Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 7, Cited by 0]

Gujarat High Court

Gujarat Mineral Development ... vs M.M. Patel And Co., Bhagirath Ginning ... on 27 August, 2018

Author: Akil Kureshi

Bench: Akil Kureshi, B.N. Karia

         C/SCA/14935/2017                                       JUDGMENT




            IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

             R/SPECIAL CIVIL APPLICATION NO. 14935 of 2017


FOR APPROVAL AND SIGNATURE:


HONOURABLE MR.JUSTICE AKIL KURESHI

and
HONOURABLE MR.JUSTICE B.N. KARIA

==========================================================

1     Whether Reporters of Local Papers may be allowed to
      see the judgment ?

2     To be referred to the Reporter or not ?

3     Whether their Lordships wish to see the fair copy of the
      judgment ?

4     Whether this case involves a substantial question of law
      as to the interpretation of the Constitution of India or any
      order made thereunder ?

==========================================================
       GUJARAT MINERAL DEVELOPMENT CORPORATION LIMITED
                               Versus
     M.M. PATEL AND CO., BHAGIRATH GINNING FACTORY BUILDING,
==========================================================
Appearance:
MS LILU K BHAYA(1705) for the PETITIONER(s) No. 1,2
MR HK PARMAR(1220) for the RESPONDENT(s) No. 1
==========================================================

    CORAM: HONOURABLE MR.JUSTICE AKIL KURESHI
           and
           HONOURABLE MR.JUSTICE B.N. KARIA

                              Date : 23,27/08/2018

                               ORAL JUDGMENT
Page 1 of 12

C/SCA/14935/2017 JUDGMENT (PER : HONOURABLE MR.JUSTICE AKIL KURESHI)

1. Petitioner   no.1   is   Gujarat   Mineral   Development  Corporation Limited ("GMDCL" for short). Petitioner no.2 is  its   General   Manager.   The   petitioners   are   the   original  defendants in Commercial Civil Suit No258/2016 (Old Civil  Suit No. 719/2013) filed by the present respondent who is  a   partnership   firm   and   is   engaged   in   the   business   of  executing works contracts. The petitioners have challenged  an order dated 4.3.2017 passed by the Commercial Court,  dismissing the application of the petitioners for rejection of  the plaint in exercise of powers under Order VII Rule 11 of  the Code of Civil Procedure

2. The challenge arises in the following background. GMDCL  had floated tenders for excavation of lignite from mines in  Lakhpat Taluka of Kutch District. Pursuant to such tender  process,   the   respondent   contractor   was   awarded   the  contract for removal of overburden/ earth excavation of all  sorts of soil and disposing the excavated materials within  the   mines   premises   for   specified   quantity   under   an  agreement dated 25.7.1997. The work had to be completed  within   24   months.   The   work   was   completed   after   some  delay. Final bill of the contractor was paid on 12.11.1999  along with which the security deposit of the contractor was  also   released.   The   contractor   issued   a   legal   notice   to  GMDCL   on   24.7.2001   raising   multiple   disputes   of   non  payment of dues for the work done and unlawful reduction  and   recoveries.   On   9.11.2001,   the   contractor   filed  Arbitration   Reference   No.82/2001   before   the   Gujarat  Public   Works   Contract   Dispute   Arbitration   Tribunal   ("the  Page 2 of 12 C/SCA/14935/2017 JUDGMENT Arbitration   Tribunal"   for   short).   Since   there   was   an  objection   of   delay  in  filing such  reference,  the   contractor  also prayed for condonation  thereof which was granted by  the Arbitration Tribunal. On 2.8.2005, the contractor filed  an   application   before   the   Arbitration   Tribunal   for  withdrawal   of   the   reference   on   the   ground   that   the  Arbitration   Tribunal   does   not   have   jurisdiction   over   the  subject   matter.   On   this   application,   the   Arbitration  Tribunal   passed   order   on   2.8.2005.   Tribunal   was   in  agreement with the contractor that the Tribunal lacked the  jurisdiction. Tribunal was of the opinion that though there  was   no   specific   power   for   granting   withdrawal   of   a  reference, in the interest of justice, such permission cannot  be withheld. The Tribunal accordingly granted permission  for   withdrawal   of   reference   with   a   liberty   to   present   it  before the appropriate forum having jurisdiction as may be  advised by the advocate. The Tribunal accordingly ordered  return of the reference petition to the contractor. 

3. The   contractor   thereupon   filed   Special   Civil   Suit  No.6/2006 before the Court of Principal Senior Civil Judge,  Bhuj on 20.1.2006.   We may record that this was a fresh  plaint   presented   by   him   and   it   was   not   a   case   of  presentation   of   the   plaint   returned   by   the   Arbitration  Tribunal. In such suit, GMDCL raised two objections. One  was that the Civil Court at Bhuj did not have jurisdiction  since as per clause­17 of the contract any dispute arising  out   of   the   contract   would   be   subject   to   jurisdiction   of  Ahmedabad   Court   only.   The   second   ground   raised   by  GMDCL   was   that   the   final   bill   was   settled   with   the  contractor, the payments of which he accepted, pursuant  Page 3 of 12 C/SCA/14935/2017 JUDGMENT to   which   security   deposit   was   returned   and   bank  guarantees   were   discharged.   In   other   words,   after   such  unconditional acceptance of final bill, the contractor could  not maintain the suit.

4. Learned   Senior   Civil   Judge,   Bhuj,   passed   an   order   on  16.4.2007 upholding the objection of the GMDCL in part.  He   was   of   the   opinion   that   the   suit   was   not   competent  before   the   Civil   Court   at   Bhuj.   In   view   of   the   agreement  between   the   parties,   under   clause17,   Ahmedabad   Court  would have exclusive jurisdiction. He accordingly returned  the   plaint   to   the   contractor   for   presentation   before   the  appropriate Court.

5. The   contractor   challenged   this   order   of   the   Civil   Court  before   the   District   Court,   Bhuj   by   filing   Civil   Misc.  Application   No.287/2007   on   19.10.2007.   District   Court,  Bhuj   dismissed   such   Civil   Misc.   Application   on   7.7.2009  on the ground that appeal was not maintainable before the  District Court. On 2.12.2009, the contractor filed Special  Civil Application No.7985/2010 challenging the judgment  of the District Court. Learned Single Judge dismissed such  petition   by   judgment   dated   28.1.2011.   Thereupon   the  contractor presented the suit returned by the Civil Court,  Bhuj, before the City Civil Court, Ahmedabad on 16.3.2013  which was numbered as Special Civil Suit No.6/2006 and  was later on renumbered as Civil Suit No.719/2013 upon  establishment   of   Commercial   Courts   under   the  Commercial Courts, Commercial Division and Commercial  Appellate   Division   of   High   Courts   Act,   2015   ("the  Commercial   Courts   Act"   for   short).   In   such   proceedings,  Page 4 of 12 C/SCA/14935/2017 JUDGMENT GMDCL   once   again  moved   an   application   for  rejection   of  the plaint  under Order VII Rule 11 of CPC in  which two  main   grounds   were   pressed   in   service.   One,   that   the  contractor is a partnership firm but proof of registration of  the firm is not produced on record and that therefore in  view of section 69 of the Partnership Act, the suit is not  maintainable.   Two,   that   the   suit   is   barred   by   limitation.  Elaborate   averments   were   made   in   such   application   to  contend that period of limitation would begin to run from  the   day   of   cause   of   action   which   GMDCL   considers   as  12.11.1999 i.e. when the final bill was settled.    According  to GMDCL even after giving set off, of all periods when the  legal   proceedings   were   pending   before   the   Arbitration  Tribunal   and   thereafter,   before   different   Civil   Courts  including the High   Court, the suit which was eventually  filed   before   the   City   Civil   Court,   Ahmedabad   was   hit   by  period   of   limitation   prescribed   under   the   law.   It   was  pointed   out   that   after   the   starting   of   limitation   on  12.11.1999, Arbitration Petition was filed nearly 23 months  later.   Thereafter,   after   the   Arbitration   Tribunal   permitted  withdrawal   of   the   reference,   suit   was   filed   before   Bhuj  Court after a gap of five months and 15 days. Once again,  after the High Court dismissed the writ petition upholding  the view of the Court below, that Civil Court at Bhuj has no  jurisdiction   by   judgment   dated   28.1.2011,   the   suit   was  presented   before   the   City   Civil   Court,   Ahmedabad   on  16.3.2013   i.e.   after   25   months   and   15   days   later.  According to GMDCL even after application of section 14 of  the   Limitation   Act,   1963,     the   suit   which   was   ultimately  filed before the City Civil Court, Ahmedabad was barred by  limitation.  It was also canvassed that  the contractor had  Page 5 of 12 C/SCA/14935/2017 JUDGMENT not   presented   the   plaint   returned   by   the   Arbitration  Tribunal but had filed an independent fresh suit before the  Civil Court, Bhuj and that therefore, also the set off could  not be granted for the period spent before the Arbitration  Tribunal. 

