Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 1, Cited by 0]

Gujarat High Court

Bhagwati Ice & Cold Storage vs Gujarat Urja Vikas Nigam Ltd on 2 February, 2015

Author: Abhilasha Kumari

Bench: Abhilasha Kumari

        C/SCA/15665/2004                                   JUDGMENT




          IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

             SPECIAL CIVIL APPLICATION NO. 15665 of 2004



FOR APPROVAL AND SIGNATURE:


HONOURABLE SMT. JUSTICE ABHILASHA KUMARI
===========================================================
1   Whether Reporters of Local Papers may be allowed to see No
    the judgment ?

2    To be referred to the Reporter or not ?                          No

3    Whether their Lordships wish to see the fair copy of the         No
     judgment ?

4    Whether this case involves a substantial question of law as No
     to the interpretation of the Constitution of India, 1950 or any
     order made thereunder ?

5    Whether it is to be circulated to the civil judge ?              No

================================================================
            BHAGWATI ICE & COLD STORAGE....Petitioner(s)
                              Versus
         GUJARAT URJA VIKAS NIGAM LTD., & 1....Respondent(s)
================================================================
Appearance:
MS SUDHA R GANGWAR, ADVOCATE for the Petitioner(s) No. 1
MR SP HASURKAR, ADVOCATE for the Respondent(s) No. 1 - 2
================================================================

         CORAM: HONOURABLE SMT. JUSTICE ABHILASHA
                KUMARI

                            Date : 02/02/2015


                            ORAL JUDGMENT

1. This   petition   under   Article   226   of   the  Page 1 of 12 C/SCA/15665/2004 JUDGMENT Constitution   of   India,   has   been   preferred   with   a  prayer   to   quash   and   set   aside   the   order   dated  09.09.2004, passed by the Appellate Committee of the  respondent­Electricity Company, whereby the appeal of  the petitioner against the Supplementary Bill issued  to it, has been partly­allowed and the said bill has  been directed to be revised, by taking the ratio of  load factor and diversity factor at 0.3 in place of  0.4, for the chargeable period of December, 2002 and  January,   2003,   and   0.75   in   place   of   0.8   for   the  remaining chargeable period keeping the connected load  factor 'A' and chargeable factor 'D' unchanged.

2. The brief facts of the case, as garnered from the  material on record, are as follows:

2.1 The   petitioner   is   a   Proprietorship   Firm  manufacturing ice and is a consumer of the respondent­ Electricity Company. There was a blast in the meter of  the   electrical   installation   on   the   premises   of   the  petitioner.   The   petitioner   informed   the   Deputy  Engineer   of   the   local   office   of   the   respondent­ Electricity   Company,   by   a   letter   dated   04.09.2003,  Page 2 of 12 C/SCA/15665/2004 JUDGMENT that the meter was not working. Pursuant thereto, the  Deputy   Engineer   (O&M),   Chorwad,   went   to   the   site   on  04.09.2003 and checked the electrical installation of  the petitioner in the presence of a representative of  the petitioner. The connected load was taken and found  to be 90.5 Horse Power (HP). During the checking, it  was found that the door of the Metal Meter Box (MMB)  was lifted on one side on the lower part and a smell  of   burning   was   coming   from   the   MMB.   The   meter   was,  therefore,   removed   and   replaced.   The   old   meter   with  the MMB was wrapped and sealed and taken for further  inspection in the laboratory. The necessary Checking  Sheet and Rojkam were prepared to that effect and were  signed by a representative of the petitioner. Proforma  No.15 was also filled in for the replacement of the  meter. The MMB and meter were thereafter inspected in  the laboratory at Jamnagar, on 09.02.2004. At the time  of the inspection in the Laboratory, a representative  of the petitioner was present. During the laboratory  inspection, the MMB seal, terminal cover seal and MMB  lock were found to be tampered with and the R and Y  Phase   PT   wire   was   found   removed   from   the   terminal  block.   The   upper   portion   of   the   meter   cover   between  Page 3 of 12 C/SCA/15665/2004 JUDGMENT the   meter   body   and   the   cover   was   found   lifted   and  there was a black dot on the display glass window of  the meter. The necessary Laboratory Inspection Report  was   prepared   to   that   effect,   which   was   signed   by   a  representative of the petitioner. The Officers of the  respondent­Electricity Company came to the conclusion,  on the strength of the Laboratory Inspection Report,  that there was tampering with the MMB seal, MMB lock  and   terminal   cover   seal   of   the   meter.   In   addition  thereto,   it   was   concluded   that   there   was   tampering  with   the  wiring   of   the   terminal   block   and,   thereby,  the   petitioner   had   dishonestly   extracted   electrical  energy.   The   connection   of   the   petitioner   was  disconnected   on   14.02.2004,   and   the   petitioner   was  booked for theft of electrical energy. A Supplementary  Bill   of   Rs.13,70,711.27   Paisa   was   issued   to   the  petitioner   as   per   the   Rules   of   the   respondent­ Electricity   Company.   The   petitioner   did   not   deposit  any   amount   towards   the   Supplementary   Bill.   Its  connection   was,   therefore,   not   reconnected.   The  petitioner   preferred   an   appeal   before   the   Appellate  Committee to challenge the Supplementary Bill of theft  without   paying   the   amount   of   the   Supplementary   Bill  Page 4 of 12 C/SCA/15665/2004 JUDGMENT and without reconnection.
2.2 On   12.09.2005,   this   Court   issued   Rule   in   the  petition   and   granted   ad­interim   relief   on   condition  that the petitioner shall pay the outstanding dues in  respect   of   the   Supplementary   Bill,   along   with  necessary   reconnection   charges   and   delayed   payment  charges,   if   any,   in   six   equal   monthly   installments. 

