Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 3, Cited by 0]

Jharkhand High Court

Veer Krishna Sahay vs M/S Vardaan Builders & Anr on 9 April, 2012

                                             1

IN THE HIGH COURT OF JHARKHAND AT RANCHI 
          W.P(C). No. 2034 of 2010

Veer Krishna Sahay                                  ...     ...     ...      Petitioner
                         Versus
1. M/s Vardaan Builders, Ranchi
2. Narendra Butala                                  ...      ...    ...    Respondents

CORAM:        HON'BLE MRS. JUSTICE POONAM SRIVASTAV
                             ­­­­­
For the Petitioner     : M/s Sumeet Gododia, Bindeshwari Singh
For the Respondents    : M/s Rajesh Kumar, Amit Sinha, M.K. Sinha
                             ­­­­­

C.A.V. on : 11.01.2012                              Pronounced on: 09/04/2012
                                     ­­­­­

       Heard   counsel   Shri   S.   Gadodia,   assisted   by   Mr.   Bindeshwari   Singh, 
appearing on behalf of the petitioner as well as counsel Shri Rajesh Kumar, 
assisted by Mr. Amit Sinha and Mr. M.K. Sinha, appearing on behalf of the 
Respondents. 
       The   instant   writ   petition   is   preferred   challenging   the   order   dated 
07.04.2010

 (Annexure­12) in Execution Case No. 3(A) of 2005 (B.K. Sahay  Vs. M/s Vardaan Builders) passed by Sub­Judge­VI, Ranchi. 

The dispute relates to execution of an Award in respect of the delivery  of possession of 14 flats, as mentioned in the Arbitral Award/Decree passed by  the sole Arbitrator. The petitioner is the owner of 33 Kathas of land situated at  17,   S.K.   Sahay   Road,   Lalpur,   Ranchi.   An   agreement   was   entered   into   on  01.10.1998 between the petitioner and the contesting respondent Nos. 1 and  2,   who   is   a   builder   and   involved   in   the   business   of   development   and  construction of multistoried residential complex in the name and style of M/s  Vardaan Builders. The parties agreed that out of the proposed construction,  the owner - builder share would be in the following ratio : 

(I) Owner's allocation (27%) :  59400 x 27     = 16,038 sq. ft.             100 (II) Builder's allocation (73%) :  59400 x 73      = 43,362 sq. ft.          100

This allocation was calculated on the basis of total areal of land which  was   33   Kathas.   The   dispute   arose   between   the   parties   regarding   the  development   agreement   including   the   handing   over   of   the   share   of   the  petitioner. Arbitration Clause of the Development agreement was invoked at  the   instance   of   the   petitioner   and   the   matter   was   referred   to   the   sole  Arbitrator­ Hon'ble Mr. Justice P.K. Sarkar, retired Judge of the Patna High  2 Court. The Award was passed on 31.10.2004 (Annexure­ 2). Extract of the  Award is detailed in paragraph­ 10 of the writ petition and the same is quoted  below : ­ "(i) In the result of the discussions above, I am of the opinion   that   the   owner­claimant   is   entitled   to   possession   of   the   14   flats   containing  built up area of  16038  sq. ft. along with 27 p.c. of the   parking space and 50 p.c. of the roof area. Out of the above 14 flats   containing built up area of 16038 sq. ft. the owner­claimant is entitled   13 flats along with 27 p.c. of the parking space as mentioned in the   report   of   the   Commissioner   within   15   days   from   today   and   the   possession of the remaining one flat containing the remaining portion   of   27   p.c.   of   the   owner­share   will   be   given   to   the   owner­claimant   within 15 days of payment of Rs. 6 lakhs the security amount and Rs.   3 lakhs as additional amount for the deviation in specification of the   construction   work   along   with   interest   at   the   rate   of   12   p.c.   on   aforesaid Rs. 9 lakhs from today i.e. the date of award till payment. In   case the Respondent­Builder fails to hand over possession of 13 flats of   the owner  share and  27 p.c. of  the car  parking space as per  above   direction within 15 days and also the remaining one flat measuring the   remaining portion of the 27 p.c. of the built up area within 15 days of   the payment of Rs. 9 lakhs along with interest at the rate of 12 p.c.   from today with payment of the value surplus of area if the case such   be in the measurement of the last (14th ) flat, the owner­claimant will   be entitled to get damages/penalty at the rate of Rs. 30,000.00 per   month for the 1st  6 months and Rs. 50,000.00 per month thereafter   with effect of the 16th day of the above payment till the day possession   is given.

