints can be made           Gopinathpur: One check-point      Gopinathpur:
    around the mines especially at those        is provided at the entry/exit     Being      complied:
    places from where there are chances of      point of the mine. The            Two check posts
    unauthorised entry of outsider for theft    discontinued mine void is         with security guard
    of coal and transport of theft coal from    properly fenced and display       were provided in
    mine to outside. It must be ensured that    boards     are   provided   at    two         entry/exit
    each of the abandoned/discontinued          approach       points     with    locations    to     the
    mine workings are provided with proper      information.                      quarry (see photos
    fencing and sufficient no. of display       Annexure (E1) Photographs of      10,11).
    boards of adequate size at all common       checkpoints     and    display    Adequate      display
    approach point with information about       boards are enclosed for           boards               for
    the    date    of    discontinuance     /   reference.                        preventing      illegal
    abandonment stating that entering into                                        entry to the mine
    the area by anyone is illegal as per rule   UPDATED          COMPLIANCE       were place near
    (as provided at Railway crossing).          STATUS:                           common approach
                                                Display      boards       with    points to the mine.
                                                information such as date of
                                                discontinuance,            etc,   Kapasara:       Being
                                                checkpoint at the entry/exit      Complied:
                                                pint of the mine, fencing, etc
                                                are being properly maintained.    Two check post with
                                                Photographs     enclosed    for   security guard were
reference as Annexure-5. provided in north Kapasara: side entry to the Two check points have been mine and one check provided in Kapasara colliery, post with security one near the weighbridge and guard was provided another at Muchi cutting. in west side entry to Proper fencing have been the mine (see photo provided. 15).
                                                Display boards have been          Adequate     display
                                                provided at check points and      boards             for
                                                other such prominent points in    preventing     illegal
                                                the mine.                         entry to the mine
                                                Annexure (E2) Photographs of      were placed near


                                                15
                                                 checkpoints     and     display     common approach
                                                boards are       enclosed for       points to the mine.
                                                reference.

                                                UPDATED          COMPLIANCE
                                                STATUS:
                                                Display    boards,   fencing,
                                                checkpoints etc are being
                                                properly maintained.
                                                Annexure (60 Photographs of
                                                checkpoints    and   display
                                                boards are enclosed for
                                                reference.


F   Round       the    clock    rounds    by    Gopinathpur: Round the clock         Being     complied
    CISF/internal security of coal companies    rounds by CISF, internal            but further action
    by mobile vehicles. This inspecting CISF    Security Personnel of ECL as        needed. Reply of
    officials and internal security members     well as concerned Local Thana       PP is as given in
    should be connected directly to local       authority is being done in both     adjacent     column.
    police control room so that they can        Kapasara and Gopanathpur            Better co-ordination
    report/ask for help, etc.                   OCP.                                and connectivity is
                                                UPDATED           COMPLIANCE        required    between
                                                STATUS:                             internal     security
                                                A       logbook/register     of     members and local
                                                patrolling by internal security     police control room
                                                by mobile vehicles is being         to    stop     illegal
                                                mainatained. Photographs of a       mining.
                                                few random pages of the
                                                register are enclosed for
                                                reference as Annexure-7.
                                                Kapasara colliery:
                                                Round the clock rounds by
                                                CISF,      internal    Security
                                                Personnel of ECL as well as
                                                concerned       Local    Thana
                                                authority is being done in both
                                                Kapasara and Gopanathpur
                                                OCP.

                                                UPDATED          COMPLIANCE
                                                STATUS:
                                                A       logbook/register     of
                                                patrolling by internal security
                                                by mobile vehicles is being
                                                mainatained. Photographs of a
                                                few random pages of the
                                                register are enclosed for
                                                reference as Annexure-8

G   Installation of CCTV cameras in and         Gopinathpur: CCTV cameras           Gopinathpur:
    around the mines that can aid in            have     been     installed    in   Being       complied
    identification of persons engaged in        Gopinathpur colliery which          but further action
    illegal/un-authorised    mining.    They    covers five prominent locations     needed: Eight CC-
    should be connected with common             of the mine, namely-                TV cameras were
    control room having access to CISF.             1. At the entry gate            installed in the mine
    Internal security in-charge, local police       2. The          discontinued    to cover the entire
    and other key person who can take                   mines area                  discontinued
    action.                                         3. The coal depot               quarry.            The
                                                    4. The sub-station              surveillance     room
                                                    5. At the back of the           was in the mine
                                                        Manager's office            office, situated near
                                                    6. Annexure              (GI)   the      mine     (see
                                                        Photographs enclosed        photo9).            As
                                                        for reference.              informed       during
                                                UPDATED           COMPLIANCE        inspection       there
                                                STATUS:                             was fifteen days


