Central Information Commission

K V Subrahmanyam vs Rail Vikas Nigam Ltd. on 15 May, 2025

                             केन्द्रीय सूचना आयोग
                       Central Information Commission
                          बाबा गंगनाथ मागग, मुननरका
                        Baba Gangnath Marg, Munirka
                         नई निल्ली, New Delhi - 110067


File No: CIC/RVNLT/A/2024/101278

K V Subrahmanyam                                      .....अपीलकर्ाग /Appellant



                                        VERSUS
                                         बनाम


CPIO,
Rail Vikas Nigam Ltd, Office
of the Divisional Railway
Manager, South Central
Railway, Guntur Division,
Commercial Branch, 2nd
Floor, Rail Vikas Bhawan,
Guntur - 522006                                       ....प्रनर्वािीगण /Respondent

Date of Hearing                     :    13.05.2025
Date of Decision                    :    14.05.2025

INFORMATION COMMISSIONER :               Vinod Kumar Tiwari

Relevant facts emerging from appeal:

RTI application filed on            :    12.07.2023
CPIO replied on                     :    Not on record
First appeal filed on               :    02.09.2023
First Appellate Authority's order   :    10.10.2023
2nd Appeal/Complaint dated          :    06.01.2024




                                                                        Page 1 of 15
 Information sought

:

1. The Appellant filed an RTI application dated 12.07.2023 (offline) seeking the following information:
"I request that the following information and copy of the documents certifying each page U/section 2 (j) (ii) of RTI Act 2005 may be supplied to the address given below. I am ready to pay the required fee as per the provisions of the Act. The details and mode of payment may be informed.
Month wise earnings at Mangalagiri, Nambur, Nallapadu, Perecherla, Phirangipuram, Nudurupadu, Santamaguluru, Savalyapuam, Kurichedu, Donakonda, Gajjalakonda, Tarlupadu, Jaggambhotlakrishnapuam, Somidevipalle, Gazulapalli, Panyam, Krisnammakona, Bugganipalli Cement Nagar, Rangapuram and Malkapuram Railway stations may be furnished for the financial years 2017-2018 to 2022-2023. It is requested to supply information duly certifying each page U/section 2 (j) (ii) of RTI Act 2005.
Vide reference 1st cited it was informed that "Competent authority has served notice in response to slow progress and the Agency M/s VBRL Infra Projects Limited, Bangalore has started balance works at RUB location ie, at LC No.241 near Gajjalakonda station". The RUB mentioned in my application is on the western side of Gajjalakonda station at manned level crossing prior to doubling, Bridge No.400,K.Μ.Νο.131/3 to 131/4. It may be informed when the RUB works will be completed in full, such as keeping signboard showing directions, lighting arrangement near the bridge, approach road, automatic drain of water with out stagnation resulting in mud formation giving troble in traffic movement especially in rainy season etc,.
Information regarding unmanned level crossings for the locations mentioned below may be supplied duly certifying each page U/section 2
(j) (ii) of RTI Act 2005.

a. Number of unmanned level crossings existed between Gajjalakonda and Donakonda prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing.

b. Number of unmanned level crossings existed between Gajjalakonda and Markapur prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing.

Page 2 of 15

c. Number of unmanned level crossings existed between Markapur and Nandyal prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing.

d. Number of unmanned level crossings existed between Donakonda and Guntur prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing.

e. Number of unmanned level crossings which are being converted into RUBs during the process of doubling that existed between Gajjalakonda and Donakonda prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing. If not converted, reasons for non conversion and alternate arrangements made to meet the purpose for which level crossing was kept prior to doubling work.

f. Number of unmanned level crossings which are being converted into RUBs during the process of doubling that existed between Gajjalakonda and Markapur prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing. If not converted, reasons for non conversion and alternate arrangements made to meet the purpose for which level crossing was kept prior to doubling work.

g. Number of unmanned level crossings which are being converted Into RUBs during the process of doubling that existed between Markapur and Nandyal prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing.If not converted, reasons for non conversion and alternate arrangements made to meet the purpose for which level crossing was kept prior to doubling work.

h. Number of unmanned level crossings which are being converted into RUBs during the process of doubling that existed between Donakonda and Nandyal prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing. If not converted, reasons for non conversion and alternate arrangements made to meet the purpose for which level crossing was kept prior to doubling work.

