Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 3, Cited by 0]

Karnataka High Court

Sri C G Nanjaraj S/O Late R S ... vs The Board Of Directors on 26 July, 2024

                            -1-



     IN THE HIGH COURT OF KARNATAKA AT BENGALURU

         DATED THIS THE 26TH DAY OF JULY, 2024

                          BEFORE

THE HON'BLE MR JUSTICE SACHIN SHANKAR MAGADUM

        WRIT PETITION NO. 22002 OF 2012 (S-RES)
                         C/W
        WRIT PETITION NO. 22003 OF 2012 (S-RES)

IN WRIT PETITION No. 22002/2012

BETWEEN:

SRI. C.G. NANJARAJ
S/O LATE R.S. GANGADHARAPPA
AGED ABOUT 59 YEARS
DEPUTY DIRECTOR
KARNATAKA RURAL INFRASTRUCTURE
DEVELOPMENT LTD
HEAD OFFICE, BANGALORE
R/A NO.711, SHIVA KRUPA
15TH A MAIN, MIG 'A', SECTOR
III PHASE, NEAR SHESHADRIPURAM COLLEGE
YELAHANKA NEW TOWN
BANGALORE-560 106.
                                             ...PETITIONER

(BY SRI. VIJAY KUMAR, ADVOCATE )

AND:

1.    THE BOARD OF DIRECTORS
      KARNATAKA RURAL INFRASTRUCTURE
      DEVELOPMENT LTD.
      REPRESENTED BY ITS MANAGING DIRECTOR
      CHINNASWAMY STADIUM
      GATE NO.18, RAJ BHAVAN ROAD
      BANGALORE-560 001.

2.    THE MANAGING DIRECTOR
      KARNATAKA RURAL INFRASTRUCTURE
      DEVELOPMENT LTD.
      CHINNASWAMY STADIUM
                            -2-



     GATE NO.18, RAJ BHAVAN ROAD
     BANGALORE-560 001.
                                            ....RESPONDENTS

(BY SRI. K. RAMACHANDRAN, ADVOCATE FOR R1 AND R2 )

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227
OF    THE   CONSTITUTION       OF   INDIA    PRAYING     TO
CALL FOR RECORDS RELATING TO THE ISSUE OF THE IMPUGNED
OFFICIAL MEMORANDUM DATED 13.9.11 VIDE ANNX-R ISSUED BY
R2 AND THE IMPUGNED ENDORSEMENT DATED 04/07.5.12 VIDE
ANNX-V ISSUED BY R2 AND AFTER PERUSAL SET ASIDE THE SAME
AND ETC.

IN WRIT PETITION No. 22003/2012

BETWEEN:

SRI. B.R. NAGARAJ
S/O. LATE B.N. RAMACHANDRAIAH
AGED ABOUT 54 YEARS
ASSISTANT DIRECTOR
KARNATAKA RURAL INFRASTRUCTURE
DEVELOPMENT LTD
HEAD OFFICE, BANGALORE
R/A NO.12, 6TH A CROSS,
MARENAHALLI EXTENSION, SUBBANNA GARDEN
VIJAYANAGAR, BANGALORE-560 040.
                                              ...PETITIONER

(BY SRI. RAGHAVENDRA G. GAYATRI)

AND:

1.   THE BOARD OF DIRECTORS
     KARNATAKA RURAL INFRASTRUCTURE
     DEVELOPMENT LTD.
     REPRESENTED BY ITS MANAGING DIRECTOR
     CHINNASWAMY STADIUM
     GATE NO.14
     RAJ BHAVAN ROAD
     BANGALORE-560 001.

2.   THE MANAGING DIRECTOR
     KARNATAKA RURAL INFRASTRUCTURE
     DEVELOPMENT LTD.
     CHINNASWAMY STADIUM
                                    -3-



    GATE NO.18, RAJ BHAVAN ROAD
    BANGALORE-560 001.
                                                       ....RESPONDENTS

(BY SRI. K. RAMACHANDRAN, ADVOCATE FOR R1 AND R2)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227
OF    THE    CONSTITUTION      OF   INDIA    PRAYING     TO
CALL FOR RECORDS RELATING TO THE ISSUE OF THE IMPUGNED
OFFICIAL MEMORANDUM DATED 13.09.2011 VIDE ANNX-R ISSUED
BY R2 AND THE IMPUGNED ENDORSEMENT DATED 04/07.05.2012
VIDE ANNX-V ISSUED BY R2 AND AFTER PERUSAL SET ASIDE THE
SAME AND ETC.

