Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 11, Cited by 0]

Bangalore District Court

M.Keshava Raju vs Government Of Karnataka on 25 October, 2019

IN THE COURT OF THE LXXXIII ADDITIONAL CITY CIVIL
  AND SESSIONS JUDGE AT BENGALURU CITY[CCH-84]

PRESENT:   Sri S.A. HIDAYATHULLA SHARIFF,
                                   B.A., LL.M.,
           LXXXIII Additional City Civil and
           Sessions Judge

      Dated this the 25th day of October 2019

                  COM.O.S.No.24/2019
             (O.S.No.9/2018 & OS 42/2017)

PLAINTIFF:            M.Keshava Raju, aged about 66
                      years, S/o late M. Narayana Raju,
                      Engineering Contractor, No.7, I.T.I
                      Layout, R.M.V. II Stage, Bangalore­
                      560094.


                      [By Sri.KMM/PHR, Advocate]

                       /v e r s u s/

DEFENDANTS:            Government of Karnataka, Public
                       Works Department.
                       Represented by its

                 1.    The Secretary,
                       Public Works Department,
                       Government of Karnataka,
                       3rd Floor, Vikasa Soudha,
                       Bangalore­560001.

                 2.    The Chief Engineer (C&B) South,
                       K.R.Circle, P.W.D,
                       Bangalore­560001.
                              2
                             CT 1390_Com.O.S.24­2019_Judgment .doc


                  3.   The Executive Engineer,
                       P.W.D. Division, Chikkaballapur,
                       Chikkaballapur District.


                       [By District Government Pleader]


Date of institution of the   :    26/02/2019(02/2/2017)
suit
Nature of the suit           :        Recovery of money
Date of commencement of      :          30/10/2017
recording of the evidence
Date    on    which    the   :           25/10/2019
Judgment               was
pronounced.
                             : Year/s Month/s          Day/s
Total duration
                                 02      08               23



                         (S.A. Hidayathulla Shariff)
                       LXXXIII ACC & SJ: Bengaluru




      Plaintiff has filed this suit against defendants for

 recovery of money. This suit was originally filed before

 the II Addl. Senior Civil Judge & JMFC, Chikkaballapur

 and suit was numbered as OS No.42/2017. Thereafter,

 the suit was transferred to 1st Addl. District & Sessions

 Judge, Chikkaballapur and suit was numbered as OS
                            3
                           CT 1390_Com.O.S.24­2019_Judgment .doc


No.09/2018.      After establishment of this court to try

commercial    disputes,    on   the    point        of     territorial

jurisdiction, the suit is transferred to this court and it

was renumbered as Commercial OS No.24/2019.

     2.   The case of the plaintiff in brief is that he is a

Class I contractor having experience in contract works.

He   submitted    tender   in   response       to        the   tender

notification issued by the Government of Karnataka for

the work of "Construction of First Grade College at

Sidlaghatta, Kolar District" presently Chikkaballapur

District. He being the lowest tenderer was awarded the

above mentioned construction work vide Agreement

No.16/92­93 dated 26/3/1993.          The cost of the work

under the above mentioned tender was Rs.38,91,629/­.

The 3rd defendant­ Executive Engineer, PWD Division,

Kolar has issued work order on 06/04/1993. As per the

terms of the contract, the monthly stipulated progress

was Rs.2,16,200/­.     As per the work order the date of

commencement of the work was 26/3/1993 and the date
                           4
                          CT 1390_Com.O.S.24­2019_Judgment .doc


of completion was 26/3/1995.        The contract contains

schedule of quantities in which rates for each of various

individual items of work are entered in Schedule B along

with a copy of agreement, the letter of acceptance, work

order etc.

     3. It is further case of the plaintiff that immediately

after receiving the work order, he started the work in

portion of the site made available by the Assistant

Executive Engineer in the portion which was clear

without obstructions.    He has mobilized the resources

including men, machinery, establishment and other

matching equipments and camped at site to execute the

work.    The site was not clear as the electric and

telephone lines were obstructing the work. Immediately

after receiving of the work order he had made all

arrangements and camped at site to execute the work.

The defendant has supplied foundation details on

3/5/1993 with a delay of about two months in the

beginning itself.   The foundation works were completed
                             5
                            CT 1390_Com.O.S.24­2019_Judgment .doc


immediately after receiving the foundation details.           He

continued with the work with the same establishment

and resources in the stipulated and prolonged period

upto 29/6/2001 and executed the work in excess of the

contract value of amount of Rs.38,91,629/­ to the tune of

Rs.46,02,146/­, but could not complete the minor items

of the work due to following reasons:

     4. The construction of buildings of any magnitude

requires detailed approved working drawings, designs

showing    the   details     of    foundations,      basement,

superstructures with all items.          The defendant was

bound to fulfill his obligations of supplying approved

working drawings / designs which is basic need to

execute the construction work.         The defendant totally

failed to supply these drawings, designs and details in

the prescribed time.       He has mentioned the delays of

supplying drawings in his letters dated 2/7/1993,

10/6/1994, 24/10/1994, 16/2/1995, 27/7/1995 and

16/10/1995 addressed to the defendants. The delay in
                             6
                           CT 1390_Com.O.S.24­2019_Judgment .doc


supply of working drawings has caused huge delay in

executing the work. Even at the time of cancellation of

the contract, defendant has not taken action to complete

water supply, sanitary and electric works.             Without

completing the water supply, sanitary and electric works,

it was not possible for him to complete the construction

work relating to laying tiles and flooring works. Inspite of

the repeated letters dated 6/11/1996, 16/4/1997 and

3/4/2000 addressed by him to the defendants, the

defendants have failed to get the above works completed.

     5. It is further case of the plaintiff that electric lines

and telephone lines were crisscrossing the work site. It

was very difficult to execute the work under the electrical

and telephone lines. Inspite of his repeated requests, the

defendants have abnormally delayed in clearing the site

by removing the electrical and telephone lines. This fact

of delays were brought to the knowledge of the defendant

through letters dated 25/11/1993, 27/7/1995.                The
                             7
                            CT 1390_Com.O.S.24­2019_Judgment .doc


delay in fixing the electric and telephone lines has caused

substantial delay in executing the work.

     6.It is further case of the plaintiff that the essential

building materials were not available at a reasonable

distance.     He had to go in search of the building

materials since the same were not available at the

distance shown by the defendant               at the time of

tendering.    This caused further delay in executing the

work and required much more investments by him.

     7. It is further case of the plaintiff that the interim

payments for the work done were very irregular.              The

contract agreement provided payment for the work done

in each month. There were inordinate delay in preparing

and payment of the bills.          In some occasions, the

defendant took 6 to 8 months for making one running bill

payment due to shortage of funds.                This created

unbalanced      working    conditions     and     delayed     the

completion of the work. Even at the time of cancellation

of   the    contract,   there   were    substantial     pending
                             8
                            CT 1390_Com.O.S.24­2019_Judgment .doc


payments.      Any construction work requires prompt

payments to complete the work and to avoid financial

loss to him. The delay in making payments was brought

to the knowledge of the defendants through letters dated

25/11/1993, 11/5/1994, 10/6/1994, 16/2/1995 &

16/10/1995

       8. It is further case of the plaintiff that inspite of

above     mentioned    impediments,      he        continued     the

execution of the work under most trying circumstances.

Inspite of non­supply of approved working drawings,

irregular payments and non­completion of water supply,

sanitary and electrical works, the work was kept in

progress by him and he has successfully completed more

than    the   tender   value    of   work     to    the   tune    of

Rs.46,02,146/­ as per the bills paid by the defendant,

whereas, the tender value of the work was only

38,91,629/­. In the mean time, the defendant has

illegally canceled the contract with a threat to execute the

balance work at plaintiff risk and cost though the delays
                            9
                          CT 1390_Com.O.S.24­2019_Judgment .doc


attributable to the defendant.     The defendant has not

even fixed further period for performance of the contract

to make the time essence of the contract after expiry of

the period of contract on 26/3/1995. Inspite of his

repeated requests for extension of time, before expiry of

original contract period, the defendant has illegally

canceled the contract without fixing period for extension

of contract. The final accounts pertaining to contractor

yet to be settled by the defendants. The defendants have

committed breach of contract since they have failed in

fulfilling contractual obligations of providing working

drawings, making prompt payments, completing the

water supply, sanitary and electric works and also failing

in fixing further period of performance of contract.

     9. It is further case of the plaintiff that after

cancellation of the contract, he has given a consolidated

claims letter dated 5/9/2002 to the 3 rd defendant for

settlement as per clause 29 of the conditions of the

contract. As there was no reply to the above letter, he
                            10
                           CT 1390_Com.O.S.24­2019_Judgment .doc


approached the 2nd defendant by letter dated 7/11/2002

for settlement as per the conditions of the contract. Even

the 2nd defendant has not replied the said letter for

settlement of claims. Thereafter, he has approached the

Hon'ble   High   Court    of    Karnataka    by    filing   CMP

No.48/2003 for appointment for arbitrator as per the

conditions of the contract.      The Hon'ble High Court of

Karnataka by its order dated 11/7/2003 has rejected the

above mentioned CMP on the ground that clause 29 of

the contract is not an arbitration clause.        Aggrieved by

the order dated 11/7/2003 passed by the Hon'ble High

Court of Karnataka, he has filed WP No.40897/2003 for

appointment of arbitrator and the said writ petition was

also dismissed on 6/11/2003.        Aggrieved by the above

mentioned   order,   he   has     approached      the   Hon'ble

Supreme Court of India by filing SLP in Civil Appeal

No.16117/2004 for appointment of arbitrator. The Apex

Court of the Land by its order dated 25/10/2013 held

that clause 29 of the contract is not an arbitration clause
                           11
                          CT 1390_Com.O.S.24­2019_Judgment .doc


and has given liberty to him to recover the dues through

legal remedy. Further he has filed review petition against

the common judgment passed in SLP No.1586/2004

before the Apex Court of the Land and the said review

petition also came to be dismissed on 16/9/2014.

     10. It is further case of the plaintiff that in

connection with breach of contract dated 26/3/1993 by

the defendants, following claims have arisen to him,

which he has sought for settlement in the present suit.

     11. Claim I : to declare that the cancellation of

contract is illegal and wrongful and to desist from

applying cost and risk action of completing the

balance work as he has already executed more than

the contract value and entitled for damages.

     With regard to above mentioned claim No.1, it is the

case of the plaintiff that the stipulated period of contract

expires on 26/3/1995, as per the terms of contract. He

continued the execution of the work even beyond the
                              12
                              CT 1390_Com.O.S.24­2019_Judgment .doc


stipulated period till cancellation of the contract.            The

defendant also accepted and permitted him to continue

the execution of work beyond the contract period. The

value of the contract was Rs.38,91,629/­ and he has

exceeded    the   work       by   completing      the    work    of

Rs.46,02,146/­ by the time of cancellation of the

contract.    The defendant has not even bothered to

approve the extra cost incurred which was under

execution where the approval was essential in terms of

the contract. Completion of the work was delayed due to

the failure on the part of the defendant to perform

contractual obligations. He has repeatedly requested the

defendants through writing several letters for grant of

extension of time since he had already established at site

with required organization by completing the work more

than tender value. The defendants have taken wrongful

action by canceling the contract without fulfilling their

contractual obligations, such as, supply of approved

working     drawings     /    designs,     prompt       payments,
                          13
                          CT 1390_Com.O.S.24­2019_Judgment .doc


completing the water supply, sanitary and electrical

works.   The question of cancellation of the contract by

the defendant was illegal as the defendants have failed to

perform their obligations in terms of the contract and the

cost of the work completed by him had already exceeded

the contract value.   Had the defendants made proper

payments, made available required drawings and taken

action to complete water supply, sanitary and electrical

works and allowed him to continue the work, he would

have completed the same in all respects in a reasonable

time.    The breach of contract is on the part of the

defendants as all the delays in performance of the

contract are totally attributable to the defendants only.

The defendants opted for illegal cancellation of work

without fulfilling their obligations and without settling

the dispute in terms of clause 29 of the contract.

Without deciding the aspect of the breach of contract, the

cancellation of the contract by defendants is illegal.

Hence, the cancellation of the contract on 29/6/2001 by
                           14
                          CT 1390_Com.O.S.24­2019_Judgment .doc


the defendants is illegal and wrongful. Hence, defendant

required to refund a sum of Rs.3,76,639/­             towards

refund of EMD, FSD and NSC recovered in bills and

defendants are liable to pay him a sum of Rs.7,04,315/­

as interest @ 12% per annum on the above mentioned

amount and liable to pay him totally a sum of

Rs.10,80,954/­ towards the claim No.1 and close the

contract as it is and where it is basis without application

of risk and cost of completing the balance work.

     12. Claim 2 : Payment of idle charges of men and

machinery     suffered   during     stoppage      period     of

execution of work in contract period.

      With regard to the above mentioned second claim,

it is the case of the plaintiff that the execution of the

work was stopped on several occasions for want of

designs / drawings and due to obstruction at work site

and lack of payments. The total period of stoppage was

308 days, during the period of execution of work from
                          15
                         CT 1390_Com.O.S.24­2019_Judgment .doc


commencement of work to the cancellation of contract.

Due to various defaults and breaches committed by the

defendant, he has suffered damages in the form of idle

charges of men and machinery, due to the default

committed by the defendant, which resulted in stoppage

of work.   The stoppage of work was intimated to the

defendant in letters dated 24/10/1994 and 16/10/1995.

