Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 3, Cited by 23]

Supreme Court of India

Tehri Hydro Dev. Corpn Ltd. & Anr vs Jai Prakash Asso. Ltd on 25 September, 2012

Equivalent citations: AIR 2013 SUPREME COURT 920, 2012 (12) SCC 10, 2012 AIR SCW 5478, 2013 (1) ALL LJ 115, 2012 (2) WLC(SC)CVL 635, 2012 (4) ARBILR 88, 2012 (9) SCALE 433, (2012) 2 CLR 1043 (SC), 2013 (115) CAL LT 424, (2013) 1 JCR 216 (SC), AIR 2012 SC (CIVIL) 2810, (2012) 4 ARBILR 88, (2013) 1 RECCIVR 262, (2012) 4 ICC 567, (2012) 6 ALL WC 5441, (2013) 1 CAL HN 69

Author: Ranjan Gogoi

Bench: Ranjan Gogoi, Anil R. Dave, R.M.Lodha

           
|REPORTABLE             |


                        IN THE SUPREME COURT OF INDIA

                         CIVIL APPELATE JURISDICTION

                      CIVIL APPEAL No.  3682   OF 2007



Tehri Hydro Dev.  Corpn. Ltd.& Anr.                      … Appellants

                                   Versus

Jai Prakash Asso. Ltd.                         … Respondent



                            J  U  D  G  M  E  N T



RANJAN GOGOI, J


      This appeal  is directed against the judgment  and  order  dated  20th
July, 2006 passed by the High Court of Uttaranchal at Nainital  whereby  the
decree passed by the learned trial court  under the  Arbitration  Act,  1940
(hereinafter referred to as ‘the Act’)  has  been  modified.  The  terms  of
award as passed by the learned Arbitrator and   the  decree  passed  by  the
learned trial court as well as the modification thereof by  the  High  Court
will now have to be noticed :

2.    The appellants and the respondent herein had entered into  a  contract
for execution of certain works  in  connection  with  the  Tehri  Hydro  Dam
Project.  The agreement between the parties  was  executed  on  29th  March,
1978 and the works in question were  completed on 31st December, 1985.   The
completion certificate   was  issued  by  the  competent  authority  of  the
appellant-Corporation on 27th  April,  1986.   As  the  final  bill  of  the
respondent-contractor  had not been prepared and security  money,  furnished
by way of bank guarantee was not released, the parties went  to  arbitration
in accordance with the Arbitration clause under the contract/agreement.   In
the  course  of  the  aforesaid  Arbitration   proceeding   the   appellant-
Corporation submitted a  final  bill  which  according  to  the  respondent-
Contractor entitled it to receive a sum of  Rs.10,17,461.09  on  account  of
work done besides a sum of Rs. 12..50 lakhs that was lying in  deposit  with
the  Corporation.   As  the  amounts  due.  according  to  the   respondent-
contractor, had become crystallized, another arbitration proceeding  between
the parties for the aforesaid specific claims commenced in  accordance  with
the arbitration clause of the agreement.

3.    The award in the aforesaid arbitration proceeding was passed  on  29th
January, 1996 holding the respondent – contractor to be entitled to the  sum
of Rs. 10,17,461/- with the interest at the rate of 6% per  annum  from  the
date of invocation of the claim till the date of the  award and at the  rate
of 12% per annum from the date of the award   till    payment  or  till  the
award is made Rule of court,  whichever is earlier.  Insofar  as  the  claim
of the respondent – contractor to the  sum  of  Rs.  12.50  lakhs  lying  in
deposit with the Corporation,  the Arbitrators held the said  amount  to  be
beyond the scope of  the  dispute  raised  in  the  arbitration  proceeding.
Accordingly, the respondent  –  contractor  was  left  with  the  option  of
settling the said claim in an amicable manner or by  resorting  to  a  civil
suit for recovery of the same.

