Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 0]

Bombay High Court

Signpost India Private Limited vs Brihan Mumbai Electric Supply And ... on 4 December, 2025

2025:BHC-OS:23431
             Neeta Sawant                                             FC-ARB NO-282 OF 2024

                              IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   ORDINARY ORIGINAL CIVIL JURISDICTION
                                    ARBITRATION PETITION NO.282 OF 2024
                                                  WITH
                                   INTERIM APPLICATION NO . 7232 OF 2025


             SIGNPOST INDIA PRIVATE LIMITED                                            ...Petitioner

                                         V/s.

              BRIHAN MUMBAI ELECTRIC SUPPLY
              AND TRANSPORT UNDERTAKING                                             ...Respondent




             Mr. Harshvardhan Kotla with Mr. Dhanesh Dhotre & Ms. Shruti
                  Bedekar i/b Mr. Ajay Basutkar, for Petitioner.

             Mr. Nirav Shah with Ms. Aprajita Mahto & Ms. Shraddha Nagaonkar
                  i/b Mr. Sagar Shetty, for Respondent.

                                                   CORAM : SANDEEP V. MARNE, J.
                                                   Reserved On : 25 NOVEMBER 2025.
                                                   Pronounced On : 04 DECEMBER 2025.

             Judgment:


             1)                Petitioner has filed the present Petition under Section 34
             of the Arbitration and Conciliation Act, 1996 (Arbitration Act)
             challenging the Award dated 2 January 2024 passed by the learned
             sole Arbitrator. By the impugned Award, the learned sole Arbitrator
             has rejected all the claims made by the Petitioner. The counterclaim
             filed by the Respondent is allowed to the extent of sum of Rs.
             49,60,063/- towards interest on delayed payment charges, Rs.
             46,78,000/- towards RTO fees and Rs. 37,29,000/- towards
             defacement charges. The learned sole Arbitrator has also awarded


             _____________________________________________________________________________
                                              PAGE NO. 1 of 46
                                            04 DECEMBER 2025


                    ::: Uploaded on - 04/12/2025                ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                 FC-ARB NO-282 OF 2024

costs of arbitral proceedings of Rs. 48,20,000/- in favour of the
Respondent. The Arbitral Tribunal has awarded interest @ 18% per
annum from 5 December 2022 i.e. date of filing of counterclaim till
the date of Award and post Award interest @10% p.a.


2)                Brief facts leading to filing of the Petition as pleaded by
the Petitioner are stated thus :-
Petitioner is engaged in the business inter-alia of advertising. The
Respondent             -Brihanmumbai       Electric   Supply       and       Transport
Undertaking (BEST) is a civic transport and electricity provider in
Mumbai. Respondent-BEST operates a large fleet of buses in Mumbai
city and neighbouring areas outside the city limits.




3)                The Respondent floated a tender on 9 November 2018
for allotment of advertisement rights for 3121 buses in its fleet for a
period of three years. Petitioner participated in the tender process
and submitted bid/offer of Rs.95.5 crores. Petitioner was declared as
a successful bidder and contract was awarded vide allotment letter
dated 23 January 2019 granting advertisement rights for a period
of three years from 11 February 2019 to 10 February 2022.
Petitioner was directed to deposit Rs.4,78,00,000/- being 30% cash
security deposit and Rs.11,14,00,000/- in the form of Bank
Guarantee towards 70% security deposit and Rs.1 crore for
defacement/repainting                 of   advertisements.        The        Petitioner
communicated its acceptance of allotment letter vide its letter dated
30 January 2019. Petitioner provided the requisite bank guarantee
towards security deposit and amount of defacement charges and
also paid 30% security deposit in cash. An Agreement dated
4 November 2020 was executed between the parties.


_____________________________________________________________________________
                                 PAGE NO. 2 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                    ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                           FC-ARB NO-282 OF 2024



4)                After commencement of the contract, the Petitioner
came across several buses, which were unfit for display of
advertisements and upon its survey, it claimed that 966 buses were
found to be majorly damaged. The Petitioner accordingly requested
Respondent for grant of rebate in November-2019. A physical
inspection was completed by both the parties where 753 buses were
found to be majorly damaged. Relying on the report of the joint
survey, Petitioner requested Respondent to grant rebate in respect
of 753 damaged buses from the date of commencement of the
contract till the buses were repaired. By letter dated 23 December
2019, Respondent contended that 672 out of 753 buses were
damaged which needed to be attended to and 81 damaged buses
needed workshop attendance /major repairs.


5)                After Covid-19 outbreak and imposition of nationwide
lockdown, the buses of the Respondent were not operational from 24
March 2020 onwards. The Petitioner claimed rebate in respect of
lockdown period. In July-2021 Second joint survey was conducted,
in which 175 buses were allegedly found to be damaged. Petitioner
sought rebate in respect of damaged 175 buses which was denied by
the Respondent. On 28 June 2021 Respondent granted partial
rebate in display charges by granting 100% rebate for 1 April 2020
to 30 September 2020 due to Covid-19 and 100% rebate for the
period from 1 October 2020 to 31 December 2020 due to display of
campaign of Municipal Corporation and 50% rebate from 1 January
2021 to 31 March 2021. The Petitioner requested for grant of
further rebate. By letter dated 15 March 2022 Respondent granted
further rebate in display charges in following terms:-




_____________________________________________________________________________
                                 PAGE NO. 3 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025              ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                    FC-ARB NO-282 OF 2024

                  (i) 75% rebate on display charges on 1 January 2021 to
                  28 February 2021.
                  (ii) Adjustment of payment of display charges amounting
                  to Rs.5,63,73,558/- for 672 buses from 11 February 2019
                  to 23 December 2019 and time for payment of
                  outstanding dues of Rs.25,06,78,641/- within 7 days.


6)                According to the Petitioner, certain excess payments
were made by it to the Respondent in respect of buses not actually
plying and on account of wrongful application of calculation formula.
The contract between the Petitioner and the Respondent expired on
10 February 2022. However, the Petitioner kept on raising various
demands with the Respondent. Petitioner thereafter sought consent
of the Respondent for reference of the disputes to arbitration. With
the consent of the Petitioner letter dated 23 March 2022 was
addressed by the Petitioner to the learned sole Arbitrator and this is
how Arbitral Tribunal was constituted. Petitioner raised 8 claims in
its Statement of Claim. In support of its 8 claims, Petitioner raised
following prayers in its Statement of Claim :-

                 a. Directing the Respondent to provide the Claimant, rebate on damaged
                 buses amounting to a total of Rs. 4,67,42,372/- (the amount is inclusive
                 of interest charged as per the Request for Proposal) (Indian Rupees
                 Four Crores Sixty Seven Lakhs Forty Two Thousand Three Hundred
                 and Seventy Two Only) and consequently order and direct the
                 Respondent to pay the said amount to the Claimant.

                 b. Directing the Respondent to provide the Claimant, rebate on the said
                 Not-Out buses and on average available buses in the fleet during the
                 tenor of the subject Tender, the rebate on rental fees for the said Not-
                 Out buses comes to a total of Rs. 18,65,481/- (the said amount is
                 inclusive of the interest calculated as mentioned under the Request for
                 Proposal) (Indian Rupees Eighteen Lakhs Sixty Five Thousand Four
                 Hundred and Eighty One).

                 c. Directing the Respondent to provide the Claimant, rebate on the 08
                 day period from 24th March 2020 to 31st March 2020 in view of the
                 Covid-19 pandemic, the total rebate comes to total of Rs. 99,42,444/-



_____________________________________________________________________________
                                 PAGE NO. 4 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                       ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                      FC-ARB NO-282 OF 2024

                 (the said amount is inclusive of the interest calculated as mentioned
                 under the Request for Proposal)

                 d. Directing the Respondent to provide the Claimant, rebate calculated
                 on the basis of pay-per-use buses during the period 01st April 2021 to
                 10th February 2022, the total calculation comes to a total of Rs.
                 16,07,33,593/- (the said amount is inclusive of interest calculated as
                 per the Request for Proposal) (Indian Rupees Sixteen Crores Seven
                 Lakh Thirty Three Thousand Five Hundred and Ninety Three)

                 e. Direct the Respondent to refund the amount paid by the Claimant to
                 the Respondent, under protest and without prejudice to its rights and
                 contentions, amounting to a total of Rs. 14,45,33,204/- (Indian Rupees
                 Fourteen Crores Forty Five Lakhs Thirty Three Thousand Two Hundred
                 and Four Only)

                 f. For the purposes aforesaid necessary directions be given and enquires
                 be made and Award be passed.


7)                The Respondent appeared before the learned Arbitrator
and filed statement of defence. Additionally, Respondent also filed
counterclaim with the following prayers:-


                    A. Directing the Claimant to pay to Respondent a sum of INR 4,13,
                    69,016 along with further interest thereon at the rate of 18% per
                    annum as agreed between the parties and as set out in Particulars of
                    Claims being Exhibit -A hereto from the date of the filing of the
                    Counter Claim till payment and/or realization;

                    B. Directing the Claimant to pay to Respondent a sum of INR
                    49,60,063 along with further interest thereon at the rate of 18% per
                    annum as agreed between the parties and as set out in Particulars of
                    Claims being Exhibit - C hereto from the date of the filing of the
                    Counter Claim till payment and/or realization;

                    C. Directing the Claimant to pay to Respondent a sum of INR 46, 78,
                    000 along with interest thereon at the rate of 18% per annum as
                    agreed between the parties and as set out in Particulars of Claims
                    being Exhibit- D hereto from the date of the filing of the Counter Claim
                    till payment and/or realization;

                    D. Directing the Claimant to pay to Respondent a sum of INR
                    37,29,000 along with interest thereon at the rate of 18% per annum
                    as agreed between the parties and as set out in Particulars of Claims
                    being Exhibit-F hereto from the date of the filing of the Counter Claim
                    till payment and/or realization;


8)                Based on the pleadings, the Arbitral Tribunal framed
following 15 issues:-


_____________________________________________________________________________
                                 PAGE NO. 5 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                         ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                      FC-ARB NO-282 OF 2024



               (1)         Does the Claimant prove that its claims have arisen under the
                     2019 Tender and not under the Contract dated January 23, 2019,
                     entered into between the Claimant and Respondent?

               (2)         If the answer to Issue No. 1 is in negative, then does the
                     Claimant prove that all their claims, as sought for by them under the
                     Statement of Claim ought not to be rejected?

               (3)           Does the Claimant prove that it has not committed any breach(
                     es) of any of the provisions of the 2019 Tender?

               (4)         Does the Respondent prove that it has not committed any
                     breach( es) of any of the provisions of the 2019 Tender?

               (5)           Does the Claimant prove that under the 2019 Tender,
                     Respondent is obliged to provide rebate to the Claimant of damaged
                     buses for an amount of Rs.4,67,42,372/-, as alleged or otherwise?

               (6)           Does the Claimant prove that under the 2019 Tender,
                     Respondent is obliged to provide rebate to the Claimant due to not out
                     I non - operational buses for an amount of Rs.18,65,481/-, as alleged
                     or otherwise?

               (7)         Does the Claimant prove that under the 2019 Tender,
                     Respondent is obliged to provide rebate for the 8 day period from
                     March 24, 2020 to March 31, 2020 in view of COVID - 19 pandemic
                     for an amount of Rs.99,42,444/-, as alleged or otherwise?

               (8)         Does the Claimant prove that under the 2019 Tender,
                     Respondent is obliged to provide rebate for the pay-per-use buses
                     during April 1, 2021 to February 10, 2022, for an amount of
                     Rs.16,07,33,593/-, as alleged or otherwise?

               (9)         Does the Claimant prove that under the 2019 Tender,
                     Respondent is obliged to provide refund of amount of
                     Rs.14,45,33,204/-,paid under protest by the Claimant, as alleged or
                     otherwise?

               (10)     Does Respondent prove that the Claimant is liable to pay
                  Respondent a sum of Rs.4,13,69,016/- along with further interest
                  at the rate of 18% p.a. for the delayed payment charges, as set
                  out in the Respondent's Counter Claim?


               (11)     Does the Respondent prove that the Claimant is liable to pay
                  the Respondent a sum of Rs.49,60,063/- along with further interest
                  at the rate of 18% p.a. for the interest on the delayed payment
                  charges, as set out in the Respondent's Counter Claim?

               (12)      Does the Respondent prove that the Claimant is liable to pay
                  the Respondent a sum of Rs.46,78,000/- along with further interest
                  at the rate of 18% p.a. for the RTO Fees, as set out in the Respondent's
                  Counter Claim?



_____________________________________________________________________________
                                 PAGE NO. 6 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                         ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                     FC-ARB NO-282 OF 2024

               (13)     Does the Respondent prove that the Claimant is liable to pay
                  the Respondent a sum of Rs.37,29,000/- along with further interest
                  at the rate of 18% p.a. for the defacement charges incurred by
                  Respondent, as set out in the Respondent's Counter Claim?

               (14)        What Order?

               (15)        What Costs?


9)                Petitioner filed application under Section 17 of the
Arbitration Act for injunction against the Respondent from
invocation of Bank Guarantees and forfeiture of security deposit.
During the course of hearing                  Petitioner filed Application under
Section 17 of the Arbitration Act, Respondent filed Application
under Section 16 challenging jurisdiction of Arbitral Tribunal
contending that non-payment of requisite stamp duty on the
contract had a reflection on jurisdiction of Arbitral Tribunal. The
Arbitral Tribunal rejected Section 16 Application by order dated 28
July 2022. Thereafter Application filed by Petitioner under Section
17 of the Arbitration Act was withdrawn by the Petitioner.


10)               Parties led evidence in support of their respective cases.
Arbitral Tribunal has made Award dated 2 January 2024 rejecting
all the claims of the Petitioner and allowing some of the claims
raised by the Respondent in counterclaim. Operative part of the
Award reads thus:-


                 A) All the Claims made by the Claimant are rejected.

                 B) The Claim of the Respondent is allowed to the extent given below:

                      i)   In terms of prayer clause 'B' of Counter Claim of the
                           Respondent, the Respondent is entitled to an Award in the sum
                           of Rs. 49,60,063 (Rs. Forty Nine Lakh Sixty Thousand Sixty
                           Three Only) along with interest@ 18% p.a. from 5-12-2022 i.e
                           filing of the Counter Claim till the date of this Award
                           Accordingly, The Claimant is directed and ordered to pay to the
                           Respondent the total sum of Rs Rs. 49,60,063 (Rs. Forty Nine
                           Lakh Sixty Thousand Sixty Three) along with interest @18%


_____________________________________________________________________________
                                 PAGE NO. 7 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                        ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                       FC-ARB NO-282 OF 2024

                           p.a from 5-12-2022 i.e filing of the Counter Claim till the date of
                           this Award.

                      ii) In terms of prayer clause 'C' of Counter Claim of the
                          Respondent, the Respondent is entitled to an Award in the sum
                          of Rs. 46,78,000 (Rs. Forty Six Lakh Seventy Eight Thousand
                          Only ) along with interest @ 18% p.a. from 5-12-2022 i.e filing of
                          the Counter Claim till the date of this Award Accordingly, The
                          Claimant is directed and ordered to pay to the Respondent the
                          total sum ofRs. 46,78,000 (Rs. Forty Six Lakh Seventy Eight
                          Thousand Only) along with interest@ 18% p.a. from 5-12-2022
                          i.e filing of the Counter Claim till the date of this Award On
                          realization of this mount the Respondent shall pay the required
                          outstanding RTO fee as per the RTO rules applicable, to the
                          concerned RTO authorities .

                      iii) In terms of prayer clause 'D' of Counter Claim of the
                           Respondent, the Respondent is entitled to an Award in the sum
                           of Rs.37,29,000(Rs. Thirty Seven Lakh Twenty Nine Thousand
                           only) along with interest @ 18% p.a. from 5-12-2022 i.e. filing of
                           the Counter Claim till the date of this Award. Accordingly, the
                           Claimant is directed and ordered to pay to the Respondent the
                           total sum Rs.37,29,000 (Rs. Thirty Seven Lakh Twenty Nine
                           Thousand only) along with interest @ 18% p.a. from 5-12-2022
                           i.e. filing of the Counter Claim till the date of this Award.

                      iv) The Claimant is directed and ordered to pay to the Respondent
                          further interest@ 10% p.a. on the total sums as detailed in i), ii)
                          and iii) above, from the date of this Award till realization.

                 C) The Respondent is also entitled to costs as are held payable by the
                     Claimant as mentioned earlier and as such the Claimant is directed
                     and ordered to pay to the Respondent a sum of Rs. 48,20,000 (Rs.
                     Forty-Eight Lakh Twenty Thousand only) towards such costs
                     together with interest @ 10% p.a. from the date of this Award up to
                     the date of payment and/or realization.

                 D) The Arbitral proceedings are accordingly terminated by this final
                    Award.

11)               Aggrieved by the Award dated 2 January 2024,
Petitioner has filed the present Petition under Section 34 of the
Arbitration Act.


SUBMISSIONS


12)               Mr. Harshavardhan Kotla, the learned counsel appearing
for the Petitioner has canvassed following submissions in support of
the Arbitration Petition:-

_____________________________________________________________________________
                                 PAGE NO. 8 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                          ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                   FC-ARB NO-282 OF 2024



               (a)That the Tribunal's finding that Petitioner is not entitled to
                  rebate for damaged buses is recorded in ignorance of vital
                  evidence and is contrary to the stipulations of the contract,
                  which expressly imposes an obligation on the Respondent
                  and further provides for rebate towards reduction of fleet.
                  That the finding is therefore contrary to public policy of
                  India and is also patently illegal.
               (b)Finding of the Tribunal that Clause-4.1 is not applicable to
                  the present dispute is patently illegal since the finding is in
                  derogation of terms of that clause. That under Clause-4.1 it
                  was the contractual obligation of the Respondent to provide
                  required support for each bus to carry out advertisement
                  in good condition. That by making available damaged buses
                  for display of advertisement, the Respondent committed
                  breach of obligation under Clause 4.1 making the Petitioner
                  entitled to seek rebate in the fees.
               (c) That the learned Arbitral Tribunal has erroneously
                  rejected Petitioner's argument of waiver raised on the basis
                  of Respondent's conduct of making available rebate in
                  respect of several buses on which advertisement could not
                  be displaced. That after granting rebate in respect of partial
                  number of damaged buses, Respondent was estopped from
                  questioning rebate entitlement of the Petitioner in respect
                  of all identified damaged buses in the joint inspection.
               (d)That the Arbitral Tribunal has erroneously treated the
                  claim of Petitioner for rebate towards damaged buses as
                  claim for damages /compensation. On such erroneous
                  assumption the Tribunal committed further error in
                  expecting the Petitioner to adduce evidence to support


_____________________________________________________________________________
                                 PAGE NO. 9 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                      ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                               FC-ARB NO-282 OF 2024

                  cause of loss. Without prejudice he would submit that the
                  Tribunal failed to appreciate that liability to pay fees in
                  respect of the damaged buses is the loss caused to the
                  Petitioner.
               (e)That the Arbitral Tribunal has failed to interpret and
                  construct various clauses of the contract without reading
                  them harmoniously.
               (f) That the contract envisaged rebate in the fees payable by
                  the Petitioner if there was reduction in the number of buses
                  for any reason.
               (g)That the Arbitral Tribunal erred in not appreciating the
                  position that Clause-1.3 of the contract is an overarching
                  provision dealing with rebate /concession and Clause-4.1 is
                  only one of the eventualities in which the rebate was
                  admissible and that therefore it was necessary to
                  separately deal with entitlement of rebate in Clause-4.1 of
                  the contract.
           (h)That the Arbitral Tribunal has not even considered the
                 stipulations under Schedule-IX of the contract dealing with
                 'Terms of Payment' under which fleet of buses, which were
                 made available for display of advertisement on first day of
                 each previous month was an important factor in the
                 formula for determination of monthly rentals. That thus,
                 payment of monthly fees was not static and was in fact
                 dynamic depending on the number of buses made available
                 for display of advertisements. That therefore if certain
                 number of buses were not made available for any reason,
                 including damaged buses, the amount of monthly rentals
                 would automatically become liable for reduction.