 

(ii) Accordingly   the   award   is   made   in   favour   of   both   the   owner/claimant and the Respondent­Builder to the extent mentioned   below : ­

(a) The   Respondent­Builder   will   make   delivery   of   possession of 13 flats and 27 p.c. of car parking space as per the   Commissioner's   report   within   15   days   of   today   i.e.   of   the   passing of award. 

(b) The Respondent Builder  should also complete the   incomplete   portion   of   the   boundary   wall   measuring   31.512   meter and should make provision for clearing the drain water   from the ground chamber towards the main Municipal drain in   the front side of the Building within 15 days, failing which he   will be liable to pay Rs. 30,000.00 per month for first 6 months   with effect from the 16th   day (from today) and Rs. 50,000.00   per month thereafter, till the above construction is complete.  

 

(c) The   owner­claimant   should   pay   a   sum   of   Rs.   9   lakhs (Rs. 6 lakhs towards return of security amount and Rs. 3   lakhs towards price of the work in deviation of the specification   in construction) along with interest at the rate of 12 p.c. on the   above amounting Rs. 9 lakhs from today i.e. the date of award,   till such payment. 

3

(d) On   such   payment   being   made   by   the   owner­ claimant the Respondent­Builder should hand over possession of   the remaining 14th flat measuring the balance portion of 27 p.c.   of  the built up area. If the measurement of the flat does not   fulfill the exact remaining 27 p.c. of built up area the difference   either more or less will be paid at the rate of Rs. 525.00 per sq.   ft. by the concerned party before such possession. The possession   of   the   14th  flat   will   be   delivered   by   the   Respondent/Builder   within 15 days of the above payment to the owner­claimant.

(e) In case the Respondent­Builder fails to hand over   possession of the 13 flats and 27 p.c. car parking space as per   Commissioner   report   within   15   days   from   today   as   directed   above the owner­claimant will be entitled for damages/penalty   at the rate of Rs. 30,000.00 per month for the first six months   from the 16th  day (from today) and Rs. 50,000.00 per month   thereafter, till such hand over of possession. 

(f) Similarly, if the Respondent­Builder fails to deliver   possession of the 14th flat constituting the remaining portion of   27% of the Built up area (with payment of less or more area as   directed   above)   within   15   days   the   owner­claimant   will   be   entitled   for   a   sum   of   Rs.   30,000.00   per   month   for   the   1st  6   months w.e.f. the 16th day (from today) and Rs. 50,000.00 per   month thereafter, till such hand over of possession. 

(g) As regards the cost of litigation in this arbitration   proceeding the parties should bear their own legal expenses.

 

(h) The petitioner/claimant also execute the remaining   Power of Attorney within 15 days from delivery of possession of   the 13 flats by the respondents/Builders to the owner/claimant.

 

Rest of the claims and counter claims of both the parties   are dismissed/rejected."

It  is   also  brought   to  my  notice   that  during   the   course  of  arbitration  proceeding, one Devabrata Bhadra, retired G.M. (Civil) CMPDI was appointed  as Commissioner to make measurements of the apartment constructed in  the  multistoried building with a view to allocate and demarcate respective shares  of the parties. The Commissioner was to submit measurements of the parking  space separately. A report was submitted by the Commissioner which included  a supplementary report duly signed by the petitioner and a representative of  the builder. There was no objection from either side regarding Commissioner's  report.   The   Award   was   given   by   the   sole   Arbitrator   on   31.10.2004   and   it  forms part of the record as Annexure­ 2. 

4

The builder filed an application challenging the Award under Section 34  of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as 'Act')  in   the   court   of   Sub­Judge,   Ranchi.   The   application   under   Section   34   was  dismissed by the Sub­Judge­VI, Ranchi, vide order dated 07.09.2005 in Misc.  Case   No.   01   of   2005.   Order   was   challenged   before   the   High   Court   in  Arbitration Appeal No. 15 of 2005, which was also dismissed, vide Annexure­4  to the writ petition dated 14.06.2007. This order was once again challenged  before the Hon'ble Supreme Court which stands dismissed, vide Annexure­ 5  to the writ petition dated 23.07.2007. 

