Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0]

National Company Law Appellate Tribunal

Essjay Ericsson Pvt. Ltd vs Frontline (Ncr) Business Solutions ... on 17 January, 2022

     NATIONAL COMPANY LAW APPELLATE TRIBUNAL, PRINCIPAL BENCH,
                             NEW DELHI
                Company Appeal (AT) (Ins) No. 936 of 2021

IN THE MATTER OF:
M/s Essjay Ericsson Pvt. Ltd.                                   ...Appellant
Vs.
M/s Frontline(NCR) Business Solutions Pvt. Ltd.                ...Respondent

Present:

For Appellant:                Mr. Partho Bhattacharya, Mr. Anand Kumar Singh,
                              Advocates

For Respondent:               Mr. Rajeev Narayan, Advocate



                                           ORDER

(Through Virtual Mode) 17.01.2022: Heard Shri P.Bhattacharya, Learned Counsel appearing for the Appellant and Shri R. Narayan, Learned Counsel for the Respondent.

2. This appeal has been filed against the order dated 08.06.2021 passed by the 'Adjudicating Authority' rejecting the application u/s 9 filed by the Appellant on the ground that there is pre-existing dispute and further the notice which was served by the 'Operational Creditor' was in form - 3 although it ought to have been in form - 4.

3. The Appellant, an 'Operational Creditor' was given Purchase Order by the Respondent (Corporate Debtor) for supply of 'Hybrid Solar Power System, spare parts of Hybrid Solar Power System for their WiFi Project'. The Corporate Debtor was awarded contract for supply and installation of commission of 'Wi-Fi Company Appeal (AT) (Ins) No. 936 of 2021 1 Choupal Program Me" in 5000 Gram Panchayats in the State of U.P. at various locations.

4. The Corporate Debtor was required to install Dual Band wi-fi devices which included among others installation of Wireless concurrent outdoor Access Points, various supporting starting equipments were needed by the Respondent Company.

5. The Purchase Order dated 18.06.2018 was issued for supply of complete set required various equipments including the battery, solar charge etc. The stipulated time was 30 days from the date of Purchase Order. The Purchase Order for 4000 unit was issued on payment of 10% i.e. 26 lacs was also given as advance.

6. The Corporate Debtor has sent email on 25.07.2018, 03.08.2018, 14.08.2018 bringing it to the notice of the Appellant Company that the material supplied by them were of inferior quality and the same need to be replaced. There was delay in supply of the materials. A notice u/s 8 of the IB Code was issued to the Respondent and thereafter the application u/s 9 was filed in March, 2020.

7. In response to Section 8 notice, reply was filed where dispute was raised in reply to Section 9 notice also, it was stated that there is a dispute regarding payment and with regard to which the Appellant was earlier informed.

8. The 'Adjudicating Authority' rejected the application on two grounds (i) that notice ought to have been in form 4 whereas it was in form - 3 and (ii) secondly there is pre-existing dispute.

Company Appeal (AT) (Ins) No. 936 of 2021 2

9. Learned Counsel Shri P.Bhattacharya appearing for the Appellant submits that the emails which were sent earlier to 03.08.2021 were all complied with and there was no deficiency after 03.08.2018 and payments were made to the Appellant after 03.08.2018, details of which has already been brought before the 'Adjudicating Authority' which indicates that no dispute subsisted thereafter.

10. Learned Counsel for the Respondent refuting the submissions contends that the dispute was very much between the parties regarding the payment. It is submitted that even the e.mail dated 13.03.2019 sent by the Appellant makes it clear that they have not supplied the requisite number of sets although billing invoice was sent for payment of 1,974 complete set. The complete set supplied were only 1110. The e.mail dated 13.03.2018 was sent by the Appellant which is also on record of the Adjudicating Authority.

We have considered the submissions of the Learned Counsel for the parties and perused the records.

11. In so far as the observation of the 'Adjudicating Authority' that notice ought to have been sent in form 4 and it should not have been sent in form 3. Hence, there was defect in the notice. We are of the view that the defect in form of the notice be ignored in the facts of the present case. We, thus proceed to look into the merits of the matter.

12. The 'Adjudicating Authority' in its judgement has noticed the pre-existing dispute and in paragraph 33 and 38 has referred to the reply issued by the Corporate Debtor which is as follows:-

Company Appeal (AT) (Ins) No. 936 of 2021 3
33. "Here in this case, reply of demand notice was sent. Of course, it was sent after ten days. Reason for delay is lockdown imposed by the Government. We further notice the reply of the main application has been filed and the dispute has also been raised by the Corporate Debtor in both the reply.
38. We further notice that the email enclosed by the respondent shows that respondent has raised the quality of the goods and that is the reason, the respondent sent an email on 03/08/2018 to replace all the batteries. Apart of that, the Corporate Debtor vide email dt.

25/07/2018 also raised about the delayed delivery, wrong delivery and incomplete deliver."

13. The 'Adjudicating Authority' ultimately came to the conclusion that there being pre-existing dispute and notice of dispute has already been issued by the 'Corporate Debtor', it is not a fit case of admitting Section 9 application.

14. The submission of Learned Counsel for the Appellant that there was no dispute subsisting after 03.08.2018 does not appear to be correct. Admittedly, Company Appeal (AT) (Ins) No. 936 of 2021 4 the bills which were issued to the Corporate Debtor were bills for 1,974 complete set whereas in the email dated 13.3.2019 which is at page 86 of the paper book, according to the e.mail sent by the Appellant, complete set with battery were only 1110. This mail is said to be sent by the Appellant with object of reconciliation of the material sent and receipt. The above is clearly a subject of dispute.

15. We are of the view that no error has been committed by the 'Adjudicating Authority' taking the view that notice of dispute having been sent, there is pre- existing dispute prior to the initiation of Section 9 proceedings. We do not find any error in the judgement of Adjudicating Authority, the appeal is dismissed.

[Justice Ashok Bhushan] Chairperson [Dr. Alok Srivastava] Member (Technical) ss/nn Company Appeal (AT) (Ins) No. 936 of 2021 5