Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 1, Cited by 0]

Gujarat High Court

Shree Sipral Construction Corporation vs State Of Gujarat & 2 on 6 May, 2014

Author: Ks Jhaveri

Bench: Ks Jhaveri, A.G.Uraizee

          C/SCA/6794/2014                                   JUDGMENT




            IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

               SPECIAL CIVIL APPLICATION NO. 6794 of 2014



FOR APPROVAL AND SIGNATURE:



HONOURABLE MR.JUSTICE KS JHAVERI
and
HONOURABLE MR.JUSTICE A.G.URAIZEE
===========================================================

1     Whether Reporters of Local Papers may be allowed to see
      the judgment ?

2     To be referred to the Reporter or not ?

3     Whether their Lordships wish to see the fair copy of the
      judgment ?

4     Whether this case involves a substantial question of law as
      to the interpretation of the Constitution of India, 1950 or any
      order made thereunder ?

5     Whether it is to be circulated to the civil judge ?

================================================================
       SHREE SIPRAL CONSTRUCTION CORPORATION....Petitioner(s)
                             Versus
               STATE OF GUJARAT & 2....Respondent(s)
================================================================
Appearance:
MR HK PARMAR, ADVOCATE for the Petitioner(s) No. 1
MR. ALPESH H PARMAR, ADVOCATE for the Petitioner(s) No. 1
GOVERNMENT PLEADER for the Respondent(s) No. 1
================================================================

          CORAM: HONOURABLE MR.JUSTICE KS JHAVERI
                 and
                 HONOURABLE MR.JUSTICE A.G.URAIZEE




                                  Page 1 of 8
     C/SCA/6794/2014                            JUDGMENT



                      Date : 06/05/2014


                      ORAL JUDGMENT

(PER : HONOURABLE MR.JUSTICE KS JHAVERI)

1. By   way   of   this   petition,   the   petitioner   has  challenged   the   order   passed   by   the   Executive  Engineer,   Road   and   Building   Department,   Nirman  Bhavan,   Sardarbag,   Junagadh   dated   2/4/2014  whereby   order   of   recovery   of   Rs.   43,98,631.84/­  was made and the same was directed to be paid by  the petitioner within ten days.

2. Brief facts of the present petition are that  on  22/10/2010,   the   respondent   authorities   issued  public invitation inviting contractors to bid for  carrying   out   the   work   of   widening   and  strengthening   of   Visdavadar­Dhari   Road   S.H.96  between   Km.   42/00   to   63/4   (Standard   Two   Lane).  The   Respondent   authority   accepted   the   offer   of  the   petitioner   for   various   amounts   subject   to  certain   conditions   so   as   to   deposit   various  amount   within   ten   days.     On   26/10/2010,   upon  fulfilling the conditions of deposit as required  by   the   respondents,   they   issued   work   order   in  favour of the petitioner.   Thereafter, the work  was carried out by the petitioner in the presence  and   under   the   supervision   of   Executive   Engineer  i.e.  the Respondent no. 3 or his sub­ordinates.  The   Deputy   Executive   Engineer,   R&B   has   prepared  Final   bill   and   has   issued   a   Completion  Page 2 of 8 C/SCA/6794/2014 JUDGMENT Certificate in final bill which was checked and  approved by the Executive Engineer.  In spite of  that,   the   respondent   has   issued   letter   of  recovery   of   Rs.   43,98,631.84     alongwith   penal  interest.

3. Learned Counsel Mr. H.K.Parmar appearing for the  petitioner   has   placed   reliance   on   the   order  passed   by   the   Division   Bench   of   this   Court   on  5/2/2014,   whereby   the   Division   Bench   of   this  Court has not entertained the writ petition as an  alternative remedy is available to the petitioner  but  the   stay  has   been  granted  in  favour  of  the  petitioner.