4. Information regarding manned level crossings for the locations mentioned below may be supplie duly certifying each page U/section 2 (j)

(ii) of RTI Act 2005.

Page 3 of 15

a. Number of manned level crossings existed between Gajjalakonda and Donakonda prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing. b. Number of manned level crossings existed between Gajjalakonda and Markapur prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing.

c. Number of manned level crossings existed between Markapur and Nandyal prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing.

d. Number of manned level crossings existed between Donakonda and Guntur prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing.

e. Number of manned level crossings which are being converted into RUBs during the process of doubling that existed between Gajjalakonda and Donakonda prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing. If not converted, reasons for non conversion and alternate arrangements made to meet the purpose for which level crossing was kept prior to doubling work.

f. Number of manned level crossings which are being converted into RUBs during the process of doubling that existed between Gajjalakonda and Markapur prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing. If not converted, reasons for non conversion and alternate arrangements made to meet the purpose for which level crossing was kept prior to doubling work.

g. Number of manned level crossings which are being converted into RUBs during the process of doubling that existed between Markapur and Nandyal prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing. If not converted, reasons for non conversion and alternate arrangements made to meet the purpose for which level crossing was kept prior to doubling work.

h. Number of manned level crossings which are being converted into RUBs during the process of doubling that existed between Donakonda and Nandyal prior to doubling work with details kilometer No., level crossing No., and purpose of level crossing. If not converted, reasons for non conversion and alternate arrangements made to meet the purpose for which level crossing was kept prior to doubling work.

Page 4 of 15

5. A representaion was submitted to Divisional Railway Manager, S.C.Railway, Guntur on 10.03.2023 during his visit to Markapur Railway station by the villagers of Gajjalakonda and surrounding villages requesting stoppage of Trains at Gajjalakonda Railway station. The action taken on the representaion may be informed.

6. Vide reference 2nd cited it was informed that Conversion of Passenger trains into express trains is in the level of Hqrs.It may be informed whether any action was taken to bring the facts to the notice of Hors such as the necessity of stoppage of trains at Gajjalakonda,problems faced by public due to non stoppage of trains, conversion of short distance trains also in to express trains, earnings at Gajjalakonda station when compared to stations with less earnings but stoppage provided at these stations such as Nudurupadu, Santamaguluru, Savalyapuam, Jaggambhotlakrishnapuam and Somidevipalle. If so a copy of the letter addressed to Hqrs.may be supplied.

7. It may be informed the list of Stations selected under Amrit Bharat Station Redevelopment Scheme in Guntur Railway Division.

8. It may be informed Station wise funds allotted, item of works proposed to be taken up station wise, proposed period of completion of all woks station wise and present stage of works station wise for the Stations selected under Amrit Bharat Station Redevelopment Scheme in Guntur Railway Division.

9.It may be informed whether display boards will be kept at all stations where required showing coach position on platform as well as in station premises, train wise platform allotment, arrival and delay if any of the trains and announcement of arrival of trains with full details. If not all, list of stations where these facilities will be provided may be informed."

2. Not having received any response from the CPIO, the Appellant filed a First Appeal dated 02.09.2023. The FAA vide its order dated 10.10.2023, held as under:

"1. As per section 2 (f) of RTI Act 2005, "information" means any material in any form including records, documents, memos, e-mails, opinions, advices, press releases, circulars, orders, logbooks, contracts, reports, papers, samples, models, data material held in any electronic form.
Page 5 of 15
As per the Act, if the information sought in form of photocopy, it shall be provided in the form of photocopy, or if it is sought in the form of floppy, it shall be provided in the form subject to the conditions given in the Act. It does not mean that the PIO shall re-shape the information. The Act, however, does not require the Public Information Officer to deduce some conclusion from the 'material' and supply the 'conclusion' so deduced to the applicant. It means that the Public Information officer is required to supply the 'material' in the form as held by the Public Authority, but not to do research on behalf of the citizen to deduce anything from the material and then supply it to him.
2. Work is in progress. Work will be completed in all aspects by December 2023.

