Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 17, Cited by 0]

Orissa High Court

Sudarsan Sahani vs State Of Odisha (Vig.) on 18 April, 2022

Author: S.K. Sahoo

Bench: S.K. Sahoo

             IN THE HIGH COURT OF ODISHA, CUTTACK

                       CRLA No. 695 of 2016

An appeal under section 374(2) of the Code of Criminal Procedure
from the judgment and order dated 13.12.2016 passed by the
Special Judge (Vigilance), Phulbani, Kandhamal in G.R. Case
No.08 of 2013(v) (T.R. No. 08 of 2013)/G.R. Case No.30 of
2005(v) BAM (T.R. No. 39 of 2009).
                      ---------------------

    Sudarsan Sahani           .......                   Appellant

                             -Versus-

    State of Odisha (Vig.)     .......                   Respondent


          For Appellant:         -       Mr. Asok Mohanty
                                         Senior Advocate

          For Respondent:        -       Mr. Srimanta Das
                                         Senior Standing Counsel (Vig.)

                       CRLA No. 687 of 2016

    Prasanta Kumar Patra      .......                   Appellant

                             -Versus-

    State of Odisha (Vig.)    .......                    Respondent


          For Appellant :        -       Mr. Pradipta Kumar Mohanty
                                         Senior Advocate

          For Respondent:        -       Mr. Srimanta Das
                                         Senior Standing Counsel (Vig.)
                              // 2 //




                        CRLA No. 694 of 2016

    Saroj Kumar Misra           .......                    Appellant

                              -Versus-

    State of Odisha (Vig.)      .......                    Respondent


          For Appellant :              -   Mr. Asok Mohanty
                                           Senior Advocate

          For Respondent:              -   Mr. Srimanta Das
                                           Senior Standing Counsel (Vig.)

                  GCRLA No. 25 of 2019

An appeal under section 378 of the Code of Criminal Procedure
from the judgment and order dated 13.12.2016 passed by the
Special Judge (Vigilance), Phulbani, Kandhamal in G.R. Case
No.08 of 2013(v) (T.R. No. 08 of 2013)/G.R. Case No.30 of
2005(v) BAM (T.R. No. 39 of 2009).

    State of Odisha (Vig.)       .......                   Appellant

                              -Versus-

    1. Saroj Kumar Mishra
    2. Sudarsan Sahani
    3. Prasanta Ku. Patra
    4. Abakash Padhy             .......                   Respondents


          For Appellant :              -   Mr. P.K. Pani
                                           Standing Counsel (Vig.)

          For Respondents:             -   Mr.Pradipta Kumar Mohanty
                                           Senior Advocate

                      ---------------------




                                                              Page 2 of 60
                                     // 3 //




                                   CORAM:
              THE HONOURABLE MR. JUSTICE S.K. SAHOO
        .....................................................................................................
        Date of Hearing: 25.03.2022           Date of Judgment: 18.04.2022
        .....................................................................................................

S.K. SAHOO, J.      Since all the appeals arise out of one case, with the

        consent of the learned counsel for the parties, those were heard

        analogously and disposed of by this common judgment.


                    The appellant Sudarsan Sahani in CRLA No. 695 of

        2016, appellant Prasanta Kumar Patra in CRLA No. 687 of 2016,

        appellant Saroj Kumar Misra in CRLA No. 694 of 2016 and

        respondent no.4 Abakash Padhy in GCRLA No. 25 of 2019 faced

        trial in the Court of learned Special Judge (Vigilance), Phulbani in

        G.R. Case No.08 of 2013(v) (T.R. No. 08 of 2013)/G.R. Case

        No.30 of 2005(v) BAM (T.R. No. 39 of 2009) for the offences

        punishable under section 13(2) read with section 13(1)(d) of the

        Prevention of Corruption Act, 1988 (hereafter '1988 Act') along

        with offences punishable under sections 420, 468, 201 and

        section 120-B of the Indian Penal Code on the accusation of

        misappropriating government money to the tune of Rs.1,50,000/-

        (rupees one lakh fifty thousand) in connivance with each other by

        corrupt or illegal means or by otherwise abusing their position

        showing false execution of pothole repair work, committing

        forgery of certain documents/records such as, pothole repair



                                                                 Page 3 of 60
                            // 4 //




estimate and causing disappearance of evidence, such as MB

No.1311 to screen themselves from legal punishment.


           The learned trial Court vide impugned judgment and

order dated 13.12.2016 though acquitted the respondent no.4

Abakash Padhy of GCRLA No. 25 of 2019 of all the charges so also

the appellants Sudarsan Sahani, Prasanta Kumar Patra and Saroj

Kumar Misra in the three criminal appeals of the charges under

sections 420, 468, 201 and section 120-B of the Indian Penal

Code, but found the appellants guilty of the offence under section

13(2) read with section 13(1)(d) of 1988 Act and sentenced each

of the appellants to undergo rigorous imprisonment for two years

each and to pay a fine of Rs.2,000/- (rupees two thousand) each,

in default, to undergo further R.I. for one month each.


             The   appellants    have   challenged   the   impugned

judgment and order dated 13.12.2016 passed by the learned trial

Court by filing the aforesaid three criminal appeals whereas the

State of Odisha has filed GCRLA No. 25 of 2019 challenging order

of acquittal of the appellants of the charges under sections 420,

468, 201 and 120-B of the Indian Penal Code so also of the

respondent no.4 Abakash Padhy of all the charges.

2.         The prosecution case, as per the First information

report (Ext.28) lodged by P.K. Dwivedy (P.W.12), Inspector of



                                                           Page 4 of 60
                              // 5 //




Police, Vigilance, Berhampur, in short, is that pursuant to receipt

of reliable information of misappropriation of government money

to the tune of Rs.1,50,000/- (rupees one lakh fifty thousand) by

showing false execution of pothole repair work in N.H. 217 from

147 K.M. to 171 K.M. in September 2004, an enquiry was taken

up, in course of which it was ascertained that during the period

from 2002 to 2004, the appellant Sudarsan Sahani was the S.D.O.

of N.H. Sub-division, Balliguda, appellant Saroj Kumar Misra was

the Executive Engineer, N.H. Division, Berhampur and appellant

Prasanta Kumar Patra was the Junior Engineer of N.H. Section,

Balliguda. During the said period, an estimate was made relating

to the periodical renewal of N.H. 217 and the same was

sanctioned and agreement was executed on 19.02.2004 with

contractor Sri Arun Kumar Choudhury relating to PR Coat of N.H.

217 from 148 K.M. to 154 K.M. for an amount of Rs.36,98,199/-

with the date of commencement and completion from 19.02.2004

to 18.06.2004 and further extension of time was given upto

30.01.2005. The enquiry further revealed that while the said

agreement was subsisting, another agreement was executed for

the same portion of work with co-accused Abakash Padhy

(respondent no.4 of GCRLA No. 25 of 2019) overlapping the

earlier agreement with an estimate of Rs.4,64,881/- with the date

of   commencement      and     completion   from   10.09.2004    to



                                                        Page 5 of 60
                              // 6 //




09.03.2005.   After   execution        of    agreement     with   co-accused

Abakash Padhy, the appellant Prasanta Kumar Patra made

necessary   entries   relating    to        pothole   repair   work   in   the

measurement book and an amount of Rs.1,50,000/- was paid to

co-accused Abakash Padhy on 14.10.2004. It further came to light

that pothole repair works from 147 K.M. to 171 K.M. was not

actually executed and false bills were prepared and payment of

Rs.1,50,000/- was shown. The Superintending Engineer, N.H.

Circle (South), Bhubaneswar conducted an inspection and came to

the conclusion that the agreement drawn by the Executive

Engineer, N.H. Division, Berhampur was unauthorized as PR

agreement over the same patch was already in force and it was

further found that inflated rates were given in the sanction and

estimate agreement with an intention to give undue financial

benefit to the agency executing pothole repair work and that the

measurement books were not produced before him for his scrutiny

and it was reported to be missing. Considering the inspection

report, the payment of Rs.1,50,000/- made to the contractor

Abakash Padhy was treated as unauthorized, unwanted and loss

to the Government.

            Consequent to the enquiry, P.W.12 P.K. Dwivedy,

Inspector of Police, Vigilance, Berhampur drew up the plain paper

F.I.R. against the three appellants so also respondent no.4



                                                                  Page 6 of 60
                            // 7 //




Abakash Padhy and     submitted the same to Superintendent of

Police, Vigilance, Berhampur Division, Berhampur for registration

of the case and accordingly, Berhampur Vigilance P.S. Case No.

30 dated 28.12.2005 was registered section 13(2) read with

section 13(1)(d) of 1988 Act along with offences punishable under

sections 420, 201 and section 120-B of the Indian Penal Code.

           During investigation, P.W.12 examined the witnesses,

seized relevant documents, obtained sanction for prosecution in

respect of the public servants and on completion of investigation,

since prima facie case was found against all the three appellants

and the respondent no. 4 of GCRLA, charge sheet was placed

under section 13(2) read with section 13(1)(d) of 1988 Act along

with offences punishable under sections 420, 468, 201 and

section 120-B of the Indian Penal Code.