4. He has relied upon the decision of the Apex Court  in case of J.G.Engineers Private Ltd Vs. Union of  India and Anr reported in (2011) 5 SCC 758 more  particularly   para   nos.   10,   17   &   18,   which   are  reproduced as under:

"10.A civil court examining the validity of  an   arbitral   award   under   Section   34   of   the  Act exercises supervisory and not appellate  jurisdiction over the awards of an Arbitral  Tribunal.  A court can set aside an arbitral  award, only if any of the grounds mentioned  in Sections 34(2)(b)(i) and (ii), or Section  28(1)(a) or 28(3) read with Section 34(2)(b)
(ii)   of   the   Act,   are   made   out.     An   award  adjudicating   claims   which   are   "expected  matters"   excluded   from   the   scope   of  arbitration, would violate Sections 34(2)(a)
(vi)   and   34(2)(b)   of   the   Act.     Making   an  award allowing or granting a claim, contrary  to   any   provision   of   the   contract,   would  Page 3 of 8 C/SCA/6794/2014 JUDGMENT violate   Section   34(2)(b)(ii)   read   with  Section 28(3) of the Act.

17.  Clauses   (2)   and   (3)   of   the   contract  relied   upon   by   the   respondents,   no   doubt  make certain decisions by the Superintending  Engineer   and   Engineer­in­Charge   final/final  and binding/final and conclusive, in regard  to   certain   matters.   But   the   question   is  whether clauses (2) and (3) of the agreement  stipulate that the decision of any authority  is final in regard to the responsibility for  the   delay   in   execution   and   consequential  breach   and   therefore   exclude   those   issues  from   being   the   subject   matter   of  arbitration.   We   will   refer   to   and   analyse  each   of   the   'excepted   matters'   in   clauses  (2) and (3) of the agreement to find their  true scope and ambit : 

(i) Clause   (2)   provides   that   if   the   work  remains   uncommenced   or   unfinished   after  proper   dates,   the   contractor   shall   pay   as  compensation for everyday's delay an amount  equal   to   1%   or   such   small   amount   as   the  Superintending   Engineer   (whose   decision   in  writing   shall   be   final)   may   decide   on   the  estimated cost of the whole work as shown in  the tender. What is made final is only the  decision   of   the   Superintending   Engineer   in  regard   to   the   percentage   of   compensation  payable   by   the   contractor   for   everyday's  delay   that   is   whether   it   should   be   1%   or  lesser.  His   decision   is   not   made   final   in  regard   to   the   question   as   to   why   the   work  was   not   commenced   on   the   due   date   or  remained   unfinished   by   the   due   date   of  completion and who was responsible for such  delay.
(ii)   Clause   (2)   also   provides   that   if   the  contractor   fails   to   ensure   progress   as   per  the   time   schedule   submitted   by   the  contractor,   he   shall   be   liable   to   pay   as  compensation   an   amount   equal   to   1%  or   such  Page 4 of 8 C/SCA/6794/2014 JUDGMENT smaller   amount   as   the   Superintending  Engineer (whose decision in writing shall be  final)   may   decide   on   the   estimated   cost   of  the whole work for everyday the due quantity  of the work remains incomplete, subject to a  ceiling of ten percent. This provision makes  the decision of the Superintending Engineer  final   only   in   regard   to   the   percentage   of  compensation   (that   is,   the   quantum)   to   be  levied and not on the question as to whether  the   contractor   had   failed   to   complete   the  work or the portion of the work within the  agreed time schedule, whether the contractor  was   prevented   by   any   reasons   beyond   its  control or by the acts or omissions of the  respondents, and who is responsible for the  delay. 
(iii) The   first   part   of   clause   (3)  provides   that   if   the   contractor   delays   or  suspends   the   execution   of  the   work   so   that  either   in   the   judgment   of   the   Engineer­in­ Charge   (which   shall   be   final   and   binding),  he   will   be   unable   to   secure   the   completion  of the work by the date of completion or he  has   already   failed   to   complete   the   work   by  that   date,   certain   consequences   as   stated  therein, will follow. What is made final by  this   provision   is   the   decision   of   the  Engineer­in­Charge   as   to   whether   the  contractor   will   be   able   to   secure   the  completion   of   the   work   by   the   due   date   of  completion,  which   could   lead   to   the  termination   of   the   contract   or   other  consequences.  The   question   whether   such  failure   to   complete   the   work   was   due   to  reasons   for   which   the   contractor   was  responsible   or   the   department   was  responsible,   or   the   question   whether   the  contractor   was   justified   in   suspending   the  execution   of   the   work,   are   not   matters   in  regard to which the decision of Engineer­in­ Charge is made final. 
(iv) The   second   part   of   clause   (3)   of   the  agreement provides that where the contractor  Page 5 of 8 C/SCA/6794/2014 JUDGMENT had made himself liable for action as stated  in   the   first   part   of   that   clause,   the  Engineer­in­Charge   shall     have   powers   to  determine   or   rescind   the   contract   and   the  notice   in   writing   to   the   contractor   under  the hand of the Engineer­in­Charge shall be  conclusive   evidence   of   such   termination   or  rescission.  This does not make the decision  of   the   Engineer­in­   Charge   as   to   the  validity   of   determination   or   rescission,  valid or final. In fact it does not make any  decision of Engineer­in­Charge final at all. 