4.    Objections against the specific  parts  of  the  award  by  which  the
respective parties felt aggrieved were filed before  the  learned   District
Judge, Tehri, Garhwal.  The learned District Judge by his order  dated  15th
October, 1997 upheld the claim of the respondent – contractor to the sum  of
Rs.10,17,461/- lakhs as awarded.  In so far as the claim of  Rs.12.50  lakhs
is concerned, the learned trial court, notwithstanding  the  fact  that  the
arbitrator did not decide the said claim, went into the issue and  held  the
respondent  –  contractor  to  be  entitled  to  the   said   amount   also.
Thereafter, a decree was passed in respect of  the  two  amounts   alongwith
interest thereon at the rate of  12% pendente  lite  and  6%  for  the  post
award period.  Aggrieved by  the  aforesaid  order  passed  by  the  learned
District Judge, Tehri  Garhwal,  the  appellant  moved  the  High  Court  of
Uttaranchal by filing an appeal under the  provisions  of  the  Act.     The
High Court by its order dated 20th July, 2006 allowed the  appeal  in  part.
While the claim of Rs.10,17,461/-  awarded  in  favour  of  the  respondent-
contractor was maintained in so far as the  claim  of  Rs.  12.50  lakhs  is
concerned, the High Court took the view that the aforesaid amount could  not
have been awarded by the learned trial court  as the  said  entitlement  was
not gone into by the learned Arbitrators.   Accordingly,   the  High   Court
remanded the aforesaid  claim to be settled by an  Arbitrator  appointed  by
it.  Insofar as the  question of interest is concerned, the High  Court  did
not deal with  the  said  aspect  of  the  matter  at  all.  Aggrieved,  the
Corporation is before this court challenging the judgment  and  order  dated
20th July, 2006 passed by the High Court of Uttaranchal.

5.    We have heard Mr. Puneet Taneja, learned counsel  for  the  appellants
and  Mr. S.B. Upadhyay,  learned senior counsel  for the respondent.
6.     Learned counsel for the appellants has contended that the  claims  of
the respondent - contractor for the unpaid amounts under the final  bill  as
well as for return/refund of security deposit, including  amounts  furnished
by way of  bank guarantee, was the subject matter of an earlier  arbitration
between the parties.  In the course of the said arbitration the  final  bill
was placed before  the arbitrators by the Corporation.  On scrutiny  of  the
aforesaid final bill the  respondent-contractor  claimed  the  two  specific
amounts in question and resorted to another process of  arbitration  without
seeking leave in the first arbitration proceeding  to  have  recourse  to  a
second round of arbitration.  The  arbitration  proceeding  leading  to  the
award is, therefore, without any authority of law. Specifically, insofar  as
the amount of Rs.12.50 lakhs is concerned, according to the learned  counsel
for the appellants,  the  said  amount  was  not  adjudicated  upon  by  the
Arbitrators and the same was to be recovered by an amicable  process  or  by
resorting to a civil suit.  In such a situation it was  clearly  beyond  the
power of the learned trial court to hold the said claim  in  favour  of  the
respondent-contractor.  Though the  High  Court  was  justified  in  setting
aside the said claim of Rs.12.50 lakhs for the aforesaid  reason,  it  could
not  have  directed  adjudication  of  the  said  issue   by  an  Arbitrator
nominated by it as has been done by the impugned order of  the  High  Court.
According to the learned counsel, the adjudication of the said claim of  the
respondent – contractor, if at all,  should have been directed by a  process
contemplated  by  the  specific  provisions  of  the  Arbitration  agreement
between the parties.