3.         The defence plea of the appellants who are the public

servants is that the PR agreement with contractor Arun Kumar

Choudhury was a conditional one which was not completed till the

departure of Executive Engineer and the said contractor Arun

Kumar Choudhury had also not applied for extension of time for

which the 1st contract came into end on 31.08.2004 and was not

in force when the 2nd contract with the respondent Abakash Padhy

was executed. It is further pleaded by the appellants that the

Executive Engineer executed the 2nd agreement for repair of



                                                       Page 7 of 60
                             // 8 //




potholes from 148 K.M. to 171 K.M. which includes the work of 6

K.M. of the 1st agreement and that MB No.1311 was submitted by

the appellant Prasanta Kumar Patra relating to the work executed

by respondent Abakash Padhy and the same was submitted by

J.E. S. Acharya to the Divisional Office. The defence plea of

respondent Abakash Padhy is that he had rightly executed the

work as per agreement and has been falsely implicated. The

payment of running bill of Rs.1.50 lakh was made with bonafide

and final bill having not been paid, there was no loss to the

Government. The 1st contractor Arun Kumar Choudhury started

the work on the verbal instruction on the day of joining of P.W.9

without extension and it is only on 24.03.2005 that post-facto

extension was granted after the final bill was paid.

4.           In order to prove its case, the prosecution examined

twelve witnesses.

             P.W.1 Kamala Padhi and P.W.2 Jabaharlal Patra were

working as the Senior Clerk and Junior Clerk respectively attached

to the office of Executive Engineer, N.H. Division, Berhampur in

whose presence some documents were seized by the Vigilance

police on production by one Rama Chandra Sethi as per seizure

list vide Ext.1.

             P.W.3 Surya Narayan Padhy was working as Junior

Clerk in the office of Executive Engineer, N.H. Division, Berhampur



                                                        Page 8 of 60
                              // 9 //




in whose presence some documents were seized by the Vigilance

as per the seizure lists vide Exts. 2, 3 and 4.

            P.W.4 Rankanidhi Padhy was working as Junior Clerk

in the office of Executive Engineer, N.H. Division, Berhampur and

is a witness to the seizure as per the seizure list vide Ext. 3.

            P.W.5 Rama Chandra Sethy was working as an

Assistant Engineer in the office of Executive Engineer, N.H.

Division, Berhampur. He stated that on the direction of the

Executive Engineer, he produced certain documents before the

Investigating Officer which were seized as per the seizure lists

vide Ext. 1 and 2. He was declared hostile by the prosecution.

            P.W.6 Mahesh Ch. Panda was the Junior Clerk in the

office of the N.H. Division, Berhampur and he is a witness to the

seizure of documents as per seizure list vide Ext.2.

            P.W.7 Muralikrushna Pattnaik was the Junior Clerk in

the office of the N.H. Division, Berhampur and he is a witness to

the seizure of documents like MB movement register (Ext.5),

correspondence file (Ext.6) as per seizure list Ext.3. He also stated

about the seizure of MB issue register (Ext.7) as per seizure list

Ext.4.

            P.W.8 Sarada Prasad Das was the Asst. Engineer

attached to the Vigilance Directorate, Odisha, Cuttack, who was

directed by the Superintending Engineer, Vigilance Direcotrate to



                                                            Page 9 of 60
                              // 10 //




submit a report on scrutiny of certain records relating to the work

providing PR coat to N.H. 217 at 13 patches under N.H. Division,

Berhampur for the year 2003-04 and he submitted the report as

per Ext.8 which was forwarded to the I.O. of the case.

             P.W.9 Pradip Ku. Sutar was the Executive Engineer of

N.H. Division, Berhampur. He stated that though the agreement

in respect of the work in question was executed during the tenure

of his predecessor, but the work started after his joining. He

proved the tender documents and bills for the work of the two

contractors i.e., Arun Kumar Choudhury and respondent no.4

Abakash Padhi and also proved the measurement book in respect

of   the   work   executed   by   the   1st   contractor   Arun   Kumar

Choudhury. He further stated that M.B. No.1311 containing

measurement for the 1st running bill passed for respondent no.4

for Rs.1,50,000/- was not available in the office.

             P.W.10 Anil Kumar Choudhury executed the work in

question being the power of attorney holder of his brother Arun

Kumar Choudhury as the agreement for the work between the

Executive Engineer and his brother. He stated that after execution

of the agreement, the work was executed jointly by him and his

brother Arun Kumar Chaudhury and he was supervising the entire

work, which was for an estimated cost of Rs.36,98,199/-. He

further stated that though as per agreement, the date of



                                                            Page 10 of 60
                               // 11 //




commencement of the           work was 19.02.2004              and date    of

completion was 18.06.2004 but it was extended from time to time

and completed in January 2005. He proved the documents like

running bills, final bill and signatures of his brother Arun Kumar

Choudhury on the measurement books.

               P.W.11 Bharat Ch. Pradhan was in additional charge of

the Superintending Engineer, National Highway, Berhampur and

he   had   inspected    the   work       in   question   and   submitted   a

consolidated report as per Ext.27.

               P.W.12 Prasanta Kumar Dwivedy was the Inspector of

Police, Vigilance, Berhampur, who submitted the written report to

the Superintendent of Police, Vigilance, Berhampur, which was

treated as F.I.R. as per Ext.28. He is also the Investigating Officer

of the case.

               The prosecution exhibited thirty six documents. Exts.1

to 4 are the seizure lists, Ext.5 is the MB movement register,

Ext.6 is the correspondence file, Ext.7 is the MB issue register,

Ext.8 is the report of P.W.8, Ext.9 is the forwarding letter, Ext.10

is the F-2 agreement, Ext.11 is the 1st running bill, Ext.12 is the

relevant entry in MB 1427, Ext.13 is the 2nd running bill, Ext.14 is

the relevant page nos.1 to 9 of MB 1446, Ext.15 is the final bill,

Ext.16 is the relevant page nos. 5 to 11 of MB 1427, Ext.17 is the

Schedule of Quantities approved by Superintending Engineer, N.H.



                                                                Page 11 of 60
                             // 12 //




Circle   (South),   Bhubaneswar,       Ext.18   is    the   comparative

statement, Ext.19 is the tender schedule, Ext.20 is the estimate,

Ext.21 is the F-2 agreement, Ext.22 is the tender submitted by

respondent no.4 Abakash Padhy, Ext.23 is the tender submitted

by Debaraj Pradhan, Ext.24 is the 1st running bill, Ext.25 is the MB

Book No.1447, Ext.26 is the MB Book No.1346, Ext.27 is the

inspection note of the Superintending Engineer, Ext.28 is the

F.I.R., Ext.29 is letter no. 154, Ext.30 is the relevant entry

No.263, Ext.31 is the letter no. 279, Ext.32 is letter No.1474,

Exts.33, 34 and 35 are the sanction orders for prosecution of the

three appellants, Ext.36 is letter no. 2453 dated 05.08.2015 of the

Executive Engineer, N.H. Division, Berhampur.

            The defence has examined four witnesses in its

support.

            D.W.1 Sarat Chandra Rout was the Assistant Engineer,

N.H. Division office, Berhampur, who was also holding the

additional work of Public Information Officer of the concerned

office and while working as such, he had furnished some

documents/letters, which were marked as Exts.G, I, J, M and Q.

            D.W.2   Sanatan     Mohanty     was      working     as   Asst.

Engineer, Estimate, N.H. Office, Berhampur and he produced the

letters vide Ext.CC, Ext.T, Ext.U, Ext.V, Ext.W, Ext.H/1, Ext.X,

Ext.Y, Ext.Z, Ext.AA and Ext.BB.



                                                               Page 12 of 60
                                // 13 //




            D.W.3 Basudev Sasmal was working as Asst. Engineer,

R & B Division, Jeypore and he produced the documents vide

Ext.O & Ext.S.

            D.W.4 Saroj Kumar Misra is the appellant in CRLA

No.694 of 2016 and he produced certain documents which are

marked as Ext.K and Ext.L.

            The defence exhibited twenty nine documents. Ext.A is

letter no. 843 dated 16.02.2005, Ext.B is letter No. 37 dated

16.02.2005, Ext.C is letter No.711 dated 11.02.2005, Ext.D is

letter no. 581 dated 04.02.2005, Ext.E is letter no. 21 dated

31.01.2005, Ext.F is letter No. 246 dated 17.01.2005, Ext.F is

letter no. 246 dated 17.01.2005, Ext.G is letter no. 5277 dated

29.10.2004, Ext.H is letter no. 56 dated 24.04.2005, Ext.I is letter

No. 38(cib) WE dated 31.10.2004, Ext.J is letter No.11342 dated

19.02.2004, Ext.K is letter no. 2816 dated 17.08.2004, Ext.L is

letter   dated   22.05.2003,     Ext.M    is   memo   no.   2682   dated

29.05.2004, Ext.N is letter No.1165(WE) dated 24.03.2005, Ext.O

is payment details of 141F-2/03-04 of respondent no.4 Arun

Kumar Choudhury, Ext.P is the rain fall data obtained from BDO,

Daringbadi, Ext.Q is the letter no. 4775 dated 22.09.2004, Ext.R

is the charge papers showing details of inspection, Ext.S is memo

no. 2584-88 dated 20.04.2005, Ext.T is D.O. letter no. 16990

dated 23.12.2003, Ext.U is the inspection report of R.K. Rao



                                                             Page 13 of 60
                            // 14 //




(CEMH), Ext.V is the tour diary of P.K. Sutar (EENH), Ext.W is the

letter no. 2500 dated 23.04.2005, Ext.X is the hand receipts of

Abakash Padhy, Ext.Y is the forwarding letter of PIO dated

07.05.2015, Ext.Z is the office order of the Executive Engineer,

NH Division, Berhampur, Ext.AA is the FDR assessment report,

Ext.BB is the bar chart of FDR and Ext.CC is the letter no. 63

dated 07.05.2015.

5.         The learned trial Court in its impugned judgment has

been pleased to hold that the appellants were the public servants

at the relevant point of time within the meaning of public servant

as defined under section 2 of 1988 Act. It was further held that

the respondent no.4 had executed the patch work on the N.H.

way and at the time of entering into the contract with the

respondent no.4, the earlier contract was not in force, as such, no

illegality has been done. It was further held that by the time Arun

Kumar Choudhury, the contractor commenced the disputed work

on 01.12.2004 till its completion on 30.01.2005, there was no

extension of time and extension of time was sought for by P.W.9

only on 21.03.2005 which was sanctioned by the Superintending

Engineer on 24.03.2005. It was further held that till 22.09.2004,

the earlier contract with the 1st Contractor Arun Kumar Choudhury

was not rescinded and was very much in force in view of Clause-2

(b)(l) of the conditions of contract. The appellant Saroj Kumar



                                                       Page 14 of 60
                              // 15 //




Misra entered into an agreement with the respondent no.4 on

10.09.2004 for the self-same work with commencement and

completion date as 10.09.2004 and 09.03.2005 and as such the

subsequent contract was illegal. It was further held that in view of

the contradictory evidence adduced by the prosecution witnesses,

it can affirmatively be concluded that the trial run of the

machineries by the 1st contractor Arun Kumar Choudhury was

doubtful. It was further held that the prosecution has not

substantiated the essential ingredients of sections 420 and 468 of

the Indian Penal Code.

           The learned trial Court further held that on careful

scrutiny of the materials on record, there appears nothing to the

fact that the appellants conspired with the respondent no.4 to

grab the government funds allotted for construction of potholes

and therefore, the prosecution has failed to bring home the

charge under section 120-B of the Indian Penal Code against the

accused persons.

           The     learned   trial      Court   further   held    that     the

disappearance of MB No.1311 against the appellants was not

founded   and    accordingly,     the     prosecution     has     failed    to

substantiate the charge under section 201 of the Indian Penal

Code against them. It was further held that the respondent no.4




                                                                 Page 15 of 60
                              // 16 //




is not guilty under any of the offences charged and accordingly,

he was acquitted of all the charges.

            However,   the     learned   trial   Court   held     that   the

prosecution has successfully established the charge under section

13(2) read with section 13(1)(d) of the 1988 Act against the

appellants and accordingly found them guilty.

6.          Mr. Asok Mohanty, learned Senior Advocate appearing

for the appellants Sudarsan Sahani and Saroj Kumar Misra argued

that the finding of the learned trial Court that the 2nd agreement

which was executed by the appellant Saroj Kumar Misra with the

respondent no.4 Abhisekh Padhi while the 1st agreement was in

force is illegal, is contrary to the evidence on record and suffers

from non-application of mind. It is further submitted that the 2nd

agreement was a valid one for the following reasons:

     (i)    Both the agreements were for different work and

            therefore, did not overlap at all. Moreover, the nature

            and scope of work in the two agreements operate in

            two different spheres. The 1st agreement was for

            periodical renewal and the 2nd agreement was for

            pothole repairs;

     (ii)   The 1st agreement was for periodical renewal from 148

            K.M. to 154 K.M. and the 2nd agreement was for

            pothole repair from 147 K.M. to 171 K.M. The value of



                                                                Page 16 of 60
                              // 17 //




        the    1st   agreement            was       Rs.36,98,199/-     for     six

        kilometers, whereas the 2nd agreement value was for

        Rs.4,70,170/- for 24 Kms.;

(iii)   At the time of execution of 2nd agreement dated

        10.09.2004, the 1st agreement/contract was not in

        force;

(iv)    In the 1st agreement, it is clearly mentioned that time

        was the essence of contract, which would be evident

        from a bare reading of clause 2(a) of the agreement

        (Ext.10) and since time was the essence of contract,

        the 1st contractor Arun Kumar Choudhury was obliged

        to finish the work within time or during the period of

        extension granted as per procedure laid down in the

        O.P.W.D.      Code.         The       1st   contractor    signed      the

        agreement (Ext.10) on 19.02.2004 wherein the date

        of    completion       of       the    work    was     mentioned       as

        18.06.2004. On account of the Code of Conduct for

        General      Election,          extension      was     granted       from

        01.05.2004      to     31.08.2004,            but    before   or     after

        31.08.2004, no extension was sought for or granted

        by the prescribed authority. Therefore, there was no

        agreement in force as on 10.09.2004 when the

        disputed     agreement            under      Ext.21    was    executed



                                                                  Page 17 of 60
                                // 18 //




            between      the   appellant    Saroj   Kumar    Misra,   the

            Executive Engineer and the respondent no.4 Abakash

            Padhi. Reliance was placed on two letters i.e. Ext.Q

            and Ext.G.

            Mr. Asok Mohanty, learned Senior Advocate further

argued that the learned trial Court rightly acquitted all the

appellants including the respondent no.4 of the charges under

sections 420, 468, 120-B and 201 of the Indian Penal Code but

most   peculiarly   without     assigning   any     reason   whatsoever,

convicted the appellants under section 13(2) read with section

13(1)(d) of 1988 Act. Such an order of conviction is perverse and

suffers from non-application of mind and therefore, cannot be

sustained in the eye of law.

           Mr. Pradipta Kumar Mohanty, learned Senior Advocate

appearing for the appellant Prasant Kumar Patra in CRLA No.687

of 2016 so also for all the respondents in GCRLA No.25 of 2019

not only adopted the argument advanced by Mr. Asok Mohanty,

Senior Advocate but added that the impugned judgment and

order of acquittal of respondent no.4 of all the charges and the

appellants of some of the charges passed by the learned trial

cannot be said to be perverse, palpably wrong, manifestly

erroneous or demonstrably unsustainable and since this Court

while dealing with an appeal against acquittal ought to be cautious



                                                             Page 18 of 60
                            // 19 //




because the presumption of innocence in favour of the accused is

not certainly weakened by the fact that he has been acquitted at

the trial, therefore, there is no compelling reasons to interfere

with the same in the GCRLA.

           Mr. Srimanta Das, learned Senior Standing Counsel

for the Vigilance Department on the other hand contended that

the appellant Saroj Kumar Misra being the Executive Engineer

executed the agreement vide Ext.10 with the 1st contractor Arun

Kumar Choudhury with date of commencement as 19.02.2004

and date of completion as 18.06.2004 and extension of time was

granted upto 30.01.2005 which was sanctioned by Superintendent

Engineer, N.H. Circle vide letter dated 24.03.2005. However, the

said appellant executed the fresh agreement vide Ext.21 within

the extended period of the 1st contractor with the respondent no.4

Abakash Padhi, i.e. the 2nd contractor on 10.09.2004 for repair of

potholes from 147 K.M. to 171 K.M. for the year 2004-05 with

date of commencement 10.09.2004 with the stipulated date of

completion as 09.03.2005 thereby overlapping the existing

agreement vide Ext.10 and the learned trial Court has rightly

given the finding that the 2nd agreement was entered into

between the appellant Saroj Kumar Misra and the respondent

no.4 Abakash Padhy while the 1st agreement was not rescinded

and was very much in force. He further argued that P.W.9 has



                                                      Page 19 of 60
                                 // 20 //




stated   that   although   he     joined   as   Executive   Engineer   on

08.10.2004, but he was not given charge of the office by his

predecessor (appellant Saroj Kumar Misra) and that during that

period, the office of the Executive Engineer was kept under lock

and key by the said appellant and that he (P.W.9) took charge

from the appellant on 01.12.2004 which was after nearly two

months and during the said period, he (P.W.9) made an

inspection of the site in question and found that no work appeared

to have been done there. It is argued that P.W.9 was deliberately

kept out of the office in order to cover up the irregularities

committed by the appellants with regard to so-called work of the

respondent no.4 which was in fact non-existent but the payment

of bill was made thereon. He further emphasized that the

respondent no.4 in his accused statement has clearly stated that

he had no knowledge regarding entrustment of work to him in

pursuance to the 2nd tender call notice for the year 2004-05,

which substantiates that the accused persons prepared false bills

and vouchers to misappropriate Government money making the

respondent no.4 as a dummy contractor only on paper. While

concluding his argument, Mr. Das contended that the respondent

no.4 should have to execute the work entrusted utilizing machines

as per specification in the tender, but he claimed the amount for

such work, which he had allegedly executed manually and there is



                                                             Page 20 of 60
                             // 21 //




no iota of doubt that had the work been done manually, the

expenses would have been more and the respondent no.4 could

not have claimed the lesser amount as if it was executed through

machines and this is another factor, which improbablises the

execution of any work by the respondent no.4 under the 2nd

contract and rather it strengthens the prosecution case that

fabricated documents were created by the accused persons to

claim charges for pothole repair works, which was in fact not been

done and whatever work has been done, that was done only by

the 1st contractor Arun Kumar Choudhury, who was paid for the

work and therefore, the learned trial Court has rightly convicted

the appellants under section 13(2) read with section 13(1)(d) of

1988 Act.

            Mr. P.K. Pani, learned Standing Counsel (Vigilance)

appearing in the Government Appeal contended that not only the

acquittal of respondent no.4 of all the charges, but also the

appellants of the charges under sections 420, 468, 201 and

section 120-B of the Indian Penal Code is faulty and it should be

set aside and all the appellants and respondent no.4 should be

held guilty for all the offences they were charged. According to

Mr. Pani, pursuant to the F-2 agreement executed with the 1st

contractor Arun Kumar Choudhury, the work was carried out and

completed   within   the   extended    time   as   allowed   by   the



                                                         Page 21 of 60
                            // 22 //




Department and after due measurement, the final bill was passed

and payment was made thereon. During the continuance of the

work under the 1st agreement which was in force, another

agreement was illegally entered into with the respondent no.4 for

a small part of the work covered under the 1st agreement and not

only that, the bill for the work under 2nd agreement for an amount

of Rs.1,50,000/- was also released in favour of the respondent

no.4 within four days of the agreement. He further argued that

the pothole repair works as per the 2nd agreement was also

covered under the original agreement, which was not permissible,

inasmuch as in case of exigencies for any small additional work

within the original work in progress, the same has to be executed

by the original contractor as per clause 10 of the F2 agreement of

the 1st contractor as well as clause 3.5.31 of O.P.W.D. Code. Mr.

