State of Rajasthan - Subsection
Section 38(3) in Rajasthan Public Procurement Rules, 2012
| Procurement Method | Open Competitive Bidding | Limited Bidding |
| Publication of NIB and launch of Biddingdocuments | Day 0 | Issue of Bidding documents-Day 0 |
| Submission of Bids | - 30 days from issueof Bidding documents- where the pre-bid conference is held 15 daysfrom date of issue of clarification/addendum | 07days from issue of Bidding documents/date ofissue of clarification/addendum |
| Technical Bid Opening | Within 1 day of last day of submission | Within 1 day of last day of submission of bids |
| Issue of Letter of Award | Within 3 days of approval of award | Within 3 days of approval of award |
| Contract Signing | Within 15 days of Issue of Letter of Award | Within 15 days of Issue of Letter of Award |
| Declaration of the Bid results on State PublicProcurement Portal and Departmental website | Within 3 days of issue of letter of acceptance. | Within 3 days of issue of letter of acceptance. |