      Insofar as the  grant of interest is concerned,  learned  counsel  for
the appellants has relied on Clauses 1.2.14 and 1.2.15 of  Part  II  of  the
contract agreement between the parties to contend that under  the  aforesaid
clauses of the agreement governing the parties there was a specific  bar  to
grant of interest.  Relying on several judgments  of this court, details  of
which will be noticed in the discussions that will follow,  learned  counsel
has contended that the award  of  interest  in  favour  of  the  respondent-
contractor  being clearly contrary to the terms  of  the  agreement  between
the parties is wholly untenable and therefore needs to  be  interfered  with
by this court.
7.    Controverting the submissions advanced on behalf  of  the  appellants,
learned  counsel for  the respondent – contractor  has  contended  that  the
appellants  had  actively  participated  in  the   proceeding   before   the
Arbitrators and therefore, cannot, at this stage, question the  jurisdiction
of the Arbitrators to make the  award in question.   It  is  contended  that
the claim of the respondent to the  amount  of  Rs.10,17,461/-  having  been
held in its favour all along, the same  does  not  disclose  any  basis  for
interference. In so far as the amount of Rs.12.50  lakhs  is  concerned  the
only  issue that will require deterimination is the manner in which  the  de
novo  adjudication is required to be carried out.  So far  as  the  question
of interest is concerned, learned counsel has placed before  the  court  the
UP Civil Laws (Reforms and Amendment) Act, 1976 by which certain  provisions
of the Arbitration Act of 1940 have been amended in its application  to  the
State of UP.  The attention of the court has been  drawn  to   Paragraph  7A
which has been added after  Para  7  of  the  First  Schedule  to  the  Act.
According to the learned counsel,  Paragraph  7A  authorized  and  empowered
the arbitrator as well as the  courts  below  to  grant  interest.   Learned
counsel has also relied on the decisions  of  this  court  in    Indian  oil
Corporation Ltd. vs. Amritsar Gas service and  others[1],  State  of  Orissa
vs. B.N. Agarwalla[2] and Asian Techs  Limited  vs  .  Union  of  India  and
others[3]  2009  10  SCC  354  (para  21)  in  support  of  the  contentions
advanced.

8.    Para 7A of the U.P. Civil  Laws  (Reforms  and  Amendment)  Act,  1976
referred to above may now be reproduced :
      “7A. Where and in so far as an award is for the payment of money,  the
      arbitrators of the umpire may, in the award, order  interest  at  such
      rate as the arbitrators or umpire may deem reasonable to  be  paid  on
      the principal sum awarded, from the date of the  commencement  of  the
      arbitration as defined in sub-section (3) of section 37, to  the  date
      of award, in addition to any interest awarded on  such  principal  sum
      for any period prior to such commencement, with  further  interest  at
      such rate not exceeding six per cent per annum as the  arbitrators  or
      umpire may deem reasonable on such principal sum  from the date of the
      award to  the  date  of  payment  or  to  such  earlier  date  as  the
      arbitrators or umpire may think fit, but in no case beyond the date of
      the decree to be passed on the award.”

9.    Insofar as the  jurisdiction of the Arbitrator to  adjudicate  on  the
two  claims   of  Rs.10,17,461/-  and  Rs.12.50  lakhs  are  concerned,  the
dispute is capable of resolution within a short  compass.   The  entitlement
of the respondent – contractor to the aforesaid  two amounts   was  not  the
subject matter of the earlier proceeding before the Arbitrators which  arose
out of the  grievance  of  the  respondent  –  contractor  that  though  the
execution of the work had been completed,  the  final  bill   had  not  been
prepared and  further that certain amounts lying in deposit as security  had
not been refunded.  Once the final bill was prepared and placed  before  the
Arbitrators the claim of the respondent-contractor got crystallized.  It  is
these specific claims, after quantification, that had been referred  to  the
Arbitrators in the proceeding in which the award has been passed.  It  will,
therefore, not be  correct  to  say  that  the   arbitration  proceeding  in
respect of the specific claims of the contractor stood  barred  in  view  of
the earlier arbitration proceeding between the parties.   That  apart,  from
an order  passed  by  the  Arbitrators  on  15th  January,  1994,  which  is
available on record  as  an  enclosure  to  the  counter  affidavit  of  the
respondent, it appears that the arbitrators in  the  aforesaid  order  dated
15th January, 1994 had clearly recorded that the “. . .  .both  the  parties
agree that we should adjudicate both the disputes   relating  to  refund  of
deposit  of Rs.12.5 lakhs and payment of final bill to the tune of  Rs.10.00
lakhs and odd . . . .”




