Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 2, Cited by 0]

Delhi High Court

Ayg Reality Private Limited vs Nbcc (India) Limited & Anr. on 2 September, 2021

Author: C. Hari Shankar

Bench: C. Hari Shankar

                          *       IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                               Reserved on: 13th August, 2020
                                                           Pronounced on: 2nd September, 2021

                          +       I.A.12354/2019 in CS(COMM)1005/2018

                                  AYG REALITY PRIVATE LIMITED             ..... Plaintiff
                                               Through: Mr. Jayant K. Mehta, Senior
                                                         Adv, Mr. Aman Verma and Mr.
                                                         Anjuman Tripathy, Advs.
                                               versus

                                  NBCC(INDIA) LIMITED AND ANR.           ....Defendants
                                                Through: Mr. Rajinder Wali, Advocate
                                                         with Mr. Ashish Rana, Adv. for
                                                         D-1

                                  CORAM:
                                  HON'BLE MR. JUSTICE C. HARI SHANKAR

                          %              ORDER
                                       (Video-Conferencing)

                          IA 12354/2019 in CS(COMM)1005/2018

                          1.      This order disposes of IA 12354/2019, preferred under Order
                          XXXIX Rules 1 and 2 of the Code of Civil Procedure, 1908 ("the
                          CPC"), whereby the plaintiff has sought interim relief.


                          Facts


                          2.      Defendant No. 1 (hereinafter referred to as "NBCC") invited

Signature Not Verified
                          tenders, for construction of infrastructure at the Subsidiary Training
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                          Page 1 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           Centre for the Border Security Force (BSF) at Chakur, District Latur,
                          Maharashtra. The plaintiff applied, and was awarded the tender, for a
                          total contract value of ₹ 30,06,15,853/-. The project involved for
                          separate "Packages" of work, designated as Package I-A, I-B, II-A
                          and II-B. A tabular representation thereof may be provided thus:


                           Package       Date of Letter Value (₹)      Nature of work
                           No.           of Acceptance
                                         (LOA)
                           I-A           16th January, 7,44,27,503/-   Construction of the Training
                                         2012                          A Building, Training B
                                                                       Building, SOS Mess Building
                                                                       and GOS Mess Building
                           I-B           10th January, 7,60,08,843/-   Construction of MI Hospital
                                         2012                          Building, Shopping Complex,
                                                                       Family Welfare Centre and
                                                                       Barracks 2.
                           II-A          10th January, 9,25,19,742/-   Construction     of    Parade
                                         2012                          Ground,      Stadium      and
                                                                       Swimming Pool
                                                                       (Swimming Pool was later
                                                                       withdrawn)
                           II-B          10th January, 5,76,59,806/-   Construction of Barracks 3, 4,
                                         2012                          5 and 6 (Barracks 5 was later
                                                                       withdrawn)


                          The work was required to be completed within Nine months.


                          3.      The plaintiff predicates its case on Clauses 9, 10, 37.1 and 74 of
                          the General Conditions of Contract (GCC), which governed the
                          contractual relationship between the plaintiff and NBCC.            NBCC
                          relies, for its part, on Clauses 37.1, 37.3 and 67.0 of the GCC. These
                          Clauses read thus:
                                  "9.0   PERFORMANCE GUARANTEE


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                               Page 2 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 Within 10 days (ten) from the date of issue of letter of award
                                or within such extended time as may be granted by NBCC in
                                writing, the contractor shall submit to NBCC a performance
                                bank guarantee in the form appended, from any Nationalized
                                bank, equivalent to 5% (five percent only) of the contract
                                value for the due and proper execution of the contract. This
                                bank guarantee shall remain valid up to 90 (ninety) days after
                                the end of defects liability period.

                                       In case the contractor fails to submit the performance
                                guarantee of the requisite amount within the stipulated period
                                or extended period, letter of intent will stand withdrawn and
                                EMD of contractor shall be forfeited."

                                10.0   SECURITY DEPOSIT/RETENTION MONEY

                                The security deposit or the retention money shall be deducted
                                from each running bill of the contractor at 5% (five percent
                                only) of the gross value of the Running Account will. The
                                Earnest Money Deposited by the tenderer in the form of D.D.
                                only will be treated as part of the security deposit. The
                                lumpsum (consolidated) EMD amount deposited by the
                                Contractor at the time of registration with NBCC shall not be
                                adjusted for security deposit.

                                       The security deposit or retention money shall be
                                refunded to the contractor after expiry of defects liability
                                period (referred to in Clause No. 74) or on payment of the
                                amount of the final bill whichever is later.

                                      If the amount of Security Deposit deduction in cash is
                                more than Rs. 10 lakhs (Rupees Ten Lakhs only), the excess
                                amount can be refunded to contractor against submission of
                                Bank Guarantee of equivalent amount from a Nationalized
                                Bank in the prescribed proforma of NBCC."

                                "37.0 PAYMENTS

                                37.1 The bill shall be submitted by contract are each month
                                on or before the date fixed by the Engineer-in-Charge for all
                                works executed in previous months. The contractor shall
                                prepare computerized bills using the program as approved by
                                Engineer-in-Charge as per the prescribed format/pro forma.
                                The Contractor shall submit five numbers of hard copies and
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                              Page 3 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 one soft copy of floppy/CD for all bills. Subject to clause
                                37.3 herein below, the payment due to the contractor shall be
                                made within fifteen days of getting the measurements verified
                                from        the       Engineer-in-Charge        on        his
                                subordinate/representative and certification of bill by the
                                Engineer-in-Charge.

                                                             *****

                                37.3 It is clearly agreed and understood by the Contractor
                                that notwithstanding anything to the contrary that may be
                                stated in the agreement between NBCC and the contractor,
                                the contractor shall become entitled to payment only after
                                NBCC has received the corresponding payment(s) from the
                                client/Owner for the work done by the contractor. Any delay
                                in the release of payment by the client/Owner to NBCC
                                leading to a delay in the release the corresponding payment
                                by NBCC to the contractor shall not entitle the contractor to
                                any compensation/interest from NBCC."

                                "67.0 SET-OFF OF CONTRACTORS LIABILITIES

                                NBCC shall have the right to deduct or set off the expenses
                                incurred or likely to be incurred by it in rectifying the defects
                                and/or any claim under this agreement against the Contractor
                                from any or against any amount payable to the contractor
                                under this agreement including security deposit and proceeds
                                of performance guarantee."

                                "74.0 DEFECTS LIABILITY PERIOD

                                The contractor shall be responsible for the rectification of
                                defects in the works for a period of 12 months from the date
                                of taking over of the works by the Owner/Client. Any defects
                                discovered and brought to the notice of the contractor
                                forthwith shall be attended to and rectified by him at his own
                                cost and expense. In case the contractor fails to carry out
                                these rectifications, the same may without prejudice to any
                                other right or remedy available, be got rectified by NBCC at
                                the cost and expense of the contractor."

                                                               (Emphasis supplied throughout)


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                                 Page 4 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           4.    The following features are plain, from a reading of the afore-
                          extracted Clauses:


                                (i)    The responsibility of the plaintiff, for rectification of
                                defects, extended only till the expiry of Twelve months from
                                the date of taking over of the works by the "Owner/Client".
                                "Works" and "Owner/Client" are defined, in sub- clauses (b)
                                and (l) of Clause 1.4 of the GCC, as under:
                                       "(b) WORKS OR WORK The expression works or
                                       work shall unless there is something either in the
                                       subject or context repugnant to such construction, be
                                       construed and taken to mean the works by or by virtue
                                       of the contract contracted to be executed whether
                                       temporary or permanent, and whether original, altered,
                                       substituted or additional."

                                       "(l) OWNER/CLIENT means the Government,
                                       Organisation,     Ministry,   Department,  Society,
                                       Cooperative etc. who has awarded the work/Project to
                                       NBCC         and/or      appointed    NBCC        as
                                       Implementing/Executing Agency/Project Manager
                                       and/or for whom NBCC is acting as an agent and on
                                       whose behalf NBCC is entering into the contract and
                                       getting the work executed."

                                The period of Twelve months, for reckoning the Defects
                                Liability Period ("DLP", in short) has, therefore, to be
                                computed from the date of taking over of the works by the
                                Border Security Force (BSF), who awarded the work to NBCC.
                                Clearly, the existence of defects in the work, or their
                                rectification/curing, by the plaintiff, is not relevant, for
                                assessing the DLP. The DLP extends only till the expiry of
                                Twelve months from the date of taking over of the work by the
                                BSF.    Clause 74.0 requires NBCC to communicate, to the
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 5 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 plaintiff, defects in the work, if any, within the said period of
                                Twelve months. The liability of the plaintiff to rectify the
                                defects extends only to that effect which are so brought to his
                                notice within the said period of Twelve months. The plaintiff
                                has no liability in respect of any defects in the work, to which
                                its notice is invited after the expiry of Twelve months from the
                                taking over of the work by the BSF.           At the same time,
                                intimation, to the plaintiff, of the existence of defects, and their
                                rectification, by the plaintiff, thereof, had no effect on the
                                operation of Clause 74.0, insofar as the Twelve months'
                                terminus ad quem of the DLP is concerned. Any which way, on
                                the expiry of Twelve months from the date of taking over of the
                                work by the BSF, the DLP comes to an end.


                                (ii)   The expression "works", as employed in Clause 74.0, is
                                also of no little significance. The submission of Mr. Mehta is
                                that Clause 74.0 is to apply on a building-wise basis, and not on
                                a Package-wise basis, whereas Mr. Wali would contend, per
                                contra, that Clause 74.0 is to be reckoned for each Package, and
                                not for each building. Mr. Mehta has, in this context, placed
                                reliance on a communication, dated 23rd April, 2018, from
                                NBCC to the plaintiff, which sets out the "actual DLP status",
                                as per the NBCC, building-wise. It is also asserted, in the said
                                communication, inter alia, that "the DLP of SOS Mess
                                completed but as on date you have not installed the solar water
                                heating at SOS building." The letter contains separate tabular
                                representations, for each Package, on a building-wise basis,
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 6 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                     explaining why, according to NBCC, the DLP, for the said
                                    building, was as yet not concluded. This communication, in my
                                    view, prima facie supports the submission of Mr. Mehta that the
                                    DLP was required to be computed on a building-wise, rather
                                    than a Package-wise, basis. Clauses in contracts, which admit
                                    of ambiguity, or suffer from any want of clarity, may be
                                    interpreted in the light of the manner in which the clauses are
                                    understood by the parties to the contract, as manifested by their
                                    actions, as held in Godhra Electricity Co. v. State of Gujarat1
                                    and Mukul Sharma v. Orion India Pvt Ltd2.