     THESE WRIT PETITIONS HAVING BEEN HEARD AND RESERVED
FOR ORDERS ON 25.07.2024, THIS DAY ORDER WAS PRONOUNCED
THEREIN, AS UNDER

  CORAM:         HON'BLE MR JUSTICE SACHIN SHANKAR MAGADUM

                            C.A.V ORDER

     These two petitions are filed by Deputy Director and

Assistant    Director     of     Karnataka     Rural   Infrastructure

Development Limited (for short "KRIDL") assailing the

order passed by respondent No.2 in a proceeding to

recover loss stated to have been caused to the tune of

Rs.92,69,149/-. Both the petitioners have questioned the

correctness and validity of official Memorandum dated

13.9.2011 issued by respondent No.2, imposing multiple

penalty     of    withholding      of    annual   increments    with

cumulative       effect   till   petitioners   retirement,   thereby

denying promotion to them and consequent recovery of a
                                -4-



sum of Rs.34,97,418.50 each to be recovered from the

assets (both movable and immovable).               This order is

confirmed by the appellate authority/respondent No.1 vide

order dated 12.04.2012 held in the 169th Board Meeting

under subject No.169/25.


       2.     The facts leading to the case are as under:

       The KRIDL is an executive agency under Rural

Development and Panchayath Department. The works of

the Statement Government and its agencies relating to

construction/civil    works   of   the   department   and   said

agencies are entrusted to KRIDL. While in turn the KRIDL

gets    the     project   executed       through    independent

contractors.


       3.     Respondent No.2 for the first time took up

execution of tender works outside the State in respect of

Madana Distributory of Narmada Valley Development

Authority(for short "NVDA") in Panagar, Jabalpur District,

Madhya Pradesh. Respondent No.2 was awarded the work

of construction of balance work of Madana Distributory and

its complete distribution system including excavation and
                                   -5-



earth         works,   cement   concrete   lining    and   structure

completion.            Respondent No.2 in turn entered into an

agreement with a private contractor and authorized the

private contractor to be an associate contractor for

execution of said project.


         4.      The Narmada Authority rescinded the contract

on 23.7.2007 on the ground that there is delay in

implementing the project.         The respondents countered the

termination notice by issuing a reply notice.               On the

contrary, contended that NVDA have breached the terms

and conditions of the agreement.                The respondents

contended that on account of non-acquisition of land by

NVDA the works at Madana Main Cannel and at some

various locations could not commence.               The respondents

also contended that there is delay in furnishing the

working drawings and there is delayed payment of interim

bills.        The respondents also contended that there was

change in quarry size and designs and there was also

delay due to non-shifting of electric power lines.              The

respondents also contended that on account of breach by
                                -6-



NVDA there was increase in quantity of works. The

respondents initiated arbitral proceedings against the

NVDA.


       5.   In   the   midst      of    the   dispute     between

respondents      and   M.P.       Government        and   pending

consideration     of   arbitral      proceedings,    respondents

appointed an Disciplinary authority against the petitioners

and charge sheet was issued.              Both the petitioners

submitted their reply to the show cause notice. One Sri.

S.V.    Anantharamaiah,       retired    Chief   Engineer     was

appointed as Inquiring Authority on 22.1.2008. Both the

petitioners contested by submitting their reply to the

Disciplinary authority.    The Disciplinary authority though

dropped the charges 1 to 5 and 7, however proceeded to

hold that charge No.6 is proved and petitioners are found

to be guilty.    Charge No. 6 related to 'advances' paid to

the associate contractors.


       6.   Respondent No.2 issued a second show-cause

notice along with inquiry report on 15.4.2009.            Both the

petitioners again tendered detailed explanation to the
                                 -7-



second show-cause notice and respondent No.2 proceeded

to impose multiple penalties which was challenged by both

the petitioners before Respondent No.1. Respondent No.1

has confirmed the orders passed by Respondent No.2.


      7.    Learned counsel appearing for the petitioners

reiterating the grounds urged in the petitions have

vehemently       argued   and   contended    that   the   penalty

inflicted   by   respondent     No.2/Disciplinary   authority   is

contrary to records. The counsel have further contended

that though the petitioners have brought to the notice of

the Disciplinary authority and have substantiated that the

findings of the Inquiry Authority are perverse, respondent

No.2 ignoring these significant details has proceeded to

impose penalty.      Both the counsel have pointed out that

though the inquiry Officer has come to the conclusion that

the Corporation has suffered a loss of Rs.64,94,897/-, the

official witnesses examined on behalf of the Corporation

have disputed the alleged loss during the course of

enquiry and therefore, the counsel would contend that the

penalty inflicted is in absence of no evidence.
                                 -8-