_____________________________________________________________________________
                                PAGE NO. 10 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                  ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                    FC-ARB NO-282 OF 2024

               (i) That the Arbitral Tribunal has egregiously erred in not
                     sanctioning the claim for refund of excess amount paid by
                     the Petitioner by ignoring the formula under Schedule-IX of
                     the contract.
               (j) That the Petitioner produced chart of buses actually
                     deployed by the Respondent every day before the Arbitral
                     Tribunal and that therefore the actual number of buses
                     deployed by the Respondent on first day of previous month
                     was required to be taken into consideration while
                     determining monthly rentals payable by the Petitioner.
                     However, no finding is recorded by the Arbitral Tribunal on
                     this vital aspect and the claim for refund of excess
                     payment     is   erroneously    rejected     by      taking        into
                     consideration reasons for rejection of claim towards
                     damaged buses.
               (k)     That the Tribunal's finding that the Petitioner is not
                     entitle to rebate for 8 days from 23 March 2020 to 31
                     March 2020 is in contravention of terms of contract and
                     hence contrary to public policy in India and is in conflict
                     with basic principles of natural justice. That the Tribunal
                     erred in rejecting claim for rebate for 8 days of Covid-19
                     period by ignoring a specific stipulation under Clause-19 of
                     the contract relieving the Petitioner from obligation to pay
                     monthly display charges due to occurrence of force
                     majeure event.
               (l) That the Tribunal erroneously rejected waiver plea raised
                     by the Petitioner by invoking reasons for rejection of claim
                     for rebate for damaged buses.
               (m) That the Arbitral Tribunal has erred in awarding interest
                     on interest in favour of the Respondent, which is clearly


_____________________________________________________________________________
                                PAGE NO. 11 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                      ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                              FC-ARB NO-282 OF 2024

                 contrary to fundamental policy of Indian law. That the
                 Arbitral Tribunal failed to consider that delayed payment
                 charges are in themselves penal interest on delayed
                 charges of monthly display charges.
               (n)   That no computations were produced by the Respondent
                 and vague figure of Rs.49,60,063/- was presented before
                 the Arbitral Tribunal sans any particulars. That Petitioner
                 paid the entire outstanding dues towards display charges
                 by clearing all the arrears and by paying contractual
                 delayed payment charges on 9 December 2022, 24
                 December 2022, 8 January 2023 and 24 January 2023.
               (o)That under the contract, the delayed payment charges
                 were in the form of interest @18% p.a. for first six months,
                 24% p.a. for next six months and 30% p.a. beyond one year.
                 That it is otherwise unjust to direct Petitioner to pay
                 further interest of 18% on such hefty amount of interest
                 already paid.
               (p)That the Arbitral Tribunal has erroneously sanctioned
                 claim for RTO fees in the sum of Rs.46,78,000/- alongwith
                 interest which is contrary to the terms of the contract.
                 That the Arbitral Tribunal only considered terms of
                 stipulation in letter dated 23 January 2019 ignoring
                 Clause-14.2.1 of the Schedule- III (General conditions of
                 contract) which gave an option to the Petitioner to pay RTO
                 fees of Rs.62,42,000/- for first year or actual RTO fees for
                 every subsequent years. That during the period from
                 March-2020 to October 2020, buses of the Respondent
                 were admittedly not plying and that therefore RTO fees
                 were not payable in respect of that period. That Petitioner
                 had paid advance RTO fees for the period from February-


_____________________________________________________________________________
                                PAGE NO. 12 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                 ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                     FC-ARB NO-282 OF 2024

                     2020 to January 2021 and therefore it was entitled to
                     adjust the said fees in the third year period.
               (q)That there is nothing on record to indicate that the
                     Respondent actually paid fees to the RTO. That the words
                     'or at actual' occurring in sub-clause (b) of Clause-14.2.1
                     would mean payment by the Petitioner of only ' actual fees
                     paid by BEST to RTO'. That in absence of no proof being
                     produced by the BEST about payment of fees to RTO, it
                     would amount to unjust enrichment for BEST to claim fees
                     from the Petitioner.
               (r) That Tribunal's conclusion that the Respondent is entitled
                     to defacement charges alongwith interest @ 18% is patently
                     illegal and contrary to fundamental policy of Indian Law.
               (s) That while awarding claim towards defacement charges,
                     the Arbitral Tribunal ignored the ratio of the judgment in
                     Kailash Nath Associates V/s. Delhi Development Authority and
                     Anr.1 in which it is held that if penalty is stipulated in the
                     contract, the same represents the maximum cap upto
                     which damages can be awarded subject to proof of cause of
                     loss. That the Respondent did not lead any evidence to
                     prove cause of loss on account of alleged non-removal of
                     advertisement by the Petitioner after expiry of the
                     contract.
               (t) That     there     is   no   evidence   to    indicate        that      the
                     advertisement were actually removed by the Respondent
                     or that it incurred any expenditure towards such removal.
               (u)     That in any case contract for the next term is also
                     awarded to the Petitioner and that therefore no eventuality



1    2015 (4) SCC 136

_____________________________________________________________________________
                                PAGE NO. 13 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                        ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                FC-ARB NO-282 OF 2024

                  occurred for removal of advertisements of previous
                  contract.
               (v)That the Arbitral Tribunal has erred in awarding hefty cost
                  of arbitration at Rs.48,20,000/- with further interest
                  @10%. He would also rely on judgment of Division Bench of
                  this Court in Anila Gautam Jain. V/s. Hindustan Petroleum
                  Corporation Ltd. through the Chief Regional Manager2.
               (w) That the interest awarded by the Arbitral Tribunal is
                  unreasonable. That pre-Award interest of 18% and post-
                  Award interest of 10% awarded by the Arbitral Tribunal is
                  unjust and contrary to the contractual term.




13)                 On above broad submissions, Mr. Kotla would pray for
setting aside the impugned Award.


14)                 The Petition is opposed by Mr. Shah, the learned counsel
appearing for the Respondent-BEST. He would raise following
submissions:


                 (a) That the Award made by the Arbitral Tribunal is strictly
                    in conformity with contractual terms agreed between the
                    parties. That the Arbitral Tribunal has acted strictly in
                    accordance with contract clauses and none of the
                    findings recorded by it contravenes any particular
                    contractual stipulations. That the findings recorded by
                    the Arbitral Tribunal are based on evidence on record
                    and that there is no element of perversity in those
                    findings. That the Arbitral Tribunal has taken plausible


2    2018 SCC Online Bom 917

_____________________________________________________________________________
                                PAGE NO. 14 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                   ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                    FC-ARB NO-282 OF 2024

                  view, if not correct view. That therefore, none of the
                  grounds enumerated in Section 34 of the Arbitration Act
                  are made out by the Petitioner warranting dismissal of
                  the Arbitration Petition.
               (b) That the claim of the Petitioner for rebate in respect of
                    damaged buses was contrary to the contractual
                    provisions. That there is no stipulation in the contract
                    under which Petitioner could be granted any rebate in
                    respect of buses which are damaged. That on the
                    contrary,         Clause-1.1.1   of   Schedule-VI         specifically
                    reserves right for BEST to increase or decrease the
                    number of buses without affecting obligation of the
                    Petitioner to pay display charges. That Clause-1.1.1 of
                    Schedule-VI specifically provides that 100% buses need
                    not be on road and that no claims could be raised by the
                    Petitioner in respect of the buses which could not be
                    deployed on road.
               (c) That Tender document contained specific provision for
                    disclaimer under which the Petitioner was required to
                    satisfy itself about the fleet of buses available with the
                    Respondent. That the Petitioner was supposed to
                    inspect and investigate the fleet of buses and thereafter
                    quote       the    Tender   price.    Though        the     Petitioner
                    conducted such inspection, it did not raise any queries
                    in respect of the alleged damaged buses. Even in pre-bid
                    meeting he did not raise any query about damaged
                    buses. Clause-4.1 of Schedule-III of the contract
                    contemplated provision of only support by BEST for the
                    purpose of display of advertisement in good condition,
                    which cannot be confused with a guarantee that


_____________________________________________________________________________
                                PAGE NO. 15 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                       ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                              FC-ARB NO-282 OF 2024

                    undamaged buses would only be made available for
                    display of advertisement to the Petitioner. That the
                    words 'good condition' applies to advertisement and not
                    to buses.
               (d) That Petitioner's claim for rebate of 8 days for Covid-19
                    period was ex-facie baseless and rightly rejected by the
                    Arbitral Tribunal by recording cogent evidence, which
                    do not suffer from vice of perversity.
               (e) That Petitioner's claim for refund of excess payment
                    was made out of misreading of contractual provisions.
                    That number of buses actually deployed on the road had
                    no corelation to Petitioner's obligation to pay display
                    fees. That Schedule-IX contemplated 'fleet' of buses
                    'available for display' of advertisement on first day of
                    previous month. This would mean the number of buses
                    available in the fleet and not number of buses actually
                    deployed on the road. That Clause-1.1.1 of Schedule-VI
                    provides that BEST had necessary flexibility to increase
                    or decrease the buses and not to deploy 100% buses on
                    the road. The Petitioner agreed not to raise any claim in
                    respect of undeployed buses.
               (f) That evidence led by the Respondent in respect of the
                    fleet size has remained uncontroverted and that
                    therefore claim raised by the Petitioner in respect of
                    refund of the alleged excess payment was totally
                    baseless and rightly rejected by the Arbitral Tribunal.
               (g) That the Arbitral Tribunal has rightly allowed the claim
                    for interest on delayed payment charges as parties had
                    agreed on clear contractual stipulation of payment of
                    'additional interest' on delayed payment charges, if the


_____________________________________________________________________________
                                PAGE NO. 16 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                 ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                               FC-ARB NO-282 OF 2024

                    contractor failed to pay delayed payment charges
                    within a period of three months. That therefore, award
                    of claim for interest on delayed payment charges was
                    perfectly as per the contractual stipulations.
               (h) That the learned Arbitrator has rightly allowed claim of
                    the      Respondent        for   RTO             fees    and    indemnified
                    Respondent of obligation to pay the same to RTO. That it
                    is well settled law that contract of indemnity becomes
                    enforceable the moment RTO's claim qua the Petitioner
                    gets fructified and also proof of actual payment of fees
                    to RTO is not necessary for enforcing indemnity against
                    the Respondent. That the Tribunal has rightly relied on
                    four judgments cited by the Respondent in this regard.
               (i) That the Arbitral Tribunal has rightly allowed the claim
                    towards defacement charges of Rs.37,29,000/- as the
                    said claim clearly flows out of contractual stipulations
                    under Clause-21of Schedule-III . That Petitioner did not
                    dispute the amount of defacement charges calculated
                    by     the        Respondent     and        is     now     estopped        from
                    questioning          the   award       of        the     said   claim.       The
                    Respondent had obligation to provide advertisement on
                    buses to the new contractor, which is a reason why
                    obligation was imposed on the Petitioner to remove all
                    its advertisements from buses or to bear expenses for
                    such removal in addition to payment of penalty of
                    Rs.1,000/- per bus per day. That Petitioner admittedly
                    breached the contractual stipulation in Clause-21 of
                    Schedule-III and failed to remove its advertisements
                    from the buses. That since the Petitioner agreed to pay
                    penalty of Rs.1,000/- per bus per day it cannot now


_____________________________________________________________________________
                                PAGE NO. 17 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                              ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                              FC-ARB NO-282 OF 2024

                    expect the Respondent to lead evidence to prove loss
                    caused to the Respondent. That the Petitioner is
                    misreading the ratio of the judgment in Kailas Nath
                    Associates (supra) which recognises right to recover
                    the entire amount of stipulated penalty /damages upon
                    breach of contract.
               (j) That mere award of contract to the Petitioner for
                    further period of three years does not absolve its
                    responsibility of paying defacement charges sans
                    penalty directed under Clause-21 of Schedule-III. The
                    Respondent could not have envisaged award of next
                    contract to the Petitioner and there was wide gap
                    between tenures of two contracts. That in any case
                    award of claim for defacement is directly in conformity
                    with Clause-21of Schedule-III of the contract.


