State of Chattisgarh - Section

Section 100 in Chhattisgarh Building and Other Construction Workers' (Regulation of Employment and Conditions of Service) Rules, 2008

100. Mixing and pouring of concrete.

- The employer shall ensure at a con.-traction site of a building or other construction work that; -
(a)the concrete mixture does not contain any material which may unduly affect the setting of such concrete, weaken such concrete or corrode steel used with such concrete;
(b)when dry ingredients of concrete are being mixed in confined spaces such as silos;
(i)the dust shall be exhausted at the time of such mixing; and
(ii)in case the dust cannot be exhausted, as specified in sub-clause (i), the building workers shall wear respirators at the time of such mixing;
(c)when concrete is being tipped from buckets, building workers are kept out of the range of any kickbacks of such buckets;
(d)loads are not dumped or placed on settling concrete.