Section 24(2)(i) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014
(i)in case of projects commissioned on or after 1st April, 2014, an additional return of 0.50 % shall be allowed, if such projects are completed within the timeline specified in Appendix-I: