Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 7, Cited by 1]

Jharkhand High Court

M/S Narsingh Ispat Limited vs State Of Jharkhand & Anr on 20 August, 2014

Equivalent citations: 2015 (1) AJR 256

Author: D. N. Upadhyay

Bench: D. N. Upadhyay

1 IN THE HIGH COURT OF JHARKHAND AT RANCHI W.P. (Cr.) No.422 of 2010 ­­­­­ M/s. Narsingh Ispat Limited.  ....... Petitioner. 

­Versus­ The State of Jharkhand & Anr. .......Respondents. 

­­­­­ CORAM : HON'BLE MR. JUSTICE D. N. UPADHYAY ­­­­­ For the Petitioner  : Mr. N. K. Pasari, Advocate For the Respondents : Mr. Ajit Kumar, Advocate  ­­­­­ th th  CAV on 18    July, 2014      Pronounced on 20    August, 2014      ­­­­­ D.N. UPADHYAY: I.A. No.3411 of 2014 has been filed with a prayer  to allow the writ petitioner to amend the writ petition and  add   prayer   in   Para­1   as   well   as   prayer   portion   of   the   writ  petition. 

On   being   satisfied   with   the   grounds   taken   in   the  interlocutory application and  the amendment prayed for is  based on same factual foundation and the same would not  change   nature   of   the   writ   petition,   the   interlocutory  application   is   allowed.   Amendment   prayed   for   stands  allowed. 

Accordingly, I.A. No.3411 of 2014 is disposed of.  W.P. (Cr.) No.422 of 2010:

This writ petition has been preferred by the petitioner­ M/s.   Narsingh   Ispat   Limited,   through   its   Director,   namely,  Hemant Goyal for quashing the first information report and  entire   criminal   proceeding,   arising   out   of   Saraikella­ Kharsawan   Chowka   P.S.   Case   No.53   of   2010   dated   16th  September,   2010,   corresponding   to   G.R.   No.748   of   2010,  registered   under   Sections   126   and   135   of   the   Indian  Electricity   Act,   2003.   Further   prayer   has   been   made   for  quashing the order dated 13th September, 2013 passed by Sri  S.   N.   Sinha,   learned   Judicial   Magistrate,   Saraikella   in  connection with G.R. No.748 of 2010, whereby cognizance  has  been  taken  under Sections  135 and  126  of  the  Indian  Electricity Act, 2003.
2

2. It   is   contended   that   the   petitioner   is   a   Company  incorporated under the provisions of Companies Act, 1956

3. The   brief   facts   of   the   case   is   that   an   electric  connection from Jharkhand State Electricity Board (for short  'JSEB') has been taken by the petitioner for running industry  (Blast   Furnace)   vide   Consumer   No.HT   60   at   33   KV   falling  under HTSS Mode of Tariff of 2004 for a contract demand of  1200   KVA.   The   power   supply   in   the   factory   premises   was  commenced from 15th September, 2008.

4. According   to   the   first   information   report   on   16th  September,   2010,   at   about   01:00   p.m.,   the   informant   and  other officials of JSEB had gone to the factory premises of  the petitioner in order to install cubical metering unit and in  course of that they found that seal bit of main meter room  was   broken.   When   the   officials   of   the   JSEB   made   further  inspection, they found that seal bit of meter and meter box  were also broken and there was sign of tampering with the  meter by using screwdriver; paper seal bit and holography  seal   were   also   found   cut;   check   meter   was   also   found  damaged after breaking seal bit of meter box. Since there  was   ample   evidence   available   on   record,   indicating  commission of theft of electricity, inspection report as well as  seizure list were prepared in presence of representative(s) of  the accused/ petitioner­Company. The loss incurred to the  JSEB   due   to   illegal   abstraction   of   electric   energy   was  assessed to the tune of Rs.11,50,000/­. 

5. A   written   report   was   prepared   by   the   Assistant  Electrical Engineer, Electric Supply Sub Division, Chandil and  was lodged with Chandil Police Station after which Chowka  P.S. Case No.53 of 2010, as indicated above, was registered. 

6. The   writ   petitioner   has   challenged   the   institution   of  criminal prosecution launched against it on the ground, inter  alia, that;

(i) The   petitioner   has   installed   a   Trivector   Energy  Meter,   which   provides   High   Accuracy   and  capable   of   recording   even   small   tripping.   Its  software quality to detect and report conditions  3 of   high   tampers   like   misuse   of   voltage,   CT  reversal   and   current   imbalances.   In   fact,   the  software   security   system   of   securing   energy  meter   virtually   eliminates   any   fraud   or   tamper  attempts on the meter.

(ii) On   1st  September,   2010   i.e.   before   fortnight   of  the alleged incident, the metering system of the  petitioner   was   inspected   for   the   purpose   of  monthly   meter   reading   and   all   the   seals  associated   to   metering   room/metering  unit/metering   box/transformer   and   other  instruments   were   found   correct   and,  accordingly,   reading   report   was   submitted  (Annexure­1). 

(iii) Before   lodging   of   the   first   information   report,  meter   existing   in   the   factory   premises   was  neither installed nor sent to National Laboratory  for   verification   about   the   accuracy   of   the  consumption. 

(iv) Provisional   assessment   served   upon   the  petitioner was for 1105 hours  i.e. from 28th  July,  2010 to 16th September, 2010, but it is to be noted  that   on   1st  September,   2010   when   the   meter  reading   report   was   prepared   no   anomaly   of  any   nature   was   recorded,   so   as   to   allege  offence under Section 135 of the Electricity Act,  2003.

(v) As   per   sub­clause   (vii)   of   Clause   15.8   of   the  Electricity Supply Code Amendment Regulation,  2010   (hereinafter   to   be   referred   as   'Supply  Code'), the authorities  of the JSEB  have been  restrained   from   booking   a   case   of   theft   of  electricity   against   any   consumer   only   on  account   of   seals   on   the   meter   missing   or  tampered or breakage of  glass  window unless  theft   of   energy   is   being   corroborated   by  consumption pattern or any other evidence. 

4

(vi) The authorities of the JSEB did not even bother  to   look   into   consumption   pattern   of   the  Company, in question. The informant and other  officials of the JSEB did not verify other required  elements   before   lodging   the   first   information  report. 

(vii) Under   Sub­clause   (x)   of   Clause   15.8   of   the  Supply   Code,   in   case   of   suspected   theft   of  energy, the officer is bound to remove the old  meter under a seizure memo and seal the same  in   presence   of   the   consumer   and   send   it   for  testing   before   third   party   approved   by   the  Commissioner   and   continue   the   supply   with   a  new meter. 

(viii) The   provision   of   sub­clause   (xi)   of   Clause   15.8  reads as under:

"The   report   shall   be   signed   by   the   Authorized   officer   and   each   member   of   the   inspection   team and the same must be handed over to the   consumer   or   his/her   representative   at   site   immediately   under   proper   receipt.   In   case   of   refusal   by   the   consumer   or   his/her   representative   to   either   accept   or   give   a   receipt,   a   copy   of   inspection   report   must   be   pasted at the conspicuous place in/outside the   premises   and   photographed.   Simultaneously,   the report shall be sent to the consumer under   Registered   Post/Speed   Post   on   the   day   or   the   next day of the inspection.
Provided that, in case of suspected theft,   if  the consumption  pattern  for last one  year is   reasonably uniform and is not less than 75% of   the   assessed   consumption,   no   further   proceedings   shall   be   taken   and   the   decision   shall be communicated to the consumer under   proper   receipt   within   three   days   and   connection   shall   be   restored   through   original   meter."

By referring the above provision and Annexure­4  (energy bill), it was submitted that consumption  was consistent and it was more than 75% and  no   evidence   with   regard   to   change   in   the  consumption pattern was noticed, therefore, no  prosecution   of   the   petitioner   for   committing  theft   of   energy   under   Section   135   of   the  5 Electricity   Act,   2003   should   have   been  launched.

(ix) Only with the allegation of tampering of seals of  the   meter,   meter   room   and   check   meter  assuming   that   theft   of   energy   has   been  committed,   the   first   information   report   was  lodged. 

(x) The   meter   was   not   found   truncated   by   any  artificial   means   nor   any   electric   wire   was  inserted   to   divert   the   consumption   nor   any  foreign   device   was   attached   to   suggest  dishonest   abstraction/   consumption   or   use   of  electrical energy.        

7. Learned   counsel   for   the   petitioner,   in   support   of   the  said contentions, relied upon the judgments reported in AIR   1967   Supreme   Court   349  [Ram   Chandra   Prasad   Sharma   &   Ors. Vs. State of Bihar & Anr.], Paras­3, 12 & 34; AIR 2007 Delhi   85 [Harvinder Motors Vs. B.S.E.S. Rajdhani Power Ltd.], Para­11   (on consumption pattern); and (2010(3) PLJR 514 [Kamaljeet   Singh Vs. The Bihar State Electricity Board & Ors.], Para­2; and  submitted that in worst case admitting all the allegations to  be   true,   the   petitioner   can   only   be   prosecuted   for   the  offence punishable under Section 138 of the Electricity Act. 

8. Needless   to   mention   here   that   the   petitioner   had  immediately deposited the loss assessed by the authorities of  JSEB.   The   investigation   done   is   perfunctory   and   the  Investigating Officer has not collected cogent evidence in  accordance with Supply Code and the Electricity Act, 2003  and by doing only table work has submitted charge sheet.  Learned   Court   has   also   taken   cognizance   in   a   routine  manner   without   appreciating   or   considering   the   law  required to be gone through.   