Pani further submitted that that is the reason why the purported

work under the 2nd tender was stopped because of irregularity and

no work appeared to have been done in the site under the 2nd

tender. He emphasized about the conspiracy between the accused

persons in preparing false paper work like tender and agreement

by showing simultaneous execution of sham work with the original

work and for such purpose, a dummy contractor like respondent

no.4 was set up. The measurement book for the work done under

the 2nd agreement, which was M.B. No. 1311 was found missing.



                                                      Page 22 of 60
                             // 23 //




According to Mr. Pani, since the learned trial Court has ignored

the material evidence brought on record by the prosecution to

substantiate various charges against the accused persons, the

view taken for acquittal is clearly unsustainable and therefore, it

should be set aside.

7.          The first and core point for determination is whether

the 1st agreement executed with the contractor Arun Kumar

Choudhury was in force when the 2nd agreement was executed

with the respondent no.4 Abakash Padhy.

            The second point for determination is whether there

was at all any necessity for entering into the 2nd agreement for

execution of pothole repair work and whether the respondent no.4

executed any work at all or false bill was claimed.

            The third point for determination is whether there was

any criminal conspiracy between the accused persons and undue

official favour was shown to the respondent no.4 for making

payment of Rs.1,50,000/- (rupees one lakh fifty thousand) to him

by showing false execution of pothole repair work.

            The fourth point for determination is whether there

was any forgery in respect of documents/records like pothole

repair estimate of Rs.4,91,800/-, agreement entered into with the

respondent no.4 and M.B. No. 1311 and whether there was any




                                                       Page 23 of 60
                            // 24 //




dishonest cheating to the Government by showing undue official

favour to the respondent no.4.

           The fifth and last point for determination is whether

the accused persons have caused disappearance of M.B. No.1311

with an intention to screen themselves from legal punishment.

First Point:

Whether the 1st agreement was in force when the 2nd

agreement was executed:

8.         Ext.10 is the F2 agreement executed between 1st

contractor Arun Kumar Choudhury and the appellant Saroj Kumar

Misra as Executive Engineer, N.H. Division, Berhampur on

19.02.2004 for the work "Periodical renewal work of N.H. 217

from KM 148/0 to 158/0". This document was proved by P.W.9,

the Executive Engineer, N.H. Division, Berhampur. The stipulated

date for commencement and completion of the work as per Ext.10

were 19.02.2004 and 18.06.2004.

           Clause 2(a) of Ext.10 reads as follows:-

           "The time allowed for carrying out the work as
           entered in the tender shall be strictly observed by
           the contractor and shall be reckoned from the date
           on which the written order to commence work is
           given to the contractor. The work shall throughout
           the stipulated period of the contract be carried on
           with all due diligence (time being deemed to be of
           the essence of the contract on the part of the


                                                      Page 24 of 60
                    // 25 //




contractor)     and     the   contractor      shall   pay     as
compensation an amount equal to ½% on the
amount of the estimated cost if the whole work as
shown by the tender for every day that the work
remains uncommenced or unfinished after the
proper dates (the work should not be considered
finished until such date as the Executive Engineer
shall certify as the date on which the work is
finished after necessary rectification of defects as
pointed out by the Executive Engineer, or his
authorized Agents, are fully complied with by the
contractor to the Executive Engineer's satisfaction)
And   further    to     ensure     good   progress        during
execution of the work, the contractor shall be
bound in all cases in which the time allowed for
any work exceeds one month, to complete one-
fourth of the whole of the work before one fourth
of the whole time allowed under the contract has
elapsed, one half of the work, before one half of
such time has elapsed and three-forth of the work
before three-fourth of such time has elapsed. In
the events of contractor failing to comply with the
condition,    he      shall   be     liable    to     pay     as
compensation       an    amount equal         to    one     third
percent on the said estimated cost of the whole
work for every day that the due quantity of work
remains incomplete provided always that the entire
amount of compensation to be paid under the
provisions of this clause shall not exceed 10% on
the estimated cost of the work as shown in the
tender."


                                                      Page 25 of 60
                               // 26 //




           Clause 4 of Ext.10 which provides for extension of
           time is quoted below:-
           "If the contractor shall desire on extension of the
           time for completion of the work, on the ground of
           his having been unavoidably hindrances in its
           execution or any other ground, he shall apply in
           writing to the Executive Engineer within 30 days of
           the date of the hindrance on account of which he
           desires such extension as aforesaid and the
           Executive Engineer shall, if in his opinion (which
           shall be final) reasonable be shown therefore,
           authorize such extension of time, if any, as may in
           his opinion, be necessary or proper. The Executive
           Engineer shall at the same time inform the
           contractor whether he claims compensation for
           delay."

           Para 3.5.30 of the O.P.W.D. Code, Vol.I provides for

extension of time, which reads as follows:-


           "3.5.30. Application for extension of time for the
           completion    of     a        work    on   the   grounds   of
           unavoidable hindrance or any other grounds shall
           be submitted by the contractor within 30 days of
           such hindrance and the Divisional Officer shall
           authorize or recommend such extension of time as
           deemed necessary or proper within fifteen days of
           the receipt of such an application. In cases where
           the sanction of the higher authority to the grant of
           extension of time is necessary, the Divisional
           Officer   should     send       his    recommendation      as

                                                                Page 26 of 60
                              // 27 //




            expeditiously as possible. The higher authority
            should communicate his decision within sixty days
            from the date of receipt on recommendation in his
            office. If the orders of the competent authority are
            not received in time, the Divisional Officer may
            grant extension of time under intimation to the
            concerned authorities so that the contract might
            remain in force, but while communicating this
            extension of time, he must inform the contractor
            that extension is granted without prejudice to
            Government's right to levy compensation under
            relevant clause of the contracts.

            Notes:- (I) The power to grant extension of time
            vests with the authority who accepted the tender
            but the period of extension that can be granted by
            such   an   authority       is   limited   to   the    period
            equivalent to the time originally stipulated in the
            agreement for completion of the work. Beyond
            this, approval of next higher authority should be
            obtained before extension of time is granted.

                      (II) The application for extension of time
            and sanction thereto should be made in the
            prescribed form."

            Mr. Asok Mohanty, learned Senior Advocate placed

reliance on Ext.Q, which is the letter no.4775 dated 22.09.2004

addressed to the 1st contractor Arun Kumar Choudhury by the

appellant Saroj Kumar Misra in his official capacity. In the said

letter, it is mentioned as follows:-


                                                                  Page 27 of 60
                               // 28 //




             "You have not executed any work till now. You
             have also not applied for grant of extension of
             time as per clause of F2 agreement in prescribed
             form."

             Mr. Ashok Mohanty, learned Senior Advocate further

placed reliance on Ext.G i.e. the letter no.5777 dated 29.10.2004

addressed to Superintending Engineer, N.H. Circle (South) by the

appellant Saroj Kumar Misra which was a submission of rescission

proposal of the 1st agreement i.e. the work assigned to the

contractor Arun Kumar Choudhury. In the said letter, it is

mentioned that the work that was awarded to Shri Arun Kumar

Choudhury was with the date of commencement and stipulated

date of completion was 19.02.2004 (shifted to 01.05.2004) and

18.06.2004    (shifted   to   31.08.2004)   respectively,     but    the

contractor had neither executed any work during the period of

contract nor has he applied to grant of extension of time in proper

format as required under clause 4 of the F2 agreement. It is

further mentioned therein that the said contractor as per letter

dated 22.09.2004 (Ext.Q) was asked to file show cause within

seven days as to why his contract should not be rescinded. It is

further mentioned therein that the contractor had not started the

work till 19.10.2004 and his revised work programme was already

returned in original and that the delay in starting the work was

therefore appeared to be intentional.


                                                            Page 28 of 60
                                // 29 //




             From these two letters i.e. Ext.Q and Ext.G, it

becomes prima facie evident that the 1st contractor Arun Kumar

Choudhury had not applied for extension of time either prior

31.08.2004 or after that particularly till the 2nd contract with

respondent no.4 vide Ext.21 was executed on 10.09.2004.

