Section 4(15) in The Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011

(15)Where the Transmission Licensee makes an application for approval of R&M proposal, the approval shall be granted after due consideration of reasonableness of the cost estimates, financing plan, schedule of completion, interest during construction, use of efficient technology, cost-benefit analysis, and such other factors as may be considered relevant by the Commission.