Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 4, Cited by 18]

Calcutta High Court (Appellete Side)

Alishan Steels Private Limited & Anr vs West Bengal Electricity Regulatory ... on 12 February, 2021

Author: Arindam Mukherjee

Bench: Arindam Mukherjee

     8
12.02.2021
 Ct. No.23
     sb.
                         IN THE HIGH COURT AT CALCUTTA
                        CONSTITUTIONAL WRIT JURISDICTION
                                 APPELLATE SIDE
                              (Via Video Conference)

                                  WPA 4174 of 2021

                      Alishan Steels Private Limited & Anr.
                                        Vs.
              West Bengal Electricity Regulatory Commission & Ors.


                       Mr. Surojit Nath Mitra, Sr. Advocate
                       Mr. Tanoy Chakraborty
                       Mr. Siddharth Shroff
                                   ... For the petitioners

                       Mr. Pratik Dhar, Sr. Advocate,
                       Ms. Neha Chakraborty
                                   ... For WBERC

                       Mr. Jaydip Kar, Sr. Advocate
                       Mr. Prasun Mukherjee
                       Mr. Deepak Agarwal
                                   ... For DVC.


                       Affidavit of service filed in Court today is taken on

             record.

                       The petitioner no.1 is a consumer under Damodar

             Valley Corporation (in short "DVC") for its factory situated

             at Hetedoba, Durgapur. The petitioners in this writ petition

             have challenged the summary statement raised by DVC,

             the licensee, dated 1st January, 2021 along with the

             amended bills claiming a sum of Rs.2,18,43,153/- and the

             disconnection notice dated 28th January, 2021 issued by

             DVC for a claim of Rs.1,95,94,996/- thereby threatening

             to disconnect the supply of petitioner no.1 within 15 days

             from the date of issuance of the said notice. The 15 days

             time period from 28th January, 2021 takes us to 12th
                      2




February, 2021. The petitioners say that nothing is payable

according to the demand made and therefor has not paid

the amount claimed or any part thereof. The petitioners

apprehend disconnection. The disconnection, if effected,

will stop the operation of the factory and will cause

immense loss to the work-in-progress. The employees of

the petitioner no.1 including the petitioner no.2 will be

deprived of their livelihood if the disconnection takes place.


       The petitioner say that after several rounds of

litigation ultimately by an order dated 19th March, 2020,

the West Bengal Electricity Regulatory Commission (in

short, WBERC) fixed the retail tariff for the year 2009-10,

2010-11 and 2012-13. By another order dated 19th June,

2020, WBERC fixed the retail tariff for the year 2006-07

and 2008-09.


       As per records it is an admitted position that a net

 principal amount of Rs.3,96,56,288/- was an excess

 payment made by the petitioners for the period 2006-09.

 DVC is required to give 6% interest to the petitioners in

 terms of the order dated 10th May, 2010 passed by the

 Appellate Tribunal for electricity.


       It is the case of the petitioners that from the

 principal sum of Rs.3,96,56,288/-, the electricity bills

 dated 5th August, 2009, 17th September, 2009, 6th

 October, 2009, 10th November, 2009, 8th December, 2009,

 7th January, 2010, 9th February, 2010, 5th March, 2010,
                     3




31st March, 2010, 10th April, 2010 and 8th May, 2010

aggregating to Rs.2,78,17,031/- have deducted which

brings the figure of Rs.3,96,56,288/- to Rs.1,18,39,257/-

being the net principal amount refundable. 6% interest

has been calculated on reducing balance of the principal

sum to arrive at a net interest of Rs.1,22,46,991/-


            Against      an     aggregate        interest    of

Rs.1,22,46,991/-,     DVC     has    adjusted    the   Delayed

Payment Surcharge (in short "DPS") and arrived at a sum

of   Rs.1,98,78,012/-.   DVC        thereafter   adjusted   the

principal sum of Rs.1,18,39,257/- with Rs.1,98,78,012/-

and added Rs.1,38,04,398/- to be allegedly due on 10th

August, 2020 as arrears of 2009-2013 to arrive at

Rs.2,18,43,153/- said to be payable by the petitioner No.1

to DVC for the period 2010-2013.

            This alleged DPS, according to DVC, is in

terms of the agreement between the petitioners and DVC.

On behalf of the petitioners, it is submitted that DVC has

wrongfully charged DPS though such DPS is neither

realisable by DVC nor payable by the petitioners. There

has been no delay on the part of the petitioner no.1 in

making payment as the bill raised by DVC which

contained arbitrary figures as the same were raised

without the tariff being fixed by the WBERC. The bill

value cannot be said to be payable by the petitioner no.1.

DVC has in an unauthorised manner reduced the interest

accrued on the principal sum and thereafter adjusted the
                          4




 DPS against such reduced interest. There is, as such,

 according to the petitioners, no amount payable if a

 proper account is taken in the matter. When the principal

 sum is admitted, DVC cannot claim DPS when bills

 became payable in 2020 after the order of WBERC.