      8.   Both the counsel arguing in the same vein have

further brought to the notice of this Court that Disciplinary

authority erred in placing reliance on the audit check while

coming to the conclusion that both the petitioners have

paid advances to the Assistant Contractors without any

proper security.    The petitioners' counsel has brought to

the notice of this Court that this is disputed by the

auditors. They would further submit that the finding of the

Inquiring authority that Project Manager has no authority

to rescind the contract is erroneous as respondent No.2

has   executed     power   of    attorney   permitting   Project

Executive to release advance. They would further submit

that during the course of enquiry, it has come on record

that these advances were released with the consent of

respondent No.2.      Both the counsel would further point

out that the advances were made within the parameters of

bills approved NADA and all the requisitions which were

sent to the Head Office were duly approved and therefore,

he would contend that the recovery initiated on the ground

that the Corporation has incurred revenue loss is perverse

and contrary to the evidence in that regard.
                             -9-




     9.    Both the counsel have also placed reliance on

the pending arbitration proceedings. They would point out

that pending consideration of arbitral proceedings between

respondent No.2 and NVDA, the loss quantified while

answering Charge No.6 against the petitioners is without

any basis and this aspect is not considered by the

Disciplinary Authority and the Appellate Authority.


     10.   On these set of grounds, both the counsel

contended that the Department enquiry initiated against

the petitioners is premature when respondent No.1 has

invoked arbitral clause and arbitration proceedings are

pending. Both the counsel have brought to the notice that

arbitral award is passed and writ petition is pending.


     11.   To buttress their arguments, they have placed

reliance on the following judgments:

1.   Union of India .vs. H.C. Goel [AIR 1964 SC 364]
2.  Kuldeep Singh        .vs.   Commissioner     of      Police
[(1999) 2 SCC 10

3.  Roop Singh Negi .vs. Punjab National Bank and
others [(2009) 2 SCC 570]
                          - 10 -



4.  State of U.P. .vs. Saroj Kumar Sinha [(2010) 2
SCC 772]

5.  Commissioner    of   Police   .vs.   Jai   Bhagwan
[(2011) 6 SCC 376

6.  Allahabad Bank and others .vs. Krishna Narayan
Tewari [(2017) 2 SCC 308]

7.  Union of India and another .vs.             Col.A.D.
Nargolkar and others [(2019) 13 SCC 723]

8.  United    Bank   of   India   .vs.         Biwanath
Bhatacharjee [(2022 SCC Online 108]

9.  Man Singh .vs. State of Haryana and others
[(2009) 12 SCC 331]

10. LIC .vs. Triveni Sharan Mishra [(2014) 10 SCC
346]

11. Pawan Kumar Agarwala .vs. General Manager-
II and Appointing Authority, State Bank of India and
others [(2015) 15 SCC 184]

12. University of Delhi .vs. Union of India [(2020)
12 SCC 745]

13. Bhagwati Prasad Dubey .vs. Food Corporation
of India [1987 Supp SCC 579]

14. State of M.P. .vs. Sheetla Sahai [(2009) 8 SCC
617]

15. Bongaigaon Refinery & Petrochemicals Ltd. .vs.
Girish Chandra Sarma [(2007) 7 SCC 206]

16. Union of India .vs. Gyan Chand Chattar [(2009)
12 SCC 78]
                              - 11 -



17. Allahabad Bank .vs. Krishna Narayan Tewari
[(2017) 2 SCC 308

18. Narinder Mohan Arya .vs. United India
Insurance Company Limited [(2006) 4 SCC 713]

19. Abhay Jain .vs. High Court of Rajasthan [(2022)
13 SCC 1]


     12.   Per   contra,   learned    counsel   appearing   for

respondents would vehemently argue and contend that

except the advance amount released as evidenced at

Annexure-F which were approved by the M.D., the amount

released by the petitioners which is to the tune of

Rs.4 Crores is in absence of M.D's approval, petitioners are

liable to remit the loss of revenue caused to the

Corporation. He would further contend that advance

amount which was the subject matter of Departmental

Enquiry is not the subject matter or arbitral proceedings.

They would contend that Arbitration proceedings were

confined to recovery of Rs.5,46,22,497/- from NVDA and

therefore, contend that the advance amount released by

the petitioners was not the subject matter of arbitral

proceedings.      Learned counsel for respondent would

therefore contend that petitioners were guilty of releasing
                                 - 12 -



Rs.69 lakhs unilaterally without seeking approval of the

M.D. and without securing security of the contract and

hence, they are principally liable to remit the revenue loss

caused to the Corporation.


     13.     Heard the learned counsel for the petitioners

and the learned counsel for respondents. This Court has

thoroughly reviewed the records in both the petitions and

has given anxious considerations to the citations relied on

by the learned counsel for the parties.


     14.     Before this Court delves upon the order of

penalty    imposed     by   the    Disciplinary   Authority,        the

conditions incorporated in the agreement of Association

entered    into   between     respondent     No.1     and   Private

Contractor at Jabalpur would be relevant.