                                    (iii)   The      buildings     under     the   Four   Packages      were
                                    handed/taken over to the BSF, as follows:

                                                  Package           Buildings             Actual Date of
                                                                                          Handing over
                                             Package I-A            Training A             01.11.2014
                                                                    Training B             03.12.2013
                                                                       SOS                 16.11.2016
                                                                      GOS                  19.05.2018
                                                                   MI Hospital             05.08.2014
                                             Package I-B         Shopping Complex          16.11.2016
                                                             Family WelfareCentre          26.05.2015
                                                                    Barrack 2              30.03.2019
                                             Package II-B           Barrack 3              30.04.2013
                                                                    Barrack 4              09.09.2017
                                                                    Barrack 6              19.06.2017



                          1
                              (1975) 1 SCC 199
                          2
                              (2016) 12 SCC 623
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                                      Page 7 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 (iv)   The expiry of the DLP does not, however, unfortunately,
                                crystallise any right, in favour of the plaintiff, to the reliefs
                                sought in this application. The plaintiff's essential claim is to
                                refund of the Security Deposit and return of the One remaining
                                PBG and the SBGs. These are governed by Clauses 9 and 10 of
                                the GCC.


                                (v)    Clause 9.0 requires the petitioner to submit to NBCC,
                                within Ten days of issuance of letter of award of the contract
                                (subject to extension by NBCC), PBG, equivalent to 5% of the
                                total contract value, and further requires the PBG to remain
                                valid till the expiry of Ninety days after the DLP ends. As the
                                PBG, in respect of Package II-A continued to remain alive till it
                                was invoked by NBCC on 30th June, 2018, Clause 9 does not
                                call for application.


                                (vi)   Clause 10.0 specifically envisages refund, of the security
                                deposit, by NBCC to the plaintiff. This, however, is to take
                                place after expiry of the DLP, or on payment of the Final Bill
                                raised by the plaintiff, whichever is later.


                                (vii) Clause 10.0 has to be read in juxtaposition with Clauses
                                37.1 and 37.3 of the GCC. Clause 37.1 is made subject to
                                Clause 37.3 and, to counterbalance, Clause 37.3 incorporates a
                                non obstante covenant; accordingly it has pre-eminence over all
                                other Clauses in the agreement between the plaintiff and
                                NBCC.
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 8 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 (viii) Clause 37.1 requires payment, due to the plaintiff, to be
                                made by NBCC within Fifteen days of getting the
                                measurements verified from the Engineer-in-Charge or his
                                representative, and certification of the bill by the Engineer-in-
                                Charge. Clause 37.3 records the agreement and understanding,
                                of the plaintiff, that the plaintiff would be entitled to payment
                                only after NBCC received the corresponding payment from
                                BSF for the concerned work.


                                (ix)   In order to claim entitlement to payment against any bill,
                                therefore, the plaintiff has, contractually, to establish that (a)
                                the measurements have been verified by the Engineer-in-Charge
                                or his subordinate/representative, (b) the bill has been certified
                                by the Engineer-in-Charge and (c) NBCC has received payment
                                of the amount, covered by the bill, from BSF.


                                (x)    The result is that the contractor cannot, merely by virtue
                                of the DLP having expired, or come to an end, seek the return
                                of the SBGs furnished by it.


                                (xi)   The PBGs were to remain alive till the expiry of Ninety
                                days from the end of the DLP. Once the DLP had expired, on a
                                building-wise basis, then, in respect of those buildings which
                                had been taken over by the BSF, Clause 9.0 requires the life of
                                the PBG, to that extent, to continue only for a period of Ninety
                                more days.


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 9 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           5.      For the purposes of the present application, and the present
                          order, it is not necessary to enter, in detail, into the allegations and
                          counter allegations in the suit.         A brief reference is, however,
                          necessary. The contract was awarded, by NBCC to the plaintiff, in
                          Four Packages - Package I-A, Package I-B, Package II-A and Package
                          II-B. Each Package was covered by a separate Letter of Acceptance
                          (LOA). The LOA, covering Packages I-B, II-A and II-B, were issued
                          on 10th January, 2012, whereas the LOA covering Package I-A was
                          dated 16th January, 2012.      Each Package required the plaintiff to
                          construct the buildings/structures covered thereby.       This may be
                          presented, in a tabular fashion, thus:
                           Package Date of LOA          Value      of Buildings covered by
                                                        Package (₹)   Package
                           I-A        16th     January, 7,44,27,503/- (1) Training           A
                                      2012                                 Building
                                                                      (2) Training B Building
                                                                      (3) SOS Mess Building
                                                                      (4) GOS Mess Building
                           I-B        10th     January, 7,60,08,843/- (1) MI           Hospital
                                      2012                                 Building
                                                                      (2) Shopping Complex
                                                                      (3) Family        Welfare
                                                                           Centre
                                                                      (4) Barrack No. 2
                           II-A       10th     January, 9,25,19,742/- (1) Parade Ground
                                      2012                            (2) Stadium
                                                                      (3) Swimming        Pool
                                                                           (later withdrawn)
                           II-B       10th     January, 5,76,59,806/- (1) Barrack No. 3
                                      2012                            (2) Barrack No. 4
                                                                      (3) Barrack No. 5 (later
                                                                           withdrawn)
                                                                      (4) Barrack No. 6



Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 10 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           6.      As required by the General Conditions of Contract (GCC),
                          applicable to the contract between the plaintiff and NBCC, the
                          following     Performance     Bank    Guarantees    (PBGs)     and   Bank
                          Guarantees towards Security Deposit (SBGs) were furnished by the
                          plaintiff to NBCC, towards Packages I-A, I-B and II-B (the present
                          application does not concern Package II-A):
                           Package          B/G No.               PBG/SBG      B/G Amount (₹)
                           I-A              00061PEBG120004       PBG          37,21,400/-
                                            00061PEBG150019       SBG          5,85,927/-
                                            00061PEBG140027       SBG          11,42,000/-
                                            00061PEBG170012       SBG          6,97,000/-
                           I-B              00061PEBG120002       PBG          38,00,500/-
                                            00061PEBG150018       SBG          8,67,910/-
                                            00061PEBG140028       SBG          8,42,000/-
                                            00061PEBG170013       SBG          3,91,000/-
                           II-B             00061PEBG120003       PBG          28,83,000/-
                                            00061PEBG150020       SBG          10,15,808/-
                                            00061PEBG140030       SBG          19,90,000/-
                                            00061PEBG170015       SBG          4,54,000/-


                          7.      Though, by the time of filing of the present suit, and even at this
                          stage of amendment thereof, some of the Bank Guarantees had been
                          invoked and encashed by NBCC (in respect to Package II-A). The
                          amounts covered by the PBGs issued in respect of Packages I-A (₹
                          37,21,400/-) and II-B (₹ 28,83,000/-) were, subsequently, released to
                          the plaintiff on 7th July, 2020. The prayers in the plaint seek return, by
                          NBCC, of the amounts covered by the Bank Guarantees invoked by it,
                          as well as of the Security Deposit furnished by the plaintiff and a
                          restraint against NBCC from invoking any further Bank Guarantees,
                          and the direction, to NBCC, to return all the Bank Guarantees to the
                          plaintiff. The prayer clause in the present IA, preferred under Order
                          XXXIX Rules 1 and 2 of the CPC, reads as under:
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 11 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 "In the aforesaid circumstances,         the   Plaintiff   most
                                respectfully prays that:

                                       (i)    This Hon'ble Court may be pleased to order and
                                       direct the Defendant No. 1 to finalize the final bills
                                       raised by the Plaintiff with respect to 'Package I-A',
                                       'Package I-B' and 'Package II-B' vide letters dated
                                       24.07.2019, 26.04.2019 and 10.08.2018 respectively in
                                       a specific time frame.

                                       (ii)   This Hon'ble Court may be pleased to order and
                                       direct the Defendant No.1 to return, release and hand
                                       over to the Plaintiff all the 12 (twelve) Bank
                                       Guarantees with immediate effect, details of which are
                                       as herein below (tabular statement of the Bank
                                       Guarantees);

                                       (iii) Alternatively, order and direct the Defendant
                                       No.1 to return, release and hand over to the Plaintiff
                                       the 08 (eight) Bank Guarantees with immediate effect
                                       with respect to the Bank Guarantees of 'Package I-A'
                                       and 'Package II-B' and to refund/return proportionate
                                       Bank Guarantees qua 'Package I-B' since the defects
                                       liability period of 3 out of the 4 buildings in the said
                                       package are over and one building is ready for
                                       possession.

                                       (iv) This Hon'ble Court may be pleased to order and
                                       direct the Defendant No.1 to return, release, refund
                                       and/or pay over the security deposit of an amount of ₹
                                       65,00,000/- (Rupees Sixty Five Lakhs only) lying with
                                       it in cash, back to the Plaintiff without any claim or
                                       demand thereunder on any count, whatsoever;

                                       (v)    This Hon'ble Court may be pleased to order and
                                       direct the Defendant no.1 to return, release, refund
                                       and/or pay over to the Plaintiff all the pending deposits
                                       and amounts etc. under the Project Contract lying with
                                       it and by whatever name called and in whichever form
                                       whether lying with the Defendant No.1 or any other
                                       person;


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                               Page 12 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                        (vi) This Hon'ble Court may be pleased to permit
                                       the Plaintiff to remove its construction material, tools
                                       and equipment lying on the project site;

                                       (vii) Ad-interim reliefs in terms of prayer clause (i)
                                       to (v);

                                       (viii) Any other such reliefs as this Hon'ble Court
                                       may deem fit and proper in the facts and circumstances
                                       of the case."


                          8.    According to the plaint, owing to unavoidable circumstances -
                          for a large part of which the plaintiff blames NBCC - the plaintiff
                          was unable to meet the milestones fixed by NBCC, from time to time.
                          As a result, various communications were addressed, by the plaintiff
                          to NBCC, inter alia on 26th September, 2012, 6th June, 2013, 9th
                          April, 2015, 10th June, 2015, 5th September, 2017, 24th January, 2018,
                          1st February, 2018, 15th February, 2018, 19th April, 2018, 12th May,
                          2018 and 26th June, 2018. Ultimately, NBCC granted the plaintiff
                          Nine months extension for completing the project which, according
                          to the plaintiff, was unreasonable.


                          9.    The plaint also alleges that there was continuous default, on the
                          part of NBCC, in making prompt payment of the bills raised by the
                          plaintiff and that, in certain cases, payment was delayed by as long as
                          a year.    When payment was made, it is alleged that arbitrary
                          deductions were effected from the bills, by NBCC suo motu. This, it
                          is alleged, violated Clause 37.1 of the GCC, which required
                          payments, against bills raised by the plaintiff, to be cleared within
                          Fifteen days from certification by the Engineer-in-Charge of NBCC.
                          The plaintiff alleges that, in violation of this covenant, NBCC, citing
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                              Page 13 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           frivolous administrative and technical reasons, failed to clear the
                          plaintiff's bills in time, and repeatedly sought accommodation,
                          pleading scarcity of funds.          This, it is submitted, resulted in
                          unnecessary financial burden on the plaintiff, which also adversely
                          affected progress of the work on the Project. It is also asserted, in the
                          plaint, that meetings were held, between the plaintiff and NBCC on
                          5th July, 2013 and 16th July, 2013, which were duly minuted, and in
                          which NBCC undertook to conduct joint measurement of the work
                          done by the plaintiff and release the payment within Seven days, as
                          well as to provide maximum assistance to the plaintiff, to complete
                          the Project within time. Even so, it is alleged that, from January to
                          December, 2015, the plaintiff's payments were not released in time
                          owing to financial difficulties being faced by NBCC. Reliance has
                          been placed, in this regard, on letters dated 9th April, 2015, 1st June,
                          2015, 9th June, 2015, 10th June, 2015, 11th June, 2015, 2nd July, 2015,
                          28th August, 2015, 8th October, 2015 and 16th December, 2015, from
                          the plaintiff to NBCC. It was only in early 2016 that, consequent to
                          assurances extended by NBCC, the plaintiff agreed to restart the
                          work. This, it is submitted, was reduced, by the plaintiff, in writing,
                          vide letter dated 16th December, 2015 addressed to NBCC.


                          10.    All   these   facts,   though     undoubtedly   interesting   and
                          informative, do not really advance adjudication of the present
                          application. Prayer (i) in the application refers to letters dated 24 th
                          July, 2019, 26th April, 2019 and 10th August, 2018, whereunder final
                          bills, in respect of Packages I-A, I-B and II-B, were raised by the
                          plaintiff.   It would be relevant, therefore, to refer to the said
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 14 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           communications, and what happened to them, as the plaintiff seeks
                          interlocutory directions to NBCC to finalise the said final bills. For
                          this purpose, a chronological excursion through the communications
                          between the parties, howsoever tedious, is essential.


                          11.   Communications between NBCC and plaintiff:


                          11.1 The original time stipulated, for completion of work under the
                          contract, expired on 9th October, 2012.


                          11.2 On 5th March, 2013 and 7th May, 2013, NBCC wrote to the
                          plaintiff, requiring it to rectify the defects in Barrack 3 (Package II-
                          B). Thirteen civil works and Nine electrical works, requiring to be
                          done, were enumerated.


                          11.3 On 25th April, 2013, NBCC wrote to the plaintiff, drawing its
                          attention to Seventeen works remaining to be done in Training
                          Building-B (Package I-A) and pointing out that the Building was
                          scheduled to be inaugurated by the Home Minister on 11 th May,
                          2013. As such, the plaintiff was directed to complete the work on
                          war footing basis.


                          11.4 The plaintiff's assertion that Barrack 3 (Package II-B) was
                          completed and handed over in September 2012 and that Training
                          Building B was completed on 31st March, 2013, was denied, by
                          NBCC, in its letter dated 31st May, 2013, to the plaintiff. The letter
                          again highlighted the defects in Barrack 3. It was further stated, in
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 15 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           the said communication, that, in exercising its right under Clause
                          72.1 of the GCC, NBCC had withheld amounts, liable to be
                          recovered from the plaintiff in respect of the works related to
                          Package II-B, as the contract was scheduled to expire on 30th April,
                          2013, and no completion program had been received from the
                          plaintiff. The letter also referred to defects in Barracks 4, 5 and 6
                          (Package II-B). It was further alleged that the Family Welfare Centre
                          (Package I-B), the SOS Mess (Package I-A), GOS Mess (Package I-
                          A), MI Hospital (Package I-B) and Shopping Complex (Package I-B)
                          were not complete. Defects, pointed out in respect of Barrack 3, it
                          was reiterated, were yet to be addressed and that the BSF Board had
                          declined to take over the said Building, for that reason.      In the
                          circumstances, the plaintiff was directed to show cause as to why sub
                          clauses (ii) to (iv) of Clause 72.2 of the GCC be not invoked by
                          NBCC.


                          11.5 On 6th June, 2013, the plaintiff responded to the aforesaid
                          Show Cause Notice dated 31st May, 2013. Apropos Barrack 3, it was
                          asserted that the building was complete and in occupation by the BSF
                          since September 2012. It was further pointed out that the Building
                          had been inaugurated by the IG, BSF, on 16th January, 2013. The
                          DLP, in respect of Barrack 3, therefore, it was submitted, had
                          commenced in September, 2012. In a somewhat contradictory vein,
                          however, the same communication went on to state that the plaintiff
                          would hand over, to NBCC, Barrack 3 (Package II-B), Training
                          Building-B (Package I-A), Training Building-A (Package I-A), the
                          MI Building (Package I-B) and the Family Welfare Centre (Package
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                         Page 16 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           I-B) within 4 months, and would complete the RCC work in Barrack-
                          6 (Package II-B), the SOS Mess (Package I-A), GOS Mess (Package
                          I-A), Barrack-2 (Package I-B) and Barrack-4 (Package II-B) within 4
                          months, and in the Shopping Centre (Package II-A) and Barrack-5
                          (Package II-B) within 8 to 10 months.


                          11.6 On 6th June, 2013, NBCC wrote to the plaintiff, reiterating its
                          request for completion of Training Building-B (Package I-A). The
                          letter alleged that the plaintiff had not yet completed the first floor of
                          the said Building, but that the Building was inaugurated as per
                          programme on 2nd June, 2013. NBCC further stated that it had taken
                          the initiative to formally hand over the building to the BSF, but that,
                          in order to initiate the proceedings, incomplete work was required to
                          be first completed. Fifteen items of work, requiring attention, were
                          enumerated in the letter.


                          11.7 The plaintiff was once again requested by NBCC, vide letter
                          dated 2nd July, 2013, to immediately rectify the defects which
                          remained in Barrack-3 (Package I-B) and Training Building-B
                          (Package I-A). Vide a subsequent communication, dated 25th July,
                          2013, NBCC informed the plaintiff that defects, in Training Building-
                          B (Package I-A) were persisting, and that the BSF had adversely
                          commented on this aspect during the process of handing over/taking
                          over inspection.


                          11.8 The plaintiff responded, vide letter dated 19th September, 2013,
                          stating that the defects, pointed out in Barrack-3 (Package II-B) and
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 17 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           Training Building-B (Package I-A) had been rectified. The NBCC
                          was, therefore, requested to expedite the process of handing
                          over/taking over of Barrack-3 (Package II-B) and Training Building-
                          B (Package I-A).


                          11.9 On 11th November, 2013, NBCC wrote to the plaintiff, alleging
                          that major rectification work continued to remain unfinished in
                          Barrack-3 (Package II-B) and Training Building-B (Package I-A), as
                          well as in the MI Hospital (Package I-B). In the circumstances,
                          NBCC stated that it was left with no alternative but to impose
                          Liquidated Damages, owing to the delay, attributable to the plaintiff,
                          in completion of the aforesaid buildings. It was stated, in the said
                          letter, that (i) the completion date had been crossed in respect of
                          Training Building-A (Package I-A), the GOS Mess (Package I-A),
                          the SOS Mess (Package I-A), the MI Building (Package I-B), Family
                          Welfare Centre (Package I-B), and Barracks 4 and 6 (Package II-B),
                          but the buildings were still incomplete, and that (ii) the Completion
                          Date was yet to reach in respect of the Shopping Complex (Package
                          I-B), Barrack-2 (Package I-B) and Barrack-5 (Package II-B). The
                          plaintiff was, therefore, requested to submit its final completion
                          programme.


                          11.10 NBCC further alleged, vide its communication dated 3rd
                          December, 2013, addressed to the plaintiff, that defects continued to
                          remain in Training Building-B (Package I-A) and the MI Building
                          (Package I-B). Further, vide communication dated 20th August, 2014,
                          NBCC alleged that defects were noticed by the BSF, at the time of
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                          Page 18 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           handing over/taking over of the MI Hospital Building as intimated by
                          the BSF vide letter dated 13th August, 2014.         The plaintiff was,
                          therefore, requested to rectify the said defects without delay.


                          11.11 On 9th October, 2014, NBCC again wrote to the plaintiff,
                          stating that, during handing over/taking over of Training Building-B
                          (Package I-A), Barrack-3 (Package II-B) and the MI Hospital
                          Building (Package I-B), various defects were found, which were
                          required to be rectified at the earliest. This was followed by further
                          communications dated (i) 13th January, 2015, alleging persistence of
                          defects in Training Building-B (Package I-A), the MI Hospital
                          Building (Package I-B), Barrack-3 (Package II-B), (ii) 16th January,
                          2015, alleging existence of defects in the Shopping Complex
                          (Package I-B) and (iii) 21st February, 2015, alleging existence of
                          defects in Training Building-B (Package I-A) and the Family Welfare
                          Centre (Package I-B).


                          11.12 The plaintiff wrote, on 9th April, 2015, to NBCC, requesting
                          for extension of time, without liquidated damages, for completion of
                          Package I-B.