      In  these  circumstances,  the  award  insofar   as   the   claim   of
Rs.10,17,461/-  made by the learned Arbitrator and affirmed by  the  learned
courts below  will not require any further scrutiny by us.

10.   Insofar as the claim in respect  of  the  sum  of  Rs.12.50  lakhs  is
concerned,  it  has  already  been  noticed  that  the  entitlement  of  the
respondent – contractor to the said amount had not been adjudicated upon  by
the Arbitrators on the ground that the said  issue  was  not  an  arbitrable
issue and the same ought be resolved either by an  amicable  process  or  by
way of a suit for recovery.  If the  aforesaid  claim  was  not  adjudicated
upon by the Arbitrators the learned  trial  court  was  patently  wrong   in
decreeing  the  said   claim.   Therefore,  the  High  Court  was  perfectly
justified in reversing the said part of the  decree.   However,  we  do  not
find any reasonable basis for the view taken by  the  High  Court  that  the
entitlement  of the respondent-contractor to the said amount should  now  be
determined by the Arbitrator nominated by it.  Rather, according to us,  the
aforesaid issue should have been left for determination in  accordance  with
the procedure agreed upon by the  parties,  if  the  parties  are,  at  all,
inclined to go into a further round of  adjudication  at  this  stage.   We,
therefore, interfere with the aforesaid part of the order of the High  Court
and, subject to our observations above,  we  leave the parties to  work  out
their remedies as may be considered best and most appropriate in  the  facts
and circumstances of the case.

11.   This will lead the court to a consideration of what is  the  principal
bone of contention between the parties in  the  present  case,  namely,  the
issue with regard to payment of interest.    Clauses 1.2.14  and  1.2.15  on
which much arguments have been advanced by learned counsel for  both   sides
may now be extracted below :
      “                      PART – II
                       CONDITIONS OF CONTRACT
             14. NO CLAIM FOR DELAYED PAYMENT DUE TO DISPUTE ETC.


           The contractor agrees that no claim for interest of damages will
           be entertained or payable by the Government in  respect  of  any
           money or balances which may be lying with  Government  owing  to
           any  disputes,  differences  or  misunderstandings  between  the
           parties or in respect of any delay or omission on  the  part  of
           the Engineer-in-charge in making immediate or final payments  or
           in any other respect whatsoever.


             15. INTEREST ON MONEY DUE TO THE   CONTRACTOR  :


           No omission on the part of the  Engineer-in-charge  to  pay  the
           amount due upon measurement or otherwise shall vitiate  or  make
           void the contract, nor  shall  the  contractor  be  entitled  to
           interest upon any guarantee or payments in arrears nor upon  any
           balance which may on the final settlement of his accounts be due
           to him.”



12.   A reading of the aforesaid  two  Clauses  of  the  contract  agreement
between the parties clearly reveal that  despite  some  overlapping  of  the
circumstances contemplated by the two Clauses, no  interest  is  payable  to
the contractor for delay in payment,  either,  interim  or  final,  for  the
works done or on any amount lying in  deposit  by  way  of  guarantee.   The
aforesaid contemplated consequence would be applicable both to  a  situation
where withholding of payment is on account of  some  dispute  or  difference
between the parties or even otherwise.