The first installment was to be paid on, or before,  01.10.2005.   It   is   further   stated   in   the   said   order  that if any default is committed on the part of the  petitioner in making the payment as mentioned above,  it   would   be   open   for   the   Electricity   Company   to  disconnect   the   power   connection   of   the   petitioner  without any further orders.

2.3 Ms.   Sudha   R.   Gangwar,   learned   advocate   for   the  petitioner,   submits   that   she   has   no   instructions  regarding whether the amount of the Supplementary Bill  has   been  paid   by   installments  by  the   petitioner,   or  not.

2.4 Being   aggrieved   by   the   order   dated   09.09.2004,  passed by the Appellate Committee, the petitioner has  approached this Court by way of the present petition. Page 5 of 12

C/SCA/15665/2004 JUDGMENT

3. Though   a   number   of   grounds   have   been   stated   in  the Memorandum of the Petition and appear to have been  urged   before   the   Appellate   Committee,   Ms.Sudha   R.  Gangwar,   learned   advocate   for   the   petitioner,   has  confined her submissions before this Court to only the  following ground:

(1) It is submitted by Ms. Sudha R. Gangwar, learned  advocate for the petitioner, that the findings of the  Appellate   Committee   are   based   upon   the   Laboratory  Inspection   Report,   which   clearly   states   that   during  inspection,   it   was   found   that   the   door   of   MMB   was  found   lifted   from   the   lower   side   and   the   smell   of  burning   was   coming   outside   the   MMB.   Admittedly,   the  meter, MMB seal and terminal cover seal were found to  be tampered with. However, there is no finding to the  effect that the alleged tampering on the external side  of   the   meter   would   have   any   effect   on   its   internal  working. Only the outside meter cover bears marks of  alleged tampering, but from this finding it cannot be  assumed that there was any effect on the registration  of energy in the meter, or that the meter would run  slow because of it.
Page 6 of 12
C/SCA/15665/2004 JUDGMENT 3.1 No   other submissions have been advanced by the  learned advocate for the petitioner.
4. Mr.S.P.   Hasurkar,   learned   advocate   for   the  respondent­Electricity Company, has submitted that it  is   specifically   stated   in   the   Laboratory   Inspection  Report that the MMB seal and terminal cover seal were  found to be tampered with and the MMB seal was found  to have been re­fitted. It is clearly stated in the  said   Report   that   wires   of   the   R   and   Y   Phases   were  removed   from   the   terminal   block   and  there  was   black  ash on the display glass window and on the cable. That  it is clear from the Laboratory Inspection Report that  there was tampering with the meter. The tampering is  not   only   with   regard   to   the   MMB   seal,   MMB   lock   and  terminal cover seal, but is also with regard to R and  Y   Phase   PT   wires,   which   would   definitely   have   an  effect   on   the   accurate   registration   of   energy.   It  cannot,   therefore,   be   said   that   the   meter   was   only  tampered   with   externally   and   not   internally,   as   the  manner   in   which   the   R   and   Y   Phase   PT   wires   were  removed constitutes sufficient tampering to ensure the  recording of inaccurate meter readings. It is further  Page 7 of 12 C/SCA/15665/2004 JUDGMENT submitted   that   the   Laboratory   Inspection   Report   has  been signed, without protest, by the representative of  the   petitioner.   The   findings   arrived   at   by   the  Appellate Committee are based upon the findings on the  Laboratory Inspection Report which has been prepared  by   experts   in   the   field.   This   Court   would   not,  therefore, interfere with the findings on fact, based  upon material on record, arrived at by the Appellate  Committee. Hence, the petition may be dismissed.
5. This   Court   has   heard   learned   counsel   for   the  respective parties, perused the averments made in the  petition,   contents   of   the   impugned   order   and   other  documents on record.
6. The only point for determination that now arises  before   this   Court   is   regarding   the   findings   of   the  Appellate   Committee,   as   rendered   in   the   impugned  order,   based   upon   the   Laboratory   Inspection   Report  dated 09.02.2004. Before the Appellate Committee, the  petitioner had raised other contentions, such as, its  representative   was   made   to   sign   the   Laboratory  Inspection Report under pressure and that the seasonal  Page 8 of 12 C/SCA/15665/2004 JUDGMENT benefit   was   not   given   to   the   petitioner.   However,  before this Court, the above submissions have not been  pressed   and   the   learned   advocate   for   the   petitioner  has   confined   herself   only   to   the   findings   of   the  Appellate   committee,   based   on   the   Laboratory  Inspection Report, to the effect that the petitioner  has committed a theft of electrical energy.
7. In   the   impugned   order,   the   Appellate   Committee  has stated as below:
"...It   is   specifically   stated   in   the   checking   sheet and even in the local Rojkam that the door   of the MMB was found lifted from one lower side   and a smell of burning was coming out from the   MMB. It is also stated in the checking sheet that   the connected load was found at 90.5 HP. It is   also   specifically   stated   in   the   checking   sheet   and   even   in   the   Rojkam   that   the   MMB   with   the   meter   was   removed,   wrapped   and   sealed   and   was   taken  for  further  inspection   in  the  laboratory.  There is no dispute with regard to the aspect of   the   case.   Now   it   is   admittedly   clear   that   the   meter   and   the   MMB   seal   and   terminal   cover   seal   were inspected in the laboratory at Jamnagar on   9.2.2004 in the presence of the representative of   the   appellant.   It   is   also   clear   that   necessary   laboratory inspection report was prepared at that  Page 9 of 12 C/SCA/15665/2004 JUDGMENT time and it was signed by the representative of   the appellant. It is specifically stated in the   laboratory   inspection   report   that   the   MMB   seal   and terminal cover seal were found tampered with   and   MMB   lock   was   found   refitted.   It   is   also  stated in that laboratory inspection report that   the wires of R and Y phase PT wire removed from   the terminal block and there was a black ash on   the display glass window and even on the cable.   Thus,   the   laboratory   inspection   report   clearly   shows   that   there   was   a   tampering   with   the   MMB   seal,   MMB   lock,   terminal   cover   seal   and   even   R   and Y phase PT wires. There is no reason for us   not to rely on this laboratory inspection report,   which   is   signed   by   the   representative   of   the   appellant without any protest...."
"... However, it is very clear from the checking   sheet,   local   Rojkam   and   particularly   from   the   laboratory   inspection   report   that   there   is   sufficient  evidence   to  establish  that  there   was  tampering with the MMB seal, MMB lock, terminal   cover   seal   and   R   and   Y   phase   PT   wires   of   the   terminal block. If this is so, then it can not be   denied that an attempt was made to abstract the   electrical energy without being it fully recorded  in the meter. So, in our view, the case of theft   of  electrical   energy  is  established  against   the  appellant."

