State of West Bengal - Section

Section 33 in West Bengal Municipal (Building) Rules, 2007

33. Completion of work.

— Within one month after the completion of the erection of a building or the execution of any work, the owner of the building shall submit a notice of completion in Form 'G' as required under section 212 of the Act. In case of deviation as stated in clause (a) of sub-rule (2) of rule 31, the notice shall be accompanied by three sets of building plan marked `completion plan' with all revisions and modifications including those referred to in sub-rule (2) of rule 31. The plans shall be duly signed by the applicant and the concerned technical personnel specified in rule 15Provided that for a residential building or educational building in any municipal area, excepting the Salt Lake Township, not exceeding 8.0 metre in height on a plot of 200 sq. metre in area, application of this rule may not be insisted upon but the owner will have to intimate in writing to the municipality about the completion of such building.Note.—The notice shall be 'accompanied by a structural safety certificate duly signed by the Architect or Licensed Building Surveyor and/or Empanelled Structural Engineer, as the case may be, and wherever applicable shall be accompanied by—
(a)in the case of a building having more than three separate and independent residential units or apartments and all buildings other than residential buildings, a certificate from the Technical persons employed as per rule 15 that inside house drainage and water supply net work have been completed to the satisfaction of the Municipal Authority:
(b)fire safety certificate, if applicable under the West Bengal Fire Services Act, 1950 (West Bengal Act No. 18 of 1950) and the rules made thereunder;
(c)in the case of building referred to in clause (a), a certificate from the electric supply undertaking regarding provision to its satisfaction, of transformer, sub-station, ancillary power supply as required; (d ) a certificate pertaining to the lift installation, if any;