             During course of hearing on 10.02.2022, Mr. Asok

Mohanty placed the letter dated 21.03.2005 written by P.W.9, the

Executive Engineer to the Superintending Engineer, N.H. Circle

(South), Bhubaneswar which is a part and parcel of Ext.N proved

by the defence through D.W.3 wherein it was mentioned that

subsequently on consideration of representation of the                 1st

contractor, the date of commencement and stipulated dated of

completion    were   shifted      to      01.06.2004   and   30.09.2004

respectively and below the letter in the enclosure portion, copy of

the representation of the 1st contractor Arun Kumar Choudhury

has been mentioned. It was argued that no such representation

was in existence and no such order has been passed on any such

representation of the 1st contractor as was mentioned in the letter

dated 21.03.2005 regarding shifting of date of commencement

and date of completion of work to 01.06.2004 and 30.09.2004

respectively. To meet the contention of Mr. Asok Mohanty, learned

Senior Advocate, time was sought for by Mr. Srimanta Das,

learned Senior Standing Counsel of Vigilance Department to



                                                             Page 29 of 60
                             // 30 //




obtain instruction as to whether any such representation of the 1st

contractor and any such order regarding shifting of the date of

commencement and the date of completion of the work is

available or not.

            On 24.02.2022, Mr. Srimanta Das, learned Senior

Standing Counsel for the Vigilance Department filed an application

under section 391 of Cr.P.C. for marking certain documents as

additional evidence and the application was registered as I.A.

No.254 of 2022.

            An affidavit was filed by the holding Investigating

Officer on 10.03.2022 in which it was clearly mentioned that the

two documents i.e. the representation of the 1st contractor Arun

Kumar Choudhury for extension of time for completion of work or

the order passed on such representation regarding shifting of the

date of commencement or date of completion of work were not

available either in the office of Executive Engineer, N.H. Division,

Berhampur or in the office of Chief Construction Engineer, N.H.

Circle, Berhampur.

            The application filed by the learned Senior Standing

Counsel for the Vigilance Department under section 391 Cr.P.C.

was heard and rejected as per order dated 10.03.2022.

            Thus, neither before the learned trial Court nor before

this   Court,   the   prosecution      was   able   to   produce   any



                                                           Page 30 of 60
                            // 31 //




representation of the 1st contractor nor any order passed on such

representation shifting the date of commencement and date of

completion   of   the   work   to     01.06.2004   and   30.09.2004

respectively. P.W.9 admits that there is a provision under

O.P.W.D. Code giving scope to the executant to apply for

extension of time one month prior to the proposed date of

completion if the extension is required due to unavoidable

hindrance. However, P.W.9 stated that he could not say if the

extension was prayed within the time stipulated unless he

referred to the record. He further stated that he could not say if

Arun Kumar Choudhury had applied for extension of time one

month prior to the end day of the stipulated time. P.W.9 further

stated that he could not say whether the Technical team had

inspected the work entrusted to the 1st contractor Arun Kumar

Choudhury and reported on 29.07.2004 that the contractor had

no equipments in order to execute the proposed work which was

submitted to the Superintending Engineer, N.H. South Circle,

Berhampur who in turn intimated the Executive Engineer, N.H.

Division, Berhampur vide letter dated 17.08.2004. P.W.9 further

stated that he could not say whether the Executive Engineer had

called on Arun Kumar Choudhury to submit his show cause within

seven days and whether the Executive Engineer vide letter dated

29.10.2004 intimated Superintending Engineer about the closure



                                                         Page 31 of 60
                            // 32 //




proposal of the work of    Arun Kumar Choudhury. P.W.9 further

stated that when a contractor fails to execute the work under the

conditions stipulated in the agreement and for his default, he is

served with a show cause notice, he cannot be directed to take up

the said work afresh after the time stipulation of the agreement.

           In view of such state of affairs, the submission of Mr.

Asok Mohanty, learned Senior Advocate has got substantial force

that the prosecution has failed to produce any document

regarding submission of any application by the 1st contractor for

extension of time to complete the work or any order passed

thereon and thus it would be deemed that after 31.08.2004, there

was no extension to the work in question under 1st agreement

Ext.10.

           The above aspect is further strengthened on perusal

of the check list which is a part and parcel of Ext.N that goes to

show at column no.4 that the application for extension of time

was submitted on 10.03.2005 after the work is said to have been

completed on 30.01.2005. This check list was signed by P.W.9

wherein the date of submission of application for extension of

time by the 1st contractor Arun Kumar Choudhury has been

mentioned as 10.03.2005.

           P.W.9 has clearly stated in his evidence that he joined

as Executive Engineer, N.H. Division, Berhampur on 08.10.2004



                                                       Page 32 of 60
                              // 33 //




and took charge from his predecessor (appellant Saroj Kumar

Misra) on 01.12.2004 and that the agreement Ext.10 was

executed during the tenure of his predecessor but the work

started after his joining and in the cross-examination, he has

clarified that the 1st contractor Arun Kumar Choudhury started

execution of work on 01.12.2004 on which date he took charge of

the office from his predecessor. The learned trial Court has also

observed (para-16 of the impugned judgment) that by the time

the 1st contractor Arun Kumar Choudhury commenced the

disputed work on 01.12.2004 till its completion on 30.01.2005,

there was no extension of time and extension of time was sought

for by P.W.9 only on 21.03.2005 and the same was sanctioned by

the Superintending Engineer on 24.03.2005. This finding of the

learned trial Court is quite justified in the facts and circumstances

of the case.

               Mr. Asok Mohanty, learned Senior Advocate contended

that 'contract remains in force' after the earlier stipulated date

only when the application for extension of time for the completion

of a work is submitted by the contractor within the period

stipulated indicating the grounds of unavoidable hindrance or any

other grounds in the work in question. The same also finds place

in clause 4 of the conditions of the contract in Ext.10. According

to him, as per Para 3.5.30 of O.P.W.D. Code, Vol.I, the term



                                                         Page 33 of 60
                             // 34 //




'contract remains in force' and 'rescission of contract' as per

clause 2(b)(i) of the conditions of the contract as per Ext.10 are

two different things. To rescind the contract, the rescission notice

in writing is to be given to the contractor under the hand of

Executive Engineer which would be the conclusive evidence and

the security deposit of the contractor shall stand forfeited and will

be absolutely at the disposal of the Government. The finding of

the learned trial Court in para-17 of the impugned judgment that

in view of the notice dated 22.09.2004 vide Ext.Q issued to the 1st

contractor, till that date the earlier contract was very much in

force, is not correct. I agree with the submission made by the

learned Senior Advocate Mr. Asok Mohanty that 'contract to

remain in force' as per the provisions of the O.P.W.D. Code and

'rescission of contract' which includes forfeiture of the security

deposit of the contractor are quite different and distinguishable

and the learned trial Court erred in holding these two aspects to

be one and the same.

            Security for the due fulfillment of a contract is

invariably taken in view of clause 3.5.19 of the O.P.W.D. Code.

The security may be taken in shape of N.S.C./Post Office Savings

Bank Account/ Post Office Time Deposit Account/ Kissan Vikash

Patra only towards E.M.D./initial security deposit/ any other

security deposit from the contractor or supplier. In Ext.10, as per



                                                         Page 34 of 60
                              // 35 //




tender call notice 1/2003-2004 issued by the Office of the

Superintending Engineer, N.H. Circle (South), Bhubaneswar under

the heading of eligibility criteria as per clause 8, it is mentioned

that the contractor shall be required to give a trial run of the

equipments for establishing their capacity to achieve the laid

down specification and tolerances to the satisfaction of the

Engineering-in-charge     within    fifteen   days   from   signing   of

agreement failing which the securities of the contractor shall be

forfeited. Basing on the inspection of Drum Mix Plant made by the

Technical Committee on 28.07.2007 as per Ext.K, it was found to

be not to the satisfaction of the Executive Engineer which is

mentioned under the heading of general remarks. The learned

trial Court also came to conclusion in the impugned judgment that

the trial run of machinery by the 1st contractor Arun Kumar

Choudhury as per clause 8 of Ext.10 is doubtful. However, the

learned trial Court gave an erroneous finding that failing to give a

trial run of the equipments for establishing the capacity by the

contractor will only result in forfeiture of his 'security deposit' and

not 'rescission of contract'. Once there would be forfeiture of

security for not giving the trial run of the equipments, it would

result in a situation of tender being submitted without security

and agreement will also be without security and as such the

agreement will lapse in view of clause 3.5.19.



                                                            Page 35 of 60
                                // 36 //




            In view of the foregoing discussions and the relevant

provision of Para 3.5.30 of O.P.W.D. Code, Vol.I and clause 4 of

the conditions of contract (Ext.10), since there was no application

for extension of time submitted by the 1st contractor either prior

to 31.08.2004 or after that, it is to be held that the contract as

per 1st agreement executed with the contractor Arun Kumar

Choudhury was not in force when the 2nd agreement was

executed on 10.09.2004 vide Ext.21 with the respondent no.4

Abakash Padhi for potholes repair works. Thus, the first point is

answered accordingly.

Second Point:

Whether there was any necessity for entering into the 2nd

agreement and whether the respondent no.4 executed any

work at all or claimed false bill:

9.          From a bare reading of the two F2 agreements i.e.

Ext.10 and Ext.21, it is apparent that the agreements were for

different work and operate in two different spheres. The 1st

agreement   (Ext.10)    with     Arun     Kumar   Choudhury   was   for

periodical renewal from 148 K.M. to 154 K.M. and the 2nd

agreement (Ext.21) with the respondent no.4 Abakash Padhy was

for pothole repair from 147 K.M. to 171 K.M. The value of the 1st

agreement was Rs.36,98,199/- for six kilometers, whereas the

2nd   agreement value was for Rs.4,70,170/- for 24 Kms. Thus,



                                                          Page 36 of 60
                             // 37 //




the nature and scope of work in two agreements are different.