3(a)
S.      LC No.   location    Between          Manned/            Purpose of LC
No.                          stations         Unmanned
1       244      124/2-3     DKD-GJJ          M                  To cross railway
                                                                 track
2       243      127/5-6     DKD-GJJ          M                  To cross railway
                                                                 track
3       242      129/1-2     DKD-GJJ          M                  To cross railway
                                                                 track

3(b)
S.      LC No.   location    Between          Manned/            Purpose of LC
No.                          stations         Unmanned
1       240      132/8-9     GJJ-MRK          M                  To cross railway
                                                                 track
2       239      138/1-2     GJJ-MRK          M                  To cross railway
                                                                 track
3       238      140/7-8     GJJ-MRK          M                  To cross railway
                                                                 track

3(c )
S.      LC No.   location     Between          Manned/            Purpose of LC
No.                           stations         Unmanned
1       235      146/1-2      MRK-TLU          UM                 To cross railway
                                                                  track
2       234      148/0-1      MRK-TLU          UM                 To cross railway
                                                                  track
3       232      153/8-9      MRK-TLU          UM                 To cross railway
                                                                  track
4       225      164/2-3      TLU-CBM          UM                 To cross railway
                                                                 Page 6 of 15
                                                           track
5      224     165/5-6       TLU-CBM      UM              To cross railway
                                                          track
6      223     166/6-7       TLU-CBM      UM              To cross railway
                                                          track
7      218     175/5-6       CBM-SDV      UM              To cross railway
                                                          track
8      215     180/2-3       CBM-SDV      UM              To cross railway
                                                          track
9      208     200/1-2       SDV-GID      UM              To cross railway
                                                          track
10     207     201/18-9      SDV-GID      UM              To cross railway
                                                          track
11     202     208/2-3       GID-DMT      UM              To cross railway
                                                          track
12     198     212/3-4       GID-DMT      UM              To cross railway
                                                          track
13     191     244/4-5       GZL-NDL      UM              To cross railway
                                                          track
14     189     247/9/248/0 GZL-NDL        UM              To cross railway
                                                          track
15     188     250/6-7       GZL-NDL      UM              To cross railway
                                                          track
16     182     258/9-259/0 NDL-PNM        UM              To cross railway
                                                          track
17     178     261/5-6       NDL-PNM      UM              To cross railway
                                                          track

3(d)
S.No. LC No.    Location       Between  Manned/Unmanned Purpose of LC
                               stations
1      308      8/14 - 9/0     NLPD-PPM UM              To         cross
                                                        railway track
2      303      15/11 - 12     NLPD-PPM UM              To         cross
                                                        railway track
3      301      17/4 - 5       NLPD-PPM UM              To         cross
                                                        railway track
4      300      18/9 - 10      NLPD-PPM UM              To         cross
                                                        railway track
5      299      20/1 - 2       NLPD-PPM UM              To         cross
                                                        railway track
6      293      32/14-33/0     PPM-STUR UM              To         cross
                                                        railway track
7      281      48/6 - 7       MUK-NRT UM               To         cross
                                                        railway track
                                                          Page 7 of 15
 8     280       50/1 - 2      NRT-SAB     UM                  To         cross
                                                              railway track
9     278       54/4 - 5      SAB-MUK     UM                  To         cross
                                                              railway track
10    277       56/0 - 1      SAB-MUK     UM                  To         cross
                                                              railway track
11    276       57/4 - 5      SAB-MUK     UM                  To         cross
                                                              railway track
12    274       63/4-5        SAB-SYM     UM                  To         cross
                                                              railway track
13    270A      68/4 - 5      SAB-SYM     UM                  To         cross
                                                              railway track
14    270       68/6 - 7      SAB-SYM     UM                  To         cross
                                                              railway track
15    261       89/4 - 5      VKN-GKM     UM                  To         cross
                                                              railway track
16    255       99/5-6        GKM-KCD     UM                  To         cross
                                                              railway track
17    252       104/6-1       GKM-KCD     UM                  To         cross
                                                              railway track
18    250       109/5-6       KCD-DKD     UM                  To         cross
                                                              railway track
19    247       117/6-7       KCD-DKD     UM                  To         cross
                                                              railway track

3(e) Doubling work was taken up by Construction organization. During doubling, no unmanned LC gate was converted into RUB by Construction organization between Donakonda and Gajjelakonda stations. Reasons for non conversion of LCs into RUBs pertains to Construction Organization.
3(f) Doubling work was taken up by Construction organization. During doubling, no unmanned LC gate was converted into RUB by Construction organization between Gajjelakonda and Markapur road stations. Reasons for non conversion of LCs into RUBs pertains to Construction Organization.
3(g) Doubling work was taken up by Construction organization. During doubling, no unmanned LC gate was converted into RUB by Construction organization between Markapur road and Nandyal stations. Reasons for non conversion of LCs into RUBs pertains to Construction Organization.
3(h) Doubling work was taken up by Construction organization. During doubling, no unmanned LC gate was converted into RUB by Construction Page 8 of 15 organization between Guntur and Donakonda stations. Reasons for non conversion of LCs into RUBs pertains to Construction Organization.