    "7. M. Channaiah will be responsible for preparation of bills
        of the work done regularly on a monthly basis. KLAC
        will not be liable for any delay. M. Channaiah will also
        liaison and act accordingly for release of all bills
        including final bill. However, the measurements will be
        restricted to those maintained and released by the
        Executive Engineer, Narmada Development Division
        No. 2, Panagar, District Jabalpur.
    8.    Security Deposit of 5% deducted as Security Deposit by
          the Executive Engineer, Narmada Development Division
          No. 2, Panagar, District Jabalpur will be retained by
          KLAC as Security Deposit until the completion of the
                                - 13 -



         work. The Security Deposit will be released on
         successful completion of work and handing over the
         site to the Executive Engineer, Narmada Development
         Division No. 2, Panagar, District Jabalpur.

    12. The Project Manager, KLAC may at his discretion
        provide advances to M. Channaiah if required which
        shall be deducted from the subsequent running bills."



     15.    The cause to initiate departmental enquiry

against the petitioners is on account of termination notice

issued by the NVDA. The NVDA alleging that progress

achieved by the respondents in a period of 32 ½ months

being not found satisfactory and thereby alleging that for

almost four months there is absolutely no progress and

the project is at standstill, has by invoking clause 4.3.3. of

the agreement, the part of the project which was left

unexecuted was withdrawn, consequently terminating the

contract.   The portion which is relevant is extracted as

under:

            "From the above details it is clear that you have
     deliberately neglected and failed to proceed with work
     with due diligence. Either you are not willing to complete
     the work or you are not capable of doing the same. As
     such you have rendered yourself liable for action under
     clause 4.3.3 of the agreement.
            Therefore clause 4.3.3 of the agreement is invoked
     and part of the work that is left unexecuted under this
     agreement is withdrawn and taken out of your hand.

           As per clause 4.3.31 of the agreement the amount
     of Rs.5,00,000/- as earnest money, Rs. 95,00,000/- as
                                - 14 -



     performance security and Rs. 4296991/- as security
     deposit deducted from running bills shall stand forfeited
     and as per clause 3.26 of the agreement additional
     security deposit on account of unbalanced rate amounting
     Rs. 5832176/- shall also, stand forfeited with immediate
     effect.
             In addition to above, as per clause 4.3.2 of the
     agreement, the amount payable for the work done but
     not paid shall also be forfeited which will be assessed
     after preparation of final bill.

            The work executed by you will be measured up
     from 27-07-2007 onward in presence of you or your
     authorized representative who may remain present at site
     during final measurements, failing which measurement
     will be taken by department and the same shall be final
     and binding on you, as per provisions in agreement."



     16.   The reply by Karnataka Land Army Corporation

Limited has a direct bearing on the departmental enquiry

initiated by respondents.     In reply, the respondents while

contesting the termination of contract by issuing a legal

notice have contended that the main reasons for delay

was account on of breach of conditions by NVDA. The

relevant portion is extracted as under:

            "Due to this non acquisition of land by NVDA in the
     following reaches the work could not be commenced at
     those places and this difficulty still exists.
     a. Madana Main Canal from 22800 RD to 25000
     b. Minor No.2, from RD 8000 to 11200 RD
     c. Sub minor M2, R2 800 to 5400 RD
     d Sub minor M2, R2 3600 to 5800 RD
     e. Sub minor M2, R3 3600 to 6000 RD

     b) Delay in furnishing working drawings:

           The Employer has expressly contracted to supply
     the drawings and instructions on demand by the contract
                           - 15 -



without which the work cannot be progressed and
prevents the performance if the drawings and instructions
are not furnished within a reasonable time.

       The District Road bridges work contemplated in the
contract was revised to Siphon type. The drawing of these
structures is still not furnished though even after lapse of
nearly 3 years.

The longitudinal levels are still not furnished all the
places.
The locations of the quarry for materials are still not
furnished.

c) Payment of Interim bills:

       This construction contract provides payment of
installments every month vide Clause No. the contract
Non payment of these interim bills for certain works
amounts to breach of contract. Upon such default the
contractor can stop the work and may abandon the
contract and seek compensation on the basis of fair and
reasonable value of the work done. A contract involving a
large expenditure stipulation for payment on account to
be made from time to time must be deemed so material
that the substantial failure to pay would justify the
contractor to decline to proceed. It is evidently was in
contemplation of the parties that the contractor could not
be expected to finance the operation to completion
without receiving the payment on account of the work
executed. Nearly about Rs.2.80 Crores of payments is still
due for the work completed. In such cases a substantial
compliance as to advance payment is a condition
precedent to the contractor's obligation to proceed with
the work.
       The Supreme Court has held that the withholding of
substantial amount over a long period without any
reasonable cause amounts to breach of contract.

d) Change in the quarry site:

      The contract clause refers to allotment of quarry for
procurement of sand and other materials. Murrum was to
be obtained from Right Bank Canal, 8 Kms from site of
works as stated in the contract. This obligation of the
Employer is not fulfilled. A quarry was shown near 1 Km
of the main canal. It later brought to our notice that this
quarry comes under Forest area and the Forest
                            - 16 -



department did not allow quarry of CNS materials. Every
request of the contractor to the the Employer to indicate
the quarry location failed. As the work was at stand still
and our tools and plants were idling at site. We have to
obtain the CNS material from other places at our own cost
and expenses. Only as small quantity sufficient enly for a
5 Kms of the Canal be obtained. In spite of repeated
requests no quarry was shown till date. In fact a latter
was written on 6-1-2006 indicating the difficulty in
obtaining CNS materials and this difficulty is still
persisting.