There is no dispute that the period of execution of the pothole

repair work under Ext.21 would have been well within the time

period of earlier agreement Ext.10 had the 1st contractor applied

for extension of time and an order would have been passed in

granting extension. It is also not in dispute that in case of

exigencies for any small additional work within the original work in

progress, the same has to be executed by the original contractor

as per clause 10 of the F2 agreement of the 1st contractor as well

as Para 3.5.31 of O.P.W.D. Code, but when the 1st contractor Arun

Kumar Choudhury has not at all progressed with his work as per

F2 agreement Ext.10 executed on 19.02.2004 and started

execution of work only on 01.12.2004 as stated by P.W.9 and on

account of rainy season, the potholes repair which was in the

nature of flood damage repair work had to be undertaken

immediately for maintaining the safety of road for movement, no

fault can be found with entering into the contract vide Ext.21 with

the respondent no.4 Abakash Padhy on the ground that those two

work overlap each other. Had the 1st contractor Arun Kumar

Choudhury started the periodical renewal work in time, there

might not have been any necessity for entering into contract with

the 2nd contractor respondent no.4 Abakash Padhy for pothole

repair work. P.W.9 admits in his cross-examination that repairing



                                                        Page 37 of 60
                            // 38 //




of potholes on N.H. is a routine work for maintenance. He further

stated that the Executive Engineer is competent to take steps for

repair of the potholes in an emergency situation by entering into

new agreement with a contractor following the official procedure.

He further stated that if the potholes on the road required to be

repaired are small in size, the work can be executed manually. In

my humble view, there were every necessity for entering into the

2nd agreement (Ext.21) as the 1st contractor had not progressed

with his assigned work.

           There are materials on record that the respondent

no.4 executed the port hole repair work assigned to him under

agreement Ext.21 and submitted the first running bill which was

passed for Rs.1,50,000/-. Ext.C is the letter dated 11.02.2005

issued by P.W.9 to the Assistant Engineer, N.H. Sub-Division,

Balliguda which clearly states that the final bill regarding

execution of work under F2 Agreement No.1 of 2004-05 (Ext.21)

has not been submitted. P.W.9 further mentioned in the letter

that it would be construed that no further work had been

executed against the above contract other than the items against

which the bills were earlier submitted. Thus, P.W.9 himself

indicates in the letter under Ext.C that the respondent no.4 had

executed the work as per Ext.21 for which running bill was

submitted. According to P.W.9, running bills are prepared taking



                                                      Page 38 of 60
                            // 39 //




into consideration the progress of a particular work and that the

payment on running bill is made during the execution of the work

and it has nothing to do with the completion of the work. P.W.9

further submits that the first running bill (Ext.24) for the second

work was prepared for Rs.2,53,418/- and passed on 14.09.2004

for Rs.1,50,000/- and in M.B. No.1311 at page No.89, the

measurement for this work was recorded.

           P.W.9 has stated that the Superintending Engineer

(P.W.11) had inspected the works along with him on 05.05.2005

and submitted the inspection note Ext.27 which was received by

him (P.W.9) on 31.05.2005. P.W.11 referring to his inspection

note Ext.27 has stated that the pothole repair work from KM

147/0 to 171/0 of NH 217 was taken up and during his inspection,

some patch work was found executed on the National Highway

towards the repair. He (P.W.11) further stated that in his

inspection report marked as Ext.27, he has observed that the

potholes between KM 147/0 to 171/0 excluding the area between

148/0 to 154/0 were found repaired manually using over sized

chips for surface dressing. In the cross-examination, P.W.11 has

stated that if those 6 Kms. are excluded from 24 Kms., the

pothole repair work was undertaken for 18 Kms. only. He further

stated that a pothole can be repaired without using WBM and by

surface dressing only if the nature of the pothole is small and due



                                                       Page 39 of 60
                             // 40 //




to wear and tear of the BT. He further stated that the record

reveals that the pothole repair from 147/0 Km. to 171/0 Km. on

NH 217 was a flood damage repair. He further stated that for

repairing pothole, machineries are required depending upon the

size of damage and it can also be repaired manually. He has

further stated that the part bill paid to contractor Abakash Padhi

(respondent no.4) for the pothole repair was calculated on the

basis of repair through machine though the work was actually

executed manually. P.W.9 also admits that in the status report

communicated to Asst. Engineer on 17.02.2005, he had instructed

him to stop the work by respondent no.4 as on that day. As per

Ext.A the respondent no.4 was intimated about the closure of

contract. From this, it is apparent that the respondent no.4

continued with the work in respect of 154 Km. to 171 Km. till

17.02.2005. In view of the evidence available on record, I am of

the humble view that after execution of           the agreement under

Ext.21, the respondent no.4 executed the pothole repair work and

submitted   the   first   running      bill   which   was   passed   for

Rs.1,50,000/- (one lakh fifty thousand) and it cannot be said that

he raised any false bill merely because the pothole repaired work

was done manually even though he could have utilized machine

as per specification in the tender but since it was the running bill,

it cannot be said that no pothole work had been done by the



                                                            Page 40 of 60
                               // 41 //




respondent no.4 and that he was a dummy contractor only on

paper and that it was a sham work and that the accused persons

prepared   false   bills   and     vouchers   to   misappropriate        the

Government     money.      Thus,    the   second   point   is    answered

accordingly.

Third Point:

Whether there was any criminal conspiracy between the

accused persons and undue official favour was shown to

respondent no.4:

10.        It has already been held while discussing the 1st point

and 2nd point that the contract as per 1st agreement (Ext.N)

executed with the contractor Arun Kumar Choudhury was not in

force when the 2nd agreement (Ext.21) was executed with the

respondent no.4 Abakash Padhi for pothole repair work and that

the nature and scope of work in the two agreements (Ext.10 and

Ext.21) are different and there was every necessity for entering

into the 2nd agreement (Ext.21) as the 1st contractor had not

progressed with his work and that there are materials on record

that the respondent no.4 executed the pothole repair work and

submitted his first running bill (Ext.24) which was passed for

Rs.1,50,000/-.

           The basic ingredients of the offence of 'criminal

conspiracy' as defined under section 120-A I.P.C. are



                                                                Page 41 of 60
                             // 42 //




           (i)    An agreement between two or more persons;

           (ii)   The agreement must relate to doing or

           causing to be done either (a) an illegal act; or (b)

           an act which is not illegal in itself but is done by

           illegal means.

           The meeting of minds of two or more persons for

doing or causing to be done an illegal act or an act by illegal

means is the sine qua non of criminal conspiracy. The offence can

be proved largely from the inferences drawn from the acts or

illegal omission committed by the conspirators in pursuance of a

common design in as much as the conspiracy is always hatched in

secrecy and it is impossible to adduce direct evidence of the

common intention of the conspirators. The entire agreement is to

be viewed as a whole and it has to be ascertained as to what in

fact the conspirators intended to do or the object they wanted to

achieve. The essence of criminal conspiracy is the unlawful

combination and ordinarily the offence is complete when the

combination is framed. Encouragement and support which co-

conspirators give to one another rendering enterprises possible

which, if left to individual effort, would have been impossible,

furnish the ground for visiting conspirators and abettors with

condign punishment. (Ref:-AIR 2008 SC 2991, Yogesh @

Sachin Jagdish Joshi -v- State of Maharashtra; (1980) 2


                                                       Page 42 of 60
                              // 43 //




SCC 465, Shivnarayan Laxminarayan Joshi -v- State of

Maharastra, 2013 (3) SCALE 565, Yakub Abdul Razaq

Menon -v- State of Maharashtra; AIR 2005 SC 128, K.

Hasim -v- State of Tamil Nadu).

           Section 120-B of the Indian Penal Code prescribes

punishment for criminal conspiracy which is defined under section

120-A of the Indian Penal Code.

           In   case   of   Devender    Pal   Singh   -Vrs.-   State

National Capital Territory of Delhi reported in (2002) 5

Supreme Court Cases 234, it is held that the element of a

criminal conspiracy consists of (a) an object to be accomplished,

(b) a plan or scheme embodying means to accomplish that object,

(c) an agreement or understanding between two or more of the

accused persons whereby they become definitely committed to

co-operate for the accomplishment of the object by the means

embodied in the agreement, or by any effectual means, (d) in the

jurisdiction where the statute required an overt act. The essence

of a criminal conspiracy is the unlawful combination and ordinarily

the offence is complete when the combination is framed. From

this, it necessarily follows that unless the statute so requires, no

overt act need be done in furtherance of the conspiracy, and that

the object of the combination need not be accomplished, in order

to constitute an indictable offence. Law making conspiracy a crime


                                                        Page 43 of 60
                               // 44 //




is designed to curb immoderate power to do mischief which is

gained by a combination of the means. The encouragement and

support which co-conspirators give to one another rendering

enterprise possible which, if left to individual effort, would have

been impossible, furnish the ground for visiting conspirators and

abettors with condign punishment. The conspiracy is held to be

continued and renewed as to all its members wherever and

whenever any member of the conspiracy acts in furtherance of the

common design. For an offence punishable under section 120-B of

the Indian Penal Code, the prosecution need not necessarily prove

that the perpetrators expressly agree to do or cause to be done

illegal   act;   the   agreement    may   be   proved   by    necessary

implication. Offence of criminal conspiracy has its foundation in an

agreement to commit an offence. A conspiracy consists not

merely in the intention of two or more, but in the agreement of

two or more to do an unlawful act by unlawful means.

