Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 11, Cited by 1]

Delhi High Court

Ion Exchange (India) Ltd. vs Panasonic Electric Works Co. Ltd. And ... on 23 December, 2014

Author: Rajiv Sahai Endlaw

Bench: Rajiv Sahai Endlaw

*      IN THE HIGH COURT OF DELHI AT NEW DELHI

                                     Date of decision: 23rd December, 2014.

+                                ARB.P. 662/2014

       ION EXCHANGE (INDIA) LTD.                  ..... Petitioner
                   Through: Mr. Amey Nargolkar and Mr.
                             Aaditya Vijaykumar, Advocates.

                                 Versus

    PANASONIC ELECTRIC WORKS CO. LTD.
    AND ANR                            ..... Respondents
                  Through: None.
CORAM:
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW


1.     The petitioner has filed this petition under Section 11(6)(a) of the

Arbitration and Conciliation Act, 1996 (Arbitration Act) impleading

Panasonic Electric Works Co. Ltd., Japan (hereinafter called „Panasonic

Japan‟) as respondent No.1 and Panasonic India Pvt. Ltd. (hereinafter called

„Panasonic India‟) as respondent No.2 thereto, and pleading:

       (i)    that Panasonic Japan through the Panasonic India, in the year

       2010, approached the petitioner to discuss the possibility of a

       business venture / relationship and alliance;

       (ii)   that during the course of negotiation, a Mutual Non-Disclosure

       Agreement dated 6th December, 2010 was executed between the

ARB.P.No.662/2014                                               Page 1 of 12
        petitioner and Panasonic India, whereunder each of them agreed that

       any confidential information exchanged during the course of

       negotiation will not be used for any other purpose;

       (iii)   that thereafter on 14th September, 2011 two agreements were

       executed between the petitioner and "the respondents"; one being a

       Sales Agreement and other being a Development Agreement;

       (iv)    that under the Development Agreement, the petitioner was to

       develop the three models of water purifiers in terms of Annexure A to

       the agreement and once the water purifier was developed, the

       petitioner was required to manufacture the said water purifiers, as per

       the Sales Agreement;

       (v)     that the Development Agreement also contained a dispute

       resolution system by which all disputes, differences or controversies

       were to be finally settled under the London Council of International

       Arbitration (LCIA) India Arbitration Rules, with the seat of

       arbitration being New Delhi, India;

       (vi)    that the Sales Agreement also contained an arbitration clause

       which mandated that all disputes and differences would be

       mandatorily resolved by arbitration;


ARB.P.No.662/2014                                                 Page 2 of 12
        (vii) that the Sales Agreement was to come into effect only, once the

       product was developed and approved by the respondents;

       (viii) that though the petitioner over the next two years, at a huge

       cost and expense, developed the product as per the Development

       Agreement, inspite of breaches by the respondents of their part of the

       Development Agreement, but subsequently, in or about November,

       2012, the petitioner became aware of the dishonest intentions of the

       respondents, when the respondents failed to shift the manufacturing

       unit to India;

       (ix)   that in May, 2013, a meeting was held between the parties to

       work out the costing and on 28th May, 2013 it was decided to

       terminate "the previous agreement and the petitioner was required to

       submit a revised costing"; it was further agreed that if the revised

       costing was agreed to between the parties, then the parties will

       execute a fresh agreement and the petitioner will not be entitled to

       development costs, if revised costing was not agreed to, then the

       petitioner would be entitled to be compensated;

       (x)    that the parties could not arrive at a consensus as to the revised

       costing and "the respondents wrongfully terminated the Sales


ARB.P.No.662/2014                                                   Page 3 of 12
        Agreement";

       (xi)      that "the respondent is liable to pay a sum of Rs.90,21,930/-

       towards non-payment of certain invoices and development costs,

       besides being liable to pay unliquidated damages and would be

       further liable to pay Rs.1,59,41,517.84 to VSE, for the costs incurred

       by it";

       (xii) that the petitioner filed a petition under Section 9 of the

       Arbitration Act being O.M.P. No.150/2014;

       (xiii) that "the respondents are liable to pay the petitioner and its sub-

       contractors a sum of Rs.2.5 crores, besides unliquidated damages";

       (xiv) that the petitioner vide its letter dated 9th August, 2014 to the

       respondents invoked the arbitration clause;

       (xv) that a vague reply was sent by the respondent No.1;

       (xvi) that another notice dated 17th November, 2014 was got sent by

       the petitioner, calling upon the respondents to appoint an Arbitrator

       mutually;

       (xvii) that however the respondents failed to appoint an Arbitrator;

       (xviii) that the seat of arbitration being at New Delhi, India and

       otherwise under Section 42 of the Arbitration Act, this Court has


ARB.P.No.662/2014                                                   Page 4 of 12
        jurisdiction.

