Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 2]

National Company Law Appellate Tribunal

Jakson Engineers Ltd vs Refex Energy Ltd on 20 September, 2019

           NATIONAL COMPANY LAW APPELLATE TRIBUNAL
                         NEW DELHI
                 Company Appeal (AT) (Ins) No.12 of 2019

IN THE MATTER OF:

Jakson Engineers Ltd.                                       ...Appellant

      Versus

Refex Energy Ltd.                                           ...Respondent


Present:

For Appellant:           Shri Krishnendu Datta, Shri Divyam Agarwal, Ms.
                         Pallavi Kumar, Shri Raghav Sabharwal and Ms.
                         Mehak Khurana, Advocates

For Respondent:          Shri Kumarpal Chopra and Shri Siddhartha Iyer,
                         Advocates


                                   ORDER

20.09.2019 The Appellant - M/s. Jakson Engineers Limited (Operational Creditor) filed an Application under Section 9 of the Insolvency and Bankruptcy Code, 2016 (I&B Code - in short) for initiation of Corporate Insolvency Resolution Process against M/s. Refex Energy Limited (Corporate Debtor). However, the Adjudicating Authority (National Company Law Tribunal, Division Bench, Chennai) by Impugned Order dated 31st October, 2018 rejected the Application under Section 9 on the ground that there is a dispute about quantum of debt.

Learned Counsel for the Appellant submits that even if the debt is disputed, the amount being much more than Rs.1 Lakh, it was incumbent on the part of the Adjudicating Authority to admit the Application in absence of any pre-existing dispute.

-2-

On the other hand, according to learned Counsel for the Corporate Debtor, there is a dispute about quantum of payment and that the amount as shown in the Demand Notice under Section 8(1) varied as the balance amount payable was only Rs.75,97,141/- which the Corporate Debtor intended to settle.

The Adjudicating Authority has noticed that there is a debt payable by the Corporate Debtor and the same is not barred by limitation as apparent from the Impugned Order as quoted below:-

"12. The Creditor relied upon a letter dated 08.12.2014 written by the Corporate Debtor on ₹1,73,61,691 as balance confirmation but when this Bench has gone through that letter, it appears that the Corporate Debtor wrote it to the Creditor sending cheques for an amount of ₹1,73,61,691, according to the Creditor those cheques were bounced but thereafter over a period of time, the Debtor sent emails requesting the Creditor to attend the defects and service requirement in respect of the PV Boxes supplied to the Debtor, finally on 24.02.2016 sent the mail stating that out of ₹1,73,47,141, the Debtor is to pay only ₹75,97,141, because the Debtor incurred expenditure on attending the defects on their own when the Creditor did not turned up despite being called upon the attend the defects and service required to be given by the Creditor. Since warranty coverage is there for about five years, Company Appeal (AT) (Ins) No.12 of 2019 -3- though the Debtor admitted the debt claim in the year 2014 and sent cheques for the same, since the Creditor failed to comply with the warranty clause subsequent thereto, the Corporate Debtor sending such emails and finally saying that he is payable only ₹75,97,141 does not amount to either crystallization of debt or confirmation of debt. Out of all this correspondence, two things emanate, one is, the Creditor failed to comply with the warranty clauses, two is, the debt has not been crystalized between the parties as on the date Section 8 Notice was served upon the Debtor because the Debtor in the year 2016 itself sent email that the balance payable is only ₹75,97,141 and not the amount claimed by the Creditor as mentioned in the Company Petition.
13. Of course, as to limitation is concerned, there are continuous issues between the parties, whereby we refrain ourselves from deciding this point so that if parties go before civil court, it could be thrashed out on examining the documents available, if required on evidence being adduced."

It is observed that there being a dispute between the parties in respect of breach of warranty and defects clause, it was observed that the dispute is in existence. However, there is nothing on record to show that before issuance of Demand Notice under Section 8(1), any letter was issued by Corporate Debtor to show that there is an existence of dispute about Rs.75,97,141/-.

The learned Counsel for the Respondent referred to an e-mail dated 24th February, 2016 which reads as follows:-

Company Appeal (AT) (Ins) No.12 of 2019 -5- However, from the said letter dated 24th February, 2016, we find that the Corporate Debtor in Reply to one Mr. Sandeep Gupta (Operational Creditor) has shown amount of Rs.75,97,141 as payable.
As we find that there is no dispute with regard to the aforesaid amount and it remaining outstanding and being more than Rs.1 Lakh, the Application under Section 9 was fit to be admitted.
For the aforesaid reasons, we set aside the Impugned Order dated 31st October, 2018 and remit the case to the Adjudicating Authority to admit the Application under Section 9 after Notice to the Respondent, so that the Respondent may get an opportunity to settle the matter prior to the admission of the Application.
The Appeal is allowed with aforesaid observations. No cost.
[Justice S.J. Mukhopadhaya] Chairperson [Justice A.I.S. Cheema] Member (Judicial) [Kanthi Narahari] Member (Technical) /rs/sk Company Appeal (AT) (Ins) No.12 of 2019