6. The contractor opposed such application of GMDCL. Copy  of   registration   of   partnership   firm   was   produced.   On  limitation,   it   was   contended   that   the   period   of   limitation  would   begin   to   run   after   the   issuance   of   notice   by   the  contractor on payment of difference of the unpaid money  and when  GMDCL refused to pay the same. 

7. The   Commercial   Court   by   the   impugned   judgment  dismissed   the   application  of  GMDCL.  On   the   question   of  registration   of   partnership   firm,   it   was   noticed   that   the  contractor had already produced the copy of registration of  firm.   Elaborate   discussion   was   made   on   the   question   of  limitation.   The   suit   was   not   barred   by   limitation.   He  recorded that after the High Court dismissed the petition of  the  contractor,  Bhuj  Court  could  not trace  the  papers  of  the Civil Suit which could be returned after tracing only on  22.1.2013.   Thereafter,   whatever   time   consumed   in  presenting the suit before the  City Civil Court, Ahmedabad  is only about one month and 22 days which would not be  fatal  delay.   On   the  question   of  presentation  of  fresh  suit  before   the   Court   at   Bhuj,   the   Commercial   Court   did   not  accept   the   objection   of   GMDCL.   This   application   for  rejection of the plaint came to be dismissed.

8. Learned   counsel   for   GMDCL   contended   that   the  Page 6 of 12 C/SCA/14935/2017 JUDGMENT Commercial Court committed a serious error of law. Even  going   by   all   the   averments   made   in   the   plaint,   suit   was  barred by limitation and the plaint therefore, should have  been   rejected   under   Order   VII   Rule   11   of   the   CPC.   She  submitted   that   period   of   limitation   for   filing   the   suit   for  recovery proceedings in the contract is three years as per  entry   18   of   the   Limitation   Act   and   the   starting   point   of  limitation is when the work is done. In the present case,  the final bill was settled on 12.11.1999 which would be the  date   from   which   the   period   of   limitation   would   begin   to  run.   She   contended   that   even   after   ignoring   the   period  during   which   the   petitioner   was   pursuing   his   remedies  before the Arbitration Tribunal and the Civil Courts having  no jurisdiction, the suit which was finally filed before the  City Civil Court, Ahmedabad was barred by limitation. For  such purpose, she counted various periods during which  either the suit  was not filed at all or the proceedings were  not pending before any Court. According to her calculation,  filing   of   the   suit   before   the   City   Civil   Court,   Ahmedabad  was barred by limitation. For the sake of arguments, she  would   accept   the   observations   of   the   Commercial   Court  that after the High Court disposed of the writ petition of  the   contractor,   Bhuj   Court   took   considerable   time   in  tracing   out   the   papers   for   returning   the   same   to   the  contractor   for   presentation   before   appropriate   Court.  According to her, even after ignoring such period, the suit  was filed beyond a period of limitation.  She contended that  the plaintiff had not presented the plaint returned by the  Arbitration Tribunal before the Bhuj Civil Court but filed a  fresh suit. 

Page 7 of 12

C/SCA/14935/2017 JUDGMENT

9. On   the   other   hand,   Shri   Parmar   for   the   contractor  submitted   that   period   of   limitation   prescribed   in   the  present case would be one indicated in Article 137 of the  Schedule to the Limitation Act. Period of limitation would  be   three   years   from   the   time   when   the   right   to   apply  accrues.  In his opinion, the  right to  apply accrued when  the contractor issued a notice of further recoveries which  GMDCL did not accept. He also relied on section 14 of the  Limitation Act to contend that the entire period when the  plaintiff   under   bona   fide   belief   was   prosecuting   his  remedies before a Court without jurisdiction should be set  off  for computing limitation.

10. We   are   dealing   in   the   present   case   with   the  application   of   the   defendant   for   rejection   of   plaint   under  Order   VII   Rule   11   of   CPC.   Scope   of   such   application   is  necessarily   circumscribed.   Only   if   upon   perusal   of   the  plaint and the averments made therein as a whole, it can  be concluded that the suit is barred by law, which would  include   law   of   limitation,   same   would   be   rejected   at   the  very threshold. The Commercial Court having rejected such  an application of the defendant, the scope of the present  petition   would   be   further   limited.   We   may   recall   the  Commercial   Courts   Act   specifically   debars   the   revision  against any such interlocutory order. 

11. For the purpose of this petition without laying down  any   proposition   which   would   prejudice   the   rights   and  contentions of the either side, we are prepared to proceed  on the basis that in the present case, period of limitation  would   be   covered   by   Entry   18   of   the   Schedule   to   the  Page 8 of 12 C/SCA/14935/2017 JUDGMENT Limitation Act which prescribes limitation for the price of  work done by the plaintiff for the defendant at his request,  when   no   time   has   been   fixed   for   payment.   Period   of  limitation prescribed is three years and the starting point  to  such limitation  is  when the  work is done. In  essence,  therefore, we are prepared to,   for the limited purpose of  the present petition, accept the contention of the counsel  for the GMDCL that period of limitation would begin to run  from   12.11.1999   when   the   final   bill   was   settled.   The  arbitration   reference   was   filed   by   the   contractor   on  9.11.2001   and   thus   by   the   time   his   first   attempt   at  resolution   of   his   disputes   through   adjudication  commenced on 9.11.2001. Thereafter, as noted, from one  stage   to   another,   his   litigation   got   entangled   in   the  question  whether he  was  before  a proper Court  agitating  his rights. The Arbitration Reference remained pending till  it was withdrawn by him on 2.8.2005 on the ground that  the   Arbitration   Tribunal   does   not   have   jurisdiction.   The  Arbitration   Tribunal   noted   that   the   Tribunal   has   no  specific powers for permitting withdrawal. Nevertheless, in  the   interest   of   justice,   the   contractor   was   allowed   to  withdraw  the reference with a liberty to present it before  the appropriate forum having jurisdiction. The contractor  thereupon   filed   Civil   Suit   before   the   Bhuj   Court   on  20.1.2006.   This   time   consumed   between   the   Tribunal  allowing   withdrawal   of   suit   for   presentation   before   the  appropriate   Court   and   actual   presentation   of   the   suit  before   the   Bhuj   Court   may   also   be   counted   towards   the  limitation   against   the   contractor.   In   addition   to   the   two  years   period   which   was   spent   before   filing   Arbitration  Reference, he thus consumed another five and half months  Page 9 of 12 C/SCA/14935/2017 JUDGMENT in approaching the Civil Court, Bhuj. Thereafter, however  the litigation remained pending right upto 28.1.2011.