15)               On above broad submissions, Mr. Shah would pray for
dismissal of the Arbitration Petition.


REASONS AND ANALYSIS


16)               Petitioner is an advertisement contractor engaged by
Respondent-BEST for display of advertisements on its municipal
buses. Respondent-BEST operates one of the largest fleets of
municipal buses in the city of Mumbai and surrounding areas. It
appears that initially the fleet of BEST was declared as 3121 buses
on which Petitioner was to exploit advertisement rights for a period
of 3 years from 11 February 2019 to 10 February 2022 after paying
display charges to the Respondent. Petitioner was selected by
Respondent-BEST through competitive bidding process and the


_____________________________________________________________________________
                                PAGE NO. 18 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                 ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                FC-ARB NO-282 OF 2024

Petitioner had bid for amount of Rs.95.50 crores for exploitation of
advertisement rights on buses of the Respondent for a period of 3
years. Under Clause-7 of the letter of allotment, Petitioner was under
obligation to pay monthly display charges in advance to the
Respondent in the prescribed formula which was, multiplication of
bid price by 36 months by fleet of buses of 3121 which was to be
further multiplied by the fleet as on the first day of previous month.
Clause-7 of the letter of allotment reads thus :-


                  7.Payment of monthly rentals: You shall pay to the Undertaking
                  the monthly display charges in advance as per the formula given
                  below on or before the first day of every month through
                  RTGS/NEFT/DD/PO under intimation to AGM(TE)'s office.

                  Amount of monthly rentals for the month= Rs. 95,50,00,000/ (36 X
                  3121) X Fleet as on first of previous month.



17)               After commencement of the contract tenure, disputes
arose between the parties as Petitioner initially raised the issue of
large number of damaged buses and claimed significant rebate.
According to the Petitioner as many as 966 buses out of total fleet of
3121 buses were damaged which were incapable of being used for
display of advertisements. Initially, Respondent-BEST refused to
accede to the demand of the Petitioner for rebate in respect of 966
buses but subsequently acceded partially to the request in respect of
672 buses by letter dated 15 March 2022. Petitioner still remained
unsatisfied and continued claiming rebate in respect of the balance
damaged buses. Though Petitioner was granted rebate in respect of
the Covid-19 period, it continued demanding rebate in respect of 8
additional days. Petitioner claimed that the formula prescribed in
the agreement for computation of monthly display charges was
erroneously applied without taking into consideration the actual
buses plying on the road each month and contended that the

_____________________________________________________________________________
                                PAGE NO. 19 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                   ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                  FC-ARB NO-282 OF 2024

Respondent had recovered excess monthly display charges from it.
The disputes raised by the Petitioner were referred to resolution by
arbitration. By filing of Statement of Claim, the Petitioner raised
following 8 claims.


                  Claim No. 1 Claim on Rebate of damaged buses.

                  Claim No.2 Claim on rebate due to Not Out buses. ( Non operational
                  buses as per the data provided by the Respondent.

                  Claim No.3 Rebate from 23rd March 2020 to 31st March 2020 in
                  the wake of COVID-19 pandemic.

                  Claim No.4 Loss of business sentiments and limited opportunities.

                  Claim No.5 Rebate on the RTO fees paid to the Respondent.

                  Claim No.6 Claim on payment of Rs. 2,31,204/- paid to the
                  Respondent under protest.

                  Claim No.7 Payment of Rs. 12,14,00,000/- paid to the Respondent
                  under protest.

                  Claim No.8. Rebate on incorrect interest levied on outstanding dues
                  since the inception of the subject Tender.


18)               Respondent, in addition to resisting the statement of
claim, filed its own counterclaim and raised claims inter alia for
interest on delayed payment charges, RTO fees, defacement charges,
etc against the Petitioner. The Arbitral Tribunal has rejected all the
claims of the Petitioner and has sanctioned 3 Counterclaims of
Respondent-BEST in addition to award of costs and interests in its
favour.


19)               Petitioner is aggrieved by rejection of all its claims and
by grant of three claims in favour of the Respondent, in addition to
direction for payment of costs and interests. Though several claims
were raised by parties against each other, the Petitioner has not
canvassed submissions before me with regard to the findings


_____________________________________________________________________________
                                PAGE NO. 20 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                     ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                            FC-ARB NO-282 OF 2024

recorded by the Arbitral Tribunal in respect of each of its claims and
counterclaims of the Respondent. The scope of the present Petition is
thus restricted in respect of rejection of three claims of Petitioner
and grant of three counterclaims of the Respondent which are as
under:
                         REJECTION OF CLAIMS OF PETITIONER

  1 Rebate for damages business amounting to                         Rejected
    Rs.4,67,42,372/-
  2 Rebated for 8 days' Covid-19 period amounting to                 Rejected
    Rs.99,42,444/-
  3 Refund of excess amount paid by the Petitioner to                Rejected
    Respondent of Rs.14,45,33,204/-

        COUNTERCLAIMS AWARDED IN FAVOUR OF THE RESPONDENT

  4 Interest on delayed payment charges of                            Allowed
    Rs.49,60,063/- alongwith further interest at 18%
    p.a.
  5 RTO fees of Rs.46,78,000/- alongwith interest @                   Allowed
    18% p.a.
  6 Defacement charges of Rs.37,92,000/- alongwith                    Allowed
    18% interest
  7 Costs of arbitration proceedings of Rs.48,20,000/-                Allowed
    with future interst @ 10% p.a.
  8 Interest @ 18% p.a. on three counterclaims granted                Allowed
    in favour of the Respondent from the date of the
    Award till realisation


20)               Now I proceed to examine whether any ground is made
out by the Petitioner for interference in rejection of its claims and
sanctioning counterclaims of the Respondent.


REJECTION OF CLAIM FOR DAMAGED BUSES


21)               Petitioner has raised claim of 4,67,42,372/- towards
rebate for damaged buses on which it allegedly could not display

_____________________________________________________________________________
                                PAGE NO. 21 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025               ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                FC-ARB NO-282 OF 2024

advertisements during the relevant period. The Arbitral Tribunal
framed Issue No.5 for deciding this claim of the Petitioner, which
was as under :-

                  Issue No.5. Does the Claimant prove that under the 2019 Tender,
                  Respondent is obliged to provide rebate to the Claimant on
                  damaged buses for an amount of Rs.4,67,42,372/-, as alleged or
                  otherwise?



22)               Petitioner's claim for rebate in respect of damaged buses
was premised essentially on the alleged joint survey conducted by
the parties in November 2019 in which 753 buses were found to be
majorly damaged. A further joint survey was apparently conducted
in July 2021 in which it was found that 131 buses were consistently
damaged since 2019 and 175 buses were identified to be damaged
after 2019. Petitioner accordingly pressed for de-notification of 966
buses from fleet of 3121 buses for computing the monthly display
charges. Initially the request was rejected by BEST vide letter dated
13 May 2019. However, subsequently Respondent-BEST partially
accepted the request for rebate in respect of damaged buses by letter
dated 15 March 2022 by adjusting payment of display charges of
5,63,73,558/- for 672 buses for the period from 11 February 2019 to
23 December 2019 due to inability in displaying advertisements on
damaged/dented buses. The relevant portion of letter dated 15
March 2022 reads thus :-

                  ii) To adjust payment of display charges amounting to
                  Rs.5,63,73,558/-for 672 buses for the period from 11th February
                  2019 to 23rd December 2019 (316 days) due to inability to display
                  advertisement on damaged/dented Buses.


23)               Based on letter dated 15 March 2022, Petitioner pressed
into service the theory of waiver for claiming that since the claim for
672 damages buses was accepted, the objection of absence of

_____________________________________________________________________________
                                PAGE NO. 22 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                   ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                   FC-ARB NO-282 OF 2024

contractual obligation for rebate for damaged buses must be treated
as having waived by the Respondent. The Arbitral Tribunal has
however rejected the contention of waiver by recording following
findings:-

                  16.4 Both the above authorities relied on by the Claimant are also
                  taken shelter of by the Respondent in order to counter the
                  arguments advanced on behalf of the Claimant as to 'Waiver'. On
                  this issue defence of the Respondent is that said rebate/concession
                  given to the Claimant was subject to the fulfilment of other
                  conditions mentioned in the letters dated 28th June 2021 and 15th
                  March 2022. Moreover, the said rebate was not granted as a matter
                  of right vested in the Claimant but it was the gratuitous act of the
                  Respondent. Considering the rival submissions on this aspect of
                  Waiver in the considered view of this Tribunal said arguments on
                  behalf of the Claimant shall not sustain, in as much as grant of
                  rebate for Covid period as detailed in the letter dated 28 June 2021
                  was conditional and was on certain conditions as detailed therein
                  Moreover, such conditional rebate is required to be looked into
                  along with various terms and conditions of the Tender document
                  and specially 'Disclaimer' mentioned therein, so also is the case
                  with respect to letter dated 15th March 2022.


                  16.5 In the considered view of this Tribunal conditional grant of
                  rebate on damaged buses is clinching material in order to hold that
                  there is nothing expressed by the Respondent to abandon its rights
                  to challenge the claim of the Claimant on damaged buses. More over
                  conditions in iii) and v) in this letter are admittedly not complied
                  by the Claimant. Furthermore this 'Waiver' issue is put to rest by
                  the clinching provision in the Contract dated 4-11-2020 (Exhibit
                  UUU to SOC) entered into between the parties and filed on record of
                  this Tribunal on 4-7-2023. Clause 38. 'b' of this Contract reads thus,
                  which is self-explanatory.