13.    Of the several decisions of this Court referred  to  by  the  learned
counsel for the appellant the judgments of the Constitution  Bench  of  this
Court in    Secretary,  Irrigation  Department,  Government  of  Orissa  and
others vs. G.C. Roy and anr.[4]  and   Executive Engineer,  Dhenkalal  Minor
Irrigation Division, Orissa and others vs. N.C. Budhraj (deceased)  By  lrs.
And others[5]   will require specific notice.  The true ratio laid  down  in
the aforesaid two judgments have  been  elaborately  considered  in  a  more
recent  pronouncement of this court  in  the  case  of  Union  of  India  vs
Krafters  Engineers  and   Leasing   Private   Limited[6].    In    Krafters
Engineers’s case (supra) the ratio of  the  decision   in  G.C.  Roy’s  case
(supra) was identified to mean that if the  agreement  between  the  parties
does not prohibit grant of interest  and the claim of a  party  to  interest
is referred to the arbitrator, the arbitrator would have the power to  award
the interest.  This is on the basis that in such a case  of  silence  (where
the agreement is silent)  it must be  presumed that interest was an  implied
term of the agreement and, therefore, whether  such a claim is  tenable  can
be examined by the arbitrator in the reference made to him.   The  aforesaid
view, specifically, is with  regard  to  pendente  lite  interest.   In  the
subsequent decision of the  Constitution  Bench   in   N.C.  Budhraj’s  case
(supra)  a similar view has been taken with regard to interest  for the  pre
reference period.

14.   In  Krafters Engineers’ case (supra)  the  somewhat  discordant   note
struck by the decisions of this court in Board of Trustees for the  Port  of
Calcutta vs. Engineers-De-Space-Age[7] and Madnani Construction  Corporation
Private Limited vs. Union of India and others[8] were also  taken  note  of.
Thereafter, it was also noticed that  the  decision  in  Engineers-De-Space-
Age’s case (supra) was  considered in  Sayeed  Ahmed  &  Co.  vs.  State  of
Uttar Pradesh & Ors. [9] and the  decision  in   Madnani  Construction  case
(supra)  was  considered  in   Sree   Kamatchi   Amman   Constructions   vs.
Divisional, Railway manager (Works),  Palghat  and  others[10].   In  Sayeed
Ahmed’s case (supra) (para 24)  it  was  held  that  in  the  light  of  the
decision of the Constitution bench in GC Roy’s case  and NC  Budhraj’s  case
it is doubtful whether the  observations  in  Engineers-de-Space-Age’s  case
(supra) to the effect that the  Arbitrator  could  award  interest  pendente
lite, ignoring the express bar in  the  contract,  is  good  law.   In  Sree
Kamatchi Amman Constructions’s  case(Supra)   while  considering   Madnani’s
case (supra) this court noted that the decision in  Madnani’s  case  follows
the decision in Engineers-de-Space-Age’s case  (supra).

15.   From the above discussions,  it  is  crystal  clear  that  insofar  as
pendente lite interest is concerned, the observations contained in  Para  43
and 44 of the judgment in GC  Roy’s  case  (supra)   will  hold  the  field.
Though the gist of the said principle has  been  noticed  earlier  it  would
still be appropriate to set out  para 44  of the  judgment   in  G.C.  Roy’s
case  (supra) which is in the following terms :
            “ 44. Having regard to the above consideration,  we  think  that
      the following is the correct principle which  should  be  followed  in
      this behalf.
            Where the agreement between the parties does not prohibit  grant
      of interest and where a party claims interest  and that dispute (along
      with the claim for principal amount or independently) is  referred  to
      the arbitrator, he shall have the  power  to  award  interest  pendent
      elite.  This is for the reason that in such a case it must be presumed
      that interest was an implied term of the agreement between the parties
      and therefore when the parties  refer all their disputes  –  or  refer
      the dispute as to interest as such – to the arbitrator, he shall  have
      the power to award interest.  This does not mean that  in  every  case
      the arbitrator should necessarily award interest pendent elite.  It is
      a matter within his discretion to be exercised in the light of all the
      facts and  circumstances of the case, keeping the ends of  justice  in
      view.”