9. Counsel   appearing   for   the   Respondent­State   as   well  as informant­JSEB have vehemently opposed the argument  advanced   by   learned   counsel   for   the   petitioner.   It   is  contended that there was ample evidence available at the  6 time of inspection, suggestive to a fact that theft of energy  was   going   on.   It   is   not   a   case   in   which   only   paper   seals  attached to the meter and other instruments were removed,  but overwhelming evidence was available that seal of lock  of meter room was removed; meter room was opened; seal  bit of main meter as well as check meter were fond broken;  holography   seal   was   also   removed;   and   sign   of   using  screwdriver   for   the   purpose   of   opening   the   meter   was  detected,   but   the   representative(s)   of   the   accused­ Company, who was/were present at the time of inspection,  failed to justify such illegality committed. 

10. It   was   contended   by   Respondent   No.2   (informant)  that   the   provision   of   Clause­15.8(vii)   has   been   made   to  protect the bona fide consumers, assuming that on account  of   any   reason   seal   associated   with   the   meter   may   get  missing  or may be tampered  by any other reason without  being  any ill motive on the part  of the consumer, but  the  consumer   like   the   petitioner   may   not   take   help   of   the  provision   of   Clause   15.8(vii)   where   almost   all   the   seals   of  meter, meter room as well as check meter have been found  tampered. No justification was given by the consumer or its  representative(s)   present   at   the   time   of   inspection.   The  evidence   available   at   the   time   of   inspection   clearly  indicates commission of theft of energy. 

11. Learned counsel appearing for the JSEB has submitted  that the bill (Annexure­4) has been referred by the petitioner,  but   it   is  not   properly  assessed  in  accordance  with  correct  provision. By giving example he has contended that it should  have   been   1127100   units   instead   of   845325   units.   If   the  correct   formula   is   considered,   the   consumption   pattern  would also indicate that it was much below 75% of regular  consumption.   Learned   counsel   for   the   JSEB   has   further  submitted   that   nowadays   meters   having   advance  technology are being installed and, therefore, availability of  foreign   device   or   any   other   means   or   connecting   wire   to  divert the consumption is not required. Evidence available  at the time of inspection had been loudly suggesting that  7 dishonest   abstraction/consumption   of   electric   energy   was  going on. There is, thus, no merit in this writ petition and the  same is liable to be dismissed. 

12. I have gone through the materials placed before me  and   the   relevant   provisions   of   law.   Evidences   collected   in  the   case   diary   and   facts   indicated   in   the   first   information  report  roaringly   suggest  men   ceria  of   the  petitioner.   There  was removal of paper seal from all the meters and the locks;  there was breakage of seal bit of the meter, meter room and  check   meter;   there   was   sign   of   use   of   screwdriver   on   the  screw of meter and check meter, suggesting that the same  were opened for the purpose suitable to the petitioner. Facts  and   circumstances,   which   were   available   at   the   time   of  inspection, were not justified by any answer and, therefore,  the representative(s) of the accused­Company kept himself/ themselves   mum   in   course   of   inspection.   Certainly,   the  provisions of Supply Code created by the Jharkhand State  Electricity   Regulatory   Commission   have   been   notified   to  supplement the provision contained in the Indian Electricity  Act,   2003.   It   would   not   have   any   overriding   effect   on   the  enactment.   I   do   agree   with   the   submission   advanced   by  counsel   for   the   JSEB   and   the   contentions   made   in   the  counter   affidavit   filed   by   the   Respondent   No.2   that   Sub­ clause (vii) of Clause 15.8 of the Supply Code is to protect  the genuine consumers and not to those who have crossed  all norms intentionally for the purpose of committing theft of  energy. 

13. The   facts   and   circumstances   indicated   in   the  judgments cited above by the petitioner are not available in  the case at hand. Again, it is reiterated that it is not a case  of simple tampering of the seal of the mater, but it is a case  in   which   all   possible   steps   have   been   taken   to   commit  energy theft by breaking seal bit attached with the meter,  check meter and other instruments. The evidence available  in the first information report itself is sufficient to distinguish  the case of the petitioner from the facts of the judgments  cited above.  

8

14. After   due   investigation,   the   occurrence   has   been  found   true   and   charge   sheet   has   been   submitted   and,  accordingly,   cognizance   has   also   been   taken   against   the  accused   persons.   The   petitioner   by   highlighting   technical  aspects has tried to demolish the case of the prosecution,  but in the writ petition filed for quashing the first information  report those technicalities are not required to be considered  and   this   Court   has   to   consider,   whether   the   evidence  available   in   the   first   information   report,   prima   faice,  constitutes an offence or not?

15. In the case at hand, the proceeding has gone to the  extent of taking cognizance and, therefore, in view of the  discussions made above, I do not feel inclined to allow this  writ petition. 

16. Accordingly, the writ application stands dismissed with  a liberty to  the  petitioner to raise its  grievance before the  Trial Court at appropriate stage. 

17. Interim   protection   granted   to   the   petitioner   by  order  dated 26th November, 2010 stands vacated. 

(D. N. Upadhyay, J.) Sanjay/NAFR