                                                16
                                                Additionally, four (04) nos. of    backup of the CCTV
                                               cameras have been installed        footage. There was
                                               at prominent locations as          no power back up
                                               follows:                           facility of operation
                                                    1. At the embankment at       of     the   installed
                                                       the vulnerable point       CCTV during power
                                                    2. At the embankment          failure. The control
                                                       near        Kalimandir     room should have
                                                       covering east side of      access to the local
                                                       the OCP.                   police.
                                                    3. At embankment near
                                                       Kalimandir      covering
                                                       the west side of the
                                                       OCP.
                                                    4. At the entrance of the
                                                       manager's office
                                               Proposal for PTZ camera has
                                               also been sent to HQ.
                                               Annexure     (GI)   Photogrphs
                                               enclosed for reference.
                                               Photographs are enclosed for
                                               reference as Annexure 9.
                                               Kapasara:                          Kapasara: Being
                                                CCTV cameras have been            complied            but
                                               installed at Entry Point &         further          action
                                               Weighbridge. Proposal for PTZ      needed.
                                               camera has been sent to HQ.        Four CCTV cameras
                                               Annexure (G2) Photographs          were installed in the
                                               enclosed for reference.            middle of the quarry
                                                                                  to cover the entire
                                               UPDATED          COMPLIANCE        face of the quarry in
                                               STATUS:                            east, south and
                                                                                  east direction (see
                                               Additionally four (04) nos. of     photo 14) . In north
                                               cameras have been installed        direction            the
                                               at the weighbridge and 5 nos.      decoaled area was
                                               of    cameras     have   been      being backfilled by
                                               installed at the active mining     overburden
                                               area.                              removed from the
                                               Annexure (G2) Photographs          mine.               The
                                               enclosed for reference.            surveillance       room
                                               Photographs are enclosed for       was in the agent
                                               reference as Annexure 10           office of the mine,
                                                                                  situated near the
                                                                                  mine. As informed
                                                                                  during       inspection
                                                                                  there was seven
                                                                                  days backup of the
                                                                                  CCTV footage. There
                                                                                  was no power back
                                                                                  up       facility     of
                                                                                  operation of the
                                                                                  installed         CCTV
                                                                                  during            power
                                                                                  failure.            The
                                                                                  Control           room
                                                                                  should             have
                                                                                  access to the local
                                                                                  police
H   Drones can be utilised for tracing         Proper      FIR      regarding     No drones has been
    illegal/un-authorised mining that may      illegal/un-authorised entries      utilized for tracing
    be going on in the project/area and also   to the mine is being done by       illegal/un-
    for action by internal security/CISF and   Manager/Agent of the mine          authorized mining
    Local Police administration.               and Area Security In-Charge.       that may be going
                                                                                  on         in        the
                                               UPDATED          COMPLIANCE        project/area        and
                                               STATUS:                            also for action by


                                               17
                                                 Drone survey has been done        internal
                                                in Gopinathpur colliery on        security/CISF and
                                                14.10.2022 to trace illegal       Local         Police
                                                mining.                           administration.
                                                Photographs     attached    for
                                                reference as Annexure 11.
                                                Kapasara colliery
                                                Proper      FIR      regarding
                                                illegal/un-authorized entries
                                                to the mine is being done by
                                                Manager/Agent of the mine
                                                and Area Security In-Charge.
                                                UPDATED          COMPLIANCE
                                                STATUS:

                                                Drone survey has been done
                                                in   Kapasara  colliery  on
                                                14.10.2022 to trace illegal
                                                mining.

                                                Phtographs     attached   for
                                                reference as Annexure 12.




I   All the above arrangements would be         UPDATED        COMPLIANCE         Being complied.
    futile if local Police department do not    STATUS:                           1. Total     FIR   on
    take strict action against the identified   Being maintained.                    illegal mining (till
    or     caught    illegal  mines.   Strict   Kapasara:                            Nov. 2022):347
action/Punishment can only deter the 2. 178 arrested illegal/un-authorised miners to leave Proper FIR regarding 3. Around 48000 this unlawful job. Proper FIRs should be illegal/un-authorized entries ton and 300 jute done and illegal/un-authorised miners to the mine is being done by bags filled with be brought to justice/punishment may Manager/Agent of mine, Area coal recovered be given as per the law, then only fear Security In-Charge. 4. Dedicated force of law can be penetrated among UPDATED COMPLIANCE provided by DIG illegal/un-authorised miners. STATUS: for raid.
Being maintained. 5. Special drives are conducted every month for minimum of 10 days.
6. Monthly meeting of mining task force for better coordination and resolution of any pending issues.
7. The above data is for Dhanbad District from January 2022 to November 2022.
18

J Alternate occupation / employment / Following Works under CSR in Partially means of livelihood can be given to relation to Alternate complied:

illegal/un-authorised miners so that if occupation/employment/mean Project authorities they leave the work of illegal mining s of livelihood/skill training showed a training they can sustain their and their family's were undertaken with are Centre at Mugma life. Skill development programmes can listed below:- area where tailoring be done/ initiated for local villagers 1. CSR project on Skill training was around the mines area in the field of Development Training for imparted to women. textile, handloom making, tailoring, unemployed youths within Six women were candle making, food processing, phenyl periphery villages. present during and liquid soap making, mobile and Implementing Partner - committee member laptop repair works, other electrical and George Telegraph inspection and they electronic repair works etc. Mine Training Institute, informed that were management can initiate the above skill Asansol given training about development programmes in a vigorous Trades: tailoring. manner and also make propaganda a. Automobile Technician about it (door to door campaign, b. AC & Refrigeration However, overall pamphlet distribution/pasting, Technician involvement of newspaper advertisement can be done). c. Household Appliances local people by PP District Mineral fund can also be utilised & Electrical for skill for such skill development program. Technicians development was Villagers can also be encouraged to do d. Mobile & Telephone not found farming/agriculture - Multiple crop Mechanic satisfactory. forming can be encouraged. Water can Duration Project- -06 be provided by BCCL/ECL mines months (Each Course) (FY management (Many of the abandoned 2016-17) mines work as water storage in the area). 2. CSR project on Skill Training of Youths (SC, ST, Backward Communities) in Plastic Engineering Trades by CIPET (Central Institute of Petrochemical Engineering & Technology) Implementing Partner-
                                                    CIPET       (Bhubaneshwar,
                                                    Haldia, Balasore).
                                                    Trades:-
                                                  1. Plastic           Processing
                                                     Technology,      testing   &
                                                     quality control.

                                                  2. Microprocessor       based
                                                     injection moulding, Process
                                                     & trouble Shooting
                                                     Duration of Project-01 Year
                                                 (Each Course) (FY-2019-20)

                                                  3. CSR project on Training of
                                                     SC & ST unemployed
                                                     youths for 04 year Mining
                                                     Sirdar Training

                                                  4. Implementing      Partner-
                                                     HRD, Dishergarh, ECL (In
                                                     house Project)
                                                 Duration of Project-04 Years
                                                 (FY 2016-2020)
                                                 Proposed skill Development
                                                 Projects   (proposals   under
                                                 Process)

                                                 1. CSR Project on Tailoring,
                                                    Dress making for 120 SC, ST
                                                    and Backward community
                                                    Women       from   different
                                                    villages within Command of


                                                 19
                                                      Mugma Area.
                                                     Duration    of    Project-02
                                                     Months
                                                     Implementing        Partner-
                                                     Through Local NGO
                                                     Outcome-Skilling,
                                                     Entrepreneurship
                                                     Development among women.

                                                   UPDATED           COMPLIANCE
                                                   STATUS:

                                                   Training of tailoring is being
                                                   given    to   PAP     families.
                                                   Photographs     attached     as
                                                   Annexure                    13.

K   At some mines it was observed that             The land acquisition of OCP to
    mine face/highwall could not advance           advance the faces is in
    due to unavailability of land. Though the      progress         and       local
    adjacent land (adjacent to coal faces)         administration/District
    are in the lease area but due to land          officials help is sought. Filling
    acquisition         problems           coal    by over burden of the
    companies/projects are unable to               discontinued faces is going on.
acquire their lands. At these places local administration/District officials can help UPDATED COMPLIANCE the coal companies in acquiring the STATUS:
land. When the coal face advances and legal mining by coal companies are Kapasara OC is presently ongoing there is little chance of illegal running and has started mining. But as the coal face advance production. stops and mine patch is discontinued / temporarily stopped due to further land acquisition, a chance is given for illegal mining (At that position coal companies could not go for backfilling as mine has to further advance and exploit the coal further). Coal companies can prepare and hand over the list of those mine (mine patches where coal face advance has been temporarily stopped due to land acquisition problems) to District administration. District admin. should co-operate with coal projects/companies to expedite the process of land acquisition.
L Internal calculation/comparison of A register as per prescribed Being complied. production, dispatch and reserve format is being maintained depletion of coal by coal companies. A and duly signed by the register can be made for comparison officers as stated in the letter. purpose that may be signed daily by UPDATED COMPLIANCE Geologist, Mines Manager, Surveyor, STATUS: Project Officer and General Manager of the Mines/Area of the coal companies. A register in prescribed format Thus with the aid of above viz., proper is being maintained. mine closure making arrangements in Photographs attached for and around the mine to make illegal/ reference as Annexure 14 unlawful mining extremely difficult, &15. identification, catching of illegal/ un- authorised miners, punishing illegal/un- authorised miners through law, providing alternative livelihood to local villagers, etc. illegal mining and accidents thereof can be reduced and eliminated."
20

8. We have considered the compliance report and the suggestions made by the Committee in the affidavit.

9. We are of the view that nothing further remains for adjudication in the present M.A. except to direct the concerned Respondent No.1 to ensure that projects which are partially complied or being complied but not complete, be completed expeditiously by 31.05.2023.

10. M.A. No. 38/2022/EZ is accordingly disposed of.

11. There shall be no order as to costs.

..................................... B. Amit Sthalekar, JM ..................................... Prof. A. Senthil Vel, EM January 24, 2023 M.A. No.38/2022/EZ In Original Application No.50/2022/EZ BD 21