He has kept separate men and machinery for the

performance of the work pertaining to contract in

dispute.   He has no chance to mitigate the damages

suffered during the idle period and there was no other

opportunity to utilize the establishment made at this

work and was always ready at work site for instruction of

the defendant to execute the work. The idle charges per

day works out to Rs.3,600/­ including labours and

machinery. The defendant required to compensate him

for the idle charges @ Rs.3,600/­ per day for 549 days,

which amounts to Rs.11,16,000/­.       Defendant required

him to pay a sum of Rs.20,87,107/­ as interest @ 12%
                             16
                            CT 1390_Com.O.S.24­2019_Judgment .doc


per annum on the above mentioned amount from

29/6/2001 upto 2/2/2017. With regard to claim 2 the

defendant   required   to    pay    him    a   total   sum     of

Rs.32,03,107/­ as payment of damages of idle charges of

men and machinery suffered by him.

     13. Claim 3 : Payment of equitable revised rates

for the work done beyond the stipulated period of

contract.

       With regard to above mentioned claim No.3,

plaintiff has stated that the period of performance was

prolonged beyond the stipulated date of completion due

to several defaults and breaches of contract committed by

the defendants. Consequently, he was forced to execute

the work in the prolonged period beyond the stipulated

period of completion, facing the burnt of all around

increase in the market prices during the period. There is

no justice in insisting him to do the contract at tendered

rates, since the delay in completing the work was not at
                             17
                             CT 1390_Com.O.S.24­2019_Judgment .doc


all attributable to him.     He is entitled for payment of

equitable revised rates for the work done beyond the

stipulated   period     taking   into     consideration    of    the

changed market conditions and circumstances under

which the work was executed.               The defendants are

required to pay equitable revised rates for the quantities

of   work    executed    beyond     the     stipulated    date    of

completion of 26/3/1995. Plaintiff has claimed a sum of

Rs.28,15,725/­ towards equitable revised rates for the

work done beyond the stipulated period of contract and

also sought for a sum of Rs.52,65,405/­ as interest on

the above mentioned amount at 12% per annum from

29/6/2001      upto     2/2/2017,       totally   amounting       to

Rs.80,81,130/­.

     14. Claim 4 : reimbursement of expenses of

monthly over head charges for longer stay at the

work site for the purpose of executing the work

beyond the contract period.
                          18
                         CT 1390_Com.O.S.24­2019_Judgment .doc


      With regard to above claim 4, it is the case of the

plaintiff that delay in completion of the work is only

attributable to the defendants and the execution of the

work beyond the stipulated date of completion has

resulted in incurring extra expenditure on additional

monthly overhead charges by him.        He had intimated

about the over head charges to the defendants through

letters dated 6/11/1996, 16/4/1997 and 5/9/2002.

But the defendants have never disputed the said charges

nor replied the letters which amounts to acceptance. He

had taken 10% of the cost of work at his quoted rates

via­a­viz stipulated period of contract as the cost of

overhead charges to meet the overheads both at head

office and site office which included payment towards

watch and ward, managerial, consultancy, legal advise,

engineering, supervision, accounts, stores and traveling.

The overhead charges are fixed in each and every month

and will not increase or decrease in proportion to the

quantum of work executed in each month.                   The
                             19
                            CT 1390_Com.O.S.24­2019_Judgment .doc


establishment     engaged    on    the    works     cannot     be

retrenched or reduced till the completion of the work.

The expenditure on monthly overheads continued from

the date of contract period from 26/3/1995 till the

cancellation of the contract on 29/6/2001.              He has

enclosed certificate of the Chartered Account pertaining

to the over head charges incurred by him. Plaintiff has

claimed a sum of Rs.29,42,100/­ towards reimbursement

of monthly over head charges for longer stay at the work

site and also claimed a sum of Rs.55,01,727/­ as interest

on the above mentioned amount from 29/6/2001 upto

2/2/2017 @ 12% per annum                 Plaintiff has totally

claimed a sum of Rs.84,43,827/­ towards this claim

No.4.

        15. Claim 5 : Payment of interest @ 12% on all

the claims.

        With regard to the above mentioned claim No.5, the

plaintiff has sought for interest @ 12% per annum on all

the amounts claimed in the present suit and sought for
                              20
                             CT 1390_Com.O.S.24­2019_Judgment .doc


future interest @ 18% per annum on the suit claim from

the date of the suit to the date of payment. It is further

case of the plaintiff that the claim amount quantified by

him is valid, legitimate and he is entitle for the same in

terms      of       the   agreement     conditions     and     the

correspondences from the time of awarding the contract

till its cancellation of work and thereafter. That he has

issued a legal notice to the defendants under Section 80

of CPC for settlement of claims vide letter dated

19/12/2014 and defendants have not taken any action

even after the decision of Apex Court of the Land for

settlement of the claim raised by him.          Plaintiff further

contended that this court is having territorial jurisdiction

to try the suit and the suit is filed within the period of

limitation. On these grounds, the plaintiff has sought for

recovery   of   a    sum    of    Rs.2,08,09,018/­     from    the

defendants towards the amount of claims made by him

with respect to contract No.16/92­93 dated 26/3/1993

together with costs and future interest @ 18% per annum
                             21
                            CT 1390_Com.O.S.24­2019_Judgment .doc


from the date of filing of the suit till the date of realization

of the amount.

     16.   In    response   to   the   suit    summons,       the

defendants No.1 to 3 have contested the suit by filing

their joint written statement.      The defendants in their

written statement have contended that the suit of the

plaintiff is not maintainable either in law or on facts and

same is liable to be dismissed.           Defendants further

contended that the plaintiff has filed a false, frivolous and

vexatious suit against them with a malafide intention of

harassing them. The suit of the plaintiff is speculative in

nature and misconceived one and liable to be dismissed.

Plaintiff has not properly instituted the suit as required

U/S.79(b) and Section 80(i)(c) of CPC.

     17. Defendants further contended that the suit

claim of the plaintiff is hypothetical and illogical.        The

plaintiff has caused substantial delay of 4 years in

constructing the building, as such, he could not claim

the overhead charges, labour charges, establishment and
                           22
                          CT 1390_Com.O.S.24­2019_Judgment .doc


maintenance of labourers and machinery. Due to poor

performance    in   construction   activity   and    financial

activity, the contract was terminated by them. Since the

plaintiff has failed to discharge the terms and conditions

of the agreement, he is not entitle for any relief sought

for.

       18. The defendants in the written statement have

not disputed the fact that the plaintiff was a class I

contractor and he being the lowest tenderer, he was

awarded the work of construction of First Grade College

at Sidlaghatta vide contract agreement No.16/92­93

dated 26/3/1993.        The defendants have also not

disputed the plaint averments with regard to cost of the

contract work, date of issuance of work order, date of

commencement of the work and date of completion of the

work stipulated in the above mentioned contract. The

defendants have denied the plaint averment that final bill

of the contract has not been prepared. The defendants

have contended that plaintiff has not come forward to put
                           23
                          CT 1390_Com.O.S.24­2019_Judgment .doc


his signature and received the same.         The defendants

have denied the plaint averments that the plaintiff has

started the construction work immediately after receiving

the work order in a portion of the site made available to

him and in the portion which was cleared without any

obstruction. The defendants further contended that the

plaintiff has not started his work after receipt of the work

order and he has delayed the to commencement of the

work at site. The defendants have also denied the plaint

averments with regard to mobilization of the resources

and camping of the plaintiff at the site to execute the

work and also denied the plaint averments that the site

was not clear as the electric and telephone lines

obstructing the work. The defendants have also denied

the plaint averments that since the electric and telephone

lines were not shifted, there was stoppage of construction

work for a major period during the stipulated period of

performance.    Defendants further contended that the

plaintiff has not complied the terms of the agreement
                             24
                            CT 1390_Com.O.S.24­2019_Judgment .doc


dated 26/3/1993. When the site was handed over to the

plaintiff, they have remitted a sum of Rs.9,893/­ vide

cheque No.965438 dt. 14/6/1993 to shift the electric

lines and poles and also sum of Rs.8,192/­ was

transferred to BSNL account vide M.B.No.5572 shift the

telephone lines and poles. After receipt of the said sum

by the above departments, they have shifted the poles

and lines from the site. There was no obstructions for

commencement of the work by the plaintiff and there is

no latches on their part.

     19. The defendants in their written statement have

also denied the plaint allegations with regard to the

alleged reasons shown by the plaintiff for non completion

of the work within the stipulated period of time.            The

defendants have denied the plaint allegations that there

was delay by the defendants in supply of approved

working drawings, which resulted in non completion of

the work in the contract period.          Defendants further

contended that the entire drawings upto the roof level
                              25
                             CT 1390_Com.O.S.24­2019_Judgment .doc


has been given to the plaintiff on 9/12/1993 vide letter

No.EE/JE3 dated 9/12/1993.

     20. The defendants in the written statement have

also denied the plaint allegations with regard to non

shifting of high tension electric line, telephone line and

Municipal water line from the site made against them as

reasons for delay in construction work.              Defendants

further   contended   that    they    have given respective

amount to the concerned departments for shifting of

electric lines and telephone lines on 14/6/1993 and

inspite of it, the plaintiff has made false allegations

against them.

     21. The defendants have also denied the plaint

allegations that non availability of essential building

materials at a reasonable distance as one of the reason

for delay in construction work.            Defendants further

contended that the plaintiff being class I contractor has

to look after the supply of building materials and he
                          26
                         CT 1390_Com.O.S.24­2019_Judgment .doc


cannot depend upon the defendants for collecting the

building material to complete the tender work.

     22. The defendants have also denied the plaint

allegations that they were irregular in payment for the

work done by the plaintiff. Defendants further contended

that the amount for the work done by the plaintiff has

been disbursed to him as per the allocation of funds

made by the government. There was no any inordinate

delay in preparing the bills on their side.      Defendants

have also denied the plaint allegations that even at the

time of canceling the contract there was substantial

pending payment to the plaintiff. The defendant further

contended that as on the date of cancellation of work,

plaintiff has received more than the amount which was

shown in the contract agreement.       On 12/6/2001, an

amount of Rs.47,60,006/­ has been disbursed on the

basis of work slip. The work slip has been prepared by

them on 9/12/1993 and the same was in the knowledge
                           27
                           CT 1390_Com.O.S.24­2019_Judgment .doc


of the plaintiff.   Such being the case, the question of

delayed payments by them will not arise.

     23. The defendants in the written statement have

also denied the plaint allegations that the delayed interim

payments, delayed supply of working drawings, abnormal

delay in completing the water supply, sanitary and

electrical   work   has   created     unbalanced       working

conditions and delayed the completion of the work. That

the above mentioned delays           were brought to the

knowledge of the defendants.            Defendants further

contended that the alleged notices issued by the plaintiff

to them was after lapse of contractual agreement dated

26/3/1993. As the contract was expired on 26/3/1995

itself the notices issued by the plaintiff is against the

contract and hence those notices does not have any

sanctity in the eye of law. Defendants further contended

that the plaintiff had received more than the tender

amount from them on the basis of clause 13(b) of the
                           28
                           CT 1390_Com.O.S.24­2019_Judgment .doc


schedule of the contract form. As such, the claim made

by the plaintiff is unsustainable in the eye of law.

     24. The defendants in the written statement have

also denied the plaint allegations that inspite of severe

impediments, the plaintiff was executing the work under

most trying circumstances and work was kept in

progress and he has successfully completed more than

the tender value work.      Defendants further contended

that the plaintiff had received the amount to the tune of

Rs.46,02,146/­ as per bills paid by them, whereas the

tender value work was only Rs.38,91,629/­. Hence,

plaintiff is estopped from taking any contention with

regard to the above mentioned aspects. The defendants

have also denied the plaint allegation that they have

illegally canceled the contract with a threat to execute the

balance work at plaintiff's risk and cost. The defendants

further contended that there is no threat on their side to

the plaintiff. They were discharging their duties within

the frame work of law and the guidelines issued by the
                              29
                             CT 1390_Com.O.S.24­2019_Judgment .doc


government from time to time. The defendants have also

denied the plaint allegations that they have failed to fix

further period for performance of the contract to make

time essence of the contract after the original contract

period expired on 23/3/1995.              Defendants further

contended that the original agreement date was expired

on 26/3/1995,       by that time there was huge work

pending from the site of the plaintiff. Inspite of the said

fact the work was continued upto 28/6/2001. Finally on

29/6/2001, the contract was rescinded by them due to

delay   caused    by   the    plaintiff   in   completing      the

construction work.       Plaintiff without any justifiable

reasons has issued notices to them. They have allowed

the plaintiff to continue the tender work upto 26/8/2001

in the interest of public at large. Their sole intention is to

see that the tender work should be completed and the

building was made available to the use of students.

There was no delay on their part in making the tendered

amount. The plaintiff deliberately misused the leniency
                             30
                            CT 1390_Com.O.S.24­2019_Judgment .doc


given by them for completion of the entrusted contract

work.   The plaintiff has made false allegations against

them alleging that the delay in performing the contract

was attributable to them.

     25. The defendants in the written statement have

admitted about the receipt of notice on 5/9/2002 and on

7/11/2002 from the plaintiff and further contended that

they have suitably relied the said notice. The defendants

have also admitted the proceedings between the plaintiff

and defendants that took place before the Hon'ble High

Court of Karnataka and Hon'ble Supreme Court of India

and the orders passed in the said proceedings.

     26. The defendants in the written statement have

denied the claim No.1 of the plaintiff seeking cancellation

of contract as illegal and desisting them from applying

risk and cost action of completing the balanced work.

Defendants further contended that the plaintiff making

false allegations against them to over come            from the

action to be taken by them against him for causing loss
                           31
                          CT 1390_Com.O.S.24­2019_Judgment .doc


and inconvenience to the public at large.        The plaintiff

has no right to make claim against them under the law.

They have not taken any illegal action against the

plaintiff in canceling the contract.     Defendant further

contended that after expiry of the contract period on

26/3/1995, plaintiff continued the work till cancellation

of the contract and he had continued the work beyond

the   contract   period   and   the    tendered      work    of

Rs.38,91,629/­ has exceeds upto Rs.46,02,146/­.             The

excess amount has been paid by them to the plaintiff on

the basis of work slip which was stipulated in schedule

contract form No.13(b). The defendants have also denied

the plaint allegations that there was no approval given by

them for extra cost incurred for execution of the work.