16.   The provisions of the UP Civil (Reforms and  Amendment)  Act  amending
the First Schedule  to  the  Arbitration  Act,  1940  does  not  assist  the
respondent - contractor in any manner to sustain   the  claim  of  award  of
interest pendente lite,  inasmuch, as paragraph 7A to  the  First  Schedule,
as amended, is only an enabling provision which will have no application  to
a situation where there is an express bar to the  entertainment  or  payment
of interest  on the delayed payment either of an amount  due  for  the  work
done or of an amount lying in deposit as  security.   The  decision  in   BN
Agarwalla’s  case (supra) on which reliance has been placed by  the  learned
counsel for the respondent, once again, does not   assist the claim  of  the
respondent to interest pendente lite inasmuch  as  in  BN  Agarwalla’s  case
(supra) the views of the Constitution Bench in GC Roy’s  case  (supra)  with
regard to interest pendente lite could not have been and, infact,  were  not
even remotely doubted.  The observation of the  bench  in  B.N.  Agarwalla’s
case that in G.C.Roy’s   case (supra) the  decision  in  Executive  Eningeer
(Irrigation), Balimela and others vs . Abhaduta Jena and others  [11]    was
not overruled  was only in the context of the issue  of  award  of  interest
for the pre reference period.  The decision  in  Asian  Techs  Limited  case
(supra) also relied on by the respondent  takes  note  of  the  decision  in
Engineers-De-Space-Age  case   (supra)  to  come  to  the   conclusion   the
prohibition on payment of interest contained in clause 11 of  the  agreement
between the parties was qua the department and did not  bar  the  Arbitrator
from entertaining   the  claim.   It  has  already  been  noticed  that  the
correctness of the propositions laid  down  in  Engineers-De-Space-Age  case
(supra) have been  doubted  in  the  subsequent  decisions  of  this  court,
reference to which has already been made.

17. Clauses 1.2.14 and 1.2.15, already extracted  and  analysed,  imposed  a
clear bar on either entertainment or payment of interest  in  any  situation
of non payment or delayed payment of either the amounts due  for  work  done
or lying in security deposit.  On the basis of  the  discussions  that  have
preceded we, therefore, take the  view  that  the  grant  of  pendente  lite
interest on the claim of Rs.10,17,461/- is  not  justified.   The  award  as
well as the orders of the courts  below  are  accordingly  modified  to  the
aforesaid extent.


18.   However, the grant of interest for the post-award period  would  stand
on a somewhat different  footing.  This  very  issue  has  been  elaborately
considered by this Court in B.N. Agarwalla  (supra)  in  the  light  of  the
provisions of Section 29 of  the  Arbitration  Act,  1940.  Eventually  this
Court took the view that in a  situation  where  the  award  passed  by  the
arbitrator granting interest from the date of the award  till  the  date  of
payment is not modified by the Court “.....the effect would  be  as  if  the
Court itself had granted interest from the date of the decree till the  date
of payment...” In view of the above, the grant of interest on the amount  of
Rs.10,17,461/-from the date of the award till the  date  of  the  decree  or
date of payment, whichever is earlier, is upheld. In the facts of  the  case
we are of the view that the rate of interest should  be  12%  per  annum  as
determined in the arbitration proceeding between the parties.

19.   In view of the foregoing discussions we allow this appeal in part




and modify  the order of the High Court dated 20th July, 2006  as  indicated
above.
                                        ...……………………J.
                                          [R.M.LODHA]


                                        ............................J.
                                        [ANIL R. DAVE]


                                        ………………………J.
                                          [RANJAN GOGOI]

New Delhi,
September 25, 2012.



























|                      |

|                     |                      |                     |





   -----------------------

[1] [(1991) 1 SCC 533 [2] [(1997) 2 SCC 469] [3] 2009 10 SCC 354 (para 21).

[4] (1992) 1 SCC 508 [5] (2001) 2 SCC 721 [6] (2011) 7 SCC 279 [7] (1996) 1 SCC 516 [8] (2010) 1 SCC 549 [9] (2009) 12 SCC 26 [10] (2010) 8 SCC 767. [11] (1988) 1 SCC 418

-----------------------

19 19