12.   Before the Bhuj Court, GMDCL raised the issue of  territorial jurisdiction. Bhuj Court accepted such objection  by an order dated 16.4.2007 ordering return of the plaint  to the contractor for presentation before appropriate Court.  The   contractor   challenged   such   order   first   before   the  District   Court.   When   the   District   Court   ruled   that   the  appeal was not maintainable, he filed a writ petition before  the High Court.  Such writ petition  was dismissed by the  High   Court   on   28.1.2011.   Contention   of   the   counsel   for  GMDCL is that the period in­between when the Civil Court  Bhuj   passed   the   order   returning   the   plaint   and   filing   of  appeal   by   the   contractor   before   the   District   Court   and  thereafter, between the District court dismissing the appeal  on 7.7.2009 and the date of filing of writ petition  by the  contractor   before   the   High   Court   should   be   excluded   for  the   purpose   of   section   14   of   the   Limitation   Act.   This   is  however highly debatable and controversial. One possible  view   could   be   that   all   through   out,   the   litigation   was  pending at some stage or the other. Merely because appeal  was filed challenging the order of Civil Court, Bhuj would  not mean that period consumed in presenting such appeal  would   be   outside   the   purview   of   section   14   of   the  Limitation Act. Once appeal was accepted and entertained,  it would be continuation of litigation and the entire period  could  arguably  be  one   spent  by  the  contractor   bona  fide  pursuing   his   remedies   before   the   Court   albeit   having   no  jurisdiction. There is a long delay between the High Court  dismissing   the   petition   on   28.1.2011   and   the   suit   being  Page 10 of 12 C/SCA/14935/2017 JUDGMENT actually presented before the City Civil Court, Ahmedabad  on   16.3.2013.   However,   as   noted,   the   Commercial   Court  has observed that after the High Court passed such order,  Civil Court, Bhuj took a long time to unearth the papers of  the   suit   and   return   the   same   to   the   contractor   for  presentation   before   appropriate   Court.   If   this   was   so,  surely, the period in question cannot be the exclusion for  the purpose of inclusion in section 14 of the Limitation Act.  As   is   well   known,   sub­section(1)   of   section   14   of   the  Limitation   Act   provides   that   in   computing   the   period   of  limitation for any suit the time during which the plaintiff  has   been   prosecuting   with   due   diligence   another   civil  proceeding,   whether   in   a   Court   of   first   instance   or   of  appeal or revision, against the defendant shall be excluded,  where the proceeding relates to the same matter in issue  and   is   prosecuted   in   good   faith   in   a   Court   from   which  defect   of   jurisdiction   or   other   cause   of   a   like   nature   is  unable to entertain it. Effect of filing fresh suit instead of  presenting   petition   returned   by   the   Tribunal   on   the  plaintiff's   claim   under   Section   14   of   the   Limitation   Act  must be examined during the course of trial. 

13. All   in   all,   it   is   not   a   case   where   the   plaint   can   be  rejected in exercise of powers under Order VII Rule 11 of  CPC. Before closing, we may clarify that nothing stated in  this order would prejudice either side in the pending suit  and without prejudice to the above general prescription,  it  is  clarified  that  it  would  also  be  open  for  the  GMDCL  to  raise the question of limitation in the pending suit which  would   have   to   be   decided   on   the   basis   of   relevant   facts  which may be brought on record through evidence.

Page 11 of 12
         C/SCA/14935/2017                           JUDGMENT




  14.         Petition is disposed of. 

                                                (AKIL KURESHI, J)


                                                   (B.N. KARIA, J)
Raghu




                                Page 12 of 12