Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 1, Cited by 0]

Delhi District Court

M/S B. Esskay Construction Co vs Delhi Development Authority on 20 September, 2018

       IN THE COURT OF PRAVEEN KUMAR: ADDITIONAL
     DISTRICT JUDGE­05 :NEW DELHI DISTRICT, PATIALA
                HOUSE COURTS, NEW DELHI.

Arbt. No.1121/2017                                               (Ten Years Old Case)
In the matter of:
M/s B. Esskay Construction Co.,
2­C/35, New Rohtak Road,
New Delhi                                                          ..................Petitioner

         Versus  

Delhi Development Authority
Through its Vice­Chairman,
Vikas Sadan, INA Office Complex,
New Delhi                                                     ..................Respondent

JUDGMENT:

1. Petitioner   filed   a   petition   u/S   14,   17   &   31   of   the Arbitration Act, 1940 before the High Court of Delhi (where the petition was earlier pending but was transferred to this court on account of change in pecuniary jurisdiction) for making the award dated 30.09.2008 Rule of the Court.

2. Respondent­DDA   filed   the   objection­petition   u/S 30/33   of   the   Arbitration   Act,   1940   praying   therein   that   the impugned award be set aside.

3. Briefly   stating,   objector/respondent   had   invited tenders   in   respect   of   the   construction   of   1200   MIG   Houses   in pocket GH­14, Paschim Vihar, Delhi as well as construction of Arbt. No.1121/2017 M/s B. Esskay Construction Co. Vs. DDA & Ors.                                           Page No.1 of 5 160 MIG Houses Group­V. The said tender was accepted and the work   was   awarded   to   petitioner.   Consequent   on   a   dispute,   an arbitrator   was   appointed   by   the   High   Court   of   Delhi   in   Suit No.CS(OS) No.1573/2006  vide  order dated 26.02.2007. The Ld. Arbitrator passed the award dated 30.09.2008 and had awarded the amount in respect of claim no.8(D), 8(vii), 9 & 11 which are being challenged in the present  objection petition by respondent. The rest of the award has been accepted by the objector/respondent.

4. The objector/respondent has challenged the impugned award on the following grounds:­

(a) that the award passed by the Ld. Arbitrator is against  the clauses of the agreement, CPWD Specifications;

(b)  that   in   respect   of   claim   no.8(D), no   amount is   payable;

(c) that the agreement item no.3.16 pertains to groove in  RCC Projections only and not in the RCC/Brick work with  respect to internal walls. Hence, this amount is not payable; 

(d) that no claim in respect of claim no.8(vii) is payable  as the period of one year expired on 25.05.1989 and by that  time 95%  of  the flats  stood already allotted. Hence,  the   claimant is not entitled to cost of deployment of watch and  ward;

(e) that   as   per   clause   17(B)   of   the   agreement,   the   maintenance period is for one year but the Ld. Arbitrator has Arbt. No.1121/2017 M/s B. Esskay Construction Co. Vs. DDA & Ors.                                           Page No.2 of 5 taken only six months;

(f) that   no   claim   pertaining   to   cost   of   deployment   of   watch and ward was referred to Ld. Arbitrator;

(g) that all overheads covered within the agreement were  paid   to   the   claimant.   The   claimant   had   also   given   an   undertaking on 03.12.1987 in this regard;

(h) that the Ld. Arbitrator has not considered the letters dated 06.10.1987 and 26.04.1985;

(i) that the objector has already paid the amount under clause 10(CC) in the agreement;

(j) that the award is silent about the date from which the   claim for interest shall start. 

5. The petitioner has filed reply to the objections and has contested the same.

6. Objector/respondent has filed rejoinder and has reiterated the contents of the objections.

7. I have heard Sh. Bhavesh Kumar Sharma, ld. Counsel for the petitioner and Ms. Promila Kapoor, ld. Counsel for the objector. Ld. Counsel  for the petitioner has contended that there is no error apparent on the face of the record. The award be made Rule of the Court. On the other hand, ld. Counsel for the objector/respondent has contended that  no amount is payable with respect to claim no.8(D), 8(vii), 9 & 11 of the award.

8. I   have   gone   through   the   file.   Claim   no.8(D)   is   with Arbt. No.1121/2017 M/s B. Esskay Construction Co. Vs. DDA & Ors.                                           Page No.3 of 5 respect to providing groove in internal plaster where ceiling and brick work meet. Ld. Arbitrator has rightly held that no provision exists in CPWD   Specification   1977   as   it   does   not   contemplate   groove   in cement plaster where ceiling and brick work meet. As per agreement (item   3.16),   the   petitioner   is   entitled   to   extra   payment   for   groove plaster. There is no error apparent on the face of the record in this respect in the award passed by the Ld. Arbitrator.

9. So far as claim no.8(vii) regarding cost of deployment of watch   and   ward   is   concerned,   on   completion   of   the   work   on 26.05.1988   the   dwelling   units   were   to   be   passed   over   to   the respondent. Respondent  did not take the possession till 28.03.1989 which led the petitioner to maintain watch and ward of the dwelling units for a period of ten months. The petitioner incurred the expenses for the same which the objector is bound to pay. Thus, there is no error apparent in the award passed by the Ld. Arbitrator on this claim.

10. The   defect   liability   period   as   per   clause   17   of   the agreement is six months. Clause 17­B contemplates only for leakage of   roofs   for   one   year   or   two   rainy   seasons   (ending   October), whichever is later. Thus, clause 17(B) is not applicable. The objection in this respect is, therefore, misconceived and is rejected.

11. The Ld. Arbitrator, on the basis of the evidence adduced before him, came to the conclusion that it is case of breach and it is conclusively proved that the objector/respondent failed to discharge its obligation. The Ld. Arbitrator found the claim of Rs.2,29,606/­ to Arbt. No.1121/2017 M/s B. Esskay Construction Co. Vs. DDA & Ors.                                           Page No.4 of 5 be reasonable. There is no apparent error on the face of the record qua this objection (claim no.9).

12. So   far   as   claim   no.11   (interest)   is   concerned,   Ld. Arbitrator allowed the simple interest @ 12% p.a. on the amounts withheld   by   the   objector/respondent.   The   award   passed   by   Ld. Arbitrator is from 1992. Thus, the simple interest @ 12% p.a. was impliedly granted by the Ld. Arbitrator from the date of invocation of the arbitration i.e. 09.02.1999 till its realization. The objection of the objector in this regard has no merit. Hence, the same is rejected.

13. Considering the facts and circumstances of this case, the objections of the objector are dismissed. The impugned award is made Rule of Court and a decree is hereby passed in terms of the said award dated   30.09.2008   which   shall   form   part   of   the   decree.  File   be consigned to Record Room after due compliance.

Digitally signed by

PRAVEEN   KUMAR PRAVEEN KUMAR Date: 2018.09.21 02:11:30 +0530 Dictated and announced in  (PRAVEEN KUMAR) open court today i.e. on 20.09.2018.        Additional District Judge­05,                      NDD,Patiala House Courts,      New Delhi. (R) Arbt. No.1121/2017 M/s B. Esskay Construction Co. Vs. DDA & Ors.                                           Page No.5 of 5