Defendant further contended that the approval for extra

cost incurred for execution of the work was given by the

Superintendent Engineer on 5/1/1994. The plaintiff has

caused inordinate delay in executing the tender work and

caused loss to the state. In view of the non­completion of
                           32
                          CT 1390_Com.O.S.24­2019_Judgment .doc


the tender work, they have canceled the contract of the

plaintiff on 12/6/2001.     Thereafter, they have called

tender for balance work and entrusted the balance work

to one Sri.C.S.Chandregowda, who is a lowest quoted

tenderor for a sum of Rs.9,46,000/­.        The subsequent

tenderor has completed the balance contract work and

handed over the building. The plaintiff has to bear the

said loss with penal interest prevailed as on that date.

There is no illegality on their part in cancellation of the

contract.   Since the plaintiff has failed to complete the

tendered work and committed breach of contract as per

clause 29 of the contract they have issued notice to the

plaintiff and since plaintiff has not properly responded to

the notice, they have canceled the contract dated

26/3/1993 on 29/6/2001 by forfeiting the EMD, FSD &

NSCs. Since they have canceled the contract in terms of

the contract and forfeited the above mentioned amount,

the question of considering the claim made by the

plaintiff for a sum of Rs.10,80,954/­ will not arise.
                            33
                            CT 1390_Com.O.S.24­2019_Judgment .doc


Defendants    further   contended      that   there    was     no

contractual obligations on their part to pay 12% interest

on the above mentioned amounts.           Once the forfeiture

clause is opened by them, the question of considering the

claim No.1 of the plaintiff will not arise.

     27. With regard to the second claim of the plaintiff

pertaining to payment of idle charges of men and

machinery suffered by him, defendants have contended

that since there was no stoppage of work by them at any

stage during subsistence of contract, plaintiff cannot

make any claim for compensation as per clause 15 of the

schedule of contract form. They reserves the right to take

action against plaintiff for the delay in execution of the

work.   The plaintiff has not maintained the men and

machineries in the site during the subsistence of

contract. There is no defaults and breaches committed

by them. Plaintiff unnecessarily making false allegations

against them.      The claim of plaintiff for a sum of

Rs.32,03,107/­ as damages for idle charges of men and
                           34
                              CT 1390_Com.O.S.24­2019_Judgment .doc


machineries is an imaginary claim. At no point of time

the plaintiff has not shown the idle of men and

machinery   at   the   site     during    the    subsistence     of

agreement. Plaintiff has not made any representation in

this regard. Plaintiff has not produced a single piece of

document to substantiate the above mentioned claim.

     28. With regard to claim 3 of the plaintiff pertaining

to payment of equitable revised rates for the work done

beyond the stipulated period of contract is concerned, the

defendants have contended that there is no legal base for

the plaintiff to make said claim.         Plaintiff without any

valid reasons has made false allegations of breach of

contract against them.        Defendants further contended

that the plaintiff has received a sum of Rs.47,60,006/­

and not Rs.46,02,146/­ on the basis of the work slip and

extra item rate list. It is further contended that schedule

B of the contract is not applicable to the case in hand,

since plaintiff has not used any extra item for executing

the work at site.       Plaintiff has not produced any
                           35
                           CT 1390_Com.O.S.24­2019_Judgment .doc


documents to substantiate the said claim and there is no

provision under the contract for payment of interest @

12% per annum. The vouchers produced by the plaintiff

are all self serving documents. At no point of time, the

plaintiff has produced any single voucher before them

certifying the said amount. In view of the clause 44 of

the contract, the claim No.3 of the plaintiff seeking

payment of equitable rates for the work done beyond the

stipulated period of contract is required to be rejected.

     29. With regard to claim No.4 pertaining                 to

reimbursement of expenses for longer stay at the work

site for the purpose of executing the work claim made by

the plaintiff, the defendants have contended that the said

calculation made by the plaintiff is self serving.        There

was no need for them to reply the notices issued by the

plaintiff claiming over head charges after expiry of the

contract period. Non reply of the notices of the plaintiff

does not amount to acceptance of claim by them.             The

documents produced by the plaintiff claiming over head
                            36
                           CT 1390_Com.O.S.24­2019_Judgment .doc


charges are fabricated documents, do not have any

evidenciary value under law.           The contract dated

26/3/1993 includes all the expenses of the plaintiff

pertaining to over head charges for the purpose of

executing the work.     The claim of the plaintiff towards

reimbursement of alleged monthly over head charges for

longer stay at the work site for the purpose of executing

the work beyond the contract the period do not arise for

consideration, since plaintiff himself has failed to reach

the stipulated tender work.

     30. With regard claim No.5 of the plaintiff pertaining

to payment of interest @ 12% per annum on all the

claims is concerned, defendants have contended that

since there is no contractual obligations with regard to

the interest, plaintiff is not entitle for payment of interest

@ 12% per annum on all the claim sought for by him.

     31. Defendants in their written statement have

further contended that they are government authorities

and they are discharging their duties under the public
                           37
                          CT 1390_Com.O.S.24­2019_Judgment .doc


works department as per the statutory norms and

guidelines issued by the government, they are engaging

the civil work through out the state as and when

government called for.     Since the plaintiff has quoted

lowest rate in his tender pertaining to construction of

First Grade College at Sidlaghatta in the year 1993, he

was awarded the above mentioned construction work in

terms   of   contract    agreement    No.16/92­93        dated

26/3/1993.    As per the terms of the above mentioned

agreement, the construction work should have been

started on 26/3/1993 and should have been completed

in all respects on or before 26/3/1995 with a monthly

stipulated progress of Rs.2,16,202/­.      The contractor -

plaintiff has not completed the work as per the schedule

and delayed very badly. Consequently, the 2 nd defendant

- Chief Engineer has canceled his contract as per the

rules applicable by his order dated 12/06/2001 and

same was communicated to the plaintiff by the 3rd

defendant by letter dated 29/6/2001.       After termination
                           38
                           CT 1390_Com.O.S.24­2019_Judgment .doc


of the contract, plaintiff has written a letter to 3 rd

defendant on 5/9/2002 by making several claims and

the said letter was suitably replied on 22/11/2002. On

3/9/1998 a final notice was issued to the plaintiff for

non­completion of the work at site and a clause was

inserted regarding cancellation of the contract.         In the

said notice reference was also made with regard to

initiation of disciplinary action for non completion of the

work by the plaintiff.         The said facts have been

mentioned in notice dated 24/3/2001. On receipt of the

above mentioned notice, plaintiff has undertaken to

complete the work at the earliest, but failed to complete

the work.   For non completion of the work as per the

undertaking of the plaintiff, he has to be penalized for the

delayed work at site.

     32. Defendants further contended that there is no

cause of action for the plaintiff to file the present suit

against them.    Defendants further contended that the

court fee paid by the plaintiff is not sufficient and suit of
                              39
                             CT 1390_Com.O.S.24­2019_Judgment .doc


the plaintiff is barred by time.       On these grounds the

defendants have sought for dismissal of the suit.

     33. Based on the above pleadings of the parties and

documents produced on record, this court has framed

following :

                             ISSUES

  1) Whether the plaintiff proves that defendants have
     failed   to   perform     their    part    of   contractual
     obligations of the contract dated 26/3/1993 entered
     between him and the defendants?
  2) Whether the plaintiff proves that the cancellation of
     the contract dated 26/3/1993 made by defendants
     on 29/6/2001, is illegal and wrongful?
  3) Whether the plaintiff proves that defendants are not
     entitle to apply risk and cost action of completing
     the balance work of the contract against him?
  4) Whether the plaintiff proves that defendants are
     liable to pay him a sum of Rs.10,80,954/­ towards
     return of EMD, FSD & NSC made by him?
  5) Whether the plaintiff proves that defendants are
     liable to pay him a sum of Rs.32,03,107/­ towards
     payment of idle charges of men and machinery
                           40
                          CT 1390_Com.O.S.24­2019_Judgment .doc


     suffered during stoppage period of execution of the
     work in contract period?
  6) Whether the plaintiff proves that defendants are
     liable to pay him a sum of Rs.80,81,130/­ towards
     payment of equitable revised rates for the work done
     beyond the stipulated period of contract?
  7) Whether the plaintiff proves that defendants are
     liable to pay him a sum of Rs.84,43,827/­ towards
     reimbursement of monthly overhead charges for
     longer stay at the work site for the purpose of
     executing the work beyond the contractual period?
  8) Whether defendants prove that suit of the plaintiff is
     not properly valued for the purpose of payment of
     court fees?
  9) Whether defendants prove that suit of the plaintiff is
     barred by limitation?
  10)     Whether the plaintiff is entitle for the suit
     claim sought for?
  11)     Whether the plaintiff is entitle for future
     interest @ 18% per annum as sought for?
  12)     What order or decree?


     34. Parties have entered into trial. In proof of the

case of the plaintiff, the plaintiff got himself examined as
                             41
                             CT 1390_Com.O.S.24­2019_Judgment .doc


PW.1 and tendered Ex.P.1 to P.18 documents in

evidence.   On behalf of the defendants, initially the 3 rd

defendant   -   Executive     Engineer     of   PWD     Division,

Chikkaballapur    District       was   examined      as    DW.1.

Thereafter, the learned ADGP has filed a memo to discard

the evidence of DW.1 on the ground that he was

transferred to some other department.            Thereafter, on

behalf of the defendants, the present Executive Engineer,

PWD Division, Chikkaballapur was examined as DW.2

and Ex.D.1 to D.17 documents were marked in his

evidence. On the application filed by the counsel for the

plaintiff, the defendants have produced the schedule of

contract form pertaining to Ex.P.1 contract, which

contains the terms and conditions of Ex.P.1 contract and

for the purpose of convenience of the reference of the

court, the said document is marked as Ex.P.1(a).

     35. Written arguments filed on behalf of the plaintiff

and also on behalf of the defendants.

     36. Perused the materials placed on record.
                             42
                            CT 1390_Com.O.S.24­2019_Judgment .doc


     37. My findings on the above framed issues are as

follows:

     Issue   No.1 : In the negative.
     Issue   No.2 : In the negative.
     Issue   No.3 : In the negative.
     Issue   No.4 : In the negative.
     Issue   No.5 : In the negative.
     Issue   No.6 : In the negative.
     Issue   No.7 : In the negative.
     Issue   No.8 : In the negative.
     Issue   No.9 : In the negative.
     Issue   No.10: In the negative.
     Issue   No.11: In the negative.
     Issue   No.12: As per final order for the following:




     38.   ISSUES No.1 & 2 : Since these two issues are

interconnected with each other, to avoid repetition of

facts and findings, both issues are taken up together for

consideration.

     39. There are certain undisputed facts pertaining to

the parties to the present suit. The fact that the plaintiff

who was a Class I Contractor has submitted tender in

response to the tender notification issued by government
                            43
                           CT 1390_Com.O.S.24­2019_Judgment .doc


of Karnataka for the work of construction of First Grade

College at Sidlaghatta, Kolar District is not in dispute.

Further fact that since the plaintiff was the lowest

tenderer, he was entrusted the above construction work

vide contract No.16/92­93 dated 26/3/1993 is also not

in dispute. Ex.P.1 is the contract dated 26/3/1993

executed between the plaintiff and defendants. Ex.P.1(a)

is the schedule of contract forms which contains the

terms of Ex.P.1 contract. Further fact that the cost of the

construction     work     under      the      contract      was

Rs.38,91,629/­ is also not in dispute. Further fact that

the date of commencement of the construction work

stipulated in the contract was 26/3/1993 and the

stipulated date of completion of the work was on

26/3/1995 is also not in dispute. Further fact that in

the   contract   the    monthly    stipulated    progress     of

construction was fixed at Rs.2,16,200/­ is also not in

dispute.    Further fact that on 6/4/1993, the 3rd

defendant ­ Executive Engineer has issued work order to
                           44
                          CT 1390_Com.O.S.24­2019_Judgment .doc


the plaintiff is also not in dispute. Further fact that on

the allegation that the plaintiff has failed to achieve the

stipulated progress in terms of the contract and failed to

complete the construction work, the 2nd defendant ­ Chief

Engineer has rescinded the contract on 12/6/2001 and

communicated to the plaintiff on 29/6/2001 is also not

in dispute.   Further fact that till the rescission of the

contract, the value of the construction work done by the

plaintiff was Rs.46,02,146/­ against the value of work of

the contract was Rs.38,91,629/­ is also not in dispute.

Further fact that subsequent to the communication of

rescission of the contract, plaintiff has filed CMP

No.48/2003 before the Hon'ble High Court of Karnataka,

Bangalore for appointment of an Arbitrator in terms of

the conditions of the contract and said CMP No.48/2003

was dismissed by the Hon'ble High Court of Karnataka,

Bangalore by its order dated 11/7/2003 on the ground

that Clause 29 of the contract do not contain an

arbitration clause is also not in dispute.       Further fact
                           45
                          CT 1390_Com.O.S.24­2019_Judgment .doc


that thereafter, the plaintiff has filed WP No.40897/2003

before the Hon'ble High Court of Karnataka, Bangalore,

seeking appointment of an arbitrator and the said writ

petition also came to be dismissed by the Hon'ble High

Court of Karnataka, Bangalore by its order dated

6/11/2003. Thereafter, the plaintiff has filed SLP in Civil

Appeal No.1586/2004 before the Hon'ble Supreme Court

of India, seeking appointment of an Arbitrator and said

SLP also came to be dismissed on 25/10/2013. Further,

the review petition filed by the plaintiff against the

common judgment passed in connected SLP leave

petitions were also dismissed by the Hon'ble Supreme

Court of India by its order dated 16/9/2014 is also not in

dispute.   Ex.P.6 is the certified copy of the judgment

passed by the Hon'ble Supreme Court of India in Civil

Appeal No.1586/2004.

