Union of India - Subsection

Section 4(2) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

(2)Date of commercial operation in relation to a generating unit of hydro generating station including pumped storage hydro generating station shall mean the date declared by the generating company from 0000 hour after the scheduling process in accordance with the Grid code is fully implemented, and in relation to the generating station as a whole, the date declared by the generating company after demonstrating peaking capability corresponding to installed capacity of the generating station through a successful trial run:Provided that:
(i)where beneficiaries have been tied up for purchasing power from generating station, scheduling process for a generating unit of the generating station or demonstration of peaking capability corresponding to installed capacity of the generating station through a successful trial run shall commence after seven days notice by the generating company to the beneficiaries and scheduling shall commence from 0000 hr after completion of trial run:
(ii)the generating company shall certify to the effect that the generating station meets key provisions of the technical standards of Central Electricity Authority (Technical Standards for Construction of Electrical plants and electric lines) Regulations, 2010 and Grid code:
(iii)the certificate shall be signed by CMD/CEO/MD of the company subsequent to its approval by the Board of Directors in the format enclosed at Appendix VI and a copy of the certificate shall be submitted to the Member Secretary, (concerned Regional Power Committee) and concerned RLDC before declaration of COD:
(iv)in case a hydro generating station with pondage or storage is not able to demonstrate peaking capability corresponding to the installed capacity for the reasons of insufficient reservoir or pond level, the date of commercial operation of the last unit of the generating station shall be considered as the date of commercial operation of the generating station as a whole, and it will be mandatory for such hydro generating station to demonstrate peaking capability equivalent to installed capacity of the generating unit or the generating station as and when such reservoir/pond level is achieved:
(v)if a run-of-river hydro generating station or a generating unit thereof is declared under commercial operation during lean inflows period when the water inflow is insufficient for such demonstration of peaking capability, it shall be mandatory for such hydro generating station or generating unit to demonstrate peaking capability equivalent to installed capacity as and when sufficient water inflow is available.