       A similar situation has occurred for other materials
such as Sand and aggregates also. Consequently the
progress was hampered financial loss we had to suffer. in
addition

     Further the contract specifies only 5 Kms lead for
CNS materials whereas at site the lead is more than 20
Kms.

e) Change in the Nalla design.

       The level of the Nalla has been changed frequently.
The levels are to be indicated at the time of handing over
of the site for the entire longitudinal section but the levels
are being given at the time of excavation only. The work
has to suffer due to default of the employer. It is evident
that the levels are not given at the time of work started
which is a bounden obligation of the NVDA. Hence KLAC
could not plan and execute the won as they envisaged at
the of tendering.

       It was seen that the earth required for the work
was not sufficient and the same has to be brought from
outside the NVDA land. For this we have to incur
additional expenditure in conveying the materials beyond
3 Kms and also the cost of the earth obtained for
embankment reaches. This is also already brought to your
notice during April 2005. This failure of NVDA to indicate
the borrow area has delayed the execution of the work
and the KLAC has to incur addition expenses.

f) Delay due to not shifting of electric power lines:

      It is an obligation of the NVDA to hand over the site
free of all encumbrances and hindrances. Though
promises were made that electric line Crisis crossing the
canal will be removed immediately after acceptance this
                            - 17 -



was not removed even up to February 2006. Because of
this hindrance the work could not be progressed and we
were facing difficulties in using JCBs for excavation. In
fact certain accidents also happened due to electrocution
and heavy expenditure has to be incurred in addition to
the delay in progress of the works. The electric power
lines were partly shifted during January to March 2007
and the work of shifting of electric power lines is still not
complete. This has prevented the progress of work.
Increase in quantity of works.

g) Increase in quantity of works:

      It is observed that the quantities. Indicated in Bill
of Quantities are inaccurate and the final quantities are
bound to increase enormously and in certain cases it may
exceed more than 30% of the quantity stated in the Bill of
Quantity. As per the terms of the Contract if there is any
increase in the quantity of works an appropriate extension
of time is required to be given. This extension is still not
been given. It is to be noted that though KLAC has been
asked to Proceed with the work no order for increase in
quantity has also been placed on the KLAC.

h) Non finalization of rates:

       The following extra works has been ordered and
executed at site for which rates have not been finalized.
In fact the measurements have been recorded in certain
cases.

a) Head Regulated gates for change of specification from
Cast iron to M.S.
b) Diversion road
c) Rubber strip for expansion joint
d) Sand and boulder treatment for foundation of the
structures
e) Filling Murrum alround the structures to avoid contact
of BC soil to the structures.

      Non-finalization of rates have resulted in non
payment for the work done and financial difficulty to
KLAC. This financial crunch also affected the progress of
work.

i) Stoppage of work:

a) The Concrete lining was being executed in the Canal.
At this juncture NVDA directed KLAC to stop the progress
                           - 18 -



of the lining work and to divert the laborers to the work of
the structures. This interference of NVDA has completely
jeopardized the planning and progress of the work by
KLAC resulting in delay in execution.

a) The Concrete lining was being executed in the Canal.
At this juncture NVDA directed KLAC to stop the progress
of the lining work and to divert the laborers to the work of
the structures. This interference of NVDA has completely
jeopardized the planning and progress of the work by
KLAC resulting in delay in execution.

b) The District Road bridge was taken up for construction
and all arrangements including fabrication of scaffolding
were carried out. At this juncture NVDA changed the
design and instructed the KLAC to provide Syphon type in
lieu. It is incumbent for the NVDA to furnish all drawings
etc., well in time much before the actual work is taken up.
This late action of NVDA particularly after the work is
taken up has delayed the progress of the work in
additional to the extra expenditure to the KLAC.