     40. The plaintiff has filed this suit for recovery of

money against the defendants, on the allegations that

they have failed to perform their part of the contractual
                           46
                          CT 1390_Com.O.S.24­2019_Judgment .doc


obligations of the contract dated 26/3/1993 entered

between him and the defendants and rescission of the

contract dated 26/3/1993 made by the defendants on

12/6/2001 is illegal and and wrongful.         Based on the

above mentioned allegations, plaintiff has sought five

claims in the present suit.         On the other hand,

defendants have contested the suit by denying the plaint

allegations with regard to non performance of their part

of contractual obligations of contract dated 26/3/1993

and also denied the plaint allegations that the rescission

of   contract   dated   26/3/1993    made     by    them     on

12/6/2001 is illegal and wrongful. In view of the rival

contentions taken by the parties to the suit, the burden

of proof is that plaintiff to prove that defendants have

failed to perform their part of the contractual obligations

of the contract dated 26/3/1993 and also to prove that

rescission of contract dated 26/3/1993 made by the

defendants on 12/6/2001 is illegal and wrongful.
                               47
                              CT 1390_Com.O.S.24­2019_Judgment .doc


      41. A perusal of the pleadings and evidence of the

plaintiff discloses that it is the case of the plaintiff that

immediately after receiving the work order, he has started

the construction work in portion of the site made

available    to    him,    which     was   clear   without     any

obstructions. He has mobilized the resources including

men and machinery, establishment and other matching

equipments and camped at site to execute the work. The

defendants        have    supplied    foundation     details     on

3/5/1993 with a delay of about two months in beginning

itself.   A foundation work was completed immediately

after receiving the foundation details. He continued with

work with the same establishment and resources in the

stipulated and prolonged period upto 29/6/2001 and

executed the work in excess of contract value amount of

Rs.38,91,629/­ to an extent of Rs.46,02,146/­, but could

not complete the minor items of the work.

      42. A perusal of the pleadings and evidence of the

plaintiff discloses that the plaintiff has mainly highlighted
                             48
                            CT 1390_Com.O.S.24­2019_Judgment .doc


the following alleged four contractual obligations, which

the defendants alleged to have failed to perform which

are   the    alleged   reasons   for   the   plaintiff   for   non

completion of the work           within stipulated period of

contract.

      (1) delay in supply of approved working drawings.

(2) delay in shifting of electric and telephone lines           (3)

non availability of essential building materials at a

distance shown by the defendants at the time of

tendering.    (4) irregular interim payments for the work

done by him under the contract.

      43. With regard to the first reason pertaining to the

alleged delay in supply of approved working drawings by

the defendants is concerned, it is the case of the plaintiff

that defendants have failed to supply the working

drawings, designs and details in time. He has brought

the delay in supply of drawings to the knowledge of the

defendants through letters dated 2/7/1993, 10/6/1994,

24/10/1994, 16/2/1995, 27/7/1995 & 16/10/1995.
                            49
                           CT 1390_Com.O.S.24­2019_Judgment .doc


The delay in supply of approved working drawings has

caused huge delay in executing the work.

     44. To prove the alleged delay in supply of approved

working drawings by the defendants, the plaintiff has

mainly relied on Ex.P.5 which contains 15 letters dated

2/7/1993,     25/11/1993,       11/5/1994,        10/6/1994,

24/10/1994,     30/12/1994,      16/2/1995,       23/3/1995,

27/7/1995,     16/10/1995,       6/11/1996,       16/4/1997,

14/10/1998,     3/4/2000    &    18/4/2001,      which     were

addressed by the plaintiff to the 3rd defendant - Executive

Engineer.    A perusal of these letters discloses that in

letter dated 2/7/1993, plaintiff has alleged that he had

received approved drawings for foundation after a lapse

of about 1 month 7 days.        In letter dated 11/5/1994,

plaintiff has alleged that there was some delay on the

part of defendants in supplying approved drawings.            In

letter dated 10/6/1994, plaintiff has alleged that there is

delay on the part of the defendants to supply working

drawings about the plinth level.             In letter dated
                          50
                          CT 1390_Com.O.S.24­2019_Judgment .doc


24/10/1994, the plaintiff has alleged that the contract

work above the plinth beam was delayed due to delay in

supplying of working drawings by the defendants.

Plaintiff has further alleged that the construction work

was stopped for want of working drawings for lintel

beams, roof beams and slab. In letters dated 16/2/1995,

27/7/1995,    16/10/1995,      16/4/1997,       14/10/1998,

plaintiff has alleged that the defendants have failed to

supply designs, drawings and other technical particulars

pertaining to different components of the work.

     45. On the other hand, the defendants have pleaded

and lead evidence by denying the allegations of non

supply of working drawings and designs to the plaintiff in

time and the alleged inordinate delay caused in supply of

the working drawings and designs to the plaintiff. The

defendants have pleaded and lead evidence stating that

the entire drawing work upto the roof level has been

given to the plaintiff on 9/12/1993 vide letter No.EE/JE­

3/dated 9/12/1993 and there is no delay on their part in
                           51
                          CT 1390_Com.O.S.24­2019_Judgment .doc


supplying working drawing and designs showing the

details of foundation, basement, superstructure with all

items.

     46. In support of their defence, the defendants have

mainly relied on Ex.D.6 letter dated 14/5/1993.               A

perusal of contents of Ex.D.6 letter dated 14/5/1993

addressed by the 2nd defendant - Chief Engineer to the 3 rd

defendant    Executive   Engineer     discloses     that    the

structural   drawings    No.CBS/SD/FGC.SDG1,            2,3,4/

1992­93 showing the details of excavation combined

footings, isolated footings and RC footing columns were

supplied to the 3rd defendant - Executive Engineer

pertaining to the construction in dispute.

     47. A perusal of the contents of Ex.P.1(a) schedule

of contract form discloses that clause 2(b) of the contract

provides for preparation of program of work. Clause 2(b)

of the contract provides that the time allowed for carrying

out of the work as entered in the tender shall be strictly

observed by the contractor. It shall be reckoned from the
                           52
                          CT 1390_Com.O.S.24­2019_Judgment .doc


date of handing over to the contractor not less than 75%

of the work site area comprising a contiguous block. It

provides that the work through out the stipulated period

of the contract be proceeded with all due diligence.          It

provides that to ensure good progress during the

execution of the work, the contractor shall be bound to

comply with the time schedule according to the program

of execution of the work as agreed upon and enclosed to

the contract.

     48. A perusal of the materials on record discloses

that as per clause 2(b) of the schedule of contract form,

which provides for preparation of program of work, the

contractor was required to carry out the work of tender

within the stipulated period of time and to ensure good

work progress during the execution of the work and to

comply with the time schedule contractor was required to

prepare program of execution of the work.         However, a

perusal of materials on record discloses that the plaintiff

has neither pleaded nor lead any evidence with regard to
                             53
                            CT 1390_Com.O.S.24­2019_Judgment .doc


the preparation of program of work pertaining to the time

schedule   of   supplying     working     drawings      by    the

defendants required for construction work.               In the

absence of producing any program of work agreed upon

by the plaintiff and defendants pertaining to supply of the

working drawings, the contention of the plaintiff that

defendants have failed to provide him necessary working

drawings within the stipulated period of time and there is

inordinate delay on the part of the defendants to furnish

the working drawings cannot be accepted.

     49. A perusal of the evidence on record discloses

that in letter dated 2/7/1993, which was the first letter

addressed by the plaintiff to the 3rd defendant marked as

one of the letter in Ex.P.5 bunch of letters, plaintiff has

admitted about the receipt of approved working drawings

for foundation on 3/5/1993.             In the letter dated

24/10/1994, plaintiff has admitted about the receipt of

working drawings for plinth beam in the month of April &
                           54
                           CT 1390_Com.O.S.24­2019_Judgment .doc


May 1994.     Plaintiff also admits about the receipt of

drawing for roof slab and beams during September 1994.

     50. A perusal of the above mentioned letters

addressed by the plaintiff to the 3rd defendant discloses

that he had received almost all the major working

drawings by September 1994. It is pertinent to note that

the working order for construction was issued to the

plaintiff on 6/4/1993. The stipulated date for completion

of the contract was 26/3/1995.         Ex.P.1 contract was

rescinded by the defendants on 12/6/2001 for non­

completion of the contract work by the plaintiff. The very

fact that by September 1994, plaintiff has admittedly

received all the major working drawings and designs

falsifies the contention of the plaintiff that due to failure

on the part of the defendant to furnish working drawings

and designs, he was unable to complete the construction

work within stipulated period of time.

     51. The second ground       urged by the plaintiff for

non completion of the construction work within the
                             55
                                CT 1390_Com.O.S.24­2019_Judgment .doc


stipulated period of time by him is the alleged failure on

the part of the defendants to get the high­tension electric

lines & telephone lines shifted from the construction site

in time.     With regard to this alleged failure of the

defendants    to      perform     their    part    of   contractual

obligations is concerned, plaintiff has pleaded and lead

evidence stating that the electric lines and telephone

lines were crisscrossing the work site.                 It was very

difficult to execute the work under the electrical and

telephone    lines.     Inspite      of   his   repeated    request,

defendants have abnormally delayed in clearing the site

by removing the electrical and telephone lines.               By his

letter dated 25/11/1993 and 27/7/1995, he has brought

to the knowledge of the defendants about the delay

caused in clearing the site by removing the electrical and

telephone line.    The delay caused by the defendants in

clearing the site has caused substantial delay for him to

execute the work. Further, the defendants have also not

taken any action to complete the water supply, sanitary
                               56
                              CT 1390_Com.O.S.24­2019_Judgment .doc


and electric works which were essential for completing

the civil work by him. By his letters dated 6/11/1996,

16/4/1997, he has requested the defendants to complete

the water supply, sanitary work, but the defendants have

failed to complete the work which they had taken up to

some other agencies.

          52. To prove the alleged delay caused by the

defendants in clearing the obstruction in the work site

and also the alleged failure on the part of the defendants

to complete the water supply, sanitary and electrical

works which were not connected to the plaintiff, plaintiff

has mainly relied on Ex.P.5 ­ 15 letters addressed by him

to the 3rd defendant. A perusal of the contents of Ex.P.5

letters    discloses   that   in   letters   dated     2/7/1993,

25/11/1993,       11/5/1994,       10/6/1994,       24/10/1994,

30/12/1994, 16/2/1995, 23/3/1995, plaintiff has not

whispered the fact that there was delay on the part of the

defendants in clearing the work site               and delay in

completion of the water supply, sanitary and electrical
                           57
                          CT 1390_Com.O.S.24­2019_Judgment .doc


works as alleged by him in the present suit.          Only in

letters   dated   27/7/1995,    6/11/1996,       16/4/1997,

14/10/1998, the plaintiff has alleged that there is delay

on the part of the defendants in shifting telephone lines

crossing the work site.

     53. On the other hand the defendants in their

pleadings and evidence have denied the allegations of

inordinate delay on their part in shifting the electric

lines, telephone line and water supply lines from the

work site. Further the defendants have pleaded and lead

evidence stating that when the site was handed over to

the plaintiff, they have remitted a sum of Rs.9,893/­ vide

cheque No.965438 dated 14/6/1993 to shift the electric

lines and poles and also remitted a sum of Rs.8,192/­ to

BSNL Account No.MB 5572 to shift the telephone lines

and poles.   After receipt of the said sum by the above

mentioned two departments, they have shifted the poles

and lines from the site. There was no obstruction for the

commencement of the work by the plaintiff. There is no
                           58
                           CT 1390_Com.O.S.24­2019_Judgment .doc


latches on their part in getting the electric and telephone

lines shifted from the work site.

     54. A perusal of the materials on record discloses

that the plaintiff who has made allegations of inordinate

delay against the defendants for shifting electric lines,

telephone lines and water supply lines has not produced

the program of work as required under clause 2(b) of the

Ex.P.1(a) schedule of contract form, wherein, the agreed

time stipulated for the defendants to get the electric lines,

telephone lines and water supply lines shifted from the

construction site and to get the site clear was stated. In

the absence of production of program of work before the

court, the contention of the plaintiff that there was

inordinate delay on the part of the defendants to get the

electric lines, telephone lines and water supply lines

shifted cannot be accepted.

     55. By perusing the materials produced on record,

this court is of the opinion that the plaintiff has failed to

prove that there is abnormal delay on the part of the
                           59
                          CT 1390_Com.O.S.24­2019_Judgment .doc


defendants in fixing the high tension electric lines,

telephone lines and Municipal water supply lines, which

has resulted in delay in completion of the contract work,

thereby, there is breach of contractual obligations on the

part of the defendants in performing their part of the

contract.

     56. The third alleged reason stated by the plaintiff

for non completion of the work within the stipulated

period of time is non availability of building materials at

the distance shown by the defendants at the time of

tendering. With regard to this reason, the plaintiff has

pleaded and lead evidence stating that the essential

building materials were not available to him at a

reasonable distance and he had to go in search of the

building materials, since same were not available at the

place shown by the defendants at the time of tendering,

which has caused further delay in executing the work

which incurred extra cost and required much more

investments by him. On the other hand the defendants
                           60
                          CT 1390_Com.O.S.24­2019_Judgment .doc


in their written statement and evidence have denied this

allegation and further contended that plaintiff being a

class­I contractor has to look after all the things, he

cannot   depend upon the defendants for             collecting

material to complete the tender work.

     57. A perusal of the evidence on record discloses

that plaintiff has not produced any document to show

that the defendants have assured him about availability

of building materials at a reasonable distance when he

has entered into contract with the defendants. Even in

Ex.P.1 tender document there is no clause stating that

defendants have assured the plaintiff about availability of

building materials at a reasonable distance from the work

site. Apart from that the plaintiff has not produced the

program of work to show that the defendants have

assured him about availability of essential building

materials at a reasonable distance at the time of

tendering.    In the absence of production of any

documentary evidence to show that the defendants have
                             61
                            CT 1390_Com.O.S.24­2019_Judgment .doc


assured the plaintiff about availability of essential

building   materials   at   a    reasonable     distance,     the

contention of the plaintiff that the essential building

materials were not available at a reasonable distance

shown by the defendants which has caused further delay

in execution of the work by him incurring extra cost and

making more investment by him cannot be accepted.