2.     A perusal of the documents filed by the petitioner, showed:

       (a)    that the   Mutual Non-Disclosure Agreement             dated 6th

       December, 2010 supra was between the petitioner and Panasonic

       India, as specifically pleaded by the petitioner also; though the same

       provided for arbitration of a sole Arbitrator to be appointed with

       mutual consent of parties, but the said agreement was for the period

       of negotiation only;

       (b)    though the petitioner had vaguely pleaded that both the

       agreements dated 14th September, 2011 were between the petitioner

       and the "respondents" but one of the agreements dated 14th

       September, 2011 i.e. the Sales Agreement, was between the petitioner

       and the Panasonic India and though executed in Mumbai, provides for

       arbitration of an Arbitral Tribunal of three Arbitrators, of which one

       is to be appointed by each of the parties and the third by the

       Arbitrators nominated by the petitioner and Panasonic India, with the

       venue of arbitration at New Delhi and in accordance with the

       Arbitration Act; and,

       (c)    the other agreement dated 14th September, 2011 titled

       "Development Agreement" is between the Panasonic Japan on the


ARB.P.No.662/2014                                                Page 5 of 12
        one hand and the petitioner on the other hand and provides for the

       resolution of disputes under the LCIA India Arbitration Rules, with

       the number of Arbitrators being one and the seat or legal place of

       arbitration being New Delhi, India and the agreement being governed

       in accordance laws of India.

3.     The matter came up first before this Court yesterday i.e. 22 nd

December, 2014, when it was enquired from the counsel for the petitioner,

whether not the mutual Non-Disclosure Agreement has ceased to exit /

operate upon the two agreements dated 14th September, 2011 being signed

and whether not the arbitration clause contained in the Mutual Non-

Disclosure Agreement is now of no avail.

4.     The counsel for the petitioner replied in the affirmative.

5.     It was next enquired from the counsel for the petitioner, whether not

the disputes for adjudication whereof the petitioner is now seeking

appointment of Arbitrator, are under the two separate agreements, one

between the petitioner and Panasonic India and other between the petitioner

and the Panasonic Japan and whether not Panasonic India and Panasonic

Japan are separate legal entities.

6.     The counsel for the petitioner again replied in the affirmative.

ARB.P.No.662/2014                                                   Page 6 of 12
 7.     It was next enquired from the counsel for the petitioner, as to how one

petition under Section 11(6)(a) has been filed with respect to two different

agreements executed by the petitioner with two different entities and

providing for different modes of arbitration. It was yet further enquired, as

to what were the LCIA India Arbitration Rules (the same have not been

filed by the petitioner) and whether the petitioner thereunder has taken any

steps for invoking the arbitration and as to whether without taking the said

requisite steps, petitioner can file a petition under Section 11(6) of the Act.

It was yet further enquired, whether not the arbitration under the

Development Agreement with Panasonic Japan is an international

commercial arbitration within the meaning of Section 2(1)(f) of the

Arbitration Act.

8.     The counsel for the petitioner though agreeing with each of the

aforesaid, contended that the disputes under the two agreements are

intermingled and common and having two arbitration proceedings before

different Arbitral Tribunals would unnecessarily increase the costs, to the

prejudice of the petitioner, and thus the petitioner has filed this petition to

have a common Arbitral Tribunal appointed for adjudication of disputes

under both the agreements and for adjudication of claims of the petitioner


ARB.P.No.662/2014                                                  Page 7 of 12
 against both, Panasonic India and Panasonic Japan. Reliance in this regard

was placed on paras 65, 66 and 67 of Chloro Controls (I) P. Ltd. Vs. Severn

Trent Water Purification Inc. (2013) 1 SCC 641 and on the order dated 18th

May, 2012 of a Co-ordinate Bench of this Court in ARB.P. No.69/2012

titled GMR Ambala Chandigarh Expressways Pvt. Ltd. Vs. National

Highways Authority of India.

9.     However, a perusal of the judgment aforesaid showed that in Chloro

Controls (I) (P). Ltd. supra, the Supreme Court observed that though

normally arbitration takes place between persons who have been parties to

both, the arbitration agreement as well as the substantive contract

underlining that agreement but it does occasionally happen that the claim is

made against or by someone who is not originally named as a party and

though the same creates some difficult situations, but they are not absolute

obstructions to the law / arbitration agreement and arbitration is possible

between a signatory to an arbitration agreement and a third party, though the

onus is heavy to show that such third party is claiming through or under the

signatory party as contemplated under Section 45 of the Arbitration Act. It

was further held that though the scope of an arbitration agreement is limited

to the parties who entered into it but in certain cases the "Group of


ARB.P.No.662/2014                                                Page 8 of 12
 Companies Doctrine" has also been applied and a non-signatory could be

subjected to arbitration provided these transactions with group of companies

and there was a clear intention to bind both, the signatory as well as the non-

signatory parties. It was further held that the intention of the parties is a

very significant feature which must be established before the scope of

arbitration can be said to including the signatory as well as the non-

signatory parties. As far as GMR Ambala Chandigarh Expressways Pvt.

Ltd. supra is concerned, the same is a consent order and thus cannot be used

as a precedent.

10.    It was thus further enquired from the counsel for the petitioner, as to

how the judgment of the Apex Court in Chloro Controls (I) (P). Ltd. supra

could be said to be applicable in the present situation, where the petitioner,

on the same day entered into two separate and distinct agreements with two

different companies, even if belonging to the same group, and providing

separate mechanism for resolution of disputes. It was enquired, whether not

the same was counter indicative of the parties having intended as aforesaid.

It further appears that Section 45 of the Arbitration Act, to which reference

was made by the Supreme Court, being in Part II of the Act relating to

enforcement of foreign awards, may not be applicable in the present case


ARB.P.No.662/2014                                                  Page 9 of 12
 which as per Section 2(2) of the Act is governed by Part I of the Arbitration

Act which applies where the place of arbitration is in India, as is the case

under both the agreements aforesaid.

11.    The counsel for the petitioner yesterday sought an adjournment to

today, stating that the respondents will be approached to find out whether

they are agreeable to a composite arbitration under both the agreements.

Accordingly, the matter was adjourned to today.

12.    The counsel for the petitioner today informed that the respondents are

not agreeable to a composite arbitration under both the agreements and

withdrew the petition with liberty to take separate steps under the two

separate and distinct agreements. However, later on, the counsel mentioned

the matter and stated that an order on merits may be made on this petition,

to enable the petitioner to approach the Supreme Court which may, in

exercise of its jurisdiction under Article 141 of the Constitution of India,

order for a composite Arbitral Tribunal.

13.    This Court having been vested the power to appoint the Arbitrator

under Section 11 of the Arbitration Act, is bound thereby and cannot

appoint an Arbitrator otherwise than as prescribed therein. Vide Section

11(2), the parties are free to agree on a procedure for appointing the

ARB.P.No.662/2014                                                Page 10 of 12
 Arbitrator or Arbitrators; failing such agreement, Section 11(3) provides

that in an arbitration with three Arbitrators, each party shall appoint one

Arbitrator, and the two appointed Arbitrators shall appoint the third

Arbitrator and Section 11(4) provides that upon failing of either party to

appoint an Arbitrator, the appointment shall be made by the Chief Justice or

any person designated by him; Section 11(5) provides that failing any

agreement under Section 11(2), in an arbitration with sole Arbitrator, if the

parties fail to agree on the Arbitrator, the sole Arbitrator shall be appointed

by the Chief Justice or his designate.      As per the said procedure, the

petitioner, for appointment of the sole Arbitrator under the Development

Agreement, governed by the LCIA India Arbitration Rules, is required to

approach LCIA i.e. London Council of International Arbitration and as per

the Sales Agreement is required to nominate an Arbitrator and call upon

Panasonic India to nominate its Arbitrator and neither of which steps have

been taken by the petitioner. The intention of the parties in the present case,

clearly was that the disputes if any of the petitioner with Panasonic India

and / or Panasonic Japan be adjudicated by separate mechanism with the

two, even if belonging to same group, being not party in each others

disputes. What the petitioner called upon the respondents jointly to do vide


ARB.P.No.662/2014                                                  Page 11 of 12
 the notices preceding the petition, is to agree on a sole Arbitrator under both

the agreements.

12.    The petition is thus clearly misconceived.        This Court, as the

designate of the Chief Justice of this High Court, in exercise of powers

under Section 11, is not empowered to grant the relief claimed.

13.    Before parting, mention may be made of the judgment of the Division

Bench of this Court (reported as Ion Exchange (India) Ltd. Vs. Panasonic

Electric Works Co. Ltd. 208 (2014) DLT 597) in a reference made by the

learned Single Judge in the Section 9 petition preferred by the petitioner,

though the counsel for the petitioner chose not to refer thereto or place on

record copy thereof and holding that this Court has territorial jurisdiction.

Though, from the judgment, the Section 9 petition appears to have been

preferred with respect to both agreement, but the question as considered

above does not appear to have been considered therein.

14.    Accordingly, the petition is dismissed. The petitioner of course will

have liberty to take appropriate steps for invoking arbitration in accordance

with the two agreements.

       No costs.
                                              RAJIV SAHAI ENDLAW, J.

DECEMBER 23, 2014/bs (corrected and released on January 05, 2015) ARB.P.No.662/2014 Page 12 of 12