34. [ Capital Cost. [Substituted by Notification No. 49-JKSERC of 2016, dated 22.3.2016 (w.e.f. 17.5.2013).]

- The normative capital cost for the biomass power projects based on Rankine cycle shall be as under:-a. 540 lakh/MW for project [other than rice straw and juliflora (plantation) based project] with water cooled condenser;b. 580 lakh/MW for Project [other than rice straw and Juliflora (plantation) based project] with air cooled condenser;c. 590 lakh/MW for rice straw and juliflora (plantation) based project with water cooled condenser;d. 630 lakh/MW for rice straw and juliflora (plantation) based project with air cooled condenser.]