     58. The fourth reason stated by the plaintiff for non

completion of the work within stipulated period of time is

the alleged irregular interim payments made by the

defendants with regard to the construction work done by

him. With regard to this reason, the plaintiff has pleaded

and lead evidence stating that the contract provided for

payment for the work done in each month. There were in

ordinate delays in preparing and payment of bills by the

defendants. In some occasion, the defendants took 6 to 8

months for making one running bill payment.                  The

irregular payments made by the defendants has created

unbalance working condition and delayed the completion
                          62
                         CT 1390_Com.O.S.24­2019_Judgment .doc


of the work. Even at the time of cancellation of the work

there were substantial pending payments. The delay in

making payments were brought to the knowledge of the

defendants through various letters addressed by him to

the defendants.

     59. On the other hand the defendants in their

written statement and also evidence have denied the

allegations of irregular payments made by them with

regard to the work done by the plaintiff.        Defendants

further contended that the amount for the work done by

the plaintiff has been disbursed as per the allocation of

funds made by the government and there was no

inordinate delay in preparing the bills on their side.

Defendants further contended that as on the date of

cancellation of the contract, plaintiff had received more

than the amount which was shown in the contract

agreement. As on 12/6/2001, a sum of Rs.47,60,006/­

has been disbursed to the plaintiff on the basis of the

work slip. The work slip has been prepared by them on
                              63
                             CT 1390_Com.O.S.24­2019_Judgment .doc


9/12/1993, the same was in knowledge of the plaintiff.

Such being the case, the question of delayed payments

by them will not arise.

     60. A perusal of the pleadings and evidence of the

plaintiff discloses that except stating the fact that the

defendants were irregular in interim payments for the

work done by him, plaintiff has not stated the details

about the preparation of the running bills and the date of

alleged delayed payments made by the defendants

pertaining to the running bills. Admittedly, on the date

of rescission of the contract on 12/6/2001, plaintiff has

received the amount which was more than the value of

the work as per the contract. In the absence of

production   of   reliable     documentary       evidence      the

contention of the plaintiff that there is inordinate delay

on the side of defendants in preparing and payment of

running bills and the interim payment for the work done

by him were very irregular by the defendants cannot be

accepted.
                          64
                          CT 1390_Com.O.S.24­2019_Judgment .doc


     61. A perusal of the materials on record discloses

that Ex.P.1 contract was entered between the plaintiff

and defendants on 26/3/1993. Date of commencement

of the work under Ex.P.1 contract was fixed on

26/3/1993. Work order was issued on 6/4/1993. Date

of completion of the work as per Ex.P.1 contract was

26/3/1995.     A period of 24 months was fixed for

performance of contract under Ex.P.1 contract.              The

defendants   have   rescinded    the    contract     only    on

12/6/2001 i.e. after 98 months of entering into the

contract.

     62. In the present case, the plaintiff has pleaded the

alleged delay in supply of working drawings, alleged delay

on the part of the defendants to get the high­tension

electric lines, telephone lines and Municipal water supply

lines as the main reasons for non completion of the work.

However, in Ex.P.5 letters addressed by the plaintiff to

the defendants, he has admitted about the receipt of

major working drawings by the month of September 1994
                            65
                               CT 1390_Com.O.S.24­2019_Judgment .doc


and shifting of telephone lines and electric lines in the

year 1995.      Under the facts and circumstances of the

case, the alleged reasons shown by the plaintiff for non

completion of the work within stipulated period of time

cannot be accepted.

      63. A perusal of the pleadings and evidence of the

plaintiff discloses that plaintiff has alleged that delay on

the part of the defendants in supply of approved working

drawings, delay in shifting of high­tension electric lines,

telephone lines and Municipal water supply lines from

the   working    site,   non     availability    of   construction

materials at the distance shown by the defendants at the

time of tendering, irregular interim payments made by

the defendants for the work done by him as the reasons

for non completion of the contract work within the

stipulated period of time. However, a perusal of Ex.P.1

schedule of the contract form discloses that clause 29 of

the contract provides for settlement of dispute or

difference that arose between the 3 rd defendant -
                              66
                             CT 1390_Com.O.S.24­2019_Judgment .doc


Executive    Engineer   and       the   Contractor    -    plaintiff

regarding any dispute arose with regard to the execution

of the work during the progress of the work to be referred

to   the   2nd   defendant   -    Chief   Engineer,       who   has

jurisdiction over the work. In the present case, a perusal

of materials on record discloses that the plaintiff who has

made allegations of non performance of contractual

obligations by the 3rd defendant during the period of

execution of the contract has admittedly not referred the

said dispute to the 2nd defendant - Chief Engineer. The

very fact that the plaintiff has not referred the settlement

of the dispute in terms of the clause 29 of the contract is

another circumstance which goes against the case of the

plaintiff with regard to alleged failure of the defendants to

perform their part of the contractual obligations as the

reason for the plaintiff for non completion of the

contractual work within the stipulated period of time.

      64. With regard to recession of Ex.P.1 contract by

the defendants on 12/6/2001 is concerned, the plaintiff
                             67
                            CT 1390_Com.O.S.24­2019_Judgment .doc


had pleaded and lead evidence stating that inspite of non

performance of contractual obligations by the defendants

which has caused delay in execution of the work, he was

executing the work under most trying circumstances and

successfully completed more than the tender value of the

work to the tune of Rs.46,02,146/­ as per the bills paid

by the defendants, whereas the tender value of the work

was only Rs.38,91,629/­.          Meantime, the defendants

have chosen to take illegal, wrongful and unwarranted

action of canceling the contract with a threat to execute

the balance work at his risk and cost, though the delay in

execution    of    the   work    were   attributable     to   the

defendants. The defendants were not even bother to fix

further period for performance to make time essence of

the contract, after original contract period expired on

26/3/1995.        Inspite of repeated requests made by him

for extension of time before the expiry of the contractual

period, the defendants have not extended the period for
                           68
                          CT 1390_Com.O.S.24­2019_Judgment .doc


performance of the contract and illegally and wrongfully

canceled the contract on 29/6/2001.

     65. On the other hand, the defendants in their

written statement and their evidence have denied            the

plaintiff's allegation that the cancellation of the contract

on 12/6/2001 by them was illegal and wrongful. On the

other hand, the defendants have pleaded and lead

evidence stating that plaintiff has received the amount to

the tune of Rs.46,02,146/­ against the tender value work

of Rs.38,91,629/­.    Even after expiry of the stipulated

period of completion of the contract on 26/3/1995, there

was huge work pending from the side of the plaintiff. In

the interest of public at large and to make the building

completed and available to the students, they have

allowed the plaintiff to continue the contract work, even

after expiry of the contractual period upto 28/6/2001.

On 29/6/2001, they have rescinded Ex.P.1 contract due

to delay caused by the plaintiff in completing the work.
                             69
                            CT 1390_Com.O.S.24­2019_Judgment .doc


     66. A perusal of the pleadings and evidence of the

plaintiff discloses that the main grievance of the plaintiff

with regard to recession of the contract dated 26/3/1993

by the defendants on 12/6/2001 is that due to failure on

the part of the defendants to perform their part of the

contract, he could not able to complete the construction

work within stipulated period of time, as a result of

which, he has addressed several letters to the defendants

before expiry of the period of contract seeking extension

of time to perform his part of the contract and defendants

have not bothered to extend the time for performance of

the contract to make time essence of the contract, after

expiry of original period of contract have illegally

rescinded the contract.

     67. A perusal of the pleadings and evidence of the

plaintiff discloses that he claims that time was not the

essence of Ex.P.1 contract and the action of the

defendants   to   rescind   the    contract    without     giving
                           70
                          CT 1390_Com.O.S.24­2019_Judgment .doc


extension of time to perform his part of the contract is

illegal.

      68. At this juncture, it is relevant to consider a

decision of the Apex Court of the Land reported between

State of Maharastra & another V/s. Digambar Balwant

Kularni reported in AIR 1979 Supreme Court 1339,

wherein, the Apex Court of the Land has held that :

      "Contract Act (9 of 1872), Ss.39 and 55 - Works
contract - Time mentioned as of essence of contract - But
contract enforceable till completion of work or its
abandonment - Rescission of contract and consequent
forfeiture of security deposit held proper within terms of
contract. Appeal No.534 of 1969, dt. 11/7/1968 (Bom),
Reversed."
      69. In the above cited decision the Apex Court of the

Land has interpreted the clauses of a work contract

similar to that of Ex.P.1 contract and held that time was

essence of the contract in the limited sense that the

contract will be continued to be in force till the

completion of the work or its abandonment. In the said
                           71
                          CT 1390_Com.O.S.24­2019_Judgment .doc


decision by interpreting the clauses of the work contract

similar to that of Ex.P.1 contract, the court held that the

rescission of the contract and forfeiture of the security

deposit by the Executive Engineer on the failure of the

part of the Contractor to achieve the work progress was

valid.

     70. The aspect as to whether the time was the

essence of Ex.P.1 contract or not has to be considered by

going through clauses of Ex.P.1(a) schedule of the

contract form.

     71. A perusal of clause 2(b) of Ex.P.1(a) schedule of

contract form discloses that the same provides that the

time allowed for carrying out the work as entered in the

tendering shall be strictly observed by the Contractor. It

further provides that the work shall through out the

stipulated period of the contract be proceeded with all

dues diligence (time being deemed to be the essence of

the contract on the part of the contractor).           It also

provides that to ensure good progress during the
                             72
                            CT 1390_Com.O.S.24­2019_Judgment .doc


execution of the work, the contractor shall be bound to

comply with the time schedule according to the program

of execution of work as agreed upon enclosed to the

contract.

     72. A perusal of clause 2(d) of the contract which

provides for penalty for delay discloses that it provides

that in respect of shortfall in progress assessed due to

the delay on the part of the contractor as per clause 2(b)

& (c), the contractor shall be liable to pay as penalty an

amount equal to 1% of the estimated cost of the balance

work assessed according to the program for every day

that the due quantity of work remains incomplete.

Further clause 3 of the contract provides that in any case

in which under any clause or clauses of the contract, the

Contractor shall have rendered himself liable to pay

compensation or penalty amounting to the whole of his

security deposit including the amount deducted in

installments from his bills as further security deposit, the

Executive   Engineer   on    behalf    of   the   Governor     of
                           73
                           CT 1390_Com.O.S.24­2019_Judgment .doc


Karnataka shall have power to adopt the recourses, such

as, forfeiture of security deposit, recession of the

contract. Clause 3(e) of the contract provides that in the

event of the Executive Engineer taking recourses with

regard to forfeiture of security deposit of the contract and

for recession of the contract, the Contractor shall have no

claim to compensation for any loss sustained by him.

     73. A perusal of the above mentioned provisions of

Ex.P.1 contract stated in Ex.P.1(a) schedule of the

contract form, if read together and interpreted with

reference to each other provision and read as single

whole closely goes to show that the contract was to

continue to be in force till the completion of the work or

its rescission. The time was the essence of the contract

only for the limited sense that if the plaintiff completed it

within the original contractual period, he would not be

liable to pay any compensation, but in case of non­

completion of the contract within the contractual period,

plaintiff has to compensate the defendants for non
                             74
                            CT 1390_Com.O.S.24­2019_Judgment .doc


completion of the work and right of recession of the

contract   would   accrue    to   the   defendants      on   non

completion of the work by the plaintiff.            Hence, the

contention of the plaintiff that under Ex.P.1 contract

dated 26/3/1993 the time was not the essence of the

contract and the act of the defendants to rescind contract

without extending period of time for performance of the

contract is illegal cannot be accepted.

     74. With regard to the grievance of the plaintiff

pertaining to non extension of time to perform contract

by the defendants is concerned, a perusal of clause 5 of

the schedule of contract discloses that the same deals

with grant of extension of time.          Clause 5(a) of the

contract provides that :

     " If the contractor shall desire an extension of the
time for completion of the work on the ground of his
having been unavoidably hindered in its execution or on
any other ground, he shall apply in writing to the
Executive Engineer before the expiration of the period
stipulated in the tender or before the expiration of 30
                           75
                          CT 1390_Com.O.S.24­2019_Judgment .doc


days from the date on which he was hindered as
aforesaid or on which the cause for asking for extension
occurred, whichever is earlier and the Executive Engineer
or other competent authority may, if in his opinion, there
are reasonable grounds for granting an extension, grant
such extension as he thinks necessary or proper.           The
decision of such competent authority in this matter shall
be final."


     75. A perusal of the clause 5(a) of the schedule of

contract form discloses that the aspect of extension of

time with regard to performance of the contract was in

the discretion of the 3rd defendant - Executive Engineer.

