Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 7, Cited by 32]

Supreme Court of India

M.Dayanand Reddy vs A.P. Industrial Infrastructure ... on 24 March, 1993

Equivalent citations: 1993 AIR 2268, 1993 SCR (2) 629, AIR 1993 SUPREME COURT 2268, 1993 (3) SCC 137, 1993 AIR SCW 2307, 1993 (2) ARBI LR 251, 1993 ( ) BOM CJ 850, (1993) 2 SCR 629 (SC), 1993 (2) UJ (SC) 180, 1993 UJ(SC) 2 180, (1993) 2 APLJ 65.1, (1993) 3 JT 566 (SC), (1993) 2 RRR 661, (1993) 2 SCJ 363, (1993) 2 ARBILR 251, (1993) 2 CIVLJ 523, (1993) 2 CURLJ(CCR) 321

Author: G.N. Ray

Bench: G.N. Ray

           PETITIONER:
M.DAYANAND REDDY

	Vs.

RESPONDENT:
A.P. INDUSTRIAL INFRASTRUCTURE CORPORATION LTD. AND ORS.

DATE OF JUDGMENT24/03/1993

BENCH:
RAY, G.N. (J)
BENCH:
RAY, G.N. (J)
VENKATACHALLIAH, M.N.(CJ)

CITATION:
 1993 AIR 2268		  1993 SCR  (2) 629
 1993 SCC  (3) 137	  JT 1993 (3)	566
 1993 SCALE  (2)270


ACT:
Indian Arbitration Act 1940.  Sections 3, 5, 11 and 12	read
with  Sections 8 and 9-Scope of-Removal and  Appointment  of
Arbitrator by Civil Court-Power thereto--Original  agreement
vis-a- vis copy of agreement-Preferability.
Whether	 the existence of an arbitration agreement to  refer
the  dispute to arbitrator can be ascertained in  the  facts
and circumstances of the case. And whether in the absence of
an  arbitration	 clause, it was necessary to  find  out	 the
terms	agreed	 between   the	 parties-Whether   unwritten
arbitration agreement can be recognised under the Act.
Arbitration Agreement and other agreement-Distinct  feature-
Mode  Of enforcement Whether the Courts	 have  discretionary
power  of  dispensation	 of a  valid  arbitration  agreement
vis-a-vis other agreements-Obligations of the Parties.