24)               I am in full agreement with the above findings recorded
by the learned Arbitrator. Mere extension of gratuitous act by
Respondent-BEST in granting rebate in respect of 672 damaged
buses cannot be used by Petitioner to advantage for claiming rebate
for balance alleged damaged buses contrary to the contractual
covenants. The advertising rights were granted in respect of 'fleet' of
buses          available      with    BEST.   While    computing         the     monthly
advertisement charges, actual number of buses available in the fleet

_____________________________________________________________________________
                                PAGE NO. 23 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                      ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                  FC-ARB NO-282 OF 2024

was taken into consideration for each month and Petitioner had
agreed for computation of charges in accordance with the formula. It
had inspected the buses before quoting the bid price. The contract
clauses specifically provided for payment of display charges even in
respect of buses rendered inoperational due to maintenance work.
Petitioner agreed for a comprehensive contract not connected with
actual number of buses plying on the road or actual number of buses
fit for display of advertisements. It quoted the bid price accordingly.
After commencement of contract, it could not have turned around
and contended that the gratuitous act of BEST in granting rebate for
few buses would constitute as admission of liability or waiver of
objection about absence of contractual clause for rebate in respect of
damaged buses. In any event,                Mr. Kotla has not raised a very
serious objection in respect of findings on waiver, and in my view,
rightly so.


25)               After debunking the theory of waiver, the Arbitral
Tribunal has also considered contractual stipulations for rejecting
Petitioner's claim for rebate for damaged buses.


26)               Turning to the contractual stipulations, the sheet anchor
of Petitioner is Clause-4.1 of Schedule-III of General Conditions of
Contract, which reads thus:-

                  4.1 The Contractor shall maintain the advertisements in good
                  condition and shall take responsibility of getting the work of
                  defacing/replacing/repairs or repainting done at their own cost.
                  The General Manager agrees to provide at its own cost such
                  support as may be required on each bus to carry out the
                  advertisements in good condition. Further, the painting or
                  repainting of advertisements directly on buses and pasting of vinyl
                  stickers will have to be done by the Contractor with proper care.
                  The Contractor shall ensure that the bus is repainted in the area
                  within three days as per the specification of BEST.



_____________________________________________________________________________
                                PAGE NO. 24 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                     ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                  FC-ARB NO-282 OF 2024



27)               Under clause-4.1, the General Manager of BEST agreed
to provide, at its own cost, such support as may be required by each
bus to carry out advertisements in good condition. The clause does
not stipulate that every bus must be provided in good condition for
display of advertisement. The words 'good condition' is attached to
the word 'advertisement' and not to the word 'bus'. Furthermore,
Clause-4.1 does not provide for any rebate in the event of any bus
being not made available for advertisement due to damage.


28)               Faced with the difficulty of absence of provision in the
contract Clause-4.1 for rebate in respect of buses which were not in
condition to display advertisements in 'good condition', Mr. Kotla
has submitted that Clause-4.1 identifies one of the eventualities
where display charges became non-leviable and the overarching
provision for rebate is to be found in Clause-1.3 of Schedule-VI.
According to him, the moment there is reduction in number of buses
available for display of advertisements, pro-rata rebate was
automatic under Clause-1.3 of Schedule-VI.


29)               Schedule-VI under heading 'Scope of Work' stipulated
that the display charges were to be paid in lumpsum in accordance
with the schedule of prices in Schedule-VII under which bidders
were expected to quote net display lumpsum charges in respect of
3121 buses. Schedule-VI under heading 'Scope of Work' stipulated
following conditions:


                  1. SCOPE OF CONTRACT
                  1.1 This contract is for the sole right for display of advertisement
                  on Undertaking's buses on payment of monthly installments based
                  on lumpsum display charges offered for a given period, as offered



_____________________________________________________________________________
                                PAGE NO. 25 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                     ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                   FC-ARB NO-282 OF 2024

                  by the tenderer as per Schedule of Prices, Schedule-VII and
                  according to the conditions given below:

                  1.1.1 The Undertaking shall have the right to increase and / or
                  reduce the number of depots, number of buses in a depot, scheduled
                  turnout and fleet composition at different depots, subject to the
                  total number of buses as mentioned below being made available and
                  to change the route/s of the buses displaying advertisements at its
                  sole discretion. The 100% buses may not be on road considering
                  their repair and maintenance. No claims shall be raised by the
                  Contractor against upkeep and maintenance of buses.

                  1.1.2 The Undertaking reserves right to vary number of buses
                  allotted for display of advertisement out of its total fleet for
                  specific/entire period of contract.

                  1.2 Initially 3121 buses of different seating capacity, make, model
                  etc. of the BEST Undertaking would available to the contractor.
                  However buses already under Public Private Partnership (PPP),
                  Electric buses, Hybrid buses, donated buses and buses given to
                  BEST in lieu of advertising rights or similar such considerations
                  will not be covered in this contract. Further, buses which are
                  specified (new Tata buses) for non-display during part/entire
                  contract period, will also be excluded from the scope of this tender.

                  1.3 The rebate / concession shall be granted to the contractor for
                  reduction in the fleet by way of pro-rata relief in the payment of
                  monthly rentals. If the fleet increases over the fleet allocated, the
                  contractor shall be charged on pro-rata basis. The Undertaking
                  reserves the right to allocate spaces other than those specified in
                  the attached tender documents, to any other contractor by issuing
                  a separate contract. The Undertaking may offer these spaces to the
                  highest bidder of this tender on pro-rata basis.

                  1.4 The area available for advertising purpose on buses is as per
                  the drawing attached.



30)               It is the contention of Mr. Kotla that Schedule-VI
stipulations are overarching agreed conditions for rebate without
specifying the exact eventualities and that Clause-4.1 Schedule-III of
dealt with one such eventuality under which rebate was required to
be granted if the bus was not in good condition. I am unable to agree.
Under Clause-1.1.1 of Schedule-VI , BEST not only had right to
increase or decrease the number of buses, but it was also specifically
agreed between the parties that '100% buses may not be on road
considering their repairs and maintenance ' and that 'No claim shall

_____________________________________________________________________________
                                PAGE NO. 26 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                      ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                  FC-ARB NO-282 OF 2024

be raised by the contractor against upkeep and maintenance of
buses.'


31)               Clause-1.3 of Schedule-VI provided for rebate/concession
in respect of 'reduction in the fleet'. Clause-1.3 is in consonance with
Schedule-IX 'Terms of Payment' which prescribed following formula
under Clause-1.1:-

                  Payment of Monthly Rentals:

                  1.1 The contractor shall pay to the Undertaking the display charges
                  quoted by it in the "Form of Offer" by way of monthly installment in
                  advance on or before the first day of every month, by demand draft
                  or pay order or through RTGS/NEFT to be submitted to the Asst.
                  General Manager (Transportation Engineering).

                  The amount of monthly rentals shall be calculated as under:

                  Amount of monthly rental for the month=A
                  Total display charges quoted for 3121 [excluding new Tata buses
                  (185), Hybrid buses (25) & Electric buses (6) from current fleet of
                  3337 Buses] buses =
                  No. of months in a contract=36
                  Total fleet of the Undertaking before commencement of contract =
                  3121 Buses
                  Fleet of the Undertaking available for display of advertisement as
                  on first of the previous month =

                  A=      B     XC
                       36 x 3121


                  On failure to do so, besides other remedies open to the Undertaking
                  under this contract and at law, the contractor shall be required to
                  pay to the Undertaking interest as specified in clause no 24 of
                  General Conditions of Contract for the period from the due date of
                  payment till the date the payment is actually received (both days
                  inclusive) by the Undertaking. In case the payment is withheld
                  beyond the period of 30 days from the due date of payment, the
                  Undertaking shall be at liberty to terminate the contract without
                  any claim or compensation / refund by contractor under the
                  provisions of clause no. 26 of General Conditions of Contract.



32)               Thus, 'fleet' of the undertaking available for display of
advertisement as on the first day of previous month' was the only

_____________________________________________________________________________
                                PAGE NO. 27 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                     ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                             FC-ARB NO-282 OF 2024

determinative factor for variance in monthly display charges since
other figures of overall fleet size of 3121, tenure of 36 months of
contract and price quoted by the Petitioner remained static
throughout the contract.              The words ' fleet of the undertaking
available for display' did not mean number of buses actually plying
on the road. If in the event, BEST decided to reduce the fleet by 500
buses, the monthly display charges would automatically get reduced
under the formula. Because in such event the fleet size reduces and
those number of buses go out of purview of contract. Petitioner has
misconstrued the word 'fleet' with the word 'buses'. The eventuality
of reduction in the number of buses in a fleet on particular
day/month is taken care of under Clause-1.1.1 of Schedule-VI
wherein no claim was to be raised by the Petitioner if the buses were
not available for plying due to 'upkeep' and 'maintenance'.


33)               The Arbitral Tribunal has rightly construed the interplay
between the terms and conditions under Schedule-VI and Clause-4.1
of Schedule-III for holding that there was no provision in the tender
document or the contract for seeking de-notification of 966 buses.
The interpretation made by the learned Arbitrator in respect of
various contractual clauses upon their holistic reading is sound.
Even otherwise, interpretation of terms of contract is in exclusive
domain of the Arbitral Tribunal. Even if the interpretation suffers
from any error, it is an error within the jurisdiction of the Arbitral
Tribunal not warranting any interference in exercise of power under
Section 34 of the Arbitration Act. In the present case, however no
error is traced in the interpretation of contractual clauses by the
Arbitral Tribunal even upon a detailed scrutiny undertaken by this
Court on account of contentions raised by the Petitioner. In my view,




_____________________________________________________________________________
                                PAGE NO. 28 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                FC-ARB NO-282 OF 2024

therefore the Arbitral Tribunal has rightly rejected the claim of
4,67,42,372/- for rebate on damaged buses.




REJECTION OF CLAIM FOR REBATE OF RS.99,42,444 FOR 8 DAYS COVID
PERIOD

34)               The Arbitral Tribunal has discussed this claim by
framing Issue No.7 which reads thus :-

                  Issue no. 7: Does the Claimant prove that under the 2019 Tender,
                  Respondent is obliged to provide rebate for the 8 day period from
                  March 24, 2020 to March 31, 2020 in view of COVID 19 pandemic
                  for an amount of Rs.99,42,444/-, as alleged or otherwise?