The decision of the 3rd defendant - Executive Engineer in

the extension of time is final. In the light of the clause

5(a) of the contract, a perusal of the materials on record

discloses that on the letters addressed by the plaintiff to

the defendants seeking extension of time to perform his

part of the contract, the defendants though have not

extended the time for performance of contract in writing,

but have impliedly granted extension of time till recession
                          76
                          CT 1390_Com.O.S.24­2019_Judgment .doc


of the contract. However, the 2nd defendant considering

the fact that the plaintiff has failed to achieve the

required work progress has issued Ex.D.7 to D.17 notices

dated 28/6/1993, 3/8/1993, 2/6/1994, 7/6/1994,

30/8/1994, 13/9/1996, 2/2/1995, 5/7/1995,               to the

plaintiff on various dates calling upon him to make up

the shortfall of the work progress and on failure of the

part of the plaintiff to make up the shortfall of the

stipulated work progress has issued Ex.D.1 final notice

dated 3/9/1998 stating that since the plaintiff has failed

to make up the shortfall of the work progress and on the

failure of the plaintiff to complete the work have decided

to rescind the contract and called upon the plaintiff to

present at the work site on 11/9/1998 to take the final

measurement of the work completed.          Further through

Ex.D.5 letter dated 12/6/2001, Ex.P.1 contract was

rescinded by the 2nd defendant on cost and risk basis of

the plaintiff for failure on the part of the plaintiff to

complete the construction work.
                           77
                          CT 1390_Com.O.S.24­2019_Judgment .doc


     76. On the aspect of recession of Ex.P.1 contract is

concerned, a perusal of the contents of Ex.P.1(a)

schedule of the contract form discloses that clause 2(d) of

the contract deals with penalty for delay in respect of

shortfall in progress assessed due to the delay on the

part of the Contractor in completing the work.         Clause

2(d) of the contract provides for payment of penalty by

the Contractor in case of shortfall in progress an amount

equal to 1% of the estimated cost of the balance work

assessed according to the program for every day that the

due quantity of work remains incomplete.

     77. A perusal of clause 3 of the contract discloses

that it provides that in any case in which under any

clause of the contract, the Contractor shall have rendered

himself liable to pay compensation / penalty, the

Executive Engineer under clause 3(a) of the contract have

right to rescind the contract by issuing a written notice to

the Contractor.
                           78
                           CT 1390_Com.O.S.24­2019_Judgment .doc


     78. In light   of the above mentioned provision of

clause 2 and 3 of the Ex.P.1 schedule of contract form a

perusal of the materials on record discloses that the

Assistant    Executive    Engineer,     PWD       Department,

Chikkaballapura has issued Ex.D.7 to D.17 notices dated

28/6/1993,       3/8/1993,        2/6/1994,         7/6/1994,

30/8/1994, 13/9/1996, 2/2/1995, 5/7/1995, calling

upon the plaintiff to make good the shortfall in the

progress of the work and to achieve the work progress in

terms of the contract. In Ex.D.7 notice dated 28/6/1993

issued by the 3rd defendant to the plaintiff a penalty of

Rs.32,430/­ was imposed on the plaintiff for the shortfall

in the progress of the work within the stipulated period.

A perusal of contents of Ex.D.1 final notice dated

3/9/1998 issued by the 3rd defendant - Executive

Engineer to the plaintiff discloses that in the said notice

it is alleged that since plaintiff has failed to complete the

construction work, the defendants have decided to

rescind the contract and to take measurement of the
                           79
                           CT 1390_Com.O.S.24­2019_Judgment .doc


construction work.       Thereafter, ExP.1 contract was

rescinded on 12/6/2001 under Ex.D.5 letter dated

12/6/2001 addressed by the 2nd defendant to the 3rd

defendant.

      79. A perusal of the materials on record discloses

that the fact that under Ex.P.1 contract dated 26/3/1993

the   agreed   monthly   stipulated    progress     fixed   was

Rs.2,16,200/­ is not in dispute. Further fact that even

after completion of the stipulated period of contract on

26/3/1995 and upto recession of the contract on

12/6/2001, plaintiff failed to achieve the agreed work

progress and failed to complete the construction work is

not in dispute.   As per the contents of Ex.D.15 notice

issued by the 3rd defendant to the plaintiff dated

2/2/1995, there was shortfall of work progress of

Rs.10,39,468/­.    Admittedly, after completion of the

contractual period on 26/3/1995 or thereafter till

rescission of the contract on 12/6/2001, the plaintiff has

failed to reach the stipulated work progress and failed to
                           80
                          CT 1390_Com.O.S.24­2019_Judgment .doc


complete the construction work. Plaintiff who has alleged

that the alleged defaults on the part of the defendants in

performing their part of the contractual obligation as

reasons for non completion of the work within the

stipulated period of time has failed to prove the same.

On the other hand, the defendants on the ground that

the plaintiff has failed to achieve the required stipulated

progress of work have issued Ex.D.1 final notice dated

3/9/1998 stating that they have decided to rescind the

contract in terms of Ex.P.1 contract for non completion of

the   contract   work   have   rescinded    Ex.P.1    contract

through Ex.D.5 letter dated 12/6/2001 on the ground

that plaintiff has failed to complete the construction work

in terms of Ex.P.1 contract. Since the defendants have

rescinded the contract in terms of Ex.P.1 contract for

failure on the part of the plaintiff to achieve the required

progress of the work and to complete the construction in

terms of the contract, the contention of the plaintiff that

the recession of the contract dated 26/3/1993 by the
                           81
                          CT 1390_Com.O.S.24­2019_Judgment .doc


defendants on 12/6/2001 is illegal and arbitrary, cannot

be accepted.

     80. The learned counsel for the plaintiff in his

written arguments and further written arguments filed

before the court has mainly relied on Section 52 to 55 of

the Indian Contract Act and argued that since the

defendants have failed to fulfill their promise in terms of

the Ex.P.1 contract, the plaintiff could not able to

complete the construction work within stipulated period

of time. It is further argued that inspite of failure on the

part of the defendants to perform their part of the

contract, the plaintiff was executing the work under most

trying circumstances and kept the work in progress and

was successfully completed more than the tender value of

the work to the tune of Rs.46,02,146/­ against the tender

value of the work of Rs.38,91,629/­.           Inspite of it,

defendants have chosen to take illegal, wrongful and

unwarranted action of cancellation of the contract with a

threat to execute balance work at his risk and cost,
                           82
                          CT 1390_Com.O.S.24­2019_Judgment .doc


though the delays and defaults were attributable to the

defendants. It is further argued that the defendants were

not even bothered to fix further period of performance to

make time essence of the contract after expiry of original

contract period. It is further argued that in view of the

breach of contractual obligations by the defendants,

plaintiff is entitle for the damages which the plaintiff has

sought for as suit claims in the present suit.

     81. On issues No.1 and 2 are concerned, the

learned counsel for the plaintiff in his written arguments

and additional written arguments has relied on following

citations, which will be considered one by one.

     (1) In Hind Construction Contractors V/s. State of

Maharastra reported in AIR 1979 page 720, wherein, the

Apex Court of the Land has stated about the tests for

deciding if the time was essence of the contract when

Contractor   has   not   completed   the contract       within

stipulated period of time and when no term in contract

making the time essence of contract.
                            83
                           CT 1390_Com.O.S.24­2019_Judgment .doc


     82. I have perused the ratio of the above cited

decision.   However, unlike cited decision in the present

case in hand in clause 2(b) of Ex.P.1 schedule of contract

form, it was specifically stated that time being deemed to

be the essence of the contract on the part of the

Contractor. Hence, the ratio of the above cited decision

is not helpful for the plaintiff to prove that time is not the

essence of the contract under Ex.P.1 agreement.

     83. The learned counsel for the plaintiff has also

relied on a decision reported between State of Karnataka

V/s. Sree Rameshwara Rice Mill, Theerthahalli, reported

in 1987 AIR 1359, wherein, the Apex Court of the Land

has held that in case of breach of agreement amount of

assessment of damages is to be made by the independent

body and not by parties to the contract.

     84. I have perused the ratio of the above cited

decision also.     However, unlike cited decision in the

present case, plaintiff has failed to prove that defendants

have committed breach of condition of agreement and he
                             84
                            CT 1390_Com.O.S.24­2019_Judgment .doc


is entitle for damages. Hence the ratio of the above cited

decision is also not helpful for the plaintiff.

     85. The plaintiff's counsel has also relied another

decision reported between J.J.Engineers Private Limited

V/s. Union of India and another reported in 2011(2)

ARB.LR.84(SC), wherein the Apex Court of the Land held

that the question whether the other party committed

breach cannot be decided by the party alleging breach. A

Contractor cannot provide that one party will be the

Arbitrator to decide whether he committed breach or the

other party committed breach, the question can only be

decided by an adjudicatory firm i.e. a Court or an Arbitral

Tribunal.

     86. I have perused the ratio of the above cited

decision.   However, considering the fact that the Ex.P.1

contract do not provide for arbitration clause for decide

breach of contract by the defendants themselves who are

the parties for the contract, the ratio of the above cited

decision is also not helpful for the plaintiff.
                             85
                            CT 1390_Com.O.S.24­2019_Judgment .doc


     87. The learned counsel for the plaintiff has also

relied   on   another   decision    reported      in   Municipal

Corporation of Delhi V/s. Jagannath Ashok Kumar

reported in Arbitrators Law Reporter 1987(2) page 344,

wherein, the Apex Court of the Land has held that if the

contract has a provision for extension of time or

compensation then it cannot be said that time was

essence of the contract.

     88. I have perused the ratio of the above cited

decision. Unlike cited decision in Ex.P.1(a) schedule of

contract form it was specifically stated that time was the

essence of the contract.     The provision for extension of

time for performance of contract was given at the

discretion of the defendants. Considering the fact that in

Ex.P.1 contract it was specifically stated that time was

the essence of the contract and contractor plaintiff was

required to perform his part of the contract strictly within

the specific period of time, the ratio of the above cited

decision is also not helpful for the plaintiff.
                             86
                            CT 1390_Com.O.S.24­2019_Judgment .doc


       89. By perusing the oral and documentary evidence

produced on record and over all assessment of the same,

I hold that plaintiff has failed to prove that defendants

have    failed   to   perform    their   part   of   contractual

obligations of the contract dated 26/3/1993 entered

between him and the defendants. Plaintiff has also failed

to prove that cancellation of contract dated 26/3/1993

made by defendants on 12/6/2001 is illegal and

wrongful. With these observations, I answer issues No.1

and 2 in the negative.

       90. ISSUE NO.3 : With regard to issue No.3 is

concerned, the plaintiff has pleaded and lead evidence

stating that the stipulated period of contract expired on

26/3/1995.        Inspite of several delays and default

committed by the defendants, he continued the execution

of the work even beyond the stipulated period.               The

defendants have also implied and permitted him to

complete the execution of the work. He has successfully

completed more than the tender value of work to the tune
                            87
                           CT 1390_Com.O.S.24­2019_Judgment .doc


of Rs.46,02,146/­ against the tender value of the work of

Rs.38,91,629/­.     The defendants not even bothered to

approve the extra cost incurred, which was under

execution where the approval was essential in terms of

contract. His repeated request for grant of extension of

time to perform part of the contract was kept in silent by

the defendants and made him to continue the work. All

of a sudden the defendants have taken illegal action of

canceling the contract by applying cost and risk action of

completing    the   balance     work.     The    question     of

cancellation of the contract work by the defendant do not

arise, since they have failed to perform their part of the

obligation in terms of contract and also the contract work

has already exceeded the contract value. The defendants

opted for illegal cancellation of the work, without fulfilling

their obligations and without opting for settlement for

dispute in terms of clause 29 of the contract without

deciding the breach of contract either by an award or

decree.
                           88
                          CT 1390_Com.O.S.24­2019_Judgment .doc


     91. On the other hand, the defendants have pleaded

and lead evidence stating that even after expiry of the

contract period on 26/3/1995, plaintiff continued the

construction work beyond the contract period and the

work of the plaintiff exceeded upto Rs.46,02,147/­

against the tender contract work of Rs..38,91,629/­.

They have already paid the excess amount to the plaintiff

on the basis of work slip which was stipulated in

schedule contract form 13(b). The approval was given by

the Superintendent Engineer with regard to payment of

the excess amount on 5/1/1994.          Since, plaintiff has

failed to execute the tender work and there was

inordinate delay on the part of the plaintiff in completing

the tender work, they have canceled the contract of the

plaintiff on 12/6/2001.     Thereafter, they have called

tender for balance work and entrusted the balance work

to one Sri.C.S.Chandregowda, who is the lowest quoted

tenderer for a sum of Rs.9,46,000/­.              The above

mentioned    contractor   has    completed      the   balance
                           89
                          CT 1390_Com.O.S.24­2019_Judgment .doc


construction work and handed over the building to them.

The plaintiff has to bear the loss caused to the

defendants pertaining to completion of balance work by

another contractor.

     92. In the present case in hand, the plaintiff has

failed to prove that cancellation of the contract dated

26/3/1993 made by the defendants on 12/6/2001 is

illegal and wrongful.    On the other hand, perusal of

evidence on record discloses that admittedly the plaintiff

has failed to achieve monthly stipulated progress of the

work in terms of the contract and there was inordinate

delay on the part of the plaintiff in completing the

construction work. A perusal of clause 2(d) of the

contract discloses that it provides for payment of penalty

by the contractor in respect of shortfall in progress due to

delay on the part of the contractor as per clause 2(b) & (c)

of the contract. Clause 3 of the contract provides that in

cases in which under any clause of the contract, the

Contractor shall have rendered himself liable to pay
                           90
                           CT 1390_Com.O.S.24­2019_Judgment .doc


penalty, the Executive Engineer have power to rescind

the work under clause 3(a) of the contract and cancel the

contract on risk and cost basis as per clause 3(c) of the

contract.

     93. A perusal of the materials on record discloses

that since the plaintiff - Contractor has failed to reach

the stipulated work progress and the shortfall in work

progress and inordinate delay in completion of the

contract work was assessed due to delay on the part of

contractor­ plaintiff, defendants rescinded the contract of

the plaintiff on cost and risk basis as per clause 3(b) & (c)

of the schedule tender.        Since Ex.P.1(a) schedule of

contract form provides for recession of the contract on

cost and risk basis and since the defendants have

rescinded the contract on cost and risk basis in terms of

the Ex.P.1(a) schedule of contract form, the contention of

the plaintiff that the defendants cannot apply the cost

and risk action for completing the balance work against

him in case of recession of contract cannot be accepted.
                          91
                         CT 1390_Com.O.S.24­2019_Judgment .doc


With these observations, I answer issue No.3 in the

negative.