HEADNOTE:
The  appellant,	 entered into an agreement  with  the  first
respondent  on December 11, 1986 for construction  of  sewer
line.	On June 27, 1988 he requested the Chairman to  refer
the   dispute	to  arbitration	 as  per   the	 preliminary
specification  of the A.P. Standard specifications.  As	 the
first respondent refused to settle the claims, the appellant
sent  a	 claim petition dated October 3, 1988 to  the  named
arbitrator.  He sent a reminder but the named arbitrator did
not enter the reference.  The appellant gave further  notice
dated  January 5, 1989 calling upon the first respondent  to
concur	for the appointment of an arbitrator  to  adjudicate
the disputes and differences arising between the parties.
On  January  18,  1989 the  first  respondent  informed	 the
appellant  that	 there	was no	arbitration  clause  in	 the
agreement   between   the  parties,  so	 the   question	  of
entertaining  the request to appoint an arbitrator  did	 not
arise.	The appellant then riled an application in the Civil
Court praying 629
630
for  removal  of the named arbitrator in the  agreement	 and
appointment of the sole arbitrator in his place.
The respondent contested the application contending that the
appellant  completed  only  a part of the  work	 within	 the
stipulated time though the site was handed over to him.	 But
the accounts were settled before the completion of work	 and
the final bill of the appellant was paid, while the  balance
of  work  was  got completed through  other  agencies.	 The
respondent also contended that the original agreement signed
between	 the  parties did not provide  for  any	 arbitration
clause and such fact was known to the appellant.
The Civil Court found that the agreement did not contain any
arbitration clause.  However, it held that the agreement was
silent about the mode of settlement of the disputes, if any,
while	every  agreement  of  civil  contract  contains	  an
arbitration  clause.  However, since there was clause  3  in
the  copy  of the agreement supplied to the  appellant	sub-
sequently  under  a  covering  letter  with  the  seal	 and
signature  of  the  second respondent,	which  provided	 for
reference   to	arbitration  in	 accordance  with   standard
specification  and  since  the copy  of	 agreement  was	 not
fabricated  by the appellant, the respondents were bound  by
the arbitration clause.
The  respondents  had  neglected  to  refer  the  matter  to
arbitration  despite  the  agreement,  so  the	civil  court
appointed the sole arbitrator.
The  respondents  assailed the order of the civil  court  in
Civil  Revision before the High Court.	The High Court	also
found  that  the  original agreement  did  not	contain	 any
arbitration   agreement	  at  all.   Since  there   was	  no
arbitration  clause  in the original agreement, it  was	 not
necessary to consider other material or circumstances.	 The
High  Court  rejected the contention that the  existence  of
such  a	 clause	 should be assumed  because  the  government
contractors  were  governed by the  standard  specification.
Therefore the High Court set aside the order appointing	 the
arbitrator.
This Court granted special leave to appeal to the  appellant
and  on	 consideration	of  respective	contentions  of	 the
parties, this Court dismissing the appeal.
HELD:Only  an  arbitration  agreement  in  writing  is-
recognised under
631
the Arbitration Act, 1940. [635-G]
Law   is  well	settled	 that  arbitration  clause  may	  be
incorporated by reference to a specific document which is in
existence   and	 whose	terms  are   easily   ascertainable.
However, the question whether or not the arbitration  clause
contained  in another document has been incorporated in	 the
contract, is always a question of construction.[636 C-D]
The  arbitration  clause is quite distinct  from  the  other
clauses	 of the contract.  While other clauses of  agreement
impose	obligation which the parties undertake towards	each
other,	arbitration  clause does not impose on	any  of	 the
parties	 any obligation in favour of the other party.	Such
arbitration  agreement	embodies an  agreement	between	 the
parties	 that  in  case of dispute, such  dispute  shall  be
settled by arbitrator or umpire of their own constitution or
by an arbitrator to be appointed by the court in appropriate
cases. [636-E]
There  is a material difference in an arbitration  agreement
inasmuch  as in an ordinary contract the obligations of	 the
parties	 to each other cannot be specifically  enforced	 and
breach	of such terms of contract results only	in  damages,
but  the arbitration clause can be specifically enforced  by
the  machinery of the Arbitration.  Act.  While	 the  courts
have   discretionary  power  of	 dispensation  of  a   valid
arbitration   agreement,   there  is  no   such	  power	  of
dispensation  of  other terms of contract.   An	 arbitration
agreement  in  no way classifies the right  of	the  parties
under  the  contract but it relates wholly to  the  mode  of
determining the rights. [636 F-H, 637 A]
In the instant case, it is the specific finding of the	High
Court and civil court that there is no arbitration clause In
the   original	agreement  signed  by  both   the   parties.
Therefore  it  Is not necessary to make any effort  for	 the
purpose	 of  finding out as to what were  the  terms  agreed
between	 the parties.  In the absence of clear intention  of
both  the  parties,  agreement for  arbitration	 cannot	 and
should	not be inferred, more so when the specific  case  of
the  respondent	 is that by mistake the clause	relating  to
arbitration crept in the copy of agreement. [637 C-D, 638 D]
The  High Court was justified in holding on facts that	only
the original agreement and not the copy, was binding between
the  parties and no reference to arbitration could  thus  be
made.	In the aforesaid circumstances, no  interference  in
called for. [638 H, 639 A]
632



JUDGMENT:

CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1427 of 1993.

From the Judgment and Order dated 13.2.1992 of the Andhra Pradesh High Court in Civil Revision Petition No .2269 of 1.991.

S.K. Mehta for the Appellant.

K. Ram Kumar for the Respondents.

The Judgment of the Court was delivered by G.N. RAY, J. Leave granted.

Pursuant to the notice issued on the Special Leave Petition No.7575 of 1992, the respondents have appeared and have filed counter affidavits and the appellant has also filed affidavit of rejoinder. The special leave petition out of which this appeal arises is directed against Order dated February 13, 1992 passed by the Andhra Pradesh High Court in Civil Revision No.2269 of 1991. The said Civil Revision was filed by the respondents against Order dated May 10, 1991 by which the learned Vth Additional Judge, City Civil Court of Hyderabad allowed the application filed under Sections 3, 5, 11 and 12 read with Sections 8 and 9 of the Indian Arbitration Act for removal of the named Arbitrator in the agreement dated December 11, 1986 and to appoint the sole arbitrator in his place.

The learned Judge, City Civil Court, inter alia came to the finding that it was a fit case where the sole arbitrator should be appointed for adjudicating the disputes and differences between the parties arising out of the agreement in question and the learned judge appointed a retired District Judge as the sole arbitrator for adjudicating the disputes and differences arising out of the arbitration agreement for entering upon the reference and sign and pass the award according to law.

The case of the appellant in short is that the appellant is a Class I Contractor. He entered into an agreement with the respondent No.1, A.P. Industrial Infrastructure Corporation Ltd., for the construction of main sewer line from Point (H) near C.C. Building IDA Nacharam to the disposal units of Nallacheru (near Uppal) on December 11, 1986. Pursuant to such agreement, the appellant completed the work in question. Since 633 certain disputes and differences had arisen between the appellant and the said Corporation during the execution and completion of the contract, the appellant by notice dated June 27, 1988 requested the. Chairman of the Corporation to refer the dispute for arbitration as per Clause 73 of the preliminary specifications of A.P. Standard specifications, hereinafter referred to as the standard specifications. As the first respondent refused to settle the claims, the appellant sent a claim petition dated October 3, 1988 to the named arbitrator which was received by the said named arbitrator on October 5, 1988. As the appellant did not receive any communication from the named arbitrator, he sent a reminder under registered post on November 28, 1988 to the named arbitrator. The named arbitrator, however, did not enter upon the reference within a period of one month and also did not pass any award within a period of four months as contemplated in the Indian Arbitration Act. The appellant also contended in the said application for appointment of arbitrator in place of the named arbitrator that the Chairman of the Corporation, namely, the first respondent had sent an undated letter signed on November 8, 1988 informing the appellant that para 3 of the article of the agreement since referred to by the appellant was erroneous and while making copies of the arbitration agreement entered into between the parties, wrong sheets were enclosed but in the original agreement, since signed between the parties, there was no arbitration clause for the work in question. The appellant, however, gave a further notice dated January 5, 1989 through his learned Advocate calling upon the said respondent to concur for the appointment of any one of the three persons named in the said notice to act as an arbitrator to adjudicate the disputes and differences arising between the parties. On receiving such notice, the first respondent by his letter dated January 18, 1989 informed the learned Advocate of the appellant that as there was no arbitration clause in the agreement entered into between the parties, the question of entertaining the request to appoint arbitrator did not arise. In view of such failure on the part of the respondent to refer the dispute to the arbitration in terms of the said agreement between the parties, the appellant made a prayer for removing the named arbitrator in respect of the works in question and to appoint any one of the three persons named in the application as sole arbitrator to adjudicate the disputes and differences.

On such application made by the applicant in the Court of the Vth Additional Judge, City Civil Court, Hyderabad, the proceeding being O.P. 634 No.132 of 1989 arose.

The respondent No.1 opposed the said application and filed counter to the said application inter alia contending therein that the appellant entered into the agreement dated December 11, 1986 with the A.P. Industrial Infrastructure Corporation for the said work and the time stipulated for the construction of the work was six months from the date of handing over of the site. The appellant, however, completed only a part of the work although the, site was handed over to him. But before the completion to the entire work, the accounts were settled between the parties and the final bill was also paid to the appellant and the balance of work was got completed through other agencies. It was further contended that the original agreement signed between the parties did not provide for any arbitration clause and such fact was made known to the appellant. In view of the aforesaid position,, the question of referring the matter to the arbitration or to the named arbitrator or to any other arbitrator did not arise.