35)               Respondent granted rebate in favour of the Petitioner on
account of Covid-19 pandemic vide two letters dated 28 June 2021
and 15 March 2022. The rebate was 100% from 1 April 2020 to 30
September 2020. It was again 100% from 1 October 2020 to 31
December 2020 as health-related advertisements were displayed by
MCGM on buses during that period. From 1 January 2021 to 28
February 2021, the rebate was 75%, and from 1 January 2021 to 31
March 2021 onwards the rebate was 50%.




36)               Despite grant of substantial rebate, the Petitioner has
raised further claim for rebate for period of 8 days from 24 March
2020 to 31 March 2020 for Rs.99,42,444/-. The Arbitral Tribunal
has rejected this claim by referring to Clause-19(a) of the contract,
under which the obligation for Petitioner to pay monthly
advertisement charges remained continuous even on occurrence of
a force majeure event. The rejection of claim is thus in accordance
with contractual stipulations, and I do not find any reason to

_____________________________________________________________________________
                                PAGE NO. 29 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                   ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                           FC-ARB NO-282 OF 2024

interfere in the findings recorded by the Arbitral Tribunal while
rejecting the claim for rebate in monthly display charges for 8 days.
Again, considering that the claim is only in respect of 8 days, the
rejection is not seriously challenged during the course of oral
submissions. It is therefore not necessary to delve deeper into this
aspect.


REJECTION OF CLAIM FOR REFUND OF EXCESS AMOUNT PAID BY PETITIONER
OF RS.14,45,33,204


37)               This was a curious claim raised by the Petitioner by
misreading of contractual stipulations by mixing the concept of
'total fleet of undertaking' with 'buses made available for plying'.
According to the Petitioner, the Respondent made available the
details of operational buses on each day to the Petitioner during the
contract period, which reflected that the actual number of
operational buses were far lesser than the fleet size considered by
Respondent while computing monthly display charges under
formula envisaged in Schedule-IX. According to Petitioner, actual
number of buses which plied on first day of a month was
substantially lesser than the number of fleet size considered for
computation formula. Petitioner therefore believed that it was
charged excess monthly advertisement charges by BEST. According
to the Petitioner, the information supplied to it vide email by
Respondent showed substantial difference in the actual buses plying
on the road as compared to the fleet size considered for
determination of monthly display charges.



38)               The above contention raised on behalf of the Petitioner
deserves rejection for the reasons which have been recorded for


_____________________________________________________________________________
                                PAGE NO. 30 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025              ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                           FC-ARB NO-282 OF 2024

discussing the claim for rebate in respect of damaged buses. The
formula under Schedule-IX prescribed the method of computation of
monthly advertisement display charges, under which the contract
price of Rs.95.5 crores quoted by the Petitioner was required to be
divided by a number '36 x 3121' and the figure so arrived was
further required to be multiplied by the 'fleet of undertaking
available for display for advertisement' as on the first day of
previous month. Here the contract did not stipulate that the figure
'C' was to represent number of buses plying on the road. The number
'C' represented the size of the fleet made available for advertisement
by the Petitioner every month. This is because though Petitioner had
quoted contract price of Rs.95.5 crore for 3121 buses, the Petitioner
had right to reduce or increase the fleet size. The contract was to run
for 3 years. In the contract period, Respondent-BEST could have
reduced the fleet size on account of various reasons such as
discarding of buses and non-replacement thereof by new buses, non-
giving of business to the Petitioner for display of advertisements, etc
Therefore, the actual number of buses made available on the road on
a particular day has no significance for computing monthly display
charges. The Arbitral Tribunal has rightly rejected the claim for
alleged excess payment by adopting the reasonings in respect of
rejection of claim for rebate on damaged buses. Petitioner's criticism
of the Award by contending that separate reasons are not recorded
for rejecting claim for excess payment is clearly misplaced. The
reasons for discussing the claim for rebate for damaged buses and
claim for refund of excess payment in bound to be similar. Therefore,
no fault can be found in the Award of Arbitral Tribunal rejecting the
claim for excess payment.




_____________________________________________________________________________
                                PAGE NO. 31 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025              ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                  FC-ARB NO-282 OF 2024

COUNTERCLAIM FOR INTEREST ON DELAYED PAYMENT CHARGES OF
RS.49,60,063

39)               This claim has been discussed by the Arbitral Tribunal
while answering Issue No.11. However, answer to Issue No.11 also
depended on answer to Issue No.10, which related to counterclaim
raised by the Respondent in respect of delayed payment charges of
Rs.4,13,69,016/-. Issue Nos.10 and 11 were as under:-


                  Issue No.10: Does Respondent prove that the Claimant is liable to
                  pay Respondent a sum of Rs.4,13,69,016/- along with further
                  interest at the rate of 18% p.a. for the delayed payment charges, as
                  set out in the Respondent's Counter Claim?

                  Issue No.11: Does the Respondent prove that the Claimant is liable
                  to pay the Respondent a sum of Rs.49,60,063/- along with further
                  interest at the rate of 18% p.a. for the interest on the delayed
                  payment charges, as set out in the Respondent's Counter Claim?



40)               While answering Issue No.10, the Tribunal noticed that
during pendency of arbitral proceedings, the outstanding amount
towards delayed payment charges were paid by the Petitioner. Para-
46 of the Affidavit of Evidence of RW1 reads thus :-

                  46. During the pendency of these proceedings, the three post dated
                  cheques of Rs. 1,00,00,000/- each have been provided by the
                  Claimant to the Respondent which have since been deposited on
                  December 9, 2022, December 24, 2022, and January 8, 2023,
                  respectively. A further cheque for INR 1,06,75,543 was also
                  provided on January 24,2023 which has also been encashed.
                  Accordingly, after giving credit for the amount of those cheques,
                  further delayed payment charges, as also a further rebate of INR
                  36 Lakh given for buses which had gone for bodybuilding, the total
                  amount due from the Claimant to the Respondent on this count is
                  nil.


41)               Thus, the claim for recovery of delayed payment charges
was recorded as satisfied. However, the amounts were paid on
different dates as indicated in para-46 of affidavit of evidence of


_____________________________________________________________________________
                                PAGE NO. 32 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                     ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                   FC-ARB NO-282 OF 2024

RW1. Therefore, the Respondent continued pressing its claim for
interest of Delayed Payment Charges (DPC).


42)               The contract did not provide for any fixed sum to be paid
towards delayed payment charges. The delayed payment charges by
itself represented interest at stipulate rates. It would be apposite to
reproduce clause-24 of Schedule III, which reads thus :-


                  24. Non-payment of charges : The GST is payable on accrual basis
                  after raising invoices/bills to the parties to avoid non compliance of
                  statutory provisions. The delayed payment charges on any sum due
                  and payable by the contractor to the Undertaking, shall be payable
                  @ 18% p.a. for the first six months, 24% p.a. for the next six months
                  and 30% p.a. for delay beyond one year irrespective of the fact
                  whether the said condition is mentioned hereinabove or not.
                  Moreover, if the contractor fails to pay interest on delayed
                  payment within three months then the additional interest @ 18%
                  p.a. will be levied on such outstanding interest.

43)               Thus, under Clause-24 of Schedule-III, delayed payment
charges in respect of any sum payable to BEST was fixed @ 18% p.a.
for first 6 months, 24% p.a. for the next 6 months and 30% p.a. for
delay beyond one year.                There is no dispute to the position that
delayed payment charges as per agreed rate of interest is actually
paid by the Petitioner to the Respondent. However, Respondent
claimed interest on delayed payment charge which virtually
tantamounts to 'interest on interest'.


44)               Clause-24 of Schedule-III of the contract provided that
'moreover if the contractor fails to pay interest on the delayed
payment within 3 months, then the additional interest @ 18% p.a.
will be levied on the outstanding interest'. Clause-24 itself makes it
clear that what is claimed by the Respondent is interest on interest.
This is because Clause-24 made the Petitioner liable to pay interest



_____________________________________________________________________________
                                PAGE NO. 33 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                      ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                            FC-ARB NO-282 OF 2024

at the rate of 18% p.a. on ' outstanding interest', if Petitioner failed to
pay 'interest' on delayed payment charges.


45)               Clause-24 of Schedule-III, so far as it relates to
stipulation for 'interest on interest' provision, appears to be a bit
confusing.          The first part of Clause-24 of Schedule-III makes the
contractor liable to pay delayed payment charges at hefty rates i.e.
@ 18% p.a. for first 6 months, 24% for next 6 months and 30%
beyond one year. The second part of Clause-24 applies when
contractor fails to pay interest on delayed payment within 3 months,
in which eventuality additional interest of 18% was leviable.


46)               Thus, under the first part of Clause-24, liability to pay
interest continues for delay in paying monthly display charges. To
illustrate, if monthly display charges of Rs.1 crore are due and
payable on 1 January 2020, the Contractor is liable to pay interest @
18% p.a. upto 30 June 2020 which increased to 24% from 1 July
2020 and thereafter 30% from 1 January 2021. However, second
part of Clause-24 makes it mandatory to pay further interest on
amount of interest which becomes leviable within a period of 3
months. This would mean that if Rs.1 crore payable on 1 January
2020 is not paid by 31 March 2020, interest of Rs.4,50,000/- for
months of January, February and March becomes due and payable.
If by 1 April 2020 also, due amount of Rs.1 crore is not paid, in
addition to liability to pay 18% interest on amount of Rs.1 crore,
additional interest on unpaid interest of Rs.4,50,000/- would become
payable under the second part of Clause-24. This dual method of
charging interest appears to be confusing and assumes character of
absurdity when due amount is not paid within the                       first three
months. There thus appears to be some ambiguity in Clause-24 of


_____________________________________________________________________________
                                PAGE NO. 34 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025               ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                               FC-ARB NO-282 OF 2024

the contract and considering the facts and circumstances of the
case, it would be appropriate to relieve Petitioner of responsibility of
paying interest on interest under Clause-24.


47)               The Learned Arbitrator has not entered into the realm of
interpretation or construction of Clause-24. Therefore, the award of
claim cannot be upheld by granting leeway to the learned Arbitrator
in the matter of interpretation of contractual clause. It is not that
Clause-24 is plain and unambiguous. There is an ambiguity in
Clause- 24, which the learned Arbitrator has failed to resolve. Not
undertaking the exercise of understanding the exact import of
Clause-24 by the learned Arbitrator would constitute a ground for
interference in the award. Awarding 18% interest on hefty delayed
payment charges of 18%, 24%, 30% is actually contrary to the first
part of Clause-24 and even otherwise in conflict with public policy of
India and in contravention with fundamental policy of Indian law. In
my view, therefore award of claim for interest on delayed payment
charges of Rs. 49,60,063/- in favour of Respondent is invalid and
liable to be set aside.


AWARD OF RESPONDENT'S COUNTERCLAIM FOR RTO FEES OF RS.46,78,000

48)               This counterclaim is discussed in Issue No.12 by the
learned Arbitrator. The learned Arbitrator took into consideration
para-3 of letter dated 23 January 2019 which reads thus :-

                  You shall pay Rs. 1,87,26,000/- through RTGS/NEFT/DD towards
                  RTO advertisement fees for three years before commencement of
                  contract or pay Rs. 62,42,000/-through RTGS/NEFT/DD towards
                  RTO advertisement fees for first year before commencement of
                  contract. For each subsequent years you shall make the payment
                  atleast three months in advance from due date, subject to the
                  revision of advertisement fees by the RTA.



_____________________________________________________________________________
                                PAGE NO. 35 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                  ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                 FC-ARB NO-282 OF 2024



49)               Petitioner accuses the learned Arbitrator of ignoring
contractual Clause-14.2.1 of Schedule-III which reads thus :-


                  14.2.1 The RTO's present advertisements fees are ₹2000/- per bus
                  per year. For this purpose, the contractor shall:

                  a. deposit 1,87,26,000/- by Demand Draft or through RTGS / NEFT,
                  towards RTO advertisement fee for 3 years for 3121 buses or at
                  actual for entire fleet, before commencement of contract. OR

                  b. deposit 62,42,000/- or at actual by Demand Draft or through
                  RTGS / NEFT, towards RTO advertisement fee for 1st year before
                  commencement of contract and deposit RTO advertising fee of
                  62,42,000/-, or at actual for every subsequent years by way of DD,
                  NEFT/RTGS payment for each year atleast 3 months in advance
                  from due date of payment. The deposit towards RTO fees shall carry
                  no interest.

                  c. The contractor shall not be allowed to display advertisement on
                  buses unless and until deposit towards RTO fees is paid as
                  mentioned above.



50)               The difference between para-3 of letter dated 23 January
2019 and Clause-14.2.1 of Schedule-III of general conditions of
contract is that the words 'or at actual for every subsequent years '
are missing in para-3 of letter dated 23 January 2019. In my view,
even if it is accepted that the Arbitral Tribunal has not taken into
consideration the above quoted words 'or at actual for every
subsequent years' appearing in Clause-14.2.1, the same would not
have any effect on the outcome of the award. So far as counterclaim
for recovery of RTO charges is concerned, the expression ' or at
actual for every subsequent years ' would mean the applicable RTO
charges for subsequent years.               The Petitioner had an option of
depositing the entire RTO charges of Rs.1,87,26,000/- for 3 years
upfront computed at the rate of Rs.2000 /- per bus per year. If
Petitioner either did not have such amount or did not desire to
deposit the entire amount of Rs.1,87,26,000/- upfront, it could

_____________________________________________________________________________
                                PAGE NO. 36 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                    ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                           FC-ARB NO-282 OF 2024

exercise the option of depositing amount of Rs.62,42,000/- for first
year and take the risk of paying the actual charges as determined by
RTO for subsequent years. The words 'at actual' would mean the
rates determined by RTO during subsequent years. If RTO was to
revise the charges and increase it beyond Rs.2000/- per bus per
year, the contractor would take the risk of paying the same to RTO.
This is the true purport of Clause-14.2.1 of the contract. The words
'or at actual' did not mean payment of RTO charges depending on
number of buses. RTO was not supposed to verify as to how many
buses were made operational each year for the purpose of
determination of charges. Petitioner undertook to pay RTO charges
of Rs.2,000/- per bus per year in respect of the entire fleet of 3121
buses under the contract. It cannot now turn around and contend
that the RTO charges in respect of actual number of buses plying
alone would be payable. It cannot contend that since buses did not
ply during COVID pandemic, no RTO fees were payable.


51)               Similarly, Petitioner cannot demand proof of payment of
RTO charges by Respondent to RTO. The learned Arbitrator has
rightly considered the indemnity offered by the Petitioner for
holding that obligation to indemnify the Respondent in respect of
RTO fees comes into play immediately upon fructification of
obligation to pay RTO fess by the Petitioner by enforcing contract of
indemnity. It is not necessary to prove that the sum in respect of
which indemnity is offered is actually paid or not. For holding so,
the Arbitral Tribunal has relied upon judgments in the case of
Gajanan Moreshwar Parelkar Versus Moreshwar Mandan Manti 3 ,
Khetarpal Amarnath Versus. Madhukar Pictures 4, Jet Airways


3      ILR 1942 Bom 672
4      AIR 1956 Bom 106

_____________________________________________________________________________
                                PAGE NO. 37 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025              ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                   FC-ARB NO-282 OF 2024

(India) Limited Versus. Sahara Airlines Limited and Others 5and
Reliance Industries Limited Versus. Balasore Alloys Limited 6.


52)               Having expressly agreed to pay the RTO fees either at
Rs.62,42,000/- per year or as per actual rates charged by RTO,
Petitioner cannot now turn around and seek an escape from
contractual obligation by citing pretext of COVID pandemic or non-
production of proof of actual payment of fees by Respondent to RTO.
I therefore do not find any reason to interfere in the award of
counterclaim in respect of RTO fees in favour of the Respondent.


AWARD OF CLAIM FOR DEFACEMENT CHARGES OF RS.37,29,000

53)               Under        Clause-21   of   Schedule-III     of    the     contract,
Petitioner had agreed for withdrawal of all the advertisements from
buses upon expiry of the contract. Clause-21 of the contract reads
thus :-

                  21. Withdrawing of advertisements from buses on expiry of the
                  Contract:

                  The contractor shall deface / remove all the advertisements
                  displayed on the buses prior to the expiry or premature
                  termination of the contract. On default of the contractor, the said
                  advertisements shall be removed / defaced by the Undertaking and
                  the cost of such departmental work shall be borne by the contractor
                  in the manner as mor specifically explained in Clause No. 5 of
                  General Conditions of Contract. In addition, the contractor shall be
                  liable for a penalty of 1000/- per day, per bus till the day the
                  advertisements is actually defaced / removed.

54)               Thus, under Clause-21, Petitioner was under obligation
for defacement/removal of advertisements displayed on the buses
prior to expiry or on premature termination of the contract. If
Respondent was to remove the advertisements, the same were to be

5      2011 SCC Online Bom 576
6      2014 14 SCC Online Bom 43

_____________________________________________________________________________
                                PAGE NO. 38 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                     ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                             FC-ARB NO-282 OF 2024

defaced/removed at the costs of the Petitioner. In addition to bearing
the costs of removal of advertisements, the Petitioner was made
liable for penalty of Rs.1,000/- per day per bus till the
advertisements were actually defaced/removed.


55)               There is no dispute to the factual position that the
advertisements on the buses were actually not removed by the
Petitioner. This was not done possibly because the Petitioner had
participated in the fresh tender. There is also no dispute to the
position that the Petitioner emerged as successful bidder even in the
fresh tender and has been awarded the very same contract once
again vide work order dated 12 May 2022. There appears to be a gap
of about 3 months between the two contracts. In anticipation of
award of new contract, possibly, Petitioner did not remove all the
advertisements from the buses. Respondent applied penalty clause
of Rs.1,000/- per day per bus and raised counterclaim of
Rs.37,29,000/-. The particulars of counterclaim filed by the
Respondent in support of its claim for defacement charges are
absolutely vague. Respondent filed following particulars in support
of its claim for defacement charges :-

     PARTICULARS OF CLAIM FOR DEFACEMENT CHARGES
SR. NO.      Particulars of Claim          Amount (Rs.)

1.             Penalty payable for Defacement Charges 37,29,000
               as on November 25, 2022

The Claimant is liable to pay Rs. 37,29,000 (Rupees Thirty Seven Lakhs Twenty
Nine Thousand only) along with further interest at 18% from November 25, 2022
till payment and / or realization.




56)               Thus, no particulars were given as to how the figure of
Rs.37,29,000/- was worked out.

_____________________________________________________________________________
                                PAGE NO. 39 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                    FC-ARB NO-282 OF 2024



57)               The learned Arbitrator has awarded entire claim of
Rs.37,29,000/- towards defacement charges. Petitioner argued
before the learned Arbitrator that penalty for defacement stipulated
in the contract could not be awarded without first proving legal
injury in the form of loss suffered by the Respondent. Reliance was
placed by the Petitioner on judgment of the Apex Court in Kailash
Nath Associate (supra).


58)               In Kailash Nath Associate the Apex Court has held that
in para-43.1 as under :-

                  43.1. Where a sum is named in a contract as a liquidated amount
                  payable by way of damages, the party complaining of a breach can
                  receive as reasonable compensation such liquidated amount only if
                  it is a genuine pre-estimate of damages fixed by both parties and
                  found to be such by the court. In other cases, where a sum is named
                  in a contract as a liquidated amount payable by way of damages,
                  only reasonable compensation can be awarded not exceeding the
                  amount so stated. Similarly, in cases where the amount fixed is in
                  the nature of penalty, only reasonable compensation can be
                  awarded not exceeding the penalty so stated. In both cases, the
                  liquidated amount or penalty is the upper limit beyond which the
                  court cannot grant reasonable compensation.


59)               In Anila Gautam, (supra) the Division Bench of this court
has held in paras-25 to 27 as under :-


                  25. The learned Arbitrator acted contrary to the basic requirement
                  of law when more particularly when one of the claims being of a
                  penalty for breach of the contract which was surely required to be
                  proved as per the requirement of Section 73 of the Contract Act.
                  Admittedly, on this claim of penalty the respondent did not lead
                  any evidence. On the other hand, the appellant not only disputed
                  the documents on the basis of which the respondent had made the
                  claim for penalty but also had filed her affidavit of evidence and was
                  ready and willing to be cross-examined. In this situation, it would
                  have been prudent as also a requirement of law for the learned
                  Arbitrator to consider whether the respondent either on oral
                  and/or     documentary      evidence,     proved      its  claim    for
                  penalty/damages as also the other claims. Further when there was
                  a dispute on reconcilliation of accounts, then, the learned arbitrator

_____________________________________________________________________________
                                PAGE NO. 40 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                       ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                    FC-ARB NO-282 OF 2024

                  himself ought to have gone into the issue of reconcilliation and on
                  the basis of evidence, the monetary liability could have been
                  fastened on the appropriate party to the dispute.