 Looking      from   a   different   angle    assuming    without

 admitting that bills of 2009-2013 became payable on their

 respective due dates then the same are barred by

 limitation being hit by provisions of section 56(2) of the

 Electricity Act, 2003. Disconnection in that event cannot

 be made in view of the ratio laid down in 2020 (4) SCC

 650 (Assistant Engineer (DI), Ajmer Vidyut Vitran

 Nigam Limited & Anr. V. Rahamatullah Khan Alias

 Rahamjulla).


       On behalf of DVC it is submitted that the bill has

been raised in terms of the various orders passed in the

proceedings inter se between the parties as also in terms of

the order of the Central and the State Electricity Regulatory

Commission. There is, as such, no error in the bill and the

petitioners    are   liable   to     pay     the   said   sum   of

Rs.2,18,43,153/-. It is also submitted on behalf of DVC that

the petitioners have disputed the bill raised by DVC. A

billing dispute is required to be adjudicated by the Regional

Grievance Redressal Officer, (in short, RGRO) set up in

terms of Section 42(5) of the said Act and then by the

electricity Ombudsman under Section 42(6) of the said Act.

The petitioners should be asked to approach the concerned
                      5




RGRO for redressal of his disputes. Some of the consumers

in similar circumstances have approached the RGRO. DVC

also says that in terms of the agreement between the

petitioners   and   respondents   there   is   an     arbitration

agreement and the disputes raised by the petitioners are squarely covered by the arbitration clause and as such they could have approached the arbitrator. The writ petition is not maintainable in view of the subsistence of the arbitration agreement and availability of a statutory forum.

On behalf of West Bengal Electricity Regulatory Commission (in short, WBERC), it is submitted that on the issue of disconnection, WBERC has nothing to say as it is inter se dispute between the petitioner and DVC. So far as the dispute regarding the bill raised by DVC, WBERC says that RGRO and then electricity Ombudsman are the statutory authorities before which the grievance has to be ventilated by the petitioners. In this regard, WBERC has relied upon a judgment reported in (2007) 8 SCC 381 (Maharashtra Electricity Regulatory Commission vs. Reliance Energy Ltd. & Ors.). Relying upon paragraphs 22, 31 and 33 it is submitted that RGRO is the only forum which can be approached by the petitioners.

After considering the respective submissions and the materials on record, the right of DVC to realise DPS and the accounting procedure as raised by the petitioners cannot be gone into without calling for affidavits. 6

So far as the interim protection as to the threat of disconnection is concerned, the Court is required to balance the scales. It is an admitted position that a sum of Rs.3,96,56,288/- is the net principal amount payable by DVC to the petitioners. It is also an admitted position that a sum of Rs.1,22,46,991/- has accrued as interest even on the reduced principal sum as per the order of Appellate Tribunal for Electricity. The aggregate sum of such interest and principal is in excess of Rs.5,31,02,393/-. The DPS realised is an issue required to be adjudicated after filing of affidavits.

With regard to the realization of DPS, I also find substance in the contention of the petitioners at this stage. As to whether DVC can realize DPS is dependant on various factors like the interpretation of the clause for the same in the agreement, the limitation as to the bills, the interpretation of various orders. These issues cannot be gone into without complete disclosure in the affidavits to be filed. At this stage, the adjustment of the interest payable to the petitioner against DPS, and then against the principal cannot be said to be realisable from the petitioners without there being detailed enquiry in this regard after filing of affidavits. DVC also did not take any steps to disconnect the electricity between 2009 - 2013 when according to them bills remained unpaid. The balance of convenience and inconvenience is therefor tilted in favour of 7 the petitioners. The petitioners have also made out a prima facie case and are, therefor, entitled to an order of injunction restraining DVC from disconnecting the supply of the petitioners for non-payment of the amount claimed in the bill dated 1st January, 2021, till the final disposal of the writ petition. The petitioner no.1, however, shall continue to pay the regular consumption bills that may be raised by DVC from time to time during the pendency of the writ petition.

With regard to the contention raised by DVC and WBERC that the matter should be sent to the RGRO, I am of the view that the dispute in hand is not a classical billing dispute wherein either the meter is defective or erroneous meter reading involving any outstanding energy charge for the consumption made by the petitioners in regular course as considered by the Commission in case of Reliance Energy (supra). The bill is on account of alleged arrears after adjustment of an admitted sum. The adjustment includes the legality to realise DPS and bills for the period 2009 to 2013 after about seven years. These issues also cannot be effectively decided by the RGRO or the arbitrator. This Court is empowered to go into the legality of realisation of DPS and adjustment on account thereof as also for bills unrealised for over seven years.

8

Since I have admitted the writ petition for being finally heard after the affidavits, I have not dealt with the judgments cited in details.

Let affidavit-in-opposition be filed within a period of three weeks from date. Reply thereto, if any, be filed within two weeks thereafter.

Liberty to mention for inclusion in the list under the heading "Hearing" after six weeks.

(Arindam Mukherjee, J.)