                          11.13 On 8th May, 2015, the plaintiff wrote to NBCC, asserting that,
                          out of Fourteen buildings, it had completed Six and handed over the
                          buildings to NBCC. The plaintiff also requested for escalation, for
                          the period by which completion of work under the contract had got
                          extended beyond the originally stipulated period of Nine months.
                          This was followed by a communication dated 1st June, 2015, in which
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 19 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           the plaintiff asserted that Barrack-3 (Package II-B), Training
                          Building-A (Package I-A), Training Building-B (Package I-A), the
                          MI Hospital (Package I-B), the Family Welfare Centre (Package I-B)
                          and the Shopping Complex (Package I-B) had been completed and
                          handed over and that the SOS Building (Package I-A), GOS Building
                          (Package I-A) and Barracks 2 (Package I-B), 4, 5 and 6 (Package II-
                          B) were nearing completion.          Escalation, beyond the originally
                          stipulated period of 9 months, was again sought, and also extension
                          of time without liquidated damages.


                          11.14 On 2nd June, 2015, NBCC wrote to the plaintiff, alleging that
                          the plaintiff had failed to adhere to the stipulated milestones in the
                          contract and that much of the work continued to be defective or
                          incomplete. It was also asserted, in the said communication, that
                          almost all payments to the plaintiff stood paid.


                          11.15 On 10th June, 2015, the plaintiff again wrote to NBCC,
                          reiterating that Six out of the Fourteen buildings contracted, i.e.
                          Barrack-3 (Package III-B), Training Building-A (Package I-A),
                          Training Building-B (Package I-A), the MI Hospital (Package I-B),
                          Family Welfare Centre (Package I-B) and Shopping Complex
                          (Package I-B) had been completed and handed over, and that the
                          remaining Eight buildings were in the process of completion. The
                          plaintiff also blamed NBCC for delay in progress of the work,
                          attributing it to an availability of cash flow and free funds. In order
                          to complete the remaining work, the plaintiff sought extension of
                          time without liquidated damages, escalation and payment of its
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                          Page 20 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           pending bills. The request for payment of its pending bills was
                          reiterated by the plaintiff, vide its letter dated 2nd July, 2015, to
                          NBCC.


                          11.16 On 3rd October, 2015, NBCC again wrote to the plaintiff,
                          assuring the plaintiff that there was no fund problem and that "as the
                          work progress, you will be paid immediately".            The following
                          assurance was contained in the said communication:
                                "Please recall our discussion held on 26-8-2015 with
                                undersigned in SBG office, Mumbai, and it was informed that
                                there is no fund problem, and as the work progress, you will
                                be paid immediately.

                                In spite of various incomplete items/non executed items
                                included in bill passed, payment of Package I/Part B has been
                                released to you, on your firm assurance that you will resume
                                the work immediately and further payment on expeditious
                                completion of incomplete items etc progressively.

                                You are advised to start the work immediately to enable us to
                                release payment as work progress."

                          11.17 Again, on 5th December, 2015, NBCC wrote to the plaintiff,
                          alleging that defects continued to persist in the MI Hospital Building,
                          Family Welfare Centre and Shopping Complex, in Package I-B. This
                          was followed by communications dated 10th June, 2016, 1st July, 2016,
                          2nd July, 2016th and 16th July, 2016, from NBCC to the plaintiff,
                          alleging persistence of defects in the MI Hospital Building (Package I-
                          B), GOS Mess (Package I-A), SOS Mess (Package I-A), Family
                          Welfare Centre (Package I-B), Training Building-A and Training
                          Building-B (Package I-A).


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 21 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           11.18 On 28th July, 2016, BSF wrote to NBCC, stating that the
                          Barracks (Packages I-B and II-B), GOS Mess (Package I-A) and SOS
                          Mess (Package I-A) were yet to be completed. This message was
                          forwarded by NBCC to the plaintiff on 1st August, 2016.


                          11.19 Persistence of the defects in the SOS Mess (Package I-A) and
                          Shopping Complex (Package I-B) was again alleged, by NBCC, in its
                          subsequent communication dated 20th January, 2017, to the plaintiff,
                          based on complaints received from the BSF in that regard.


                          11.20 On 12th February, 2017, the plaintiff forwarded, to NBCC, the
                          deviation statements in respect of Packages I-A, I-B and II-A.


                          11.21 On 23rd March, 2017, BSF wrote to NBCC, informing that,
                          during the inspection prior to handing over/taking over, Barrack-6
                          (Package II-B) was inspected by the BSF, and several shortcomings,
                          in civil and electrical works, were noticed, which were also shown to
                          the representative of the plaintiff, present at the site.   The letter
                          attached a list of the shortcomings, Twenty Six in number, with a
                          request that all shortcomings be rectified at the earliest. This was
                          reiterated by the BSF, in its subsequent communication dated 21 st
                          April, 2017, which was forwarded by NBCC to the plaintiff on 25th
                          April, 2017.


                          11.22 On 19th June, 2017, BSF wrote to the NBCC, again intimating
                          the NBCC that, on inspection, seepage was found in Training
                          Building-A (Package I-A), the SOS Mess (Package I-A), as well as in
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                          Page 22 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           Training Building-B (Package I-A) and Barracks 2 (Package I-B), 3
                          (Package II-B) and 6 (Package II-B). This, it was pointed out, was
                          required to be rectified. The complaint was forwarded by NBCC to
                          the plaintiff on 21st June, 2017.


                          11.23 On 7th August, 2017, BSF again wrote to NBCC, drawing its
                          attention to defects which persisted in Barrack-6 (Package II-B), and
                          calling for their rectification. This was communicated by NBCC to
                          the plaintiff on 12th August, 2017.


                          11.24 On 13th September, 2017, BSF again wrote to NBCC, alleging
                          that shortcomings were still found pending in Barracks 4 and 6
                          (Package II-B), before handing over/taking over. It was requested that
                          this pending work be completed at the earliest. The request was
                          communicated by NBCC to the plaintiff under cover of letter dated
                          22nd September, 2017.


                          11.25 On 28th September, 2017, NBCC wrote to the plaintiff, alleging
                          that the plaintiff's claims for excess work having been undertaken by
                          it were not reflected from the position on the ground. Defects in the
                          SOS Mess (Package I-A) were also referred to. It was further alleged
                          that work was still incomplete in Barrack-5 (Package II-B).


                          11.26 On 6th October, 2017, the plaintiff wrote to NBCC, stating, inter
                          alia, that the 26th RA Bill raised by the plaintiff on 24th August, 2017
                          for Package I-A was still awaiting payment, those certified by NBCC
                          for ₹ 9,54,287/-. Prompt payment was requested.
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 23 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           11.27 Vide communications dated 7th November, 2017, NBCC alleged
                          that work relating to Packages I-A and II-B was still incomplete,
                          despite the expiry of the last date stipulated in that regard. Provisional
                          extension of time was granted, therefore, to 30th November, 2017,
                          reserving the right of NBCC to recover liquidated damages as per the
                          GCC. The plaintiff was directed to intimate the proposed programme
                          for completion of the remaining work.


                          11.28 On 22nd December, 2017, BSF again wrote to NBCC,
                          communicating the shortcomings/defects which still persisted in
                          Barrack-6 (Package II-B).      This was forwarded by NBCC to the
                          plaintiff on 2nd January, 2018, with the request that the defects be
                          rectified. On the same day, i.e. 2nd January, 2018, NBCC forwarded,
                          to the plaintiff, defects noticed by the BSF in respect of Barrack-4
                          (Package II-B), with a request that they be attended to, immediately.


                          11.29 On 24th January, 2018, the plaintiff wrote to NBCC, asserting
                          that the work relating to Packages I-A and II-B had been completed,
                          and the work relating to Package I-B was also completed except one
                          building, i.e. Barrack-2, which would be completed shortly.           The
                          attention of NBCC was drawn to the pending payments of the
                          plaintiff, with a request that the payments be expeditiously released,
                          extension of time be granted without liquidated damages and the
                          deviation file submitted by the plaintiff be approved.




Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 24 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           11.30 NBCC, vide its response, dated 25th January, 2018, to the
                          aforesaid letter dated 24th January, 2018, of the plaintiff, denied the
                          submission, of the plaintiff, that work relating to Packages I-A and II-
                          B was completed, or that the work relating to Package I-B was
                          completed, except for Barrack 2. Rather, submitted NBCC,
                                (i)     in respect of Package I-A,
                                        (a)    despite repeated communications, the defects in
                                        Training Building-A and Training Building-B were yet to
                                        be rectified by the plaintiff;
                                        (b)    solar water heating system was not yet installed in
                                        the SOS Mess, though the building had been handed over
                                        on 16th November, 2016, due to which reason "this board
                                        proceeding has not been concluded for starting the defect
                                        liability period" and
                                        (c)    work was still in progress in the GOS Mess;
                                (ii)    in respect of Package I-B,
                                        (a)    defects, pointed out in respect of the Shopping
                                        Complex, MI Hospital and the Family Welfare Centre,
                                        were yet to be rectified, and
                                        (b)    work, in respect of Barrack-2, was not progressing
                                        well since long, and


                                (iii)   in respect of Package II-B,
                                        (a)    Barracks 3, 4 and 6 had been handed over on 30 th
                                        April, 2013, 9th September, 2017 and 19th June, 2017, but
                                        rectification therein were yet to be carried out, and


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 25 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                         (b)    Barrack 5 had been withdrawn from the scope of
                                        work of the plaintiff, and would be executed otherwise, at
                                        the risk and cost of the plaintiff.


                          No payments of the plaintiff, it was asserted, had been unjustifiably
                          withheld by NBCC.


                          11.31 The plaintiff rejoined to the aforesaid communication, dated
                          25th January, 2018, of NBCC, vide letter dated 10th February, 2018, re-
                          asserting that
                                (i)     in Package I-A,
                                        (a)    Training Building-A, Training Building-B, the
                                        SOS Mess and the GOS Mess were handed over, to
                                        NBCC, on 20th September, 2014, 2nd June, 2013, 8th
                                        February, 2017 and 24th January, 2018, respectively,
                                        (b)    resultantly, the DLP, in respect of Training
                                        Buildings-A and B, and the SOS Mess, stood completed,
                                        whereas the DLP, in respect of the GOS Mess was still
                                        continuing,
                                (ii)    in Package I-B, the MI Hospital, Shopping Complex and
                                Family Welfare Centre had been handed over on 15 th
                                December, 2013, 21st February, 2015 and 21st January, 2015,
                                respectively, and the DLP, in respect of all 3 buildings, already
                                stood completed, and
                                (iii)   in Package II-B,




Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 26 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                         (a)    Barracks-3, 4 and 6 had been handed over on 30 th
                                        April, 2017, 9th September, 2017 and 1019 June, 2017,
                                        respectively, and
                                        (b)    consequently, the DLP, in respect of Barrack 3
                                        stood completed, whereas the DLP in respect of Barracks
                                        4 and 6 was still continuing.
                          The plaintiff further submitted that payment of its bills was being
                          unjustifiably delayed.


                          11.32 NBCC again wrote to the plaintiff on 7th March, 2018, alleging
                          that rectification of the enlisted defects, in the SOS Mess (Package I-
                          A) was still incomplete, and requesting the plaintiff to remedy the
                          situation at the earliest.


                          11.33 Vide letter dated 10th March, 2018, NBCC responded to the
                          communication dated 10th February, 2018 supra of the plaintiff, to the
                          following effect, in respect of the various Packages of work:
                                 (i)    in Package I-A, though all 4 buildings had been handed
                                 over on the dates indicated by the plaintiff,
                                        (a)    the DLP, for Training Building-A, Training
                                        Building-B and the SOS Mess, was "not concluded as on
                                        date due to non-completion of rectification of defects",
                                        and
                                        (b)    the work in respect of the GOS Mess was still
                                        incomplete on the date of handing over,
                                 (ii)   in Package I-B,


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                          Page 27 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                         (a)   though the MI Hospital Building, Shopping
                                        Complex and Family Welfare Centre had been handed
                                        over on the dates indicated by the plaintiff, the DLP, in
                                        respect thereof, was "not concluded as on date due to
                                        non-completion of rectification of defects", and
                                        (b)   work, in respect of Barrack-2, was not progressing
                                        well, and
                                (iii)   in Package II-B, too, though all 3 buildings (Barracks 3, 4
                                and 6) had been handed over on the dates indicated by the
                                plaintiff,
                                        (a)   the DLP, in respect of Barrack-3, was "not
                                        concluded as on date due to non-completion of
                                        rectification of defects", and
                                        (b)   the DLP, in respect of Barracks-4 and 6 was yet to
                                        commence, as "rectification of defects/balance works had
                                        not yet been completed".


                          11.34 On 19th April, 2018, the plaintiff again wrote to NBCC, inter
                          alia reiterating its earlier stand regarding handing over of the
                          buildings and status of completion of DLP, in respect of Packages I-A,
                          I-B and II-B. NBCC was once again requested to release the pending
                          payments of the plaintiff. NBCC, in its response dated 23 rd April,
                          2018, also reiterated its stand, as already conveyed to the plaintiff on
                          10th March, 2018. The plaintiff, too, in its communication dated 12th
                          May, 2018, addressed by way of response thereto, reiterated its stand.




Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 28 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           11.35 In the interregnum, on 8th May, 2018, the BSF wrote to NBCC,
                          alleging that defects continued to persist in the SOS Building
                          (Package I-A), and requesting that they be rectified so that the BSF
                          could recheck the defect/shortcomings "to complete the handing
                          taking over process". The said letter was forwarded by NBCC to the
                          plaintiff on 11th May, 2018, requesting that necessary remedial action
                          be taken.


                          11.36 On 15th May, 2018, NBCC wrote to the plaintiff, advising the
                          plaintiff to submit the Final Bill for Package IA in accordance with
                          Clause 43.6 of the GCC. Para-3 of the communication further stated
                          that, though Clause 37.3 of the GCC required payments to be made,
                          by NBCC to the plaintiff only on receipt of corresponding payment
                          from BSF, NBCC was releasing payment in the interests of work to
                          expedite the progress of work at site.


                          11.37 On 16th May, 2018, NBCC wrote to the plaintiff, granting
                          extension of time for completion of the work relating to Packages I-A
                          and II-B, as sought by the plaintiff, till 30th June, 2018, subject to levy
                          of liquidated damages.


                          11.38 Four Show Cause Notices were issued by the NBCC to the
                          plaintiff on 20th June, 2018, under sub- clauses (i) to (xi) of Clause
                          72.2 of the GCC, one for each Package, threatening the plaintiff with
                          cancellation of the contract for any Package in respect of which the
                          plaintiff failed to remedy the defaults, within 7 days.


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 29 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           11.39 The plaintiff responded on 26th June, 2018, reiterating the
                          submissions already advanced by it earlier.


                          11.40 On 30th June, 2018, NBCC wrote to the Bank and invoked the
                          Performance Bank Guarantee provided by the plaintiff in respect of
                          Package II-A.


                          11.41 On 3rd July, 2018, NBCC again wrote to the plaintiff, alleging
                          that work remained incomplete in Packages I-A, I-B and II-B. The
                          plaintiff was, therefore, advised to "act as per the GCC and complete
                          the work immediately".


                          11.42 BSF wrote to NBCC on 17th July, 2018, again alleging that, at
                          the time of handing and taking over of the works performed by the
                          plaintiff, defects were found to be persisting, and had not been
                          rectified even 30 days after they had been brought to the notice of the
                          plaintiff.   In the circumstances, NBCC was requested to expedite
                          rectification thereof. The letter was communicated, by NBCC to the
                          plaintiff on 19th July, 2018.


                          11.43 The plaintiff forwarded its Final Bill, for Package I-A, under
                          cover of letter dated 24th July, 2018, for a net payable amount of ₹
                          1,43,18,300/-. The appeal was accompanied by its abstract, a bill for
                          escalation and measurements of the work done.


                          11.44 The Final Bill, for Package II-B, for a net payable amount of ₹
                          1,64,03,331/- was forwarded by the plaintiff to NBCC under cover of
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                          Page 30 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           letter dated 10th August, 2018, along with its abstract, a bill for
                          escalation, measurements of the work done and a "50% Excess
                          Quantity claim statement".


                          11.45 BSF again wrote to NBCC on 21st August, 2018, intimating that
                          "some defects were found by BOO during handing taking" and that,
                          despite 30 days having passed since then, the defects were yet to be
                          rectified. NBCC was, therefore, requested to take necessary action at
                          the earliest, to ensure that the defects were set right. Attached, to the
                          letter, was a list of defects/discrepancies/balance work as on 30th July,
                          2018, which included
                                (i)     in respect of Package I-A,
                                        (a)   5 civil and 3 electrical works in Training Building-
                                        A,
                                        (b)   10 civil works in Training Building-B,
                                        (c)   16 civil and 13 electrical works, and 9 works
                                        relating to firefighting, in the SOS Mess and 53 works in
                                        the GOS Mess,
                                (ii)    in respect of Package I-B,
                                        (a)   8 civil works, 1 electrical work and 10 works
                                        relating to firefighting in the MI Hospital Building,
                                        (b)   12 civil works, 7 electrical works and 5 works
                                        relating to firefighting in the Shopping Complex and
                                        (c)   5 civil works, 5 electrical works and 9 works
                                        relating to firefighting in the Family Welfare Centre, and
                                (iii)   in respect of Package II-B,
                                        (a)   13 civil works in Barrack-3,
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 31 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                        (b)    27 civil works, 11 electrical works and one item of
                                       work relating to firefighting, in Barrack-4 and
                                       (c)    20 civil works and 10 electrical works in Barrack-
                                       6.
                          The communication was forwarded to the plaintiff on the very same
                          day, i.e. 21st August, 2018.


                          11.46 By a separate communication of the same date, i.e. 21st August,
                          2018, NBCC rejected the 23rd RA Bill submitted by the plaintiff in
                          respect of Package I-B. The plaintiff responded on 29th August, 2018,
                          requesting NBCC to grant extension of time, to the plaintiff, in respect
                          of Packages I-A and II-B till the date when the buildings in the said
                          packages were handed over to NBCC, and to grant extension of time,
                          without Liquidated Damages, up to 31st December, 2018, for Package
                          I-B (in respect of Barrack-2). In response, NBCC, vide letter dated
                          12th September, 2019, granted extension of time, for Package I-B, till
                          30th September, 2018, without prejudice to the right of NBCC to
                          recover liquidated damages as per the GCC.


                          11.47 Vide letter dated 24th September, 2018, NBCC intimated the
                          plaintiff that work, in respect of Package I-B still remained to be
                          completed. On 27th September, 2018, the plaintiff applied to NBCC
                          for extension of time, to complete Package I-B, till 31st December,
                          2018, without liquidated damages.


                          11.48 Vide letter dated 24th October, 2018, the plaintiff sought that the
                          time for completion of Package I-A be extended till 31st May, 2018,
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 32 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           when the buildings relating to the said Package were handed over by
                          the petitioner to NBCC. A similar request was made, vide letter dated
                          27th October, 2018, in respect of Package II-B, for extension of time
                          till 30th June, 2018.


                          11.49 NBCC informed the plaintiff, vide letter dated 5th February,
                          2019, that the Final Bill relating to Package I-A had duly been
                          checked with the representative of the plaintiff, and requested the
                          plaintiff, therefore, to submit the deviation statement in respect of the
                          said Package, so that the Final Bill could be processed at the earliest.
                          The plaintiff submitted the said Deviation Statement, under cover of
                          letter dated 22nd February, 2019. It was requested, therefore, that the
                          Final Bill for Package I-A be processed and payment released.


                          11.50 On 30th March, 2019, NBCC wrote to BSF, informing the BSF
                          that Barrack-2 (Package I-B) was ready for handing over, and
                          requesting that Board be constituted for verifying inventories and
                          taking over of the building. As subsequent communications would
                          reveal, this has, however, not taken place till date.


                          11.51 Vide letter dated 18th April, 2019, addressed to NBCC, the
                          plaintiff asserted that, except for Barrack-2, which was ready for being
                          taken over by the BSF, all other buildings had been handed over and
                          DLP, in respect thereof, completed. The dates of handing over, in the
                          said communication, stated to be
                                 (i)    in respect of Package I-A,
                                        (a)       20th September, 2013 for Training Building-A,
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 33 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                          (b)   2nd June, 2013 for Training Building-B,
                                         (c)   8 February, 2017 for the SOS Mess and
                                         (d)   24th January, 2018 for the GOS Mess,
                                 (ii)    in respect of Package I-B,
                                         (a)   15th December, 2013, for the MI Hospital Building,
                                         (b)   21st February, 2015, for the Shopping Complex and
                                         (c)   21st January, 2015 for the Family Welfare Centre,
                                         and
                                 (iii)   in respect of Package II-B,
                                         (a)   30th April, 2013, for Barrack-3,
                                         (b)   9th September, 2017, for Barrack-4 and
                                         (c)   19th June, 2017, for Barrack-6.
                          It was also pointed out, in the said communication, that the Final Bills
                          for Packages I-A and II-B, submitted by the plaintiff, were awaiting
                          clearance. The plaintiff also requested that the Three Performance
                          Bank Guarantees and Nine Security Bank Guarantees, furnished by it,
                          be released, along with the Security Deposit of ₹ 65 lakhs.