The learned Judge inter alia came to the finding that the original agreement dated December 11, 1986 executed between the parties in relation to the contract work did not contain any arbitration clause and the articles of the agreement only provided for various terms and conditions of the work and such agreement containing the aforesaid terms was also signed by both the parties. The learned Judge, however, held that conspicuously the agreement was silent about the mode of settlement of the disputes, if any, arising between the parties in respect of the work. Generally, every agreement of civil contract between the government and the contractors or between the local bodies and the contractors contains an arbitration clause for settling the disputes between the parties. In the copy of the agreement which was supplied to the appellant since marked as Ex. A-3, the clauses appearing in the agreement were similarly entered without variation. In the copy of agreement since furnished to the applicant, there was a clause being clause 3 which provided for reference to arbitration in accordance with the standard specifications. It was further held by the learned Judge that the copy since supplied to the applicant had the stamp of the respondent No.2 and the covering letter under which the copy of the agreement was forwarded to the applicant also bore the seal and signature of the second respondent. Since the said copy of the agreement had not been fabricated by the applicant, the respondents were bound by the said 635 Clause (3) as referred to in the copy of the agreement' As, despite such agreement, the respondents failed and neglected to refer the matter for arbitration, the learned Judge was of the view that the application should be allowed. The learned Judge, therefore, appointed Sri J. VenuGopal Rao, a retired District Judge, as the sole arbitrator for adjudicating all the disputes and differences between the parties and for entering upon the reference and thereafter sip and pass the award in accordance with law. The respondents being aggrieved by the aforesaid order of the learned Civil Additional Judge, moved the Andhra Pradesh High Court for revision. The learned Judge inter alia came to the finding that the original agreement Ex.B-1 since signed by the parties did not contain any arbitration clause at all. A copy of the agreement (Ex.A-3) was, however, for- warded to the applicant eleven days after the original agreement and the clause relating to arbitration as contained in Ex.A-3 was absent in the original agreement. The learned Judge was of the view that only the terms contained in original agreement since signed by the parties and not the terms contained in the copy forwarded to the applicant were binding between the parties. The learned Judge was also of the view. that as in the original agreement, (Ex.B-1) signed by both the parties, there was no arbitration clause at all, it was not necessary to look into the other material or to consider other circumstances for the purpose of finding that the parties had also agreed for arbitration. The contention on behalf of the applicant that in the absence of any specific clause for reference of disputes to arbitration in the original agreement (Ex.B-1) the existence of such a clause should be assumed because the government contractors arc governed by the standard specifications, was not accepted by the High Court. In that view of the matter, the revision application was allowed by the High Court inter alia holding that the impugned order appointing an arbitrator was erroneous and not sustainable in law. As aforesaid, such order of the Andhra Pradesh High Court is impugned in the instant appeal.

Under the Arbitration Act, 1940, only an arbitration agreement in writing is recognised by the Act. In has been held by this Court in Jugal Kishore Rameshwardas v. Mrs. Goolbai Hormusji, [1955] 2 SCR 857 that it is not necessary that the contract between the parties should be signed by both the parties. But it is necessary that the terms should be reduced in writing and the agreement between the parties on such written terms is 636 established. It has also been held by this Court in Rallia Ram v. Union of India, [1964] 3 SCR 164 that it is not necessary that all the terms of the agreement should be contained in one document. Such terms may be ascertained from the correspondence consisting of number of letters. In Smt. Rukmanibai Gupta v. The Collector, Jabalpur & Ors., AIR 1981 SC 479 this Court has laid down that an arbitration clause is not required to be stated in any particular form. If the intention of the parties to refer the dispute to arbitration can be clearly ascertained from the terms of the agreement, it is immaterial whether or not the expression arbitration or 'arbitrator' or 'arbitrators' has been used in the agreement. It is also not necessary that agreement to arbitration should appear in the document containing the other terms of agreement between the parties. Law is well settled that arbitration clause may be incorporated by reference to a specific document which is in existence and whose terms are easily ascertainable. It is to be noted, however, that the question whether or not the arbitration clause contained in another document is incorporated in the contract, is always a question of construction. It should also be noted that the arbitration clause is quite distinct from the other clauses of the contract. Other clauses of agreement impose obligation which the parties undertake towards each other. But arbitration clause does not impose on any of the parties any obligation in favour of the other party. Such arbitration agreement embodies an agreement between the parties that in case of a dispute, such dispute shall be settled by arbitrator, or umpire of their own constitution or by an arbitrator to be appointed by the Court in an appropriate case. It is pertinent to mention that there is a material difference in an arbitration agreement inasmuch as in an ordinary contract the obligation of the parties to each other cannot, in general, be specifically enforced and breach of such terms of contract results only in damages. The arbitration clause however can be specifically enforced by the machinery of the Arbitration Act. The appropriate remedy for breach of an agreement to arbitrate is enforcement of the agreement to arbitrate and not to damage arising out of such breach. Moreover, there is a further significant difference between an ordinary agreement and an arbitration agreement. In An arbitration agreement, the Courts have discretionary power of dispen- sation of a valid arbitration agreement but the Courts have no such power of dispensation of other terms of contract entered between the parties. This very distinctive feature of an agreement for arbitration has been highlighted 637 in the decision in Heyman v. Damins Ltd., 1942 AC 356. It has been held in North Westen Rubber Company, 1908 2 KB 907 (over-ruled in (1961 (1) AC 1314) on other points), that an arbitration agreement in no way classifies the right of the parties under the Contract but it relates wholly to the mode of determining the rights. In the backdrop of such position in law relating to an agreement for arbitration, it is to be decided whether the existence of an agreement to refer the dispute to arbitration can be clearly ascertained in the facts and circumstances of the case. This, in turn, depends on the interaction of the parties to be gathered from the relevant documents and surrounding circumstances. In the instant case, it is the specific finding of the learned Judge of the City Civil Court, Hyderabad and also the Andhra Pradesh High Court that in the original agreement signed by the parties, there is no clause for referring the disputes to arbitration. The agreement between the parties in this case has been reduced in writing and has been signed by both the parties. It is therefore not necessary to make any effort for the purpose of finding out as to what were the terms agreed between the parties. The learned Judge, City Civil Court, allowed the application for appointment of arbitrator simply on the ground that a copy of the agreement was forwarded to the appellant with the seal and signature of a competent officer of the Corporation, namely, the respondent No.2 and in such copy, which was not fabricated by the applicant there was a reference for arbitration as contained in the standard specifications. The learned Judge, City Civil Court, also proceeded on the footing that usually in the agreements relating to the nature of the contract, a provision for arbitration is made. As in the original agreement signed between the parties there was no such provision and the agreement was silent on the question as to what would happen if the disputes would arise between the parties, it should be presumed that the parties had really intended to refer the dispute to arbitration in accordance with the standard specifications and in the copy of the agreement which was forwarded to the applicant the provision for arbitration was included. The High Court however, was not inclined to accept this view of the learned Judge of the City Civil Court. The High Court was of the view that it was the signed agreement between the parties which was binding on the parties and only such written terms in the original agreement signed by the parties should be taken into consideration and not the terms contained in the copy of the agreement which was forwarded to the applicant after some time.