                  26. This is a case where the respondent asserted breach of contract
                  (dealership agreement) on the part of the appellant and as a
                  consequence of a breach of contract, the respondent made a
                  counter-claim inter-alia seeking penalty and other claims which
                  pertain to variation of stock, debit balance of the account between
                  the parties. Once a claim for penalty is made, then necessarily the
                  provisions of Chapter VI of the Contract Act which deal with
                  consequence of breach of contract and the provisions of Sections 73
                  and 74 of the Contract Act which deal with award of compensation
                  when a party suffers on account of breach of contract and
                  compensation for breach of contract when penalty is stipulated in
                  the agreement itself respectively, are attracted. It cannot be
                  disputed that a liability to pay damages must arise under the
                  contract and not otherwise. The Arbitrator has power to decide the
                  question of liability for a particular amount as damages. In the
                  assumption of damages, the arbitrator was required to consider the
                  legal obligations the law would confer on the parties to prove such
                  claims. Once there was no evidence on record, oral or documentary,
                  which could prove the damages suffered by the respondent, then,
                  certainly it can be said that there was a patent illegality on the face
                  of the award. All these requirements have been completely
                  overlooked by the learned Arbitrator.

                  27. In our opinion, the learned arbitrator has gravely faltered in
                  overlooking the fundamental provisions under Section 73 of the
                  Contract Act, namely unless the party proves the damages suffered
                  by it on account of breach of contract, it is not entitled to any
                  damages on compensation. If the counter claims of the respondent
                  are to be seen in the context of clauses 5, 6, 10, 11, 12, 24(a),
                  28B(a) and B(k), B(g), B(h), these are claims which can be only
                  proved on evidence and in event any claim for damages/penalty on
                  these breaches has to be on the proof of damages suffered in the
                  absence of any liquidated damages agreed between the parties.
                  Even if the parties were to agree on a quantum of liquidated
                  damages, the party claiming such damages was required to prove
                  the actual damage suffered by it. (See "Kailash Nath Associates v.
                  DDA" 1).


60)               Thus, under the contract, where an amount is fixed in
the nature of penalty, only reasonable compensation can be awarded
not exceeding the penalty so stipulated. However, though the
submission is noted, the learned Arbitrator has not decided the
same. Petitioner had specifically contended before the learned
Arbitrator that Rs.1,000/- per day per bus stipulated in Clause-21 of


_____________________________________________________________________________
                                PAGE NO. 41 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                       ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                     FC-ARB NO-282 OF 2024

Schedule-III of the contract was not agreed genuine pre-estimate of
damages. In Kailash Nath Associates, the Apex Court has held that
a sum named in the contract as liquidated damages can be claimed
as a reasonable compensation only if it is genuine pre-estimate of
damages fixed by both the parties and found to be such by the Court.
Clause-21 of Schedule-III of the contract does not stipulate that
Rs.1,000/- per day per bus is a genuine pre-estimate of damages
agreed by both the parties. The learned Arbitrator has completely
glossed over this vital aspect and has erroneously awarded the
counterclaim for defacement charges by recording following findings
in para-22.3 and 22.4 :-


                  22.3 In the written arguments it is mentioned by the Claimant that
                  the Respondent cannot be permitted to make a case for the
                  imposition of defacement charges in the form of liquidated damage,
                  without first proving the legal injury in the form of loss suffered by
                  it. In support of these submissions Claimant placed reliance on the
                  following Judgments:

                           1) (2015) 4 SCC 136.
                           Kailash Nath Associates v Delhi Development Authority

                           2) 2023 SCC OnLine Del 6097.
                           Sudershan Kumar Bhayana (Deceased) v Vinod Seth
                           (Deceased),

                           Applying the the principles of the above authorities to the
                           present matter following submissions were made by the
                           aimant in its written arguments.

                           7.22. The Respondent has not placed anything on record to
                           demonstrate that there was a delay in defacing the buses.

                           7/23. The Respondent has neither pleaded nor proved that
                           the Respondent has suffered any damages or incurred any
                           loss on account of delay in defacing the buses. In this regard,
                           it is submitted that the Claimant was also awarded the
                           subsequent tender to display advertisements on the
                           Respondent's buses, and as such, no loss could have been
                           caused to the Respondent.

                           7.24. In the Tender, it does not state that the liquidated
                           damages of Rs 1000/- per bus per day as stipulated in Clause
                           21 of the Tender is a genuine pre-estimate of damages likely


_____________________________________________________________________________
                                PAGE NO. 42 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                        ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                                     FC-ARB NO-282 OF 2024

                           to be suffered by the Respondent in case of delay in
                           defacement of the buses upon expiry of the Contract. The
                           Respondent has neither pleaded nor proved that it is difficult
                           or impossible of to prove the loss.

                           7.25. Therefore, it is submitted that the Respondent is not
                           entitled to the defacement charges in the form of liquidated
                           damages.

                  22.4 The submissions on behalf of the Claimant are required to be
                  analyzed in juxtaposition of pleadings of the parties and specifically
                  pleadings of the Claimant on this Issue and overall effect of the
                  substantive evidence of RW-1 including his cross examination.
                  More over the factual position cannot be lost sight of as to terms
                  and conditions of Tender document, Contract document and other
                  correspondence between the parties. Further it must be understood
                  that imposing of 'penalty' which is quantified and agreed as per the
                  terms of the Tender document is factually a part of the contractual
                  arrangement between the parties. In the result the submissions
                  advance by learned counsel on this aspect shall not sustain.
                  Accordingly, it is held that Respondent has proved this Issue No.13
                  and the same is accordingly answered in the affirmative.


61)               Admittedly, no evidence is led by the Respondent to
prove cause of any loss to it on account of non-removal of
advertisements. Since the sum named in Clause-21 of the contract
was not agreed as genuine pre-estimate of damages by the parties, it
was incumbent on Respondent to prove the cause of loss. In my
view, therefore award of counterclaim for defacement charges by
the Arbitral Tribunal is contrary to contractual Clause-21 and
provisions of Section 74 of the Contract Act,1872 (Contract Act).


62)               Even otherwise, the Respondent has not actually faced
any loss on account of non-removal of advertisements by the
Petitioner since the Petitioner was awarded the contract for next
tenure. Therefore, merely because some advertisements remained
on the buses after expiry of earlier contract, it cannot be presumed
that any loss was caused to the Petitioner. There is nothing on
record to indicate that Respondent got the advertisements removed
by incurring of any expenditure. Therefore, in the peculiar facts and

_____________________________________________________________________________
                                PAGE NO. 43 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                        ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                               FC-ARB NO-282 OF 2024

circumstances of the case, claim of defacement charges by the
Respondent from the Petitioner would actually constitute unjust
enrichment.


63)               In my view, therefore the award of defacement charges
of Rs.37,29,000/- by the Arbitral Tribunal cannot be sustained and
the same is liable to be set aside.


AWARD OF COSTS


64)               The        Arbitral   Tribunal   has   awarded           costs       of
Rs.48,20,000/- in favour of the Respondent under Section 31A of the
Arbitration Act. Thus, the Arbitral Tribunal has applied the
yardstick of Respondent being the successful party and has
accordingly awarded entire costs claimed by the Respondent.
However, two of the counterclaims awarded in favour of the
Respondent are found to be invalid. In my view therefore,
Respondent is not completely successful in the arbitration
proceedings. In that view of the matter, it would be appropriate to
restrict the amount of costs at Rs.25,00,000/-, which can be
awarded in favour of the Respondent.


POST AWARD INTEREST @ 10% P.A.


65)               The Arbitral Tribunal has awarded interest @ 10% p.a. on
the sums awarded in favour of the Respondent from the date of the
award.         This Court has already set aside the award relating to
interest on delayed payment charges and defacement charges. This
would mean that award in respect of RTO fees of Rs.46,78,000/-
alone is confirmed. Therefore Petitioner would be liable to pay 10%


_____________________________________________________________________________
                                PAGE NO. 44 of 46
                               04 DECEMBER 2025


       ::: Uploaded on - 04/12/2025                  ::: Downloaded on - 06/12/2025 00:14:44 :::
 Neeta Sawant                                               FC-ARB NO-282 OF 2024

interest from the date of the award only on counterclaim relating to
RTO fees. I find no reason to interfere in the said direction.


SEVERANCE OF BAD PART FROM GOOD PART


66)               The Constitution Bench in Gayatri Balasamy Versus ISG
Novasoft Technologies Ltd.7 has ruled that the court exercising
power under Section 34 of the Arbitration Act can modify the award
by severing the good part of the award from the bad part. In the
present case, award of only two claims relating to interest on delay
payment charges and defacement charges is being set aside. Rest of
the award is being confirmed. Bad part of the Award relating to
interest on delayed payment charges and defacement charges is not
inseparably intertwined with the good part of the award. Therefore,
bad part of the Award can be separated from good part by modifying
the Award.




ORDER :

67) I accordingly proceed to pass the following order :

The Award dated 2 January 2024 passed by the Arbitral Tribunal is modified to the following extent :
(i) The Award of counterclaim in favour of the Respondent towards interest on delayed payment charges of Rs.49,60,063/- with interest @ 18% p.a. is set aside.

7 (2025) 7 SCC 1 _____________________________________________________________________________ PAGE NO. 45 of 46 04 DECEMBER 2025 ::: Uploaded on - 04/12/2025 ::: Downloaded on - 06/12/2025 00:14:44 ::: Neeta Sawant FC-ARB NO-282 OF 2024

(ii) Award of counterclaim in favour of the Respondent towards defacement charges in the sum of Rs.37,29,000/- alongwith interest @ 18% p.a. is set aside.

(iii) Amount of costs awarded by the Arbitral Tribunal are reduced to Rs.25,00,000/- which shall be payable by the Petitioner to the Respondent along with interest @ 10% from the date of the Award.

(iv) Rest of the Award is confirmed.

68) Arbitration Petition is partly allowed to the above extent. Considering the facts and circumstances of the present case, I consider it appropriate not to award any further costs in the present Arbitration Petition.

69) With disposal of the Petition, nothing would survive in the Interim Application taken out for stay of the impugned order. The same also stands disposed of.




           Digitally
           signed by
           NEETA                                          [SANDEEP V. MARNE, J.]
NEETA      SHAILESH
SHAILESH   SAWANT
SAWANT     Date:
           2025.12.04
           18:30:14
           +0530




_____________________________________________________________________________ PAGE NO. 46 of 46 04 DECEMBER 2025 ::: Uploaded on - 04/12/2025 ::: Downloaded on - 06/12/2025 00:14:44 :::