     94. ISSUE NO.4 : With regard to issue No.4 is

concerned, the plaintiff has pleaded and lead evidence

stating that due to several delays and defaults committed

by the defendants, he was unable to complete the

construction work within stipulated period of time. The

defendants instead of granting extension of time to him

to complete the construction work have wrongfully

rescinded the contract. That the defendants are liable to

refund EMD of Rs.40,000/­, FSD recovered under bills

amounting to Rs.2,99,139/­ and NSC recovered in bill

amounting    to   Rs.37,500/­,    totally   amounting       to

Rs.3,76,639/­. Plaintiff has claimed interest @ 12% per

annum on the above mentioned sum of Rs.3,76,639/­

amounting to Rs.7,04,315/­.      Plaintiff has sought for

total claim of Rs.10,80,954/­ on the above mentioned

amounts.
                             92
                            CT 1390_Com.O.S.24­2019_Judgment .doc


      95. On the other hand, the defendants have pleaded

and lead evidence stating that since the plaintiff has

failed to complete the work within stipulated period of

time, they have canceled the contract on cost and risk

basis as per clause 3(b) & (c) of the schedule of contract

and   security    deposit   has    been     forfeited    to   the

government.      Hence, the question of considering the

claim made by the plaintiff for a sum of Rs.3,76,639/­

and interest of Rs.7,04,315/­ will not arise.           Once the

forfeiture clause is opened by them, the question of

considering the above claim of the plaintiff will not arise.

      96. In the present case in hand, the plaintiff has

failed to prove that recession of the contract dated

26/3/1993 on 12/6/2001 by the defendants is illegal

and wrongful. On the other hand, since the plaintiff has

failed to reach the stipulated work progress in terms of

the contract and failed to complete the construction

work, the defendants by invoking clause 3(a) of the

contract have rescinded the contract and forfeited the
                          93
                         CT 1390_Com.O.S.24­2019_Judgment .doc


security deposit of the plaintiff - Contractor. Since the

defendants have forfeited the amount deposited by the

plaintiff in term of clause 3(a) of the contract, the

contention of the plaintiff that defendants are liable to

pay him claim of Rs.10,80,954/­ on the forfeited security

deposits cannot be accepted. With these observations, I

answer issue No.4 in the negative.

     97. ISSUE NO.5 : As claim No.2 plaintiff has sought

for payment of damages of Rs.32,03,107/­ from the

defendants towards payment of damages of idle charges

for men and machinery suffered by him during stoppage

period of execution of the work in contract period. With

regard to this claim is concerned, the plaintiff has

pleaded and lead evidence stating that the execution of

the work was stopped on several occasions for want of

design details and due to obstruction on work site and

lack of payment. The total period of stoppage was 308

days during the period of execution of the work from

commencement of the work to the cancellation of the
                               94
                              CT 1390_Com.O.S.24­2019_Judgment .doc


contract due to various defaults and breaches committed

by the defendants, as a result of which, he has suffered

damages in the form of idle charges for men and

machinery.         He had written various letters to the

defendants by intimating the stoppage of the work before

the expiry of the contract period. He has kept separate

men and machinery for this work. He has no chance to

mitigate the damages suffered during the idle period and

there   are    no     other    opportunity        to    utilize   the

establishment made by this aspect and he was always

ready at work site waiting for instructions of defendants

to execute the work. The idle charges per day works out

to Rs.3,600/­ including labourers machinery.                      The

defendants are required to compensate him for idle

charges at the rate of Rs.3,600/­ per day for the period of

308 days.      The idle charges were calculated for the

construction period when the stoppage was occurred. On

this claim, the plaintiff has sought for payment of

damages       of     Rs.11,16,000/­        plus        interest    of
                           95
                           CT 1390_Com.O.S.24­2019_Judgment .doc


Rs.20,87,107/­ @ 12% per annum, totally amounting to

Rs.32,03,107/­.

     98. With regard to the above mentioned alleged

claim No.2 of the plaintiff is concerned, the defendants

have pleaded and lead evidence stating that the payment

of damages by them for the idle charges of men and

machinery alleged to have been suffered by the plaintiff

do not arise, since there was no stoppage of work ordered

by them at any stage during the subsistence of the

contract.    The Contractor cannot made any claim for

compensation as per clause 15 of the schedule of

contract form.    They reserved their right to take action

against the plaintiff for the delay in execution of the

work.       Plaintiff has not maintained the men and

machinery in the site during the subsistence of the

contract. There is no default and breach committed by

them.   Plaintiff unnecessarily making false allegations

against them and has sought for imaginary amount of

compensation on this claim. At no point of time, plaintiff
                          96
                          CT 1390_Com.O.S.24­2019_Judgment .doc


has shown the idle of men and machinery at the site

during the subsistence of agreement and plaintiff          has

not made any representation in this regard.

     99. With regard to claim No.2 pertaining to payment

of alleged idle charges for men and machinery suffered

during stoppage period of execution of the work, plaintiff

has mainly relied on Ex.P.11 statement showing the

payments made by him with regard to skilled and

unskilled labourers with regard to idle charges of men

and machinery suffered during the stoppage period of

execution of the work. Further, plaintiff has also relied

on Ex.P.14    totally 51 vouchers under which plaintiff

alleged to have made payment of Rs.10,200/­ under each

voucher on various dates to one Kuppuswamy.

     100. It is pertinent to note that except producing

Ex.P.11 self prepared statement and Ex.P.14 vouchers

before the court, plaintiff has not proved the contents of

Ex.P.11 statement or Ex.P.14 vouchers by examining the

above mentioned D. Kuppuswamy to prove that he had
                           97
                          CT 1390_Com.O.S.24­2019_Judgment .doc


made any payments to him with regard to the labourers

as alleged in the said vouchers. Hence mere production of

Ex.P.11 statement and Ex.P.14 vouchers are not helpful

for the plaintiff to claim any compensation towards idle

charges of men and machinery, alleged to have been

suffered by him.

     101. A perusal of the evidence on record discloses

that the plaintiff has failed to prove that the stoppage of

work of construction was ordered by the defendants at

any point of time. No documentary evidence produced on

record by the plaintiff to show that the total period of

stoppage of the work was 308 days.         Plaintiff has not

produced any documentary evidence to show that he has

kept separate men and machinery for this work and as a

result of the alleged stoppage of the work he has suffered

any damages.       Plaintiff has also not produced any

documentary evidence to show that he had incurred

expenses of Rs.3,600/­ per day as idle charges for

stoppage of the work. On the other hand, a perusal of
                           98
                          CT 1390_Com.O.S.24­2019_Judgment .doc


the evidence on record discloses that admittedly, plaintiff

has failed to reach the stipulated work progress in terms

of the contract. Inspite of issuance of repeated notices by

the defendants to the plaintiff, he has failed to make up

the shortfall of the work and there was inordinate delay

on the part of the plaintiff to complete the construction

work, as a result of which, defendants have rescinded the

contract of the plaintiff in terms of the contract.           A

perusal of Ex.P.1(a) schedule of contract form discloses

that clause 3 (d) of the contract provides that if the

contractor does not maintain the rate of progress as

required under clause 2 of the contract and failed to

maintain the rate of progress even after taking action

under clause 2(c) & (d) by the Executive Engineer, then

the contractor will have no claim for compensation for

any loss sustained by him owing to such actions.

     102. Since the plaintiff has failed to prove that due

to various defaults and breaches committed by the

defendants, he has suffered damages in the form of idle
                           99
                          CT 1390_Com.O.S.24­2019_Judgment .doc


charges for men and machinery and since clause 3 (b) of

the contract provides that the plaintiff will have no claim

for compensation for any loss sustained by him due to

failure on his part to maintain the rate of progress as

required under the contract, plaintiff is not entitle for

payment of damages of idle charges for men and

machinery alleged to have been suffered by him.           With

these observations, I answered issue No.5 in the negative.

     103. ISSUE No.6 : With regard to issue No.6

pertaining to claim No.3 sought for by the plaintiff is

concerned, the plaintiff claimed a sum of Rs.80,81,130/­

as payment of equitable revised rates for the work done

by him beyond the stipulated period of time.

     104. With regard to this claim is concerned, the

plaintiff has pleaded and lead evidence stating that the

period of performance of the contract was prolonged

beyond the stipulated date of completion of 26/3/1995,

due to several defaults and breach of contract committed

by the defendants. Due to the defaults committed by the
                          100
                          CT 1390_Com.O.S.24­2019_Judgment .doc


defendants he was forced to execute the work in the

prolonged   period   beyond    the   stipulated    period    of

completion facing the burnt of all round increase in the

market price during that period. There was no justice in

insisting him to do the work at tender rates, since the

delay in completing the work was not at all attributable

to him, he is entitle for payment of equitable revised rates

for the work done beyond the stipulated period taking

into consideration of the changed market conditions and

circumstances under which the work was executed. He

has requested the defendants to pay the equitable revised

rates for the quantity of work executed beyond the

stipulated period of completion of 26/3/1995, but the

defendant has kept silent and not made payment at

equitable revised rates for the work done by him beyond

the stipulated period of contract. On this claim, plaintiff

has sought for a sum of Rs.28,15,725/­ and interest of

Rs.52,65,405/­ from 29/6/2001 upto 2/2/2017, totally

amounting to Rs.80,81,130/­.
                            101
                            CT 1390_Com.O.S.24­2019_Judgment .doc


       105. On this alleged claim of the plaintiff, the

defendants have pleaded and lead evidence stating that

the alleged payment of equitable revised rates for the

work done beyond the stipulated period of contract does

not fall under the schedule of contract form. The plaintiff

by making false allegations has claimed huge amount

from them according to his whims and fancies and the

claim of the plaintiff is hypothetical and illogical.

       106. With regard to this claim of plaintiff seeking

payment of equitable revised rates for the work done

beyond the stipulated period of contract, plaintiff has

mainly relied on Ex.P.12 & P.13 statements prepared by

him showing the details of quantities of the work

executed beyond he contract period along with claimed

rates, amounts and also deduction of the amount paid to

him.

       107. However, a perusal of the evidence on record

discloses that except disclosing Ex.P.12 & P.13, the self

interested statements prepared by the plaintiff, he has
                            102
                           CT 1390_Com.O.S.24­2019_Judgment .doc


not made any attempt to prove the contents of the

statements.    Mere production of Ex.P.12 & P.13 self

interested statements prepared by the plaintiff is not

helpful for him with regard to the alleged claim.

     108. In the present case in hand, the plaintiff has

failed to prove that the period of completion of work was

prolonged beyond the stipulated date of contract due to

several   defaults   and   breaches     committed      by    the

defendants. On the other hand, a perusal of the evidence

on record discloses that admittedly it is the plaintiff who

has failed to reach the stipulated work progress in terms

of the contract and inspite of issuance of number of

notices by the defendants, the plaintiff has failed to make

up the shortfall of the work.           Further, there was

inordinate delay on the part of the plaintiff in completing

the construction work, which resulted in rescission of

Ex.P.1 contract by the defendants. Further, a perusal of

the Ex.P.1(a) schedule of contract form discloses that

there is no provision for payment of equitable revised
                          103
                          CT 1390_Com.O.S.24­2019_Judgment .doc


rates for the work done beyond the stipulated period of

contract as claimed by the plaintiff particularly when the

plaintiff has failed to prove that the period of performance

of the contract was prolonged beyond the stipulated date

of completion due to defaults and breach of contract

committed by the defendants.       Since the plaintiff has

failed to prove that the period of performance was

prolonged beyond the stipulated date of completion due

to defaults and breach of contract committed by the

defendants, plaintiff is not entitle for any payment for

equitable revised rates for the work done beyond the

stipulated period of contract. With these observations, I

answer issue No.6 in the negative.

     109. ISSUE No.7 : With regard to issue No.7

pertaining to claim No.4 of the plaintiff is concerned, the

plaintiff has sought for a sum of Rs.84,43,827/­ as

reimbursement of expenses for longer stay at the work

site for the purpose of executing the work. With regard to

this claim is concerned, the plaintiff has pleaded and lead
                           104
                           CT 1390_Com.O.S.24­2019_Judgment .doc


evidence stating that as a result of defaults and breach of

contract committed by the defendants, the execution of

the work prolonged beyond the stipulated date of

completion due to which he was made to incur extra

expenses and additional monthly overhead charges. He

had taken 10% of the cost of work at quoted rates vis­a­

vis stipulated period of contract as the cost of over head

charges to meet the overhead both at head office and site

office, which included payment towards managerial

consultancy,   legal   advise,   Engineering,     Supervision,

Account stores and traveling overhead charges are fixed

in each and every month and will not increase or

decrease in proportion to quantum of work executed in

each month.    The establishment engaged on the works

cannot be retrenched or reduced till the completion of the

work.    Hence the expenses on monthly overhead

continued from the date of contract period dated

26/3/1993 till the cancellation of the contract on

12/6/2001.     On this claim, plaintiff has sought for a
                           105
                           CT 1390_Com.O.S.24­2019_Judgment .doc


reimbursement of Rs.29,42,100/­ along with interest of

Rs.55,01,727/­, totally amounting to Rs.84,43,827/­ as

reimbursement      expenses     from      29/6/2001        upto

2/2/2017 for longer stay at the work site for the purpose

of executing the work.

     110. With regard to this claim is concerned, the

defendants have pleaded and lead evidence stating that

there is no base for the plaintiff to claim a sum of

Rs.84,43,827/­ as reimbursement expenses for the

longer stay at the work site for the purpose of executing

the work.   The plaintiff on assumptions has calculated

the amount.     Since the plaintiff has not reached the

monthly tender work, which prescribed under the

agreement, the plaintiff is not entitle for the said claim.

     111. With regard to the above claim No.4 pertaining

to reimbursement of monthly over head charges for

longer stay at the work site for the purpose of executing

the work beyond the contract period, plaintiff has mainly

relied on Ex.P.15 certificate issued by a Chartered
                           106
                           CT 1390_Com.O.S.24­2019_Judgment .doc


Accountant certifying that as per their knowledge and

information, plaintiff had incurred the expenditures

stated in the said certificate pertaining to expenditure on

over heads for executing the work of construction of First

Grade     College,   Shidlaghatta,    Kolar     District    vide

Agreement No.16/92­93 dated 26/3/1993.

      112. A perusal of the evidence on record discloses

that except producing Ex.P.15 certificate in evidence,

plaintiff has not examined the author of the said

certificate to prove the contents of the said certificate. In

the absence of examination of the author of Ex.P.15

certificate and in the absence of proving the contents of

Ex.P.15 certificate mere production of the said certificate

is not helpful for the plaintiff to claim reimbursement of

monthly over head charges in the rate stated in Ex.P.15

certificate.

      113. A perusal of the evidence on record discloses

that the plaintiff has failed to prove that the construction

work prolonged beyond the stipulated date of completion
                             107
                             CT 1390_Com.O.S.24­2019_Judgment .doc


due to defaults and breach committed by the defendants.

The alleged breach of contract and the alleged defaults

committed by the defendants resulting into delay in

performance of the contract work is base for the plaintiff

to make this claim. In the absence of proving the alleged

defaults and breach of the contract by the defendants

resulting into longer stay of the plaintiff at work site,

plaintiff is not entitle for this claim.

     114. With regard to issue No.7 is concerned, the

learned counsel for the plaintiff has relied on a decision

reported    between     Government         of   Karnataka     V/s

Sudhakar Reddy reported in ILR 1992 Karnataka 3276,

wherein, with regard to the tender agreement it was held

that whatever be the quantity of work that remains over,

the Contractor should have been in readiness to complete

the work and for that purpose he should keep his entire

establishment and machinery idle for the entire period. In

that view of the matter, it cannot be said that overhead
                            108
                            CT 1390_Com.O.S.24­2019_Judgment .doc


charges should have been calculated only on the quantity

of work that remains over beyond the period in question.

     115. I have perused the ratio of the above cited

decision.   Unlike cited decision, in the present case in

hand the plaintiff has failed to prove that the defendants

have ordered for stoppage of the construction work. On

the other hand, due to the inability of the plaintiff -

Contractor to reach the stipulated work progress the

contract was rescinded by the defendants.            Hence the

question of defendants paying overhead charges with

respect to the balance of the construction work will not

arise. Hence the ratio of the above mentioned decision is

not helpful for the plaintiff.

     116. Plaintiff's counsel has relied on another

decision between Mcdermott International Inc. V/s burn

standard co. Ltd. & others reported in 2006(2) Arb.Lr 498

(SC), wherein the Apex Court of the Land has held that in

case of challenge of the arbitration award, the scope of

intervention    of   the   court    is   envisaged      in    few
                            109
                            CT 1390_Com.O.S.24­2019_Judgment .doc


circumstances only like in case of fraud or bias by

arbitrators, violation of natural justice­ where arbitrator

has gone contrary to or beyond expressed law of contract

or granted relief in matter not in dispute would come

within purview of Section 34. When Arbitrator quantified

claim by taking recourse to Emden formula which is

widely accepted one. Arbitrator cannot be committed an

error warranting interference by court.

     117. I have perused the ratio         of the above cited

decision. Since the plaintiff has failed to prove that the

recession of the contract by the defendants is illegal, the

question of defendants paying any compensation to the

plaintiff towards reimbursement of expenses for longer

stay at work site will not arise. Hence, even the ratio of

this decision is also not helpful for the plaintiff.

     118. Plaintiff's counsel has also relied on another

decision   reported   between    M/s. National         Highways

Authority of India Vs. M/s. Tantia­TBL (JV) rendered in

OMP 482 of 2009 dated 16/2/2012, wherein the Hon'ble
                          110
                          CT 1390_Com.O.S.24­2019_Judgment .doc


High Court of Delhi has upheld the finding of the arbitral

tribunal that when the contractor issued early warning

notices to the National Highways Authority of India

seeking extension of time and when National Highways

Authority of India had notified with compensation event,

the contractor has not committed breach of contract.

The Delhi High Court has also upheld the finding of the

Tribunal that when the construction work undertaken by

the contractor prolonged because of indecisiveness on the

part of the NHAI it had resulted in loss and damage to

the contractor.

     119. I have perused the ratio of the above cited

decision.   Unlike cited decision, in the present case in

hand the plaintiff has failed to prove that the contract

work was prolonged because of        indecisiveness on the

part of the defendants. On the other hand, the contract

was rescinded due to inordinate delay on the part of the

plaintiff to complete the construction work. Hence, the
                           111
                           CT 1390_Com.O.S.24­2019_Judgment .doc


ratio of the above cited decision is also not helpful for the

plaintiff.

      120. The learned counsel for the plaintiff has relied

on another decision between M/s. National Highways

Authority of India V/s. M/s. Elsamex­TWS­SNC­JV

rendered in OMP 789 of 2012, wherein, the Hon'ble High

Court of Delhi has rejected the petition filed by the

National Highways Authority of India challenging the

award passed by the Arbitral Tribunal by awarding

compensation to the Contractor on the breach of the

contract.

      121. I have perused the ratio of the above cited

decision.    Unlike cited decision in the present case in

hand, the plaintiff has failed to prove that the delay in

execution of the work was not due to the reasons

attributable to him. On the other hand, the contract was

rescinded by the defendants for failure on the part of the

plaintiff to complete the construction work in terms of the
                              112
                             CT 1390_Com.O.S.24­2019_Judgment .doc


contract.   Hence, the ratio of this decision is also not

helpful for the plaintiff.

     122. The plaintiff's counsel has relied on another

decision reported between U.P.State Electricity Board

V/s. Om Metals and Minerals (Pvt) Ltd, reported in

Arbitration Law Reporter 1994(2), wherein Allahabad

High Court has upheld the finding of the arbitral

Tribunal granting compensation to the contractor where

delay of construction work was resulted due to obstacle

created by the U.P.State Electricity Board in providing

suitable site.

     123. I have perused the ratio of the above cited

decision.   Unlike cited decision in the present case in

hand, the plaintiff has failed to prove that due to

obstacles created by the defendants, he could not able to

complete the construction work within stipulated period

of time.    Hence, the ratio of this decision is also not

helpful for the plaintiff.
                            113
                            CT 1390_Com.O.S.24­2019_Judgment .doc


      124. The learned counsel for the plaintiff has also

relied on another decision reported between Government

of Karnataka    V/s. K. Sudhakar Reddy reported in ILR

1992 Karnataka 3276, wherein, while interpreting the

clause of tender agreement it was held that over head

charges not confined only to balance of quantity of work,

entire establishment and machinery kept idle by the

plaintiff.

      125. I have perused the ratio of the above cited

decision. However, unlike cited decision in the present

case the plaintiff has failed to prove that due to defaults

on the part of the defendants to perform their part of the

contract, he has failed to complete the construction work

within stipulated period of time. Hence the question of

payment of over head charges by the defendants to the

plaintiff will not arise. Hence the ratio of this decision is

also not helpful for the plaintiff.

      126. The learned counsel for the plaintiff in his

arguments has also relied on a decision reported between
                            114
                            CT 1390_Com.O.S.24­2019_Judgment .doc


Rail India Technical and Economic Services Limited, New

Delhi V/s. Ravi Constructions, Bangalore and another

reported in 2001 (Suppl) Arb. LR 436 Karnataka (DB),

wherein, the Division Bench of Hon'ble High Court of

Karnataka has held that parties are bound to strictly

abide by the appointment procedure pertaining to the

Arbitral Tribunal.

     127. I have perused the ratio of the above

mentioned decision.     The ratio of the above mentioned

decision is not helpful for the plaintiff.

     128. By perusing the materials produced on record,

I hold that the plaintiff has failed to prove that the

defendants are liable to pay him a sum of Rs.84,43,827/­

towards reimbursement of expenses for longer stay at the

work site for the purpose of executing the work. With

these observations, I answer issue No.7 in the negative.

     129. ISSUE No.8 : The defendants in the written

statement have taken a defence that the court fee paid by

the plaintiff is insufficient.   However, a perusal of the
                          115
                          CT 1390_Com.O.S.24­2019_Judgment .doc


evidence on record discloses that the defendants have not

lead any specific evidence to prove that the plaintiff has

not properly valued the suit for the purpose of payment

of court fee and court fee paid by him is insufficient. On

the other hand, a perusal of the materials on record

discloses that on the suit claim of Rs.2,08,09,018/­, the

plaintiff has paid proper court fee of Rs.3,11,170/­ as per

clause 79 and schedule (1) Article (1) of the Karnataka

Court Fees & Suits Valuation Act, 1958. By considering

the materials produced on record, I hold that defendants

have failed to prove that the suit of the plaintiff is not

properly valued for the purpose of payment of court fees.

With these observations, I answer issue No.8 in the

negative.

     130. ISSUE No.9 : The defendants in the written

statement have taken another legal defence that the suit

of the plaintiff is barred by limitation.        However, a

perusal of the pleadings and evidence of the defendants

discloses that they have not lead any specific evidence to
                           116
                           CT 1390_Com.O.S.24­2019_Judgment .doc


prove that the suit of the plaintiff is barred by limitation.

Further no arguments were addressed on the aspect of

limitation by the counsel for defendants. In the absence

of specific pleadings and evidence to prove that the suit

of the plaintiff is barred by limitation, a stray sentence in

the written statement of the defendants is not sufficient

to come to the conclusion that the suit of the plaintiff is

barred by limitation.   By perusing the materials placed

on record, I hold that the defendants have failed to prove

that suit of the plaintiff is barred by limitation.        With

these observation, I answer issue No.9 in the negative.

     131. ISSUE No.10 : Since plaintiff has failed to

prove that the defendants have failed to perform their

part of the contractual obligations of contract dated

26/3/1993 entered between him and the defendants as

the reasons for non completion of the contract work

within the stipulated period of time and also failed to

prove that rescission of the contract dated 26/3/1993

made by the defendants on 12/6/2001 is illegal and
                           117
                           CT 1390_Com.O.S.24­2019_Judgment .doc


wrongful, plaintiff is not entitle for the suit claims sought

for. With these observations, I answer issue No.10 in the

negative.


     132. ISSUE No.11 : In the present suit, plaintiff has

sought for future interest @ 18% per annum.                 The

learned counsel for the plaintiff on the aspect of payment

of future interest has relied on number of decisions in his

written arguments.       However, since the plaintiff has

failed to prove that he is entitle for suit claims sought for,

the question for awarding future interest on the suit

claims sought for by the plaintiff do not arise. Hence, I

answer issue No.11 in the negative.


     133. ISSUE No.12 : In view of my findings on issues

No.1 to 11 and the reasons assigned thereon, I proceed

to pass the following:

                      ORDER

Suit of the plaintiff is dismissed. Parties are directed to bear their costs. 118

CT 1390_Com.O.S.24­2019_Judgment .doc Draw decree accordingly.

[Dictated to the Judgment Writer; transcript thereof corrected, initialed and then pronounced by me, in the Open Court on this the 25th day of October 2019] [S.A.Hidayathulla Shariff] LXXXIII Additional City Civil Judge.

BENGALURU.

1. List of witnesses examined on behalf of the Plaintiff/s:

       PW.1       Sri. M. Keshava Raju
2.     List of witnesses examined           on   behalf    of   the
       Defendant/s:

DW.1 : Sri. H.P.Ajith (discarded) DW 2 : Manjunatha L.N

3. List of documents marked on behalf of the Plaintiff/s:

     Ex.P 1        Agreement.
                   .




     Ex.P.1(a)     Schedule of contract form.
     Ex.P 2        Schedule B - 33 sheets.
     Ex.P 3        Note
     Ex.P 4        Note of schedule A.
     Ex.P.5        Correspondence - 52 sheets.
     Ex.P.6        C.C of Civil Appeal No.1587/2004.

     Ex.P.7        Notice U/S.8 of CPC.

Ex.P.8 to 10 Postal receipts.

Ex.P.11 Statement of idle charges 119 CT 1390_Com.O.S.24­2019_Judgment .doc Ex.P.12 Statement of quantization executed beyond contract.

Ex.P.13 Rate Analysis.

Ex.P.14 to Copy of Ex.P.13, two certificates and 18 two letters of defendants.

4. List of the documents marked for the defendant/s:

Ex.D.1 Letter of correspondence by the defendant for taking measurement. .
Ex.D.2 Postal Acknowledgement Ex.D.3 Mahazar dt. 11/9/1998 Ex.D.4 Contract certificate dt. 25/6/2003.
Ex.D.5 Rescind Order dt. 12/6/2001.
Ex.D.6 Letter addressed to S.E. Bangalore Circle.
Ex.D.7 Letter dt. 28/6/1993 addressed to the plaintiff by the EE,Kolar Division.
Ex.D.8 Letter dt. 3/8/1993 addressed by the EE to the plaintiff.
Ex.D.9 Letter dt. 2/6/1999 addressed by the AEE to the plaintiff.
Ex.D.10 Notice dt. 7/6/1994 addressed to the plaintiff.
Ex.D.11 RPAD Acknowledgement.
120
CT 1390_Com.O.S.24­2019_Judgment .doc Ex.D.12 Notice dt. 30/8/194 addressed to the plaintiff.
Ex.D.13 RPAD Acknowledgement.
Ex.D.14 Notice dt. 30/9/1994 addressed to the plaintiff.
Ex.D.15 Notice dt. 2/2/1995 addressed to the plaintiff.
Ex.D.16 RPAD acknowledgement.
Ex.D.17 Notice dt. 5/7/1995 addressed to the plaintiff.
[S.A.Hidayathulla Shariff] LXXXIII Additional City Civil Judge.
BENGALURU.
1 CT 1390_Com.O.S.24­2019_Judgment .doc 2 .
1 CT 1390_Com.O.S.24­2019_Judgment .doc 2 .