4(a)
S.No. LC     Location     Between Purpose Manned/Unmanned Purpose of LC
      No.                 stations of LC
1     245    120/9-       DKD-GJJ To cross M              To        cross
             121/0                 railway                railway track
                                   track

4(b)
S.No. LC        Location Between stations   Manned/Unmanned    Purpose of LC
      No.
1     241       131/1-2    GJJ-MRK          M                  To cross railway
                                                               track
2      237      142/6-7    GJJ-MRK          M                  To cross railway
                                                               track
3      236      143/6-7    GJJ_MRK          M                  To cross railway
                                                               track

4(c)
Sl.No. LC No.     Location     Between       Manned/Unmanned Purpose of LC
                               stations
1      233        150/0 - 1    MRK-TLU       M                  To        cross
                                                                railway track
2      231        154/9     - MRK-TLU        M                  To        cross
                  155/0                                         railway track
3      230        155/7 - 8   MRK-TLU        M                  To        cross
                                                                railway track
4      229        158/5 - 6    TLU-CBM       M                  To        cross
                                                                railway track
5      228        164/2 - 3    TLU-CBM       M                  To        cross
                                                                railway track
6      227        167/5 - 6    TLU-CBM       M                  To        cross
                                                                railway track
7      226        169/5 - 6    TLU-CBM       M                  To        cross
                                                                railway track
8      222        171/2 - 3    TLU-CBM       M                  To        cross
                                                                railway track
9      221        173/7 - 8    TLU-CBM       M                  To        cross
                                                                railway track
10     220        178/4 - 5    CBM-SDV       M                  To        cross
                                                                railway track
11     219        185/6 - 7    CBM-SDV       M                  To        cross
                                                              Page 9 of 15
                                           railway track
12   217    188/1 - 2   CBM-SDV    M      To        cross
                                          railway track
13   216    177/2 - 3   CBM-SDV    M      To        cross
                                          railway track
14   214    162/8 - 9   CBM-SDV    M      To        cross
                                          railway track
15   213    156/7 - 8   CBM-SDV    M      To        cross
                                          railway track
16   212    189/8 - 9   SDV-GID    M      To        cross
                                          railway track
17   211    192/5 - 6   SDV-GID    M      To        cross
                                          railway track
18   210    194/5 - 6   SDV-GID    M      To        cross
                                          railway track
19   209    197/1 - 2   SDV-GID    M      To        cross
                                          railway track
20   206    203/0 - 1   SDV-GID    M      To        cross
                                          railway track
21   205    203/2 - 3   SDV-GID    M      To        cross
                                          railway track
22   204    204/5 - 6   GID-DMT    M      To        cross
                                          railway track
23   203    207/0-1     GID-DMT    M      To        cross
                                          railway track
24   201    208/8 - 9   GID-DMT    M      To        cross
                                          railway track
25   199    211/2 - 3   GID-DMT    M      To        cross
                                          railway track
26   197    258/0 - 1   DMT YARD   M      To        cross
                                          railway track
27   192    260/6 - 7   CMZ-GZL    M      To        cross
                                          railway track
28   190    248/4 - 5   GZL-NDL    M      To        cross
                                          railway track
29   188A   252/4 - 5   GZL-NDL    M      To        cross
                                          railway track
30   187    215/2 - 3   GZL-NDL    M      To        cross
                                          railway track
31   186    253/1 - 8   GZL-NDL    M      To        cross
                                          railway track
32   184    242/0 - 1   NDL-PNM    M      To        cross
                                          railway track
33   183    245/0 - 1   NDL-PNM    M      To        cross
                                          railway track
                                       Page 10 of 15
 34       181       257/4 - 5     NDL-PNM    M                    To        cross
                                                                 railway track
35       180       259/4 - 5     NDL-PNM    M                    To        cross
                                                                 railway track

