Section 89(8) in Andhra Pradesh Metropolitan Region and Urban Development Authorities Act, 2016

(8)Where an appeal is preferred under sub-section (7) against an order made under sub-section (3), the Tribunal may stay the enforcement of the order on such terms, and for such period, as it may think fit:Provided that where the construction or re-construction of the building or the execution of the work has not been completed at the time of the order made under sub-section (3), no order staying the enforcement of the order made under that sub-section shall be made by the Tribunal unless a surety, sufficient in the opinion of the said Tribunal, has been given by the appellant for not proceeding with such construction or re-construction or work pending the disposal of the appeal.