Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Entire Act]

State of Rajasthan - Section

Section 10 in Rajasthan Enterprises Single Window Enabling and Clearance Rules, 2011

10. Removal of doubt.

- If any difficulty arises in the application or interpretation of these rules, it shall be decided by the State Government in the Industries Department whose decision thereon shall be final.[Schedule-I] [Substituted by Rajasthan Notification No. G.S.R. 7, dated 24.5.2016.](See rule 3 (1) 6 and 6(A))Part - ATime Limit for Various Permissions/Clearances
S. No. Departments /Organization Permissions/ Clearances Time Limit (Within Working Days)
1. Factories and Boilers Inspectorate (a) Factory building plan approval (under theFactories Act, 1948)
(i) Factories as defined under section 2m(ii) andinvolving non hazardous process as defined under rule 2(m) 10 days
(ii) Other factories 30 days
(b) Factories license
(i) Factories as defined under section 2m(ii) andinvolving non hazardous process as defined under rule 2(m) 7 days
(ii) Factories involving non hazardous process asdefined under rule 2(m) 15 days
(iii) Factories involving hazardous process as definedunder section 2(cb) 21 days
(iv) Factories involving dangerous operations asdefined under section 87 21 days
(v) MAH factories as defined under Rajasthan Controlof Major Accident Hazard Rules, 1991 60 days
(c) Renewal under Factories license
(i) Factories as defined under section 2m(ii) andinvolving non hazardous process as defined under rule 2(m) 7 days
(ii) Factories involving non hazardous process asdefined under rule 2(m) 15 days
(iii) Factories involving hazardous process as definedunder section 2(cb) 21 days
(iv) Factories involving dangerous operations asdefined under section 87 21 days
(v) MAH factories as defined under Rajasthan Controlof Major Accident Hazard Rules, 1991 60 days
(d) Registration under Boiler Act After the receipt of complete application
(i) Provisional order (under the Boilers Act, 1923) Exempted
(ii) Final order (under the Boilers Act, 1923) 30 days
(e) Renewal under 'Registration under Boiler Act'  
(i) In cases in which the Competent Person isempowered to issue a certificate under section 8 without furtherreference. 48 hours
(ii) In any other case 15 days
(f) Steam Pipeline Drawing approval (under theBoilers Act, 1923) 15 days
2. Labour Department (a) Permission for engaging contractor for labourUnder Contract Labour (Regulation and Abolition) Act, 1970
(i) Registration of Principal EmployersEstablishments 30 days
(ii) Issuance of Licence to Contractor for employmentof contract labours 15 days
(b) Registration of Establishments under Buildingand other Construction Workers (Regulation of. Employment andconditions of Services) Act, 1996 15 days
(c) 'Registration under Shops and EstablishmentsAct' 30 days
(d) Renewal under 'Shops and Establishments Act' 15 days
3. Revenue Department (a) Land conversion - Conversion of land use underRajasthan Land Revenue (Conversion of Agricultural Land for Non-Agricultural Purposes in Rural Areas) Rules, 2007 Sending applications directly to the concernedDistrict Collectors under intimation to Revenue Department,Jaipur, to save time. Revenue Department would issue on linereceipt and update online status of the application. Allcommunication would be addressed to PS, Revenue for early action.
(i) up to 10 hectares 60 days from submission of completed applicationto District Collector
(ii) above 10 hectares 90 days from submission of completed applicationto State Government
4. Energy Department (All Vidhyut Vitran NigamLtd.) (a) Release Connection (where no extension inDistribution Mains is required) Electricity connection
(1) Release of ConnectionExplanation:i) If LT supply ofelectricity can be provided to a premises by existing serviceline or by laying service line up to 50 meters, from an existingoverhead line or underground cable where a cable box, junctionbox pillar box etc. has been provided, the distribution mainsshall be deemed to require no extension.ii) In case of HT supply of electricity to apremises, the distribution system shall be deemed to requireaugmentation and procedure laid down in Clauses b) & c)hereunder shall be followed. Within one month of the receipt of completedapplication
(b) Supply where distribution mains requireextension
(1) Notice to the applicant to deposit additionalexpenses Within one month of the receipt of application(for a period of one month)
(2) Where extension of distribution mains isrequired but no additional sum is required to be deposited The Nigam shall complete the extension workwithin 15 days
(3) The Nigam shall complete the extension ofdistribution mains within the time specified below for differentvoltage levels after deposit of additional sum by the applicant  
(i) L.T. line 15 days
(ii) 11 KV line-first 5KmpNext 5 Km each 30 days15 days
(iii) 33 KV line-first 5 KmNext 5 Km each 60 days30 days
(iv) 132 KV line-first 5KmNext 5 Km each 180 days45 days
Note:After extension work connectionwill be released within 15 days after inspection of theinstallation.
(c) Supply where new sub-station or augmentation oftransformer substation is required
(1) Supply where new substation is to becommissioned The Nigam will intimate within two month ofreceipt of application, the date of commencement of work, to theconsumer and complete the work within time limit specified below
(i) 11/0.4 KV sub-station 30 days
(ii) 33/11 KV sub-station 120 days
(iii) Extension of bay at 33/11 KV sub-station 30 days
(iv) 132/33/11 KV sub-station 12 month
(v) Extension of bay at 132 KV sub-station 45 days
(2) Supply where augmentation of transformersub-station capacity is required  
(i) 11/0.4 KV sub-station 15 days
(ii) 33/11 KV sub-station 60 days
(iii) 132/33/11 KV sub-station 6 months
  After commencement of work of sub-station  
  (i) Intimation to theconsumer if any additional sum is to be deposited by theapplicant.Intimation -Time of deposition -Release of connection - Within 15 days aftercommencement of work.1 month or suchextended period as the Nigam may allow.Within 15 days of commissioning of substation.
(d) Supply in localities where no provision forsupply exists Once electrification of such locality iscompleted supply shall be provided to the applicant in accordancewith the provisions of sub-clauses a) to c) above as may beapplicable to him.
(e) Supply where electric line/plant is provided byapplicant The Nigam shall provide supply of electricitywithin 15 days of intimation given by the applicant regardingcompletion of work.
5. RIICO (a) Allotment of plots in Industrial Areas Form A - 30 days Form A(Preferential) - 90 days
(b) Approval of building plans 15 Days (After receiving completemodification/correction in submitted drawing )
(c) Water Connection 20 days (After receiving of complete information)
6. UDH Department (JDA/UITs) (a) 90A of Agriculture Land/ Conversion of landunder Rajasthan Land Revenue Rules 2012 60 days
(b) Change of Land use/Conversion of land use fromresidential to commercial (i) Matters to bedecided at Local level committees- 60 days(ii) Matters to be decided at State levelcommittees-120 days
(c) Issuance of Lease Deed for institutional plots (i) To be issued atlocal level-30 days(ii) When approval of State Govt. is required-60 days
(d) Allotment ofinstitutional land except the allotment of land throughlottery/auction and of the developed land given as compensationfor Government/Semi-Government departments/ institutions andacquired land - under instruction of Urban Development and LocalSelf Department dated 4.1.2010 90 days
(e) Building map approval of all kinds ofinstitutional buildings 60 days
7. Local Self Government (LSG) (a) NOC from Fire Department 30 Days
(b) 90A of Agriculture Land/ Conversion of landunder Rajasthan Land Revenue Rules 2012 60 Days
(c) Change of Land use/Conversion of land use fromresidential to commercial (i) Matters to bedecided at Local level committees- 60 days(ii) Matters to be decided at State levelcommittees - 120 days
(d) Building map approval of all kinds ofinstitutional buildings 60 days
8. Public Health Engineering Department (PHED) (a) Water Connection 07 days as per availability of water and afterdeposition of all fees
9. Tourism Department (a) Project Approval 45 days from the date of submission of completeapplication
10. Industries Department (a) Incentives under Industrial Policy/InvestmentPromotion Scheme As per Schedule I(b)
Part - BTime Limit for Incentives under RIPS-2014
S. No. Department Application for Benefits under RajasthanInvestment Promotion Scheme -2014 Time Limit for disposal of application(Decision on eligibility under RIPS-2014)
1. Industries Department (a) Exemption from stamp duty and conversion charge 07 days from date of submission of completeapplication
    (b) Exemption from land tax 45 days from date of submission of completeapplication
    (c) Investment subsidy and Employment subsidy 45 days from date of submission of completeapplication
    (d) Exemption from(8) Electricity duty(9) Entertainment tax(10) Luxury tax(11) Mandi fee(12) Entrytax 45 days from date of submission of completeapplication
    (e) Interest subsidy 45 days from date of submission of completeapplication
    (f) Reimbursement of VAT 45 days from date of submission of completeapplication
    (g) Capital subsidy on ZLD treatment plant 45 days from date of submission of completeapplication
Part - CTime Limit for Various Permissions/Clearances
S. No. Organisation Permissions/ Clearances Time Limit (Within Working Days)
1. Rajasthan Pollution Control Board (RPCB) (a) Consent to Establish (under Water Act & AirAct) 120 Days
(b) Consent to Operate (under Water Act & AirAct) 120 Days
(c) Renewal of 'Consent to Operate (under Water Act& Air Act) 120 Days
(d) Authorization under Hazardous Waste Rules 120 Days