Section 4(7) in The Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011

(7)The Commission shall approve the system augmentation plan submitted by the Transmission Licensee, based on the load growth forecast during the Control Period. The same would be considered for computation of ARR, wherein the amount of electricity transmitted by the Transmission System shall be projected considering the estimated growth plan of its Beneficiaries and any plans of new transmission system, based on network expansion plans within the State.