4(d)
Sl.No.    LC No. Location      Between     Manned/   Purpose of LC
                               stations    Unmanne
                                           d
1         314     1/15 - 17    GNT-NLPD    M         To cross railway track
2         313     1/31 - 33    GNT-NLPD    M         To cross railway track
3         312     3/9 - 11     GNT-NLPD    M         To cross railway track
4         311/1   4/31-33      NLPD YARD   M         To cross railway track
5         310/2   6/3-4        NLPD-PPM    M         To cross railway track
6         309     7/6-7        NLPD-PPM    M         To cross railway track
7         307     10/3-4       NLPD-PPM    M         To cross railway track
8         305     11/10-11     NLPD-PPM    M         To cross railway track
9         304     13/0-1       NLPD-PPM    M         To cross railway track
10        302     17/0-1       NLPD-PPM    M         To cross railway track
11        298     20/5-6       NLPD-PPM    M         To cross railway track
12        297     22/11-12     PPM-STUR    M         To cross railway track
13        296A    24/11-12     PPM-STUR    M         To cross railway track
14        296     25/9-10      PPM-STUR    M         To cross railway track
15        294     30/7-8       PPM-STUR    M         To cross railway track
16        291     34/4-5       STUR-NRT    M         To cross railway track
17        290     36/0-1       STUR-NRT    M         To cross railway track
18        289     36/11-12     STUR-NRT    M         To cross railway track
19        288     37/4-5       STUR-NRT    M         To cross railway track
20        287     40/7-8       STUR-NRT    M         To cross railway track
21        286     43/1-2       STUR-NRT    M         To cross railway track
22        284     44/7-8       STUR-NRT    M         To cross railway track
23        283     44/13-14     STUR-NRT    M         To cross railway track
24        282     46/5-6       STUR-NRT    M         To cross railway track
25        279     52/7-8       SAB-MUK     M         To cross railway track
26        275     58/7-8       SAB-MUK     M         To cross railway track
27        273     65/1-2       SAB-SYM     M         To cross railway track
28        271     67/6-7       SAB-SYM     M         To cross railway track
29        269     70/1-2       SAB-SYM     M         To cross railway track
30        268     73/0-1       SYM-VKN     M         To cross railway track
31        267     75/0-2       SYM-VKN     M         To cross railway track
32        265     79/4-5       SYM-VKN     M         To cross railway track
33        264     82/9-        VKN-GKM     M         To cross railway track
                  83/0
34        263     84/0-1       VKN-GKM     M         To cross railway track
                                                             Page 11 of 15
 35        260    90/0-1     VKN-GKM         M         To cross railway track
36        258    94/1-2     VKN-GKM         M         To cross railway track
37        257    95/5-6     VKN-GKM         M         To cross railway track
38        256    96/7-8     GKM-KCD         M         To cross railway track
39        254    100/5-6    GKM-KCD         M         To cross railway track
40        253    104/3-4    GKM-KCD         M         To cross railway track
41        251    106/8-9    GKM-KCD         M         To cross railway track
42        250A   108/7-8    KCD-DKD         M         To cross railway track
43        249    112/4-5    KCD-DKD         M         To cross railway track
44        248    114/1-2    KCD-DKD         M         To cross railway track
45        246    119/4-5    DKD-KCD         M         To cross railway track

4(e) Doubling work was taken up by Construction organization. During doubling, no manned LC gate was converted into RUB by Construction organization between Markapur road and Nandyal stations. Reasons for non conversion of LCs into RUBs pertains to Construction Organization.
4(f) Doubling work was taken up by Construction organization. During doubling, no manned LC gate was converted into RUB by Construction organization between Markapur road and Nandyal stations. Reasons for non conversion of LCs into RUBs pertains to Construction Organization.
4(g) Doubling work was taken up by Construction organization. During doubling, no manned LC gate was converted into RUB by Construction organization between Markapur road and Nandyal stations. Reasons for non conversion of LCs into RUBs pertains to Construction Organization.
4(h) Doubling work was taken up by Construction organization. During doubling, no manned LC gate was converted into RUB by Construction organization between Guntur and Donakonda stations. Reasons for non conversion of LCs into RUBs pertains to Construction Organization.
5 At present, the following trains are having stoppage at Gajjalakonda.
S.No. Train No. From-To PTT Timing 1 07889 RAL-MRK 09:21 09:22 2 17252 KCG-GNT 08:17 08:18 3 07890 MRK-GNT 09:59 10:00 4 17251 GNT-KCG 19:33 19:34 Page 12 of 15 However, a proposal for T.No. 17253/17254, 17227/17228 & 17329/17320 was sent to HQ vide letter No. GNT/T.463/WTT/Vol.1/2023 27.04.2023. dt.
6 Conversion of passenger trains into express trains is in the level of Headquarters. The decision will not be taken at Divisional level. However, following proposals were sent to Headquarters on 27-4- 23 for providing halt at Gajjelakonda.
Tr.No. From-To Provision of stoppage at station.
17253/54              GNT-SC-GNT                 GJJ, SYM
17227/28              DHNE-GNT-DHNE              GJJ
17329/30              UBL-BZA-UBL                GJJ

