Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 10, Cited by 29]

Supreme Court of India

Neelakantan & Bros. Construction vs Superintending Engineer, National ... on 16 August, 1988

Equivalent citations: 1988 AIR 2045, 1988 SCR SUPL. (2) 462, AIR 1988 SUPREME COURT 2045, (1988) 2 KER LT 82, (1988) 3 JT 743 (SC), 1988 (4) SCC 462

Author: Sabyasachi Mukharji

Bench: Sabyasachi Mukharji

           PETITIONER:
NEELAKANTAN & BROS. CONSTRUCTION

	Vs.

RESPONDENT:
SUPERINTENDING ENGINEER, NATIONAL HIGHWAYS,SALEM & ORS.

DATE OF JUDGMENT16/08/1988

BENCH:
MUKHARJI, SABYASACHI (J)
BENCH:
MUKHARJI, SABYASACHI (J)
RANGNATHAN, S.

CITATION:
 1988 AIR 2045		  1988 SCR  Supl. (2) 462
 1988 SCC  (4) 462	  JT 1988 (3)	743
 1988 SCALE  (2)586


ACT:
    Arbitration	 Act,  1940:  Sections 2,  20,	30  and	 33-
Arbitration-  Statements of parties filed-Evidence  adduced-
Change	 of   Arbitrator  -Parties  did	 not   protest	 and
participate in proceedings before successor-Whether  amounts
to  acquiescence-Appointment  of  successor-Whether  can  be
challenged  as invalidating  proceedings_Award-Unreasoned-No
legal proposition made-Whether can be interfered with.



HEADNOTE:
    The petitioner-Construction firm entered into agreements
with  respondent No. 3, Superintending Engineer of a  Circle
for  execution	of certain civil works.	 Respondent  No.  1-
Superintending	Engineer  of another Circle entered  into  a
reference  for arbitration and parties filed statements	 and
adduced	 evidence.  Before the adjudication  was  completed,
respondent No. 1 was transferred and his successor-in-office
entered	 into the task of adjudication with  the  knowledge,
consent	 and active participation of the petitioner  in	 the
proceeding.  Since  the arbitrator could  not  complete	 the
award  within time, be sought extension of time by a  letter
to  the	 petitioner  and  the  petitioner  agreed  to	such
extension  by a letter. The petitioner did not ask  for	 any
further	 or  fresh opportunity for  adducing  any  evidence.
Thereafter, the arbitrator made his award.
    The petitioner challenged the award under ss. 30 and  33
of  the Arbitration Act, 1940 before the District  Judge  on
the ground that the previous arbitrator having entered	into
reference,  his successor-in-office had no  jurisdiction  to
conclude  it  and the award was violative of  principles  of
natural justice.
    The District Judge held that the successor-in-office  to
the  original  arbitrator was competent to pass	 the  award.
Upholding this, the High Court rejected the challenge to the
award. Hence the petitioner filed the Special Leave Petition
in this Court contending that once an arbitrator had entered
into a reference, the next incumbent could not conclude	 the
said arbitration proceedings without a fresh agreement, that
there  was  violation of principles of natural	justice	 and
						  PG NO 462
						  PG NO 463
that the award was bad.
    Dismissing the Special Leave Petition,
    HELD:  1. If the parties to the reference  either  agree
before,hand  to	 the method of	appointment,  or  afterwards
acquiesce  in the appointment made, with full  knowledge  of
all the circumstances, they will be precluded from objecting
to such. appointment as invalidating subsequent proceedings.
Attending  and	taking	part in the  proceedings  with	full
knowledge   of	the  relevant  fact  will  amount  to	such
acquiescence [465G ]
    N.	Challappan  v. Secretary, Kerala  State	 Electricity
Board and another, [1975] 1 S.C.C. 289 relied on.
    Chowdhury Murtaza Hossein v. Mussumat Bibi	Bechunnissa,
3  I.A.	 209  and Prasun Roy v.	 The  Calcutta	Metropolitan
Development  Authority	and  another, [1982]  2	 Scale	125,
referred to.
    Russell on Arbitration, 18th Edition/20th Edition, pages
105/432-435, referred to.
    In	the instant case, the petitioner had full  knowledge
of  the	 change	 of the incumbent and did  not	protest	 and
proceedings  went  on before the new  incumbent.  Thus,	 the
petitioner  had	 knowledge  of the alleged  defect  and	 had
acquiesced  in the proceedings before the  successor.  There
was,  therefore,  no  violation	 of  principles	 of  natural
justice. [465C, F]
    2.	Unless there was a patent mistake of law  and  gross
misstatement of facts resulting in miscarriage of justice or
of equity, the award remains unassailable. [466C]
    Champsey  Bhara & Company v. Jivraj Ballo  Spinning	 and
Weaving	 Company  Ltd.,	 50  I.A.  324	and  Firm   Madanlal
Roshanlal Mahajan v. Hukumchand Mills Ltd., lndore, [1967j 1
S.C.R. 105, referred to.
    In	the instant case, the arbitrator gave no reason	 for
the award. There is no legal proposition which is the  basis
of  the	 award,	 far less any  legal  proposition  which  is
erroneous.  There  is  no appeal from  the  verdict  of	 the
arbitrator.    The    Court   cannot   review,	  in	such
circumstances,the  award  and  correct any  mistake  in	 the
adjudication by the arbitrator. [466D]
						  PG NO 464
    3. In the facts and circumstances of the case, the award
is  unassailable. The High Court was right in upholding	 the
District  Judge's dismissal of the challenge to	 the  award.
[466F]



JUDGMENT:

CIVIL APPELLATE JURISDICTION: Special Leave Petition [Civil) Nos. 1 l(i50-58 of 1987.

From the Judgment and Order dated 3 1.7. 1987 of the Madras High Court in Appeal against Order Nos. 54 1 to 544 and 558 to 562 of 1981.

A.K. Sen, V. Krishnamurthy and V. Balachandran for the Petitioner.

A. V. Rangam for the Respondents.

The Judgment of the Court was delivered by SABYASACHI MUKHARJI, J. These are petitions under Article 136 of the Constitution seeking leave to appeal against the judgment and order of the High Court of Madras dated 31st July, 1987. The petitioner company undertook the work of widening and strengthening pavements in Nation Highway No. 7, Madurai-Kanya-kumari Road from Reaches 37.6 k.m. to '1', k.m. on the Madurai-Kanyakumari Road and the work was divided into fourteen Reaches and 14 separate agreements were entered into between the petitioner and the Superintending Engineer, National Highways, Tirunelveli. respondent No. 3 to the present petitions. There is not much dispute on this point. At the relevant time, according to, the petitioner, the Superintending Engineer. National Highways, Salem was one Thiru Mohan. He entered into reference. He took up the matter for arbitration and called for statements from the parties. Statements were filed before him and evidence were also adduced before him. But before he could complete the adjudication he was transferred and was succeeded by one Thiru J.R. Cornelius, Superintending Engineer. The contention of the petitioner in this case was that he had no Jurisdiction to, proceed and complete the arbitration. It appears however, that he entered into the task of adjudication with the knowledge and consent of the petitioner and the petitioner had participated actively in the proceeding before him. From the notices served by Thiru Mohan previously and subsequently by Thiru Cornelius. it is apparent that the petitioner had knowledge of the change of the incumbent of the Superintending Engineer who was to arbitrate in the matter. This is evident from the documents appearing at pages 164 PG NO 465 and 165 of the present paper book and both the parties had notice of the succession in office. The arbitrator could not complete the award within time and there was need for extension of time. He wrote a letter to the petitioner on lst May 1977 stating "extension of time was necessary to pass orders on reference and hearing has been concluded". In reply to that fetter on 11th May, 1977 the petitioner agreed to such extension. The petitioner was content with that situation and never asked for any further or fresh opportunity either to make any submission or to adduce any evidence. In that light the arbitrator has made the award. This was challenged before the learned District Judge by means of a suit under sections 30 and 33 of the Arbitration Act, 1940 that the previous arbitrator Thiru Mohan having entered into reference and Thiru Cornelius had-no jurisdiction to conclude. It was violative of the principles of natural justice, it was submitted. But as mentioned hereinbefore, the petitioner had knowledge of the change of the incumbent. He did not protest and the proceedings went on before Thiru Cornelius. It is apparent from the terms of the agreement between the parties that the Superintending Engineer of the Circle for the time being was the named arbitrator. The learned District Judge held that Thiru Cornelius was competent to pass the award. The High Court also upheld that and rejected the challenge to the award on this ground made by the petitioner.

Shri A.K. Sen, learned counsel for the petitioners, urged before us that once an arbitrator had entered into reference, the next incumbent could not conclude the said arbitration proceeding without a fresh agreement. In the facts of this case, as the petitioner had knowledge of the alleged defect and had acquiesced in the proceedings before the successor, namely, Thiru Cornelius; we are of the c,pinion, that this contention of Shri Sen cannot be entertained. It was contended that there was violation of the principles of natural justice. This objection cannot be entertained. If the parties to the reference either agree beforehand to the method of appointment, or afterwards acquiescence in the appointment made with full knowledge of all the circumstances. they will be precluded from objection~ to such appointment as invalidating subsequent proceedings. Attending and taking part in the proceedings with full knowledge of the relevant fact will amount to such acquiescence, explains Russell on Arbitration. 18th Edition at page 105. This was stated by the Judicial Committee long ago in Chowdhury Murtaza Hossein v. Mussumat Bibi Bechunnissa, 3 I.A. 209. See also the observations of P.B. Mukherji, J. in the decision of the Calcutta High Court PG NO 466 Calcutta, A.I.R. 1456 Calcutta 470 at 472. This Court held in N. Challappan v. Secretary, Kerala State Electricity Board and another, [1975] 1 S.C.C. 289 that acquiescence defeated the right of the appellant at a latter stage. See also the observations of this Court in Prasun Roy v. The Calcutta Metropolitan Development Authority and another, [1982] 2 Scale 125. See Russell on Arbitration, 20th Edition, pages 432-435. Shri Sen contended that no notice was issued after the appointment of the new arbitrator. This was factually incorrect, as mentioned before. Then, it was said that the award was bad as it did not consider all the claims. This also cannot be entertained. It must be assumed that the arbitrator had considered all the evidence adduced before him. There was no disregard of any principle of law. There was nothing to indicate that the arbitrator had not considered all the evidence. Unless there was a patent mistake of law and gross misstatement of facts resulting in miscarriage of justice or of equity, the award remains unassailable. In this case the arbitrator gave no reason for the award. There is no legal proposition which is the basis of the award, far less any legal proposition which is erroneous. There is no appeal from the verdict of the arbitrator. The Court cannot review, in such circumstances, the award and correct any mistake in the adjudication by the arbitrator-See Champsey Bhara B Company v. Jivray Ballo Spinning and Weaving Company Ltd., 50 I.A. 324 and the observations of Bachawat, J. in Firm Madanlal Roshanlal Mahajan v. Hukumchand Mills Ltd., Indore, [ l967] 1 S. C. R. 105 of this Court.

In the facts and circumstances of the case, in our opinion, this award is not assailable. The High Court was, therefore, right in upholding the learned District judge's dismissal of the challenge to the award. These petitions, therefore, fail and are dismissed accordingly ,without any order as to costs.

    N.P.V.				Petitions dismissed.