             Since in the factual scenario, the execution of 2nd

agreement with the respondent no.4 cannot be said to be an

illegal act but was a sheer necessity in the situation of flood

damage and there is absence of any material that there was any

agreement between the accused persons for doing the pothole

repair work by illegal means or for doing an unlawful act by

unlawful means rather the respondent no.4 has executed the



                                                             Page 44 of 60
                             // 45 //




pothole repair work entrusted to him in a lawful manner and got a

sum of Rs.1,50,000/- towards the first running bill and there is no

material also on record that there was any inflated cost or any

loss to the Government and specifically in view of the evidence of

P.W.11 that the part bill paid to respondent no.4 was calculated

on the basis of repair through machine though the work was

actually executed manually, I am of the humble view that the

learned trial Court has rightly held that the prosecution has failed

to bring home the charge under section 120-B of the Indian Penal

Code against the accused persons. Thus, the third point is

answered accordingly.

Fourth Point:

Whether     there     was     any      forgery   in   respect     of

documents/records or there was any dishonest cheating to

the Government by showing undue official favour to the

respondent no.4:

11.         The essential ingredients of the offence of "cheating"

are that (i) deception of a person either by making a false or

misleading representation or by dishonest concealment or by any

other act or omission; (ii) fraudulent or dishonest inducement of

that person to either deliver any property or to consent to the

retention thereof by any person or to intentionally induce that

person so deceived to do or omit to do anything which he would



                                                        Page 45 of 60
                              // 46 //




not do or omit if he were not so deceived; and (iii) such act or

omission causing or is likely to cause damage or harm to that

person in body, mind, reputation or property. To constitute an

offence under section 420 of the Indian Penal Code, there should

not only be cheating, but as a consequence of such cheating, the

accused should have dishonestly induced the person deceived (i)

to deliver any property to any person, or (ii) to make, alter or

destroy wholly or in part a valuable security (or anything signed

or sealed and which is capable of being converted into a valuable

security). (Ref:- Md. Ibrahim -Vrs.- State of Bihar reported

in (2009) 8 Supreme Court Cases 751)

             In case of Inder Mohan Goswami -Vrs.- State of

Uttaranchal reported in (2008) 39 Orissa Criminal Reports

(SC) 188, it is held that to hold a person guilty of 'cheating', it is

necessary to show that he had a fraudulent or dishonest intention

at the time of making the promise. From his mere failure to

subsequently keep a promise, one cannot presume that he all

along had a culpable intention to break the promise from the

beginning.

             In case of Joseph Salvaraj A. -Vrs.- State of

Gujarat reported in (2011) 49 Orissa Criminal Reports (SC)

924, it is held that under section 420 of the Indian Penal Code, it

is inbuilt that there has to be a dishonest intention from the very



                                                          Page 46 of 60
                               // 47 //




beginning, which is sine qua non to hold the accused guilty for

commission of the said offence.

            In case of Devendra -Vrs.- State of U.P. reported

in (2009) 43 Orissa Criminal Reports (SC) 680, it is held that

a misrepresentation from the very beginning is a sine qua non for

constitution of an offence of cheating, although in some cases, an

intention to cheat may develop at a later stage of formation of the

contract.

            In case of Alpic Finance Ltd. -Vrs.- P. Sadasivan

reported in A.I.R. 2001 S.C. 1226, it is held as follows:-

            "10. The facts in the present case have to be
            appreciated in the light of the various decisions of
            this Court. When somebody suffers injury to his
            person, property or reputation, he may have
            remedies both under civil and criminal law.
                  The injury alleged may form basis of civil
            claim and may also constitute the ingredients of
            some crime punishable under criminal law. When
            there is dispute between the parties arising out of
            a   transaction    involving    passing   of   valuable
            properties between them, the aggrieved person
            may    have   right      to   sue   for   damages    or
            compensation and at the same time, law permits
            the victim to proceed against the wrongdoer for
            having committed an offence of criminal breach of
            trust or cheating. Here the main offence alleged
            by the appellant is that respondents committed


                                                            Page 47 of 60
                     // 48 //




the offence under Section 420 I.P.C. and the case
of the appellant is that respondents have cheated
him and thereby dishonestly induced him to
deliver property. To deceive is to induce a man to
believe that a thing is true which is false and
which the person practicing the deceit knows or
believes to be false. It must also be shown that
there existed a fraudulent and dishonest intention
at the time of commission of the offence. There is
no allegation that the respondents made any
willful misrepresentation. Even according to the
appellant, parties entered into a valid lease
agreement and the grievance of the appellant is
that the respondents failed to discharge their
contractual obligations. In the complaint, there is
no allegation that there was fraud or dishonest
inducement on the part of the respondents and
thereby      the    respondents          parted        with      the
property. It is trite law and common sense that
an honest man entering into a contract is deemed
to represent that he has the present intention of
carrying it out but if, having accepted the
pecuniary advantage involved in the transaction,
he fails to pay his debt, he does not necessarily
evade the debt by deception.

11. Moreover, the appellant has no case that the
respondents        obtained        the    article       by      any
fraudulent         inducement            or       by          willful
misrepresentation. We are told that respondents,
though    committed            default   in   paying          some



                                                          Page 48 of 60
                              // 49 //




            installments,    have       paid   substantial   amount
            towards the consideration.

            12. Having regard to the facts and circumstances,
            it is difficult to discern an element of deception in
            the whole transaction, whereas it is palpably
            evident that the appellant had an oblique motive
            of causing harassment to the respondents by
            seizing the entire articles through magisterial
            proceedings. We are of the view that the learned
            judge was perfectly justified in quashing the
            proceedings and we are disinclined to interfere in
            such matters."

            In case of Hridaya Ranjan Pd. Verma -Vrs.- State

of Bihar reported in A.I.R. 2000 S.C. 2341, it is held as

follows:-

            "13. Cheating is defined in Section 415 of the
            Code as, "Whoever, by deceiving any person,
            fraudulently or dishonestly induces the person so
            deceived to deliver any property to any person, or
            to consent that any person shall retain any
            property, or intentionally induces the person so
            deceived to do or omit to do anything which he
            would not do or omit if he were not so deceived,
            and which act or omission causes or is likely to
            cause damage or harm to that person in body,
            mind, reputation or property, is said to "cheat".
            Explanation - A dishonest concealment of facts is
            a deception within the meaning of this section.




                                                             Page 49 of 60
                 // 50 //




    The section requires - (1) Deception of any
person.
(2) (a) Fraudulently or dishonestly inducing that
person
(i) to deliver any property to any person; or
(ii) to consent that any person shall retain any
property; or
(b) intentionally inducing that person to do or
omit to do anything which he would not do or
omit if he were not so deceived, and which act or
omission causes or is likely to cause damage or
harm to that person in body mind, reputation or
property.
14. On a reading of the section, it is manifest that
in the definition there are set forth two separate
classes of acts which the person deceived may be
induced to do. In the first place he may be
induced fraudulently or dishonestly to deliver any
property to any person. The second class of acts
set forth in the section is the doing or omitting to
do anything which the person deceived would not
do or omit to do if he were not so deceived. In
the first class of cases the inducing must be
fraudulent or dishonest. In the second class of
acts, the inducing must be intentional but not
fraudulent or dishonest.

15. In determining the question, it has to be kept
in mind that the distinction between mere breach
of contract and the offence of cheating is a fine
one. It depends upon the intention of the accused



                                             Page 50 of 60
                             // 51 //




           at the time to inducement which may be judged
           by   his    subsequent           conduct   but     for   this
           subsequent conduct is not the sole test. Mere
           breach of contract cannot give rise to criminal
           prosecution for cheating unless fraudulent or
           dishonest    intention      is    shown    right    at   the
           beginning of the transaction, that is the time
           when the offence is said to have been committed.
           Therefore it is the intention which is the gist of
           the offence. To hold a person guilty of cheating, it
           is necessary to show that he had fraudulent or
           dishonest intention at the time of making the
           promise.

           16. From his mere failure to keep up promise
           subsequently such a culpable intention right at
           the beginning, that is, when he made the promise
           cannot be presumed."

           The basic ingredients of the offence under section 467

of the Indian Penal Code are that (i) the document in question is

forged; (ii) the accused forged it and (iii) the document is one of

the kinds enumerated in the said section. Section 468 of the

Indian Penal Code applies to those cases where forgery has been

committed for the purpose of cheating. If it is proved that the

purpose of the offender in committing the 'forgery' is to obtain

property dishonestly or if the guilty purpose comes within the

definition of 'cheating' as defined under section 415 of the Indian

Penal Code, then his act would be punishable under section 468 of


                                                                Page 51 of 60
                             // 52 //




the Indian Penal Code. For both these offences, the very first

thing which is required to be proved is that a 'forgery' as defined

under sections 463 and 464 of the Indian Penal Code have been

committed.

             There is absolutely no material that any fraud has

been perpetuated in making the document Ext.21. There is no

dispute that final bill in respect of the work executed by

respondent no.4 had not been prepared and the amount paid to

him to the tune of Rs.1,50,000/- (rupees one lakh fifty thousand)

was in the nature of first running bill. The evidence on record as

already discussed clearly indicates that the pothole repair work

was done manually but the bill of respondent no.4 has been

calculated on the basis of repair through machine and thus the

payment of the running bill cannot be said to be with an inflated

rate or it cannot be said that there was any wrongful loss to the

Government in making such payment. The prosecution had not

adduced any satisfactory evidence that any of the documents like

agreement entered into with the respondent no.4 or M.B. No.1311

or the pothole repair estimate are false documents and that the

accused persons prepared such documents for the purpose of

cheating and therefore, the learned trial Court is quite justified in

holding that the prosecution has not substantiated the essential




                                                         Page 52 of 60
                             // 53 //




ingredients of offences under sections 420 and 468 of the Indian

Penal Code. Thus, the fourth point is answered accordingly.