       In the absence of expression stipulation, the NVDA
has no right to dictate the order in which work will be
carried out and the refusal to alow KLAC to carry out the
work in the order of their choice has affected the progress
of work. KLAC for that reason is entitled to damages for
wrongful    interferences.    The   contract    does    not
contemplate interference by the employer in the method
and order of execution of work planned by the KLAC.

c) M5 Canal which was originally included in the contract.
The site was cleared of Shrubs and vegetation by KLAC
and arrangement was made to progress the works. NVDA
did not furnished the alignment and level thereby
preventing KLAC to progress the work. Even on date the
alignment is not furnished and resulted in delay in
progress of work.

j) Curtailment of payment:

       As already stated entire payment has not been
made for CNS soil, change in specification for the gates,
escalation for the work executed as the period of contract
has been enlarged, for more than 12 months. As the work
is being executed beyond the original contracted period
revised rates are also payable to the KLAC. This crunch in
the financial flow has greatly affected the progress of
work.
                           - 19 -




h) Foreclosure of works

       The Contract contemplates various works as
indicated in Bill of Quantities as well as drawing NVDA has
omitted certain which are as follows:

i)   193 Structures were originally contemplated for
     execution. This has been reduced to 145 number
     which is more than the limit stipulated in the
     contract. This has affected the progress as proper
     planning-could not be done. Also due to this
     reduction revised rates has to be agreed between the
     parties for the work executed.

ii) It is also been stated in the letter referred above that
    certain works have also been withdrawn from the
    contract. As per the terms of the contract KLAC is
    entitled to execute the entire work and NVDA cannot
    order omission of certain works, perhaps with the
    intention of getting it done by other agencies, If such
    an event occurred KLAC has the right for the
    damages incurred.

5. It can be seen from the above that the main causes of
the delay are:
a) Delay in land acquisition
b) Non availability of CNS material
c) Non payment of the monies due to the contractor.

6. The above has been highlighted by no less than the
Chief Minister of Karnataka himself as far back as 12-06-
2007. However no constructive action has been taken by
you. Apart from the above the delay is also due to non
furnishing of instructions and drawings in time, increase
in the quantity of work, curtailment of payment of certain
works, increase in lead for materials and deviation and
stoppage of works. In fact the entire site devoid of any
interferences and hindrances has still not been handed
over to us. As per the Contract Act, the obligations of the
contractor commences only after the completion of the
obligations of the employer. This has not been completed
by you yet. The main requirement is handing over the
entire site. KLAC cannot commence the work at all
reaches without handing over the entire site and this is
still not completed.

It is therefore requested that the letter dated 23-07-2007
may please be cancelled and our request for extension of
                                   - 20 -



     time as requested in our letter dated 05-06-2007 may
     please be granted at an early date.

           We, on our part are ready to do our best to
     complete the work as early as possible provided that the
     main issues as brought out above are sorted out by you."


     17.   The respondents while submitting the draft

letter of claims before the Superintendent Engineer,

Jabalpur, have furnished significant details under clause

4.3.29.2   of   the     agreement,          the   relevant     portion   is

extracted as under:

    "The salient features of the afore said contracted
    work are:-

    1. Name of Work                    : As above

    2. Date of Tender submitted        : 06/08/2004

    3. Date of Acceptance by NVDA : 06/09/2004 Secretary
                                     NVDA

    4. Value of Contract awarded       : Rs.18,88,61,477.00

    5. Percentage over USR 1998            : @14.89 of above 1998 USR

    6. Date of agreement                   : 05/11/2004

    7. Work order No.                      : 818/SAC/Panagar/2004
                                             Date: 05/11/2004.

    8. Stipulated Time for completion : 12 months excluding 3
                                        months Rainy season.

    9. Stipulated date of completion        : 04/02/2006.

    10. Period of contract extended         : a) 1st extension granted
                                                 upto 31/3/06.
                                              b) 2nd extension granted
                                                 upto 15/6/06.
                                              c) 3rd extension granted
                                                 upto 31/12/06.
                                   - 21 -



                                           d) 4th Extension granted
                                              upto 31/3/07 further
                                              extension applied upto
                                              31/3/2008 and is under
                                              consideration.

    11. Value of bills cleared by NVDA     : Rs.8,61,08,841
         upto 31/3/07.

    12. Date of Termination of Contract : 23/7/07

    13. Position of Final Bill              : It is in the process of
                                              preparing the final bill by
                                              the employer.

    14. Amount of EMD deposited             : Rs.500000.00 (Forfeited
    With the tender                            by EE on 23/7/07.

    15. Performance Security deposited : Rs.9500000.00
    amount at the time Contract         (5%Forfeited by EE on
    of signing agreement                 23/7/07).


    16. Amount of security deposit          : Rs.4296991.00 forfeited
       Recovered from running Bills           by E.E on 23/7/07
       @ 5% upto 20th RA bill :

    17. Addl. Security deposit towards: Rs.4972158.00 forfeited
    Unbalanced rate                     by E.E on 23/7/07.

    18. Amount with held from              : Rs.1860758.00 forfeited
       R.Bills or some filmsy and             by E.E on 23/7/07
       unjust grounds

    19. Amount of pending bills            : Rs.31248795.00
      Submitted as per the Actual          : Communicated to E.E.
      execution                              vide Itr No:
                                             PM/KLAC/NVDA/ Madana.
                                             2007-08 /932 dt:
                                             4/7/07."



