Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 0]

Delhi District Court

Brpl vs . Rukhshana & Anr Cis No.641871/16 Page ... on 20 November, 2017

                                                    1

IN THE COURT OF MS. NEELAM SINGH, ADDL. SESSIONS JUDGE,
 THE SPECIAL COURT UNDER THE ELECTRICITY  ACT 2003, 
               SAKET COURTS, NEW DELHI


Complaint Case No.                  :          598/14
Police Station                      :          Malviya Nagar, New Delhi.
U/s                                 :          135 of Electricity Act, 2003
CIS No.                             :          641871/16

BSES Rajdhani Power Ltd.
having its registered Office at 
BSES Bhawan, Nehru Place,
New Delhi­110019 
and its Corporate, Legal and Enforcement 
Cell at Andrews Ganj,
Near Andrews Ganj Market,
New Delhi­110049.

Acting through Sh. Ashutosh Kumar,
(Authorised Representative)                                                          ..Complainant
                                  Versus
1.

  Rukhshana (User) House No. 63, Second Floor, Kalu Sarai, Begampur, Malviya Nagar, New Delhi­110017.

2.  Jaferyddin (RC/Owner) House No. 63, Second Floor, Kalu Sarai, Begampur, Malviya Nagar, New Delhi­110017. ...Accused Complaint instituted on    : 07.08.2014 Judgment reserved on  : 20.11.2017 Judgment pronounced on  : 20.11.2017      BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 1 of 15 2 JUDGMENT 

1. Complaint u/sec. 151 of the Electricity Act, 2003 (hereinafter called as 'the Act') has been filed by the complainant company against accused Rukhshana (user) for the offence punishable u/s. 135 of the Act and against accused Jaffryddin @ Jafruddin for the offence punishable u/s. 135 r/w Section 150 of the Act.  Determination of civil liability has also been prayed for.  

2. As per contents of the said complaint, the case of the complainant in brief   is   that   on   25.03.2014   at   about   3.30   p.m.,   the   officers   of   the complainant   company   namely,   Shri   Mani   Bhushan   Saroj­Senior Manager,   Sh.   Jamal  Akhtar­DET   and  Sh.   Sanjay  Kumar­   Technician inspected   the   premises   i.e   House   No.   63,   Second   Floor,   Kalu   Sarai, Begampur, Malviya Nagar, New Delhi­110017, which was being used and occupied by the accused namely Rukhshana (User) and Jaffryddin (RC/Owner), where the theft of electricity was being committed.   It is further   mentioned   in   the   complaint   that   one   single   phase   electronic meter   bearing   no.   13352577   with   current   reading   5125   KWH,   MDI 2.27 KW was found installed at site.   However, accused were found      BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 2 of 15 3 involved in direct theft of electricity by directly connecting to meter input   with   the   help   of   illegal   wire.     It   is   further   mentioned   in   the complaint that connected load of 5.355 KW for domestic purpose was taken.  It is further mentioned in the said complaint that one number of black   colour   copper   wire   size   7/20   SWG   having   length   of   1   meter approx, one number of red and black colour copper wire size 7/20 SWG having   length   of   2   meter   approx   and   one   number   of   single   phase electronic meter bearing no. 13352577 with current reading 5125 Kwh, were   seized   by   the   officials   of   complainant   company   and   that   the videography of the inspection proceedings was got conducted and the documents  i.e.  inspection report,  load report and seizure  memo  were also prepared at site and thus, accused were causing wrongful loss to the complainant   and   wrongful   gain   to   themselves   and   was   thus   acting dishonestly.

3. It is further mentioned in the complaint that it was a case of direct theft of electricity and theft bill, as per the DERC regulations and tariff order was   raised   by   the   complainant   for   Rs.1,05,314/­   with   due   date   as 14.04.2014 and was served upon the accused but they failed to pay the said theft bill hence the present complaint.

     BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 3 of 15 4

4. The   case   was   fixed   for   pre­summoning   evidence   and   accused   were summoned to face the said allegations  by my Ld. Predecessor vide his order   dated   17.11.2014.     Both   accused   persons   appeared   and   were granted bail.  

5. Notice   U/sec.   251   Cr.P.C.   for   commission   of   offence   punishable u/s. 135 of the Electricity Act, 2003 against the accused Rukhshana and for the offence punishable u/s 135 r/w Section 150 of the Electricity Act, 2003   against   the   accused   Jaferyddin   @   Jafruddin   framed   separately. Both   accused   persons   did   not   plead   guilty   and   claimed   trial   on   the ground that they were not committing any theft of electricity and that false   and   fabricated   case   was   filed   against   them   by   the   complainant company.

6. In   order   to   prove   the   case   of   the   complainant,   five   witnesses   were produced, which have been discussed below.  

7. Incriminating evidence was put to the accused and their statement under Section   313   Cr.P.C.   was   recorded  separately.     Both   accused  persons namely Ruhkshana and Jaferyddin @ Jafruddin denied evidence as false      BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 4 of 15 5 and submitted that they had a valid connection at the time of inspection and had been regularly paying the consumption charges as raised by company.     Accused   further   opted   to   lead   defence   evidence   and examined one witness which has been discussed below.  

8. PW­1  Shri Mani  Bhushan  Saroj­ Senior  Manager  in the  complainant company deposed that on 25.03.2014 at about 3.30 p.m., he alongwith DET­ Jamal Akhtar, Lineman­Sanjay and Photographer ­Vijay inspected the premises bearing no. House no. 63, 2 nd floor, Kalu Sarai, Begampur, Malviya   Nagar,   New   Delhi.     He   further   deposed   that   direct   theft   of electricity was going on at the premises in question and the accused was indulged in direct theft by directly connecting to meter input with the help of illegal wire.  He further deposed that the connected load of the premises   in   question   was   approximately   5.355   KW   for   domestic purpose.     Videography   of   connected   load   was   conducted   at   site. PW­1 proved the documents prepared at site i.e. inspection report, load report   and   seizure   memo   as   Ex.CW­2/A   (Colly)   to   Ex.CW­2/C. PW­1   proved   the   case   property   i.e.   electronic   meter   bearing   no. 13352577 as Ex.P­2 and the wires as Ex.P­3 (Colly).  PW­1 identified the   videography   as   Ex.CW­2/D   and   also   identified   both   accused   by      BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 5 of 15 6 pointing out in the videography and also present in the court on the day of his deposition.  

9. In   his   cross­examiantion   on   behalf   of   both   accused   persons,   PW­1 replied that the MDI of seized meter was 2.27 KW.  He further replied that there was no terminal cover of the meter in question.   He further replied that there is no necessity to remove the terminal cover of the meter to insert any illegal wire.     He further replied that there was no breach in the service line of the meter in question but illegal wires were connected at the input terminal of the meter in question.  He denied the suggestion that there was no theft of electricity at the time of inspection. He further denied the suggestion that load was recorded at the higher side.  

 

10. PW­2   Sh.   Jamal   Akhtar­DET   in   the   complainant   company   who   has deposed on the similar lines as deposed by PW­1.  

11. In his cross­examination on behalf of accused persons, he replied that there were two more electricity meters in the entire property wherein inspected   premises   was   situated.     He   further   replied   that   there   is   no      BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 6 of 15 7 necessity to remove the terminal cover in the meter to insert any illegal wire.  He further replied that the premises in question was inspected as a routine check.  He further replied that there was no breach in the service line of the meter in question but illegal wires were connected at the input terminal of the meter in question.  

12. PW­3   Sh.   Vijay­Videographer,   who   has   proved   the   videography conducted by him at the time of inspection as Ex.CW­2/D.  

13. PW­4 Sh. G. B. Barapatre, who prepared the theft bill in the present case and proved the same as Ex. CW­2/E.  

14. PW­5 Sh. Binay Kumar, who proved the filing of present complaint and his  G.P.A. as Ex.PW­5/A.  

15. DW­1 Sh. Vinay Kumar­Customer Care Associate in the complainant company, who brought the summoned record pertaining   to C. A. No. 102239926 for meter bearing no. 13352577 installed at H. No. 63, S/F, Kalu Sarai, Begumpur, Malviya Nagar, New Delhi­110017 in the name of accused Jaffaryddin and proved the electricity bill of said connection      BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 7 of 15 8 as Ex.DW­1/A.  He further deposed that the electricity connection was disconnected   due   to   non­payment   in   the   month   of   January,   2014. He   further   deposed   that   accused   made   a   payment   of   Rs.   7,000/­ thereafter.  The connection was not restored and the accused was using the   electricity   through   direct   theft   of   electricity.     During   cross­ examination on behalf of complainant company, DW­1 replied that after making payment of Rs. 7,000/­ in the month of March 2014, the dues of Rs. 46,080/­ were remained on behalf of accused persons.    

16. During arguments, it is submitted by ld. counsel for the complainant company that in the leadership of Sh. Mani  Bhushan Saroj, the officials of the complainant company on 25.03.2014 at about 3.30 p.m. visited and inspected the premises bearing H. No. 63, Second Floor, Kalu Sarai, Begampur, Malviya Nagar, New Delhi­110017 and on reaching the site, officials   found   that   direct   theft   of   electricity   was   going   on   at   the premises   in   question   and   accused   were   indulged   in   direct   theft   by directly connecting through meter input with the help of illegal wires. The connected load was taken as 5.355 KW for domestic purpose.  It is submitted   that   the   illegal   wires   were   seized   at   site   and   necessary documents   were   prepared   which   are   duly   proved   by   the   witnesses      BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 8 of 15 9 deposed before this Court. The necessary videography was conducted and is duly proved.  It is further submitted that PW­1 Sh. Mani Bhushan Saroj has duly identified the presence of accused persons at the time of inspection and the same is also depicted in the videography.  

17. It   is   further   submitted   that   in   order   to   prove   its   case,   complainant company has examined five witnesses who have duly proved the case of the complainant company.     Ld. counsel for complainant company has further submitted that it has been held in catena of cases decided by Hon'ble Apex Court as well as Hon'ble High Court of Delhi that in the cases of direct theft of electricity, the complainant company is required to establish three ingredients:­

 (i)   identity of premises in question;

(ii)   identity of accused persons;

(iii)   the   connection   of   accused   persons   with   the   premises   in question and that direct theft of electricity was being committed at the premises in question.  

18. It is further submitted that all the witnesses during trial have duly proved abovesaid three facts.  Ld. counsel for complainant company has argued      BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 9 of 15 10 that   premises   in   question   is   not   disputed,   the   presence   of   accused persons and the connection of accused persons with premises in question is also not disputed.  Ld. counsel for complainant company has taken me to the cross­examination of PW­1 and submits that it has come in the cross­examination of said witness that the illegal wires were connected at the input terminal of the meter in question.  The relevant extract of his cross­examination is reproduced as under:­  ......."There was no breach in the service line of the meter in question but illegal wires were conducted at the input terminal of the meter in question.   It is wrong to suggest that   there   was   no   theft   of   electricity   at   the   time   of inspection.   It   is   wrong   to   suggest   that   connected   load shown   in   the   load   report   was   not   covered   under videography at all.  It is wrong to suggest that AC shown in the load report was having a load of 2.150 KW.   Vol. It was of 2.250 KW.   It is wrong to suggest that load was recorded on higher side."

19. Ld. Counsel for the complainant company has further submitted that it has come in the defence evidence produced by accused that at the time of inspection, the electricity connection at the premises of accused was disconnected  due   to  non­payment in  the  month  of  January  2014 and accused only made the part payment of Rs. 7,000/­ and Rs. 46,080/­ still remained as due.   It is further argued by ld. counsel for complainant company that even in statement of DW­1 Sh. Vinay Kumar,  it has come that accused are still indulged in direct theft of electricity.        BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 10 of 15 11

20. On the other hand, ld. counsel for accused has submitted that there was no theft of electricity at site and accused were using the electricity by paying   legal   charges   to   the   complainant   company.     Ld.   counsel   for accused has further argued that it is a case on deviations of DERC rules and regulations to the fact that preparation of documents is not depicted in the CD and accordingly, the said documents were not prepared at site and also no enquiry to accused persons was done at site.   It is further submitted that excess and exhorbitant load has been taken in this case as the load of AC is shown as 2.150 KW but the AC is only of 1 KW.  

21. In   rebuttal   to   abovesaid   arguments,   ld.   counsel   for   complainant company   has   submitted   that   nothing   has   been   placed   on   record   by accused persons to show that they were paying legal charges against the electricity consumed by them at their premises since no electricity bill has been placed on record.   It is further argued that it is only a bald assertion on behalf of accused that the load of AC was only 1 KW as nothing has been placed on record in order to substantiate his pleading.        BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 11 of 15 12

22. It   was   argued   by   ld.   counsel   for   accused   that   accused   have   already deposited the amount of Rs. 40,000/­ in this case and the complainant company has issued the NOC but since accused had a fair case so he chose not to accept the NOC issued by complainant company in this case and to face the trial.  However, in rebuttal to these arguments, ld. counsel for the complainant company has submitted that nothing has been placed on record to show that the complainant company had issued any NOC in this case and further submitted that even if NOC is issued to accused in some case but once the accused has not accepted the NOC and is ready to face the Trial then he is liable for the outcome of the Trial.   Ld. counsel for the complainant company has taken me to the deposition of DW­1, which is reproduced as under:­ ".............I am a summoned witness and I have brought the record   vide   C.A.   No.   102239926,   meter   no.   13352577 installed at H. No. 63, S/F, Kalu Sarai, Begumpur, Malviya Nagar, New Delhi­110017, in the name of Jaffaryddin and sanctioned   load   of   the   supply   is   4   KWs   and   sanctioned category   of   the   supply   is   domestic   purpose   and   date   of energisation 29.04.1998 and computer generated electricity bill is exhibited as Ex.DW­1/A.  The electricity connection was   disconnected   due   to   non­payment   in   the   month   of January, 2014.  Thereafter, accused made a payment of Rs. 7,000/­. Thereafter,  also the  connection  was not restored and the accused is using the electricity through direct theft of electricity.   I inspected the premises yesterday since I have   to   come   to   depose   before   this   Court   to   know   the status of the premises in question and still the accused is indulged in direct theft and there is no electricity meter at site.  

     BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 12 of 15 13    XXXX   by   Sh.   Naresh   Bhardwaj,   Counsel   for complainant company. 

   After   the   payment   of   Rs.   7000/­   made   by   the accused in the month of March, 2014, the remaining dues are Rs. 46,080/­.  It is correct that only after the payment of this amount, the electricity connection will be restored.   I am deposing on the basis of summoned record brought by me in the Court today........."

23. Heard.  Considered.  Record perused carefully.

24. After hearing the arguments on both sides, the Court has come to the conclusion that the premises in question is not disputed, the connection of the accused with the premises in question is also not disputed as well as the presence of accused persons at the time of inspection is also not disputed and is duly depicted in the videography.   Certain facts have come on record on the basis of deposition of witnesses that at the time of inspection,  meter in question was disconnected as has duly found in the deposition of PW­1 Sh. Mani Bhushan Saroj, it has come in the fora that the electricity supply of accused persons was disconnected on account of non­payment   of   due   charges.     It   has   been   duly   depicted   in   the videography and also deposed by witnesses that the illegal wires were connected  at  the   input   terminal  of  the   meter  for   committing   theft   of electricity.  The submission of ld. counsel for accused that the NOC was      BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 13 of 15 14 issued against the theft bill to the accused is irrelevant in this case as the accused had chosen to face the Trial and to take chance for acquittal and once   the   accused   has   chosen   to   face   the   Trial,   he   is   bound   by   the outcome of the same.  Nothing has been placed on record by the accused persons that at the time of inspection at the premises in question, he was paying the electricity charges as no electricity bill for the time when inspection was conducted has been placed on record by the accused. Reliance is placed on a judgment in case title as  Mukesh Rastogi Vs. North Delhi Power Limited, in Criminal Appeal No. 531/2007, decided on 23.10.2007, wherein, the Hon'ble High Court of Delhi has held as under:­  ".........6. The contention of the appellant is that electricity supply was through meter.  Had the electricity been going to the appellant's premises through meter, the easiest way to prove it was by producing the electricity bills paid by the appellant to the complainant company.  The very fact that the appellant did not prove a single bill showing payment of electricity charges fortifies the plea of the complainant company that electricity was being used by the appellant directly from LT Main by committing theft. Paid electricity bills would have been the best evidence to show that the appellant   was   using   electricity   through   meter.   Under Section   106   of   the   Evidence   Act,   the   onus   was   on   the appellant to produce and prove such bills paid for the use of electricity.  However, this was not even the case of the appellant either before trial court or in appeal that he had been using electricity through meter and had been paying bills of electricity as per meter.   The appellant had only taken the stand that inspection was not valid inspection and the photographs were not proved properly".  

     BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 14 of 15 15

7.   "I consider that even if the inspection was not a valid inspection,   complainant   had   a   right   to   prove   theft   of electricity done by the appellant irrespective of the status of inspection. The invalid inspection does not make theft of electricity as a non­crime.   Theft of electricity remains a crime  irrespective of fact  that inspection is valid  or not. Supreme Court in State & Ors. v. N. M. T. Joy Immaculate 2004(5) SCC 729 observed that admissibility or otherwise of a piece of evidence has to be judged having regard to the provisions of the Evidence Act. Neither Evidence Act nor Cr.P.C. or any other law excludes relevant evidence on the ground   that   it   was   obtained   under   an   illegal   search   or seizure.   I, therefore, consider that even if the inspection was not conducted by an Officer as designated under the notification   date   31st  March,   2004,   the   members   of   the inspection team, who had visited the site and found that electricity being stolen are competent witnesses to depose in the Court about the theft of electricity and the manner in which electricity was being stolen....." 

25. In  view  of  aforesaid  discussion,  I  am  of  the  considered  opinion  that complainant has been successful in proving the case against both the accused   beyond   reasonable   doubt.     Accordingly,   accused   namely Rukhshana   is   held   guilty   u/s.   135   of   the   Electricity   Act,   2003   and accused Jaferyddin @ Jafruddin is held guilty u/s 135 r/w Section 150 of the Electricity Act, 2003. The file be consigned to record room.

         Announced in the open                              ( NEELAM SINGH)
         court on this 20th November, 2017                      ADDL. SESSIONS JUDGE
                                                                SPL. ELECTRICITY COURT
                                                              SAKET COURTS, NEW DELHI




     BRPL VS. RUKHSHANA & ANR              CIS NO.641871/16                        Page no. 15 of 15