8. From the above findings, it can clearly be seen  Page 10 of 12 C/SCA/15665/2004 JUDGMENT that   not   only   were   the   MMB   seal   and   terminal   cover  seal of the meter found to be tampered with, but the  MMB lock was also found to be re­fitted. In addition  thereto,   the   R   and   Y   Phases   PT   wires   were   also  tampered   with.   The   tampering   with   the   wires   would  definitely   have   an   effect   on   the   accuracy   of   the  recording   of   energy   in   the   meter;   therefore,   the  submission of the learned advocate for the petitioner  that only the external part of the meter was tampered  with and not the internal, is without any substance.

9. There is no material on record to indicate that  the   Laboratory   Inspection   Report   is   erroneous.   The  said Report has been prepared by experts in the field  and   the   petitioner   has   not   placed   any   material   on  record to undermine its veracity. The findings of the  Appellate   Committee,   based   on   the   Laboratory  Inspection   Report,   are   findings   of   fact   based   upon  cogent material on record. It is a settled position of  law   that   this   Court,   while   exercising   its  extraordinary   jurisdiction   under   Article   226   of   the  Constitution   of   India,   may   not   interfere   with  findings of fact, unless and until they are proved to  Page 11 of 12 C/SCA/15665/2004 JUDGMENT be perverse or illegal. The learned advocate for the  petitioner has not succeeded in showing any perversity  or illegality in the said findings.

10. The   impugned   order   passed   by   the   Appellate  Committee is a well­reasoned one. It cannot be said,  after   perusing   the   same,   that   it   suffers   from   any  legal   defect,   so   as   to   warrant   the   interference   of  this Court.

11. For the aforesaid reasons, the petition fails and  is rejected. Rule is discharged. The interim relief,  if any, stands vacated. There shall be no orders as to  costs.

12. The petitioner shall pay the full amount of the  Supplementary   Bill   to   the   respondent­Electricity  Company, if not already paid, within a period of two  weeks from the date of the receipt of a copy of this  judgment. 

(SMT. ABHILASHA KUMARI, J.) piyush Page 12 of 12