     18.    The entire edifice on which the enquiry is

constituted and petitioners are subjected to departmental

proceedings      relates     to   advances        paid     to    associate

contractors.      Disciplinary authority while dealing with
                                  - 22 -



charge No.6 has made certain observations and therefore,

this Court is of the view that these observations are too

critical to analyze whether departmental proceedings

initiated against the petitioners are sustainable pending

consideration       of   the    arbitral   proceedings     between

respondents and State of Madhya Pradesh.


     19.       The relevant extracts are extracted as under:

     "15. The works entrusted to KLAC by NVDA authorities were
       being executed by the following four (4) agencies, as per
       "Agreement for Association" entered into by KLAC

            •    Shri. M. Channaih
            •    M/s SV Quality Construction Co.
            •    M/s. Elcon Infratech
            •    Shri. B. Ramesh Naidu.

    A copy of such an agreement with Shri. M. Channaih is
    placed as Exhibits ME11. Agreements with others are
    identical. Clause 12 of this agreement states "The project
    manager KLAC may at his discretion, provide advances to M.
    Channaih, if required, which shall be deducted from the
    subsequent running bills". The agreement however, does not
    provide for any guarantee clause for such advance
    payments.

    16.     Advance payments were being made to the above
           agencies by the Project Manager and the Project
           Executive, being Joint Account, operated by both.

    17.     An audit check was conducted by officers of KLAC
           during May 2007. After examining all the monthly A/c's
           (KLAC Job Bills, MRA's etc.), it was established that
           total net outstanding advances against the above four
           agencies as on 29.05.2007 were as under

           •     Mr Channiah                    Rs. 4,03,07,712
           •     M/s. SV Quality constant co.   Rs. 28,43,879
           •     M/s. Elcon Infratec            Rs. 33,36,563
                               - 23 -



      •       Mr. Ramesh Naidu               Rs. 11,67,761
                      TOTAL                  Rs. 4,76,55,915

     Copy of Audit Check report is at Exhibit ME9

18. The Presenting Officer in his written statements brought
    out that as per a final abstract statement furnished by
    the Project Manager and the Project Executive, the
    reconciled figures of advance, were as under (as on
    06.06.2007).

          •   Mr Channiah                    Rs. 4,05,12,024
          •   M/s. SV Quality constant co.   Rs. 28,77,556
          •   M/s. E/con Infratec            Rs. 33,36,563
          •   Mr. Ramesh Naidu               Rs. 11,96,111
                       TOTAL                 Rs. 4,79,22,254

19. As the advances outstanding against the above four
     agencies, have become irrecoverable as the works
     have been withdrawn by NVDA authorities, and no
     security is held with KLAC, the amount is considered as
     loss to KLAC. Both the CSO's viz the Project Manager
     (PM) and the Project Executive (PE) have therefore
     been made responsible for this loss of Rs. 4,79,22
     Lakhs

20. The pleadings of the CSO's (Exhibits DE5 and DE6) have
     been examined in detail. The main points brought out
     by them, and my views on the same, wherever
     applicable are recorded in the succeeding paragraphs.

20.1. There is no dispute on the total amount of Rs.
     4,79,22,254 shown as outstanding advances against
     the four agencies, as on 06.06.2007. In fact the
     statement showing details leading to this figure is
     signed by both CSO's (Exhibits ME6 & ME7).

20.2. The CSO's in their defence statement (page 13 of
     Exhibits DES and DE6) have stated that all advance
     payments at various stages, were made by the Project
     Manager, after obtaining specific approvals from the
     Managing Director. This statement is not in line with
     the evidences produced, and cannot be accepted. Only
     two payments viz Rs.,60 Lakhs on 08.10.2004 and Rs.
     75 Lakhs on 19.01.2006 have the specific approval of
     MD KLAC. (Exhibits D II Pages 2 & 10 refer). Other
     payments made to the agencies appear to be at the
     discretion of the Project Manager/Project Executive, out
     of the bulk allotments periodically placed at the
                            - 24 -



     disposal of the Project Manager. It is seen that as per
     the procedure introduced and followed as per found
     indicated BHUSIRI ACCOUNT. full details like work done
     so far and basis of advance payments if any, planned
     to be made, are not (Exhibits ME12 & ME13). The
     requirement of bulk funds demanded by the Project
     Manager, appear to be on an ad hoc basis. This is
     evident such demand projected for Rs. 75 Lakhs during
     Jan 2006. from one Approval bulk allotment is seen to
     have been periodically issued by MD for KLAC.
     Statements of the CSO's that all advance payments are
     made to the Associate contractors, after obtaining
     approval of MD KLAC are not borne by facts. The power
     of Attorney documents signed by MD KLAC on 12 Oct
     2004 (Exhibit ME10) does not empower Sri. CG
     Nanjaraj to make any advance payments. Release of
     funds cannot be taken as approval for making advance
     payments.