Fifth Point:

Whether the accused persons have caused disappearance

of M.B. No.1311 with an intention to screen themselves

from legal punishment:

12.        In order to attract the ingredients of the offence under

section 201 of the Indian Penal Code, the prosecution is required

to prove the following aspects:-

           (i)     The accused had knowledge or reason to believe

           that an offence has been committed;

           (ii)    The   accused       caused   disappearance    of   the

           evidence which is related to such offence;

           (iii)   Such disappearance has been done with the

           intention of screening himself or any other offender

           from legal punishment which is co-related to such

           offence;

           (iv)    After having knowledge or reason to believe

           regarding     commission       of    offence,   the   accused

           intentionally gave any false information relating to

           such offence and thereby caused disappearance of

           evidence.




                                                             Page 53 of 60
                             // 54 //




            The Investigating Officer (P.W.12) has stated that

during investigation, J.E. Sasikanta Acharya disclosed before him

to have received and handed over M.B. No.1311 to the Head Clerk

Prakash Chandra Panda but had not received a receipt for the

same from Shri Panda. Neither the prosecution has examined J.E.

Sasikanta Acharya nor Prakash Chandra Panda.

            P.W.9 has stated that a letter was written to Assistant

Engineer to ascertain about the M.B. No.1311 and in his letter

dated 03.04.2006, the Assistant Engineer intimated that the M.B.

was submitted along with the bill in the Office of the Executive

Engineer's Head Clerk in-charge Shri P.C. Panda on 15.03.2005.

He further stated that after receipt of the reply from the Assistant

Engineer, a letter was issued to the Head Clerk in-charge Shri P.C.

Panda. He further stated that M.B. No.1311 was in his office on

03.02.2005 and on that day, he was the Executive Engineer of

N.H. Division, Berhampur and the M.B. movement registers

remain under the custody of the dealing assistant. He further

stated that a departmental proceeding was initiated against the

Junior Engineer S.K. Acharya for the untraced M.B. and the bills

and that J.E. S.K. Acharya was awarded with a punishment in that

D.P.

            In view of such materials, it cannot be said that

merely because M.B. No.1311 was not found, the accused persons



                                                        Page 54 of 60
                             // 55 //




caused its disappearance. The finding of the learned trial Court

that disappearance of M.B. No.1311 against the accused persons

is not found and the prosecution has failed to substantiate the

charge under section 201 of the Indian Penal Code against the

accused persons is quite justified and I also agree with the same.

Thus, the fifth point is answered accordingly.

13.         Coming to the charge under section 13(2) read with

section 13(1)(d) of the 1988 Act for which the three appellants

were found guilty by the learned trial Court after acquitting all the

accused persons of the charges under sections 420, 468, 120-B

and 201 of the Indian Penal Code without assigning any reason

whatsoever is quite surprising, reflects non-application of mind to

the ingredients required to substantiate such charge.

            The charge was framed under section 13(2) read with

section 13(1)(d) of the 1988 Act on the ground that that all the

three appellants-public servants in connivance with each other

and also with the respondent no.4 Abakash Padhi by corrupt and

illegal means or by otherwise abusing their position as such public

servant obtained for themselves pecuniary advantages to the

extent of amount of Rs.1,50,000/- (rupees one lakh fifty

thousand) by showing undue official favour to the respondent

no.4 by showing false execution of pothole repair work.




                                                          Page 55 of 60
                             // 56 //




            Since I have already found that there has been

execution of pothole repair work by the respondent no.4 for which

he was paid Rs.1,50,000/- (rupees one lakh fifty thousand)

towards his first running bill, the question of showing of undue

official favour to anybody does not arise. Therefore, the conviction

of the appellants under section 13(2) read with section 13(1)(d)

of the 1988 Act is not sustainable in the eye of law and hereby set

aside.

14.         Coming to the appeal against acquittal filed by the

State of Odisha, law is well settled as held in case of Babu -Vrs.-

State of Uttar Pradesh reported in A.I.R. 1983 Supreme

Court 308 that in appeal against acquittal, if two views are

possible, the appellate Court should not interfere with the

conclusions arrived at by the trial Court unless the conclusions are

not possible. If the finding reached by the trial Judge cannot be

said to be unreasonable, the appellate Court should not disturb it

even if it were possible to reach a different conclusion on the basis

of the material on the record because the trial Judge has the

advantage of seeing and hearing the witnesses and the initial

presumption of innocence in favour of the accused is not

weakened by his acquittal. The appellate Court, therefore, should

be slow in disturbing the finding of fact of the trial Court and if

two views are reasonably possible on the evidence on the record,



                                                         Page 56 of 60
                             // 57 //




it is not expected to interfere simply because it feels that it would

have taken a different view if the case had been tried by it.

            Thus, an order of acquittal should not be disturbed in

appeal under section 378 of Cr.P.C. unless it is perverse or

unreasonable. There must exist very strong and compelling

reasons in order to interfere with the same.

            The right of appeal against acquittal vested in the

State   Government     should     be   used    sparingly   and     with

circumspection and it is to be made only in case of public

importance or where there has been a miscarriage of justice of a

very grave nature.

            In case of Bannareddy -Vrs.- State of Karnataka

reported in (2018) 5 Supreme Court Cases 790, it is held as

follows:-

            "10....It is well-settled principle of law that the
            High Court should not interfere in the well-
            reasoned order of the trial court which has been
            arrived at after proper appreciation of the
            evidence. The High Court should give due regard
            to the findings and the conclusions reached by
            the trial court unless strong and compelling
            reasons exist in the evidence itself which can
            dislodge the findings itself".

            In case of Ghurey Lal -Vrs.- State of Uttar Pradesh

reported in (2008) 10 Supreme Court Cases 450, it is held as

follows:-



                                                           Page 57 of 60
                             // 58 //




            75....The trial court has the advantage of
            watching the demeanour of the witnesses who
            have given evidence, therefore, the appellate
            court should be slow to interfere with the
            decisions of the trial court. An acquittal by the
            trial court should not be interfered with unless it
            is totally perverse or wholly unsustainable."

            Thus in a case of appeal against acquittal, although

the powers of the High Court to reassess the evidence and reach

its own conclusions are as extensive as in an appeal against an

order of conviction, yet, as a rule of prudence, proper weight

should be given to the views of the Trial Judge as to the credibility

of the witnesses, the presumption of innocence in favour of the

accused, a presumption certainly not weakened by the fact that

he has been acquitted at the trial, the right of an accused to the

benefit of any doubt and the slowness of an appellate Court in

disturbing a finding of fact arrived at by a Trial Judge who had the

advantage of seeing the witnesses. Where two reasonable views

are possible or two reasonable conclusions can be drawn on the

evidence on record, the appellate Court, as a matter of judicial

caution should not interfere with the conclusion arrived at by the

learned trial Court unless the conclusions are not possible. Even if

the appellate Court can review the trial Court's conclusion both on

facts as well as law, but if the grounds of acquittal cannot be

entirely and effectively dislodged or demolished and unless there

has been flagrant miscarriage of justice by pronouncing the order


                                                         Page 58 of 60
                             // 59 //




of acquittal substantially and compelling reasons are there to

interfere with the conclusions arrived at by the trial Court, the

findings of acquittal should not be disturbed.

            Keeping the ratio laid down by the Hon'ble Supreme

Court and the settled position of law, on the basis of careful

analysis of evidence on record as made above, I am of the humble

view that the view taken for the acquittal of the respondent no.4

of all the charges so also the appellants of the charges under

sections 420, 468, 201 and 120-B of the Indian Penal Code is

reasonable and plausible and I find no compelling reason to

interfere with the conclusions arrived at by the learned trial Court

so far as the order of acquittal is concerned.

15.         In view of the foregoing discussions, all the three

criminal appeals i.e.   CRLA No.695 of 2016 filed by appellant

Sudarsan Sahani, CRLA No.687 of 2016 filed by appellant

Prasanta Kumar Patra and CRLA No.694 of 2016 filed by appellant

Saroj Kumar Misra are allowed. The impugned judgment and

order of conviction of the three appellants under section 13(2)

read with section 13(1)(d) of the 1988 Act and the sentence

passed thereunder is hereby set aside and they are acquitted of

such charge. The appellants are on bail by virtue of the orders of

this Court. They are discharged from liability of their bail bonds.

The personal bonds and the surety bonds stand cancelled.



                                                        Page 59 of 60
                                       // 60 //




                GCRLA No.25 of 2019 filed by the State of Odisha also

stands dismissed. The respondent no.4 Abakash Padhy who is on

bail by virtue of the order dated 02.08.2019 is discharged from

the liability of the bail bonds. The personal bond and the surety

bonds stand cancelled.

                The trial Court records with a copy of this judgment

be sent down to the concerned Court forthwith for information.



                                                 ...............................
                                                  S.K. Sahoo, J.

Odisha High Court, Cuttack The 18th April 2022/PKSahoo/Pravakar/RKMishra Page 60 of 60