Shri   S.   Gododia   appearing   on   behalf   of   the   petitioner   has   also  emphasized that the Commissioner's report was confirmed and the same was  never challenged. 

In fact, the controversy arose on account of the reason that after the  actual construction was completed and measurements were made, there was  an   excess   construction   of   634   sq.   ft.   The   report   of   the   Commissioner   is  Annexure­ 3 to the writ petition. 

Contention of the learned counsel is that altogether 14 flats were to be  allotted to the petitioner. 13 flats were already reserved measuring an area of  1470.57 sq. meter, which is equivalent to 15829.51 sq. ft. The remaining area  of the share of owner/petitioner was 16678.81 - 15829.51 = 849.30 sq. ft.,  but due to conversion, there was a difference of approximately 1.30 sq. ft. The  Arbitrator has mentioned in the order that the owner was entitled for 848 sq.  ft. of the remaining area. There is no dispute on this 848 sq. ft. It is further  stated that 14th flat comprises an area of 91.22 sq. meter, which is equivalent  to 987.27 sq. ft. Since the owner was entitled for 848 sq. ft., he is also entitled  to   the   additional   area,   subject   to   payment   at   the   rate   of   agreed   cost.  Therefore, the petitioner deposited the cost of the excess area in the court  below i.e. approximately 138/139 sq. ft. at a price of Rs. 525/­ sq. ft. 

Shri.   Gododia   while   emphasizing   his   submissions   stated   that   the  executing court while passing the impugned order was swayed by a certain  typographical error and placed reliance upon an inadvertent observation made  by the Arbitrator that the area allotted to the petitioner was only 16038 sq. ft.  The executing court merely on the basis of the said figure mentioned in the  Award proceeded to execute the decree and held that after making calculation  of   the   owner's   share   on   the   basis   of   16038   sq.   ft.,   an   area   of   214   sq.   ft.  remains   to   be   allocated.   The   court   held   that   the   owner­petitioner   is   not  5 entitled to the 14th flat and at best he can claim the value of 214 sq. ft. @ Rs.  525/­ per sq. ft. from the builder.

Shri   Rajesh   Kumar,   counsel   appearing   on   behalf   of   the   respondent­ builder   has   countered   the   arguments   of   Shri   S.   Gadodia   on   the   basis   of  assertion made in Annexure­ B to the rejoinder of the supplementary affidavit  filed on behalf of the builder that the executing court passed the order after  hearing both the parties. He made an offer to the judgment debtor to fulfill  the Award by giving 27% of the car parking space and a flat of 213 sq. ft. 

Contention of the respondent's counsel is that the claim of the petitioner  is altogether baseless. He cannot be given 14th flat as it will be in excess of the  area   given   in   Award.   The   builder's   counsel   has   also   pointed   out   certain  anomalies regarding the measurement of the Commissioner and argued that  in   the   event   the   said   measurement   of   the   Award   is   accepted,   the   Award  becomes inexecutable. 

I   have   heard   counsel   for   the   respective   parties   at   length   and   gone  through the records as well as the judgments. Apparently, both the parties  have   tried   to   raise   a   factual   controversy   regarding   measurements.   The  measurements were made by the Commissioner and the report was accepted  by the  Arbitrator. No objections  were raised and the  Award was passed in  terms of the Commissioner's report. The Award and its intention are liable to  be given effect by the executing court. 

I am not inclined to examine the  factual controversies in exercise  of  jurisdiction under Article 226 of the Constitution of India. However, the legal  submissions raised on behalf of the petitioner is regarding the question that  whether   the   execution   court   could   go   behind   the   Award   relying   upon   a  solitary typographical  error in para­ 38 of the Award. Learned counsel has  emphasized   that   the   findings   has   to   be   looked   into   and   if   there   is   some  anomalies then it had to be got rectified at the instance of the aggrieved party.  I cannot loose sight of the fact that the Award was challenged by respondent­ builder under Section 34 of the Act, thereafter in appeal and finally, before  the   Apex   Court   which   was   dismissed.   In   the   event   the   builder   was   not  aggrieved by the Award and he was satisfied with the observations, then there  was no occasion for him to challenge the Award. The Award has also been  appended   to   the   writ   petition   as   Annexure­   2.   The   Award   given   by   an  Arbitrator   after   examining   the   entire   controversy,   cannot   be   turned   and  twisted so lightly. 

6

On bare perusal of the extract of the Award as well as the operative  portion, it is stated in sub­para D of Issue No. 9 that on such payment being  made   by   the   owner   claimant   the   respondent   builder   should   hand   over  possession of the remaining 14th flat measuring the balance portion of 27 p.c.  of the built up area. In the event the measurement of the flat does not fulfill  the exact 27 p.c. of the built up area the difference either more or less will be  paid at the rate of Rs. 525.00 per sq. ft. by the concerned party before such  possession. The possession of the 14th flat will be delivered by the respondent/ builder within 15 days of the above payment to the owner claimant. 

A mere mention in sub­Clause A that the respondent­builder will make  delivery of possession of 13 flats and 27 p.c. of car parking space will not  render the Award redundant. The mistake occurred while mentioning the area  as 16038 sq. ft. in para 38 ­ Issue No. 9 sub­Clause (i)  is an error which the  executing court was liable to examine. On bare reading of the entire Award,  besides, Annexures - 6 and 6/1, which are orders of this Court in W.P.(C) No.  1818 of 2008 dated 21.10.2008 and also in Civil Review No. 106 of 2008  dated 03.03.2009, is sufficient to substantiate the contention on behalf of the  petitioner.  The   review   application   was   dismissed  with   cost   of   Rs.  25,000/­  payable by the  respondent­builder to the petitioner by the executing court.  These orders were part of the record before the executing court, but I fail to  understand how all these aspects and orders and judgments were completely  overlooked by the executing court. In fact, I fully agree with the observations  made by this Court in the writ petition and also Review application that the  respondent­builder has all along abused the process of law by raising frivolous  and vexatious objections. The process of law has blatantly been abused. The  petitioner has approached equity jurisdiction. This Court has also to examine  and ensure equities as well as that the orders and decree passed are complied  with.   The   Award   was   given   in   the   year   2004,   but   the   petitioner   who   is  incidentally also the owner of the property has been dragged into unnecessary  litigation. It is not the case of the respondent either before the executing court  or any other court that his share is less than the allocation of share agreed  upon in the initial agreement. Even if there was some discrepancy then it had  to   be   raised   and   got   corrected   before   the   Arbitrator.   The   Commissioner's  report  was   also not  challenged  and  it   is   only  at  a  subsequent  stage,  some  inadvertent  error was  noticed  by the  builder  which  he  tried to use  it as a  7 weapon to his advantage against the petitioner to somehow stall the execution  of the Award.

Before I part with the writ petition, I must express my concern over the  lackadaisical approach of the executing court either mistakenly or it was step­ in­aid to ensure that the decree is not executed. 

In the facts and circumstances detailed hereinabove, the writ petition is  allowed. The order of the executing court is set at naught and the executing  court is directed to ensure that the delivery of 14th  flat, which has an excess  area, then other 13 flats is handed over to the petitioner within a period of  two months from the date a certified copy of this order is produced before  him. He has also to ensure that the calculated amount already deposited by  the petitioner in lieu of the excess area is correctly calculated, but without  interfering with the decision  of the  Arbitrator  which  was  confirmed by the  Sub­Judge under Section 34 of the Act upheld by the Hon'ble High Court in  Arbitration Appeal as well as accepted and confirmed by the Apex Court. The  Award is liable to be given effect to within the aforesaid stipulated period of  two  months   and   any  dereliction   on   the   part   of   the  executing  court   or   the  respondent cannot be accepted since this Court while exercising jurisdiction  under Article 226 of the Constitution of India also exercises the supervisory  power under Article 227 of the Constitution.

The writ petition is accordingly allowed in the terms and observations  made hereinabove. 

         (Poonam Srivastav, J.) Jharkhand High Court, Ranchi dated 09/04/2012 Manish/N.A.F.R.