$~31
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. (COMM) 311/2021
MBL INFRASTRUCTURES LIMITED ..... Petitioner
Through: Appearance not given
versus
DELHI METRO RAIL CORPORATION ..... Respondent
Through: Mr. Ankur Chhiber, Mr. Nikunj
Arora and Mr. Parv Garg, Advocates
CORAM:
HON'BLE MR. JUSTICE CHANDRA DHARI SINGH
ORDER
% 30.11.2022
I.A. 13235/2021
Subject to the plaintiff filing the clear, original and legible/typed copies of any dim documents on which the plaintiff may seek to place reliance, within four weeks from today, exemption is granted for the present.
The application is disposed of.
I.A. 5670/2022 (Delay)
1. This is an application under Section 5 of Limitation Act, 1963 read with Section 151 of the Code of Civil Procedure, 1908 for condonation of delay in filing the written submissions on behalf of the respondent.
2. For the reason stated in the application, the delay of 57 days in filing the written submissions on behalf of respondent is condoned.
3. The application is disposed of.
Signature Not Verified Digitally Signed By:DAMINI YADAV Signing Date:01.12.2022 18:22:00O.M.P. (COMM) 311/2021 Learned Arbitral Tribunal is directed to place the record before this Court.
List on 21st March 2023.
CHANDRA DHARI SINGH, J NOVEMBER 30, 2022 Pkb/mg Signature Not Verified Digitally Signed By:DAMINI YADAV Signing Date:01.12.2022 18:22:00