638

It has been indicated herein before that the case of the respondent is that through mistake the clause containing the arbitration agreement was not scored out in the copy of the agreement since forwarded to the applicant. The attention of the appellant was drawn to such mistake by the respondents before initiation of the proceedings before the City Civil Court. It also appears that on April 9, 1984, which is long before the agreement dated December 11, 1986, the respondent No.1, Corporation, came to the decision that arbitration was not really necessary as the aggrieved party to the agreement could always seek redress in a court of law. It was, therefore, decided that the arbitration clause in the standard specifications should be deleted altogether and the agreement was to be finalised in respect of engineering work without any provision for arbitration. It was also indicated that the instruction for deleting the arbitration clause should be followed with immediate effect. If inspite of such policy decision, the original agreement entered between the parties had contained the arbitration clause there is no manner of doubt that the parties to the agreement would have been bound by such arbitration agreement. Admittedly, in the instant case, in the original agreement signed between the parties, there is no clause for arbitration and the reason for absence of arbitration clause can be well explained by the aforesaid policy decision of the Corporation. An arbitration clause may be incorporated by reference to a specific document but the intention to refer to arbitration by such incorporation must be clear and specific. In the instant case, the original agreement signed between the parties does not contain any clause for arbitration. It is not the case of the applicant that the applicant had no occasion to know the terms of the agreement since singed by the parties and there was any clear representation that the copy of agreement was to be followed by the parties and terms contained in the copy were to be treated as the terms of agreement between the parties. Hence, it cannot be held that after the signed agreement the parties had clearly intended to include arbitration clause in the standard specifications. In the absence of clear intention of both the parties, agreement for arbitration cannot and should not be inferred more so when the specific case of the respondents is that by mistake the clause relating to arbitration crept. in the copy of agreement. In our view, the High Court was justified in holding that in the facts of the case, only the original agreement, and not the copy, was binding between the parties. Hence, no reference to arbitration could be made. In 639 the aforesaid circumstances, no interference is called for in the instant appeal and the appeal therefore, fails and is dismissed without, however, my order as to costs. S.P.S. Appeal dismissed.

640