Section 8(1)(b) in Andhra Pradesh Electricity Regulatory Commission (Standards of Performance) Regulations, 2000

(b)Estimate charges for providing connection and security deposit required shall be intimated after the point of entry of supply mains and the position of mains, cutouts or circuit breakers and meter has been settled within 10 days if the connection is proposed to be given from existing network and within 30 days if extension is required or if additional/ enhancement of distribution transformer is needed.