20.3. It can be seen from the statement at Annexure H to
     the audit check referred to in para 17 ante (Exhibit
     ME9) payments have been made on a regular basis to
     the Associate contractors, without maintaining any
     measurements of work done. There are instances
     where such "work advance" payments have been made
     more than once, on a single day. No details were
     produced to establish the basis for the advance
     payments.

20.4. It is agreed that, there are two stages involved for
     making payments. The work is executed by Associate
     Contractors, and the work done is jointly measured by
     the Project Manager/Project Executive, with the NVDA
     authorities, and the bill is released for payment by the
     NVDA. In the meanwhile, the associate contractors
     need payments for the work done by them, to enable
     them to progress the work further. There should have
     been a set of measurements with the PM/PE to
     examine and justify demand for "work advance"
     payments by the Associate Contractors. Keeping a
     record of work done by Associate contractors, has been
     stressed in HQ KLAC letters dt. 13.02.07 and 19.02.07
     (Exhibit ME8). No such details are made available by
     the PM/PE in their defence statements, and as such the
     payments made are considered to be ad-hoc without
     any authority.

20.5. It is an established practice that there should be some
     sort of Security to be retained with the Department
                                - 25 -



           before making any advance payment of huge amounts
           to an external agency. Even otherwise, the periodical
           "work advances" paid should have been related to the
           actual work executed/ to executed, by the Associate
           Contractors. This aspect seems to have been missed at
           all levels, even at the time of release of funds."

     20.    The     department          alleges   that   both     the

petitioners have lent advances to the external agency

without retaining some amount towards security with the

department. To consider these allegations, this Court now

deems fit to examine the stand taken by respondents in

arbitration proceedings. The relevant portion is extracted

as under:

     "c) Payment of Interim bills:

            This construction contract provides payment of
     installments every month vide Clause No. the contract
     Non payment of these interim bills for certain works
     amounts to breach of contract. Upon such default the
     contractor can stop the work and may abandon the
     contract and seek compensation on the basis of fair and
     reasonable value of the work done. A contract involving a
     large expenditure stipulation for payment on account to
     be made from time to time must be deemed so material
     that the substantial failure to pay would justify the
     contractor to decline to proceed. It is evidently was in
     contemplation of the parties that the contractor could not
     be expected to finance the operation to completion
     without receiving the payment on account of the work
     executed. Nearly about Rs.2.80 Crores of payments is still
     due for the work completed. In such cases a substantial
     compliance as to advance payment is a condition
     precedent to the contractor's obligation to proceed with
     the work.
            The Supreme Court has held that the withholding of
     substantial amount over a long period without any
     reasonable cause amounts to breach of contract.
                                - 26 -



     g) Increase in quantity of works:

           It is observed that the quantities. Indicated in Bill
     of Quantities are inaccurate and the final quantities are
     bound to increase enormously and in certain cases it may
     exceed more than 30% of the quantity stated in the Bill of
     Quantity. As per the terms of the Contract if there is any
     increase in the quantity of works an appropriate extension
     of time is required to be given. This extension is still not
     been given. It is to be noted that though KLAC has been
     asked to Proceed with the work no order for increase in
     quantity has also been placed on the KLAC.

     h) Non finalization of rates:

            The following extra works has been ordered and
     executed at site for which rates have not been finalized.
     In fact the measurements have been recorded in certain
     cases.

     a) Head Regulated gates for change of specification from
     Cast iron to M.S.
     b) Diversion road
     c) Rubber strip for expansion joint
     d) Sand and boulder treatment for foundation of the
     structures
     e) Filling Murrum alround the structures to avoid contact
     of BC soil to the structures.

           Non-finalization of rates have resulted in non
     payment for the work done and financial difficulty to
     KLAC. This financial crunch also affected the progress of
     work."



     21.   If   the   stand     by      the   first   respondent     in

arbitration proceedings is examined in the context of

charge No.6 leveled against the petitioners, this Court is of

the view that department is blowing hot and cold.                   The

culled out stand taken by respondents in arbitration

proceedings clearly gives an indication that the claim
                                   - 27 -



made   in    the   departmental            proceedings   against     the

petitioners relating to advance payment which is subject-

matter of Charge No.6 is clearly inter linked with the claim

made by respondent No.1 in arbitral proceedings.                     The

allegations in the departmental proceedings are complex

in nature and the superior authorities of petitioners

obviously constituted a committee to enquire relating to

advance