Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Section 18(2)] [Section 18] [Entire Act]

Union of India - Subsection

Section 18(2)(c) in The Petroleum and Natural Gas Regulatory Board (Authorizing Entities to Lay, Build, Operate or Expand City or Local Natural Gas Distribution Networks) Regulations, 2008

(c)a satisfactory assessment of the actual physical progress made and the financial commitment thereof till immediately before the appointed day in comparison with the entity's DFR appraised by the financial institution funding the project. In case the project has not been funded by any financial institution, the Board may appraise the DFR. The DFR of the entity should clearly indicate the specified geographical area of the project and also specify the coverage proposed for CNG and PNG. In case upon scrutiny of the DFR by the Board by taking into account the geographical area, segments, infrastructure requirements, etc. proposed by the entity, the DFR is found to be sub-optimal and unacceptable, the Board may not consider the case of the entity for issuing the authorization;