                          11.52 Under cover of letter dated 23rd April, 2019, the plaintiff
                          submitted, to NBCC, the Final Deviation Statement for Package I-A,
                          for approval, with the request that the statement be approved on
                          priority basis.


                          11.53 Vide letter dated 26th April, 2019, the plaintiff submitted, to
                          NBCC, the Final Bill for Package I-B, for ₹ 1,17,17,328/-.




Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 34 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           11.54 Package I-B, however, faced a further hurdle, as BSF wrote, to
                          NBCC, on 3rd May, 2019, that as defects were found in Barrack-2, it
                          could not be handed over/taking over.          NBCC was, therefore,
                          requested to ensure that the defects be remedied at the earliest. As a
                          consequence, NBCC, under cover of letter dated 28 th May, 2019,
                          returned, to the plaintiff, the Final Bill submitted by it in respect of
                          Package I-B, requiring the plaintiff to complete the work relating to
                          the said Package and re-submit the bill.


                          11.55 Vide letter dated 29th July, 2019, the defendant informed the
                          plaintiff that the Final Bills, submitted by the plaintiff in respect of
                          Package II-B, had been duly checked with the representative of the
                          plaintiff. The plaintiff was, therefore, directed to submit the Deviation
                          Statement, etc., in respect thereof.


                          11.56 On 16th April, 2019, BSF wrote to the NBCC, stating that
                          defects still remained in the GOS Mess (Package I-A).


                          11.57 Vide letter dated 30th August, 2019, NBCC informed the
                          plaintiff that the Final Deviation statement, as well as the statement of
                          extra/substituted items, submitted by the plaintiff in respect of
                          Package I-A, stood approved and that, therefore, the amended value
                          for Package I-A was ₹ 75,885,922/-.


                          11.58 On 30th November, 2019, NBCC informed the plaintiff that, as
                          the final Deviation Statement and statement of substituted items in
                          respect of Packages I-B and II-B were still awaited from the plaintiff,
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 35 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           NBCC had prepared the Final Bill for all the packages. According to
                          the said Final Bill, the total value of Packages I-A, I-B and II-B was ₹
                          757.86 lakhs, ₹ 701.39 lakhs ₹ 896.66 lakhs.          The plaintiff was
                          requested to acknowledge the communication and provide its
                          acquiescence to the finalisation of the Bills by NBCC within 15 days,
                          failing which, it was stated, the bills would be adjusted at the aforesaid
                          amounts without further communication.           The plaintiff was also
                          requested to complete the work relating to Barrack-2 (Package I-B)
                          without further delay, as, otherwise, BSF would not accept the Final
                          Bill for the said Package.


                          11.59 The plaintiff responded on 18th December, 2019, objecting to
                          the Final Bills as computed by NBCC, clearly stating that they were
                          unacceptable. The plaintiff, therefore, requested that the bills be not
                          submitted to BSF. The plaintiff verified the measurements sent by
                          NBCC. It was also pointed out by the plaintiff, in the said letter, that
                          Barrack-2 had been completed by or on 30th March, 2019 and
                          inaugurated by the BSF on 23rd July, 2019. The plaintiff undertook to
                          rectify defects in Barrack-2, as pointed out during the DLP.


                          11.60 Reiterating this position, the plaintiff wrote, again, to NBCC on
                          8th January, 2020, asserting that the DLP was complete in respect of
                          all structures, except Barrack-2 (Package I-B). It was again reiterated
                          that Final Bills to be submitted by the plaintiff.


                          11.61 On 22nd January, 2020, NBCC wrote to the plaintiff, alleging
                          that the defects, pointed out in the MI Hospital, Shopping Complex
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 36 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           and Family Welfare Centre (all of Package I-B) were still not
                          rectified.   The plaintiff was, therefore, requested to provide a
                          programme for rectification of the said defects and also to complete
                          Barrack-2, so that the building could be taken over by the BSF.


                          11.62 On 6th March, 2020, BSF wrote to NBCC, clarifying that any
                          proposal for extension of time was to be obtained from NBCC only on
                          completion of the work, and not where the work was in progress. BSF
                          authorised NBCC, vide the said communication, to withhold, from the
                          bills of the plaintiff in cases where scheduled time had been extended,
                          10% of the sanctioned amount.


                          11.63 The plaintiff wrote, on 22nd May, 2020, to NBCC, drawing the
                          attention of NBCC to Office Memorandum dated 13th May, 2020,
                          issued by the Ministry of Finance (MOF), requiring Governmental and
                          public Sector undertakings to return the value of security/Bank
                          Guarantees to the contractors.       The plaintiff asserted that it had
                          completed the work assigned to it, submitted the Final Bills and that
                          the DLP was also complete.           In the circumstances, the plaintiff
                          requested NBCC to released, forthwith, all the bank Guarantees as
                          well as the security deposit furnished by the plaintiff.


                          11.64 This was followed by a communication, dated 15 th June, 2020,
                          from the plaintiff to NBCC, stating that, pursuant to the meeting
                          between the plaintiff and NBCC on 13th March 2020, the plaintiff had
                          signed the measurements and quantities as verified for Package I-A
                          vide letter dated 30th November, 2019. It was, therefore, requested
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 37 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           that the amounts as per the said bill be released to the plaintiff,
                          including escalation. A similar request, for Package I-B, was sent by
                          the plaintiff to NBCC on 20th June, 2020.


                          11.65 On 6th July, 2020, NBCC wrote to its Bank to discharge the
                          PBGs submitted by the plaintiff for Packages I-A and II-B.


                          11.66 The plaintiff again wrote to NBCC on 10th July, 2020, vis-à-vis
                          Package I-B. It was asserted, in the said communication, that the
                          plaintiff had completed Barrack-2, which was handed over to NBCC
                          on 30th March, 2019, inaugurated on 23rd July, 2019 and was being
                          used by the BSF. It was further pointed out that the Final Bill for
                          Package I-B had also been submitted by the plaintiff on 30th April,
                          2019.    Rectification, in respect of the said Package, too, it was
                          asserted, had been completed.


                          11.67 On 21st July, 2020, NBCC wrote to the plaintiff, apropos the
                          Final Bill raised by the plaintiff for Package I-A. The letter alleged
                          that defects, observed in Package I-A during the DLP had not yet been
                          rectified.   It was further alleged that the Final Bill had not been
                          submitted in time. NBCC further drew attention to the GCC, which
                          required security deposit to be released only after the DLP was
                          completed and the final bill was adjusted, whichever was later. The
                          plaintiff was, therefore, requested to process the Final Bill for Package
                          I-A and resend it as soon as possible. Additionally, the plaintiff was
                          requested to submit the Final Bill for Package II-B without further
                          delay.
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 38 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           11.68 On 25th July, 2020, NBCC again wrote to the petitioner,
                          drawing the attention of the petitioner to defects observed in Package
                          II-B during the taking over of the works and during the DLP. The
                          petitioner was directed to rectify the defects on or before 5th August,
                          2020. Similar correspondences were sent by NBCC to the plaintiff,
                          on the same day, i.e. 25th July, 2020, with respect to Packages I-A and
                          I-B, in the latter case specifically with respect to defects in Barrack-2.
                          With respect to Package I-B, the letter asserted that, as Barrack-2 had
                          not been taken over, DLP, in respect thereof, has yet to start.


                          The Upshot


                          12.    The entitlement of the plaintiff, to the interlocutory prayers in
                          this application, has to be decided on the basis of the position as it
                          emerges from the above communications, vis-à-vis the clauses in the
                          GCC.


                          13.    The communications between the plaintiff and NBCC make it
                          clear that, as on date, all buildings in Packages I-A, I-B and II-B,
                          except Barrack-5 in Package II-B and Barrack-2 in Package I-B, stand
                          handed over to NBCC. Barrack-5 in Package II-B was withdrawn,
                          from the contract, by NBCC, and, in respect of Barrack-2 in Package
                          I-B, defects still remain to be rectified.


                          14.    Completion of DLP


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 39 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           14.1 Clause 74.0 of the GCC requires the plaintiff to be responsible
                          for rectification of defects only for a period of 12 months from the
                          date of taking over of the works by the owner/client.                    The
                          communications on record make it clear that plaintiff and NBCC have
                          both been reckoning the DLP building-wise, and not package-wise. I
                          am unable, therefore, to agree with the submission of Mr. Wali,
                          learned Counsel for NBCC, that the DLP was required to be assessed
                          package-wise.


                          14.2 Clause 74.0 fixes the DLP as twelve months from the date of
                          taking over of the works by NBCC/BSF. The communications cited
                          hereinabove make it clear that all buildings have been taken over, in
                          all Packages, except those which were withdrawn from the contract
                          and Barrack-2. More than twelve months have also elapsed, since the
                          date of such taking over. Clause 74.0 does not permit extending the
                          DLP beyond twelve months, merely because defects are found in the
                          buildings after they are taken over. The import of Clause 74.0 is clear
                          and unequivocal. It is not open to the NBCC to, indefinitely, continue
                          to point out defects in the buildings as handed over by the plaintiff,
                          even after the buildings are taken over by the BSF. That liberty
                          enures, in favour of NBCC, only for a period of twelve months, and
                          no more. The attendant liability on the plaintiff is to ensure that
                          defects, pointed out within the said period of twelve months, are
                          remedied and rectified. The DLP does not stand extended till the
                          defects are remedied or rectified to the satisfaction of the NBCC or the
                          BSF. Clause 74.0 also provides for the consequence, in the event of
                          default, on the part of the plaintiff, in carrying out the rectifications, as
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                               Page 40 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           pointed out during the DLP, which is that NBCC may have the defects
                          rectified otherwise, at the cost and expense of the plaintiff. The stand
                          of NBCC, as manifested from various communications addressed to
                          the plaintiff, that, as the defects, pointed out in the buildings handed
                          over by the plaintiff were yet to be completely rectified, the DLP
                          would not come to an end, is contrary to Clause 74.0 and cannot be
                          accepted. To reiterate, therefore, the DLP, in respect of all buildings
                          except Barrack-2 (Package I-B), has come to an end.


                          15.   Re. Clause 37.3 of the GCC


                          Clause 37.3 of the GCC provides that plaintiff would be entitled to
                          payment, from NBCC, only after NBCC receives the corresponding
                          payment from BSF, for the work done by the plaintiff. The very
                          enforceability of such a clause, which makes payment to the plaintiff,
                          of the work done by the plaintiff, contingent on payment being made
                          by BSF to NBCC, with no stipulation as to time, may itself be
                          questionable under the Indian Contract Act, 1872. In the present case,
                          however, it would not be open to NBCC to seek shelter behind Clause
                          37.3, as NBCC itself novated the said clause, vide its communications
                          dated 3rd October, 2015 and 15th May, 2018 supra. In its letter dated
                          3rd October, 2015, NBCC clearly undertook to pay, "immediately", to
                          the plaintiff, payments against works executed by it, as the works
                          progress. The concluding sentence of the said communication further
                          advised the plaintiff to commence work immediately, so as to enable
                          NBCC "to release payment as work progresses". In its subsequent
                          communication dated 15th May, 2018, NBCC expressly noted that,
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 41 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           despite Clause 37.3 of the GCC, it "was releasing payment in the
                          interest of work to expedite the progress of work at site". Prima facie,
                          in my view, NBCC cannot seek to oppose the application of the
                          plaintiff on the basis of Clause 37.3 of the GCC.


                          16.   Clause 67.0 of the GCC


                          NBCC also relies on Clause 67.0 of the GCC, which confers, on
                          NBCC, the right to deduct or set off expenses incurred or likely to be
                          incurred in rectifying defects or any claim under the GCC against the
                          plaintiff against any amount payable to the plaintiff, from, inter alia,
                          "security deposit and proceeds of performance guarantee".           This
                          clause applies, at best, only to the security deposit, or payment, to the
                          plaintiff, of the "proceeds of performance guarantee", and does not
                          impact, in any way, the entitlement of the plaintiff to release of the
                          Bank Guarantees provided by it as security. Even otherwise, what the
                          Clause permits NBCC to set off, are the expenses incurred or likely to
                          be incurred in rectifying defects. The actual expenses which NBCC
                          would have to incur, or would be likely to incur, for rectifying any
                          defects which remained after completion of the work by the plaintiff,
                          would be a matter of evidence and trial. NBCC has not, either in oral
                          arguments during hearing, or in its written submissions, specifically
                          identified any expenses which NBCC would have to incur, to rectify
                          defects, or provided any prima facie material on the basis of which
                          this Court could come to a conclusion, at this stage, that set off, or
                          deduction, of such amounts, from the dues of the plaintiff, could be


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 42 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           justified under Clause 67.0. The reliance, by the plaintiff, on Clause
                          67.0 is also, therefore, in my view, at least at this stage, misguided.


                          17.   Which takes us to the prayers in this application.


                          18.   Re. Prayer (i)


                          18.1 Prayer (i) seeks a direction to NBCC to finalise the Final Bills
                          submitted by the plaintiff in respect of Packages I-A, I-B and II-B.


                          18.2 Unlike conclusion of the DLP, payment of the bills raised by
                          the plaintiff is, contractually, to be effected on a bill-wise, and
                          package-wise, rather than building-wise, basis. This position also
                          emerges from the communications between the parties, to which
                          detailed reference has already been made. NBCC had, vide its letter
                          dated 30th November, 2019, communicated, to the plaintiff, the
                          amount which, according to NBCC, was payable to the plaintiff in
                          respect of the three Packages. The plaintiff initially objected to the
                          said computation, vide its reply dated 18th December, 2019.
                          Thereafter, however, consequent on the meeting between the plaintiff
                          and NBCC on 13th March, 2020, the plaintiff had signed the
                          measurements and quantities as verified by NBCC for Package I-A in
                          its letter dated 30th November, 2019. The plaintiff, therefore,
                          requested NBCC to finalise the bill and release the amounts payable to
                          the plaintiff. To my mind, no further impediment, to the finalisation
                          of the Final Bill of the plaintiff, in respect of Package I-A, remains. A


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                             Page 43 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           clear case is made out, therefore, for a direction to NBCC to finalise
                          the Final Bill in respect of Package I-A.


                          18.3 The position, in respect of the other two Packages under
                          consideration, is, however, different. The communications between
                          the parties indicate that, till date, Barrack-2 remains unfinished, for
                          which reason BSF has not taken over the said building either. As the
                          Final Bill has to be settled package-wise, no direction for finalising of
                          the Final Bill in respect of Package I-B can be issued, so long as
                          Barrack-2 is not completed to the satisfaction of NBCC.


                          18.4 The Final Bill in respect of Package II-B, as computed by
                          NBCC and communicated vide its letter dated 30th November, 2019,
                          has also been disputed by the plaintiff, in its reply dated 18 th
                          December, 2019.        The record does not refer to any further
                          communications      from    the plaintiff to     NBCC,      apropos      the
                          computation, by NBCC, of the amount payable to the plaintiff
                          thereunder. It would be for the plaintiff, therefore, now, to propose, to
                          NBCC, the amount which, according to the plaintiff, constitutes its
                          entitlement for the work done in respect of Package I-B. Thereafter,
                          the plaintiff and NBCC would have to work out the amount payable.
                          It is only after this exercise is undertaken that finalisation of the Final
                          Bill, in respect of Package I-B, is possible.


                          18.5 Resultantly, no direction, for finalisation of the Final Bills, in
                          respect of Packages I-B and II-B can be issued at this stage.


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                              Page 44 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           19.   Re. Prayers (ii) and (iii)


                          19.1 Two of the three Performance Bank Guarantees stand released
                          by NBCC. The Performance Bank Guarantee relating to Package I-B
                          is yet to be released. Clause 9.0 of the GCC required the Performance
                          Bank Guarantee to be kept alive only for a period of 90 days after the
                          end of the DLP. There is no stipulation, in the GCC, requiring the
                          continuance of the Performance Bank Guarantee even after the expiry
                          of the period of 90 days after conclusion of the DLP, or till all defects,
                          in respect of any particular Package, are remedied to the satisfaction
                          of NBCC or BSF. Indeed, the said stipulation would be manifestly
                          unreasonable, as NBCC and BSF could continue to point out defects
                          and, thereby, indefinitely protract the release of the Performance Bank
                          Guarantee. Clause 9.0 of the GCC requires the Performance Bank
                          Guarantee to be 5% of the contract value. In my prima facie opinion,
                          NBCC would be entitled to continuance of the Performance Bank
                          Guarantee, furnished by the plaintiff in respect of Package I-B, at best
                          to the extent of 5% of the value of Barrack-2.


                          19.2 Mr. Mehta had sought to contend that no building-wise
                          computation of value, for the contract, existed and that the values had
                          been worked out on a package-wise basis. Be that as it may, the value
                          of the contract has been worked out by NBCC in the first instance.
                          NBCC is, therefore, aware of the value to be apportioned to individual
                          buildings in any Package. Balancing of equities, in respect of the
                          Performance Bank Guarantee furnished by the plaintiff for Package I-
                          B would, therefore, in my opinion, require NBCC to indicate the value
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 45 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           attributable to Barrack-2.     The value of the Performance Bank
                          Guarantee, furnished by the plaintiff in respect of Package I-B, would
                          stand reduced to 5% of such value.


                          19.3 In the event NBCC is unwilling to apportion any specific value
                          to Barrack-2, then, given the fact that the DLP stands concluded in
                          respect of all buildings in the said Package except Barrack-2, the
                          Performance Bank Guarantee furnished by the plaintiff would have to
                          be released. In that event, the right of NBCC, to claim the differential
                          from the plaintiff would stand reserved.


                          19.4 The position, in relation to the Bank Guarantees furnished
                          towards security is, however, somewhat different.


                          19.5 Mr. Mehta has impressed, on this Court, the fact that Clause
                          10.0 of the GCC requires the Security Deposit - which, in his
                          submission, would include the Bank Guarantees furnished towards
                          security - to be returned only after expiry of the DLP, on payment of
                          the Final Bill to the plaintiff, whichever is later. Till payment of the
                          Final Bill, in respect of any Package, remains to be made, therefore,
                          Mr. Mehta would submit that there can be no question of release, to
                          the plaintiff, of the Bank Guarantee furnished by way of security for
                          that Package.


                          19.6 I am not willing, at least prima facie, to accord, to Clause 10.0,
                          as rigid interpretation as Mr. Mehta would lend to it.


Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 46 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           19.7 Clause 10.0 of the GCC cannot, in my prima facie opinion, be
                          so interpreted as to allow NBCC to delay payment of the Final Bill,
                          qua any particular Package, without due justification and, thereafter,
                          take advantage of the "whichever is later" caveat incorporated into the
                          said Clause. Where all buildings, for any particular Package have
                          been handed over by the plaintiff, and DLP also stands completed,
                          release of the Bank Guarantee provided by the plaintiff by way of
                          security for that Package cannot be allowed to remain pending
                          indefinitely, till payment is made, to the plaintiff, against the relevant
                          Final Bill.


                          19.8 At the same time, Clause 10.0 makes refund of the security
                          deposit conditional, not on finalisation of the Final Bill for any
                          particular Package, but on payment thereof. This is a contractual
                          covenant which the parties have executed with open eyes, and the
                          plaintiff, as much as NBCC, must remain bound thereby. It is not
                          possible for this Court, therefore, to direct release of the Security
                          Bank Guarantee, for any particular Package, unmindful of the fact of
                          payment, by NBCC, of the said Final Bill, to the plaintiff.


                          19.9 The sequitur would be that where, for any reason, the stage of
                          payment of the Final Bill, for any particular Package, has not reached,
                          there can be no direction, interlocutory or otherwise, to NBCC, to
                          release the Security Bank Guarantee furnished by the plaintiff in
                          respect of that Package.




Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 47 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           19.10 Where, however, the Final Bill, in respect of any particular
                          Package, is ripe for payment, in my opinion, release of the Security
                          Bank Guarantee, furnished by the plaintiff in respect of that particular
                          Package, cannot be delayed indefinitely merely by inaction, on the
                          part of NBCC, in making payment, to the plaintiff, of the Final Bill
                          raised in respect thereof.


                          19.11 Only thus, in my prima facie view, can the equities be balanced
                          at this stage.


                          19.12 I have already held, hereinabove, that the Final Bills, raised by
                          the plaintiff, in respect of Packages I-B and II-B, are not ripe for
                          finalisation. The only Final Bill which can be finalised at this stage is
                          the Final Bill pertaining to Package I-A, and necessary directions in
                          that regard have, therefore, already been incorporated in this order.
                          Consequent on finalisation, the only intervening act, which requires to
                          be performed, before the Security Bank Guarantee, in respect of
                          Package I-A, can be released to the plaintiff, is payment of the Final
                          Bill. There is, however, no prayer, in this application, for a direction
                          to NBCC to make payment, forthwith, to the plaintiff, against any of
                          the Final Bills raised by it. Directing release of the Security Bank
                          Guarantee, prior to making of payment, by NBCC, against the Final
                          Bills raised in respect of any particular Package would, however,
                          transgress Clause 10.0 of the GCC.


                          19.13 In order to ensure that equities are balanced, I am of the view
                          that NBCC requires to be directed to, consequent on finalisation of the
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 48 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           Final Bill for Package I-A, deposit, with the Registrar General of this
                          Court, the amount found payable to the plaintiff against the said Final
                          Bill.   Release of the Security Bank Guarantee is not specifically
                          dependent on the amount found to be payable to the plaintiff, against
                          any Final Bills raised by it, though Clause 10.0 does use the
                          expression "payment of the amount of the final bill". The letter, dated
                          30th November, 2019, from NBCC to the plaintiff, computed the total
                          amount payable, against Package I-A, as ₹ 757.86 lakhs. This figure
                          stands accepted by the plaintiff, consequent on the meeting between
                          the plaintiff and NBCC on 13th March, 2020 and the subsequent
                          communication dated 15th June, 2020, from the plaintiff to NBCC. In
                          any event, NBCC has acknowledged that the plaintiff is entitled to
                          further payment against the Final Bill raised in respect of Package I-A.
                          The balance payment requires, in my view, at this stage, to be
                          deposited, by NBCC, with the Registrar General of this Court, subject
                          to further proceedings in the suit.


                          19.14 Once payment, against the Final Bill raised by the plaintiff in
                          respect of Package I-A thus stands "made" by NBCC, Clause 10.0 of
                          the GCC would justify a direction to NBCC to release, to the plaintiff,
                          the Bank Guarantees furnished by the Plaintiff by way of security for
                          the said Package.


                          19.15 The prayer, in the application, for interlocutory directions to
                          NBCC to release, to the plaintiff, the Bank Guarantees furnished by
                          them as security, in my opinion, be, at this stage, allowed only to this
                          limited extent, and no more.
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 49 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           19.16 Directions for release, to the plaintiff, of the entire security
                          deposit of ₹ 65 lakhs, made by it, cannot be issued at this juncture,
                          even while the work, in respect of Package I-B, remains to be
                          completed, and the amount payable to the plaintiff against the Final
                          Bill for Package II-B, remains to be finalised. Security Deposit has
                          been furnished for the entire contract as a whole, and not package-
                          wise. The maximum to which the plaintiff would be entitled, in the
                          matter of release of the Security Deposit, in view of the above
                          reasoning, would be for an amount proportionate to the quantum
                          found payable to the plaintiff, against the Final Bills raised by the
                          plaintiff in respect of Package I-A. At the same time, there is no
                          provision, in the GCC, for "piecemeal" or "package-wise" release of
                          the Security Deposit. I am not, therefore, inclined to direct, at this
                          stage, release, to the plaintiff, of the Security Deposit furnished by it.
                          The right of the plaintiff, for directions in that regard at a later more
                          appropriate stage would, however, stand reserved.


                          Conclusions and Order


                          20.   Resultantly, the following directions are issued:


                                (1)    DLP is to be reckoned on a building-wise, rather than a
                                Package-wise, basis.


                                (2)    The DLP stands completed in respect of all buildings in
                                Packages I-A, I-B and II-B except Barrack-2 in Package I-B.
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 50 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 (3)    Clause 9.0 of the contract between the plaintiff and
                                NBCC requires Performance Bank Guarantee to be furnished
                                equivalent to 5% of the contract value. Separate Performance
                                Bank Guarantees have been furnished in respect of each
                                Package.    The Performance Bank Guarantees in respect of
                                Packages I-A and II-B already stand released by NBCC. The
                                only justification, therefore, for non-release of the Performance
                                Bank Guarantee in respect of Package I-B, is the work
                                remaining to be completed in respect of Barrack 2.           This,
                                however, in my view, cannot justify withholding of the entire
                                Performance     Bank    Guarantee.    The    Performance     Bank
                                Guarantee furnished in respect of Package I-B has, therefore, in
                                my opinion, to be reduced to 5% of the value of the Package, as
                                attributable to Barrack 2. The contract value of each package
                                has been worked out by NBCC. NBCC is, therefore, directed to
                                file, under cover of an affidavit, the contract value applicable to
                                Barrack 2, within a period of two weeks. The value of the
                                Performance     Bank     Guarantee    No.    00061PEBG120002,
                                furnished by the plaintiff in respect of Package I-B, would stand
                                reduced to 5% of the said contract value, attributable to Barrack
                                2.


                                (4)    In the event the NBCC is unable, or unwilling, to
                                apportion or attribute a particular value to Barrack 2, out of the
                                total contract value in respect of Package I-B, I am of the
                                opinion that, possibly, a direction to release the Performance
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                           Page 51 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 Bank Guarantee furnished by the plaintiff in respect of the said
                                Package, may be justified, as it would not be in the interests of
                                justice to withhold the entire Performance Bank Guarantee
                                merely because of work remaining to be done in respect of
                                Barrack 2.      I refrain, however, from expressing any final
                                opinion in that regard at this stage, and the decision on this
                                aspect would be taken after compliance, by NBCC, with the
                                direction contained in (3) supra.


                                (5)     The above directions are justified, even though Barrack 2
                                remains unfinished, as the value of the Performance Bank
                                Guarantee is based on the contract value of the concerned
                                Package, and not on the amount payable to the plaintiff against
                                the bill, or the Final Bill, raised by it.


                                (6)     So long as Barrack 2 remains unfinished, no direction for
                                finalisation of the Final Bill, submitted by the plaintiff in
                                respect of Package I-B, can be issued, as the bill is required to
                                be finalised on package-wise, and not on a building-wise, basis.
                                Consequently, no interim directions, for release of Bank
                                Guarantees No. 00061PEBG150018, 00061PEBG140028 and
                                00061PEBG170013, can be passed at this stage, in view of
                                Clause 10.0 of the contract between the parties, which makes
                                refund of security deposit conditional on payment of the final
                                bill.




Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                          Page 52 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 (7)    In respect of Package I-A, however, there is no
                                justification for further delay, on the part of NBCC, in finalising
                                the Final Bill, duly signed by the plaintiff and received by
                                NBCC on 3rd July, 2020. The NBCC is, accordingly, directed
                                to finalise the Final Bill relating to Package I-A within 30 days.


                                (8)    Clause 10.0 makes the release of security deposit
                                conditional, however, not to finalisation of the final bill in
                                respect of any package, but to payment of the final bill. At this
                                stage, however, instead of directing release of payment of the
                                Final Bill to the plaintiff - in respect whereof no prayer is
                                contained in the application either - NBCC is directed to
                                deposit, with the Registrar General of this Court, the amount
                                found payable to the plaintiff, consequent to finalisation of the
                                Final Bill in respect of Package I-A, within 15 days of such
                                finalisation.     Bank Guarantees No 00061PEBG150019,
                                00061PEBG140027 and 00061PEBG170012, furnished by the
                                plaintiff towards security in respect of Package I-A would be
                                released, in full, within a week thereof. Compliance report, in
                                respect of these directions, would be filed by the NBCC, before
                                this Court.


                                (9)    In respect of Package II-B, the Final Bill, as computed by
                                NBCC and forwarded to the plaintiff, has been disputed by the
                                plaintiff. In this view of the matter, no directions, for release of
                                any Security Bank Guarantee, furnished by the plaintiff in
                                respect of Package II-B, can be issued at this stage.
Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 53 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                                 Performance Bank Guarantee, furnished by the plaintiff in
                                respect of Package II-B, already stands released.


                                (10) As the plaintiff has chosen to dispute the amount payable
                                to it against the final bills raised by it in respect of Package II-
                                B, with a specific request not to forward the Final Bill to the
                                BSF, the ball, in respect of Package II-B is, so to speak, in the
                                court of the plaintiff. It would be for the plaintiff and NBCC to
                                work out, between themselves, the amount payable to the
                                plaintiff against Package II-B. Liberty would, therefore, stand
                                reserved to the plaintiff to move this Court, in respect of any
                                interlocutory directions, in respect of Package II-B, at a later,
                                and appropriate, stage.


                                (11) No direction for release of the Bank Guarantees furnished
                                by the plaintiff as security towards Package II-B can, therefore,
                                be passed at this stage. Liberty would, however, stand reserved
                                to the plaintiff to move the Court, in that regard, at any later,
                                and more appropriate, stage.


                          21.   The time for compliance, by NBCC, with the above directions,
                          would stand reckoned from the date of uploading, on the website of
                          this Court, of this order or of communication by the Registry, to
                          NBCC, by email, of a copy thereof, whichever is earlier.




Signature Not Verified
Digitally Signed          IA12354/2019 in CS(COMM) 1005/2018                            Page 54 of 55
By:SUNIL SINGH NEGI
Signing Date:08.09.2021
19:49:51
                           22.   Observations and findings, in this order, are only intended for
                          disposal of the present application, and would not influence the Court,
                          in further progress of the proceedings in the suit.




                                                                         C. HARI SHANKAR, J.

SEPTEMBER 2, 2021/hmj Signature Not Verified Digitally Signed IA12354/2019 in CS(COMM) 1005/2018 Page 55 of 55 By:SUNIL SINGH NEGI Signing Date:08.09.2021 19:49:51