It   only   provides   that   if   a   notice   of  termination   or   rescission   is   issued   by   the  Engineer­in­Charge   under   his   signature,   it  shall   be   conclusive   evidence   of   the   fact  that   the   contract   has   been   rescinded   or  determined.

(v)   After   determination   or   rescission   of  the   contract,   if   the   Engineer­in­   Charge  entrusts the unexecuted part of the work to  another contractor, for completion, and any  expense   is   incurred   in   excess   of   the   sum  which   would   have   been   paid   to   the   original  contractor   if   the   whole   work   had   been  executed by him, the decision in writing of  the   Engineer­in­Charge   in   regard   to   such  excess shall be final and conclusive, shall  be   borne   and   paid   by   the   original  contractor. What is made final is the actual  calculation of the difference or the excess,  that is if the value of the unexecuted work  as   per   the   contract   with   the   original  contractor   was   Rs.1   lakh   and   the   cost   of  getting   it   executed   by   an   alternative  contractor   was   Rs.1,50,000/­   what   is   made  final   is   the   certificate   in   writing   issued  by the Engineer­in­Charge that Rs.50,000 is  the   excess   cost.   The   question   whether   the  determination   or   rescission   of   the  contractor   by   the   Engineer­in­Charge   is  valid   and   legal   and   whether   it   was   due   to  any breach on the part of the contractor, or  whether the contractor could be made liable  to pay such excess, are not issues on which  Page 6 of 8 C/SCA/6794/2014 JUDGMENT the   decision   of   Engineer­in­Charge   is   made  final.

18.Thus what is made final and conclusive by  Clauses (2) and (3) of the agreement, is not  the   decision   of   any   authority  on  the   issue  whether   the   contractor   was   responsible   for  the delay or the Department was responsible  for   the   delay   or   on   the   question   whether  termination/rescission   is   valid   or   illegal.  What   is   made   final,   is   the   decisions   on  consequential   issues   relating   to  quantification, if there is no dispute as to  who   committed   breach.     That   is,   if   the  contractor   admits  that   he   is   in   breach,   or  if the arbitrator finds that the contractor  is   in   breach   by   being   responsible   for   the  delay,   the   decision   of   the   Superintending  Engineer   will   be   final   in   regard   to   two  issues.     The   first   is   the   percentage  (whether   it   should   be   1%   or   less)   of   the  value   of   the   work   that   is   to   be   levied   as  liquidated   damages   as   per   day.     The  second  is   the   determination   of   the   actual   excess  cost   in   getting   the   work   completed   through  an  alternative  agency.    The   decision   as   to  who   is   responsible   for   the   delay   in  execution   and   who   committed   breach   is   not  made   subject   to   any   decision   of   the  respondents   or   its   officers,   nor   excepted  from arbitration under any provision of the  contract."

5. We have heard learned counsel  appearing for the  petitioner   at   length   and   in   great   detail.     We  have also perused the documents on record. 

6. Considering the facts of this case and the fact  that   an   alternative   remedy   is   available   to   the  petitioner, it will not be appropriate for us to  entertain this writ petition or grant any stay. 

Page 7 of 8

C/SCA/6794/2014 JUDGMENT However,   it   will   be   open   for   the   petitioner   to  revive the same in case if the Tribunal refuse to  grant any stay against the order of recovery.  

7. Hence,   there   is   no   substance   in   the   present  petition.  The same is dismissed accordingly.

(K.S.JHAVERI, J.) (A.G.URAIZEE,J) *asma Page 8 of 8