7 List of stations selected under Amrit Bharat Station Redevelopment Scheme in Guntur Railway Division Guntur are furnished bellow:
Sl.No.      Station            Aminities
            Mangalagiri,       Provision of Display systems
            Giddalur,          Improvements to MEA & Divyangjan facilities
            Narasaraopet,      Provision of Passenger lifts
1           Vinukonda,         Improvements to Façade
            Satenapalli, Nadikudi,
Improvements to Station Circulating Areas, Station Macherla approaches Improvements to Platforms and their Shelters Improvements to MEA & Divyangjan facilities Provision of Passenger lifts Improvements to Façade 2 Repalle Improvements to Station Circulating Areas, Station approaches Improvement to Station Buildings (Construction of new station buildings) 12.0m Wide FOB Improvements to Platforms and their Shelters Donakonda, Guntur, Improvements to MEA & Divyangjan facilities Nandyala, Markapur Provision of Passenger lifts Road, Cumbum, Improvements to Façade

3 Piduguralla, Improvements to Station Circulating Areas, Station Nalgonda, approaches Miryalaguda. 12.0m Wide FOB Improvements to Platforms and their Shelters Improvements to MEA & Divyangjan facilities Provision of Passenger lifts Improvements to Façade Page 13 of 15 4 Piduguralla Improvements to Station Circulating Areas, Station approaches Improvement to Station Buildings (Construction of new station buildings) Improvements to Platforms and their Shelters 8 List of Stations (ABSS) Sl.no Station Phase-I Sanctioned Phase-II (FOB's) Total (Cost in (Cost in Thousands Sanctioned (Cost in Thousands of of Rs.) Thousands of Rs.) Rs.) 1 Guntur 158071 248682 406753 2 Mangalagiri 125653 - 125653 3 Repalle 255671 - 255671 4 Nandyal 105934 112100 218034 5 Giddalur 117224 - 117224 6 Cumbum 117224 - 117224 7 Markapur 115820 99200 215020 8 Narasaraopet 113269 118000 231269 9 Vinukonda 124559 - 124559 10 Donakonda 183120 - 183120 11 Piduguralla 193069 84282 277351 12 Satenapalli 112990 - 112990 13 Nadikudi 112990 - 112990 14 Nalgonda 95169 75000 170169 15 Miryalaguda 95169 72700 167869 16 Macherla 95169 - 95169 Total 2121102 809964 2931066 9 Guntur, New Guntur, Nandyala, Vinukonda, Narasaraopeta, Sattenapalli, Piduguralla, Nadikudi, Miryalaguda, Nalgonda."

3. Feeling aggrieved and dissatisfied, Appellant approached the Commission with the instant Second Appeal.

Relevant Facts emerged during Hearing:

The following were present:-
Appellant: Absent Respondent: Shri Ravi Raju, CPIO/ Assistant Operations Manager, appeared through video conference.
Page 14 of 15

4. The Respondent while defending their case inter alia submitted that the information sought by the Appellant was duly provided within the stipulated time under the RTI Act. Additionally, they clarified that the available records were disclosed, and no further documents exist in the Respondent's custody.

Decision:

5. The Commission after adverting to the facts and circumstances of the case, hearing the Respondent and perusal of the records, observed that the Respondent has provided the available information to the Appellant as per the provisions of the RTI Act vide letter dated 10.10.2023. The Appellant remained absent despite service of hearing notice and in his absence the reasons for dissatisfaction to the information/reply provided by the Respondent authority could not be ascertained. That being so, and the detained information having been furnished to the Appellant, the Commission finds no scope for intervention under the RTI Act.

The appeal is dismissed accordingly.

Vinod Kumar Tiwari (विनोद कुमार वििारी) Information Commissioner (सूचना आयुक्त) Authenticated true copy (अनिप्रमानणर् सत्यानपर् प्रनर्) (S. Anantharaman) Dy. Registrar 011- 26181927 Date Copy To: