Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 1]

Punjab-Haryana High Court

M/S Gawar Construction Company vs State Of Haryana And Ors on 11 August, 2011

Author: Hemant Gupta

Bench: Hemant Gupta

          IN THE HIGH COURT OF PUNJAB AND HARYANA
                     AT CHANDIGARH

                                   Arb. Case No. 25 of 2011

                                Date of Decision: 11.8.2011

    M/s Gawar Construction Company ....Petitioner

                          vs.

    State of Haryana and ors                 ..Respondents

CORAM: - HON'BLE MR. JUSTICE HEMANT GUPTA Present: - Mr. John Kumar, Advocate for the petitioner.

Mr. Pradeep Singh Poonia, Addl. AG, Haryana Hemant Gupta, J The Petitioner has sought appointment of an Arbitrator in respect of the dispute arising out of an agreement dated 18.11.2005. As per the said agreement, the petitioner was given the contract of work of Improvement of Widening & Strengthening of Jhajjar- Badli Road from Km. 0.00 to 18.25 in Jhajjar District. It was on 24.8.2006, the scope of work was extended and the work was to be completed on or before 20.10.2006. It is pointed out by Mr. Poonia, learned counsel for the respondent that in fact, the petitioner completed the work on 10.10.2006.

In the agreement, there is clause of defect liability. As per the said clause, the contractor is to maintain the work completed for a period of two years after the date when the work is completed. The grievance Arb. Case No. 25 of 2011 2 of the petitioner is that as per the Defect Liability Clause, the petitioner is to maintain the constructed road for a period of two years and since, the said period has come to an end, therefore, he is entitled to payment for the maintenance of the road.

Mr. Poonia states that the direction to maintain the road was issued within the validity period of Defect Liability Clause which expired on 31.1.2009. He has further pointed out that the petitioner has not raised any dispute before the Dispute Review Expert Committee within 14 days of the notification of the Engineer's decision in terms of Clause 24.1. It is contended that since, the petitioner has not raised any dispute in respect of extension of Defect Liability Clause, therefore, the petitioner cannot seek resolution of the alleged dispute through arbitration.

Having heard learned counsel for the parties, I do not find that the petitioner can be permitted to raise dispute in respect of issue of extension of Defect Liability Clause. The Defect Liability clause as per the averments made in the written statement was extended from time to time, lastly vide the communication dated 31.12.2008. The petitioner has not raised any dispute within 14 days of such notification. The communication to raise dispute is Annexure P-2 i.e. on 17.2.2010. In terms of Clause 24.1of the agreement, the petitioner can raise dispute Arb. Case No. 25 of 2011 3 within 14 days of the notification of the Engineer's decision i.e. from 31.12.2008. Since, the petitioner has not complied with the terms of the agreement, therefore, the petitioner cannot be permitted to raise the dispute at this stage. The petitioner is estopped to raise dispute now having failed to object to the decision of the engineer for more than one year.

Thus, there is no dispute which is required to be adjudicated by an arbitrator.

Dismissed.

(HEMANT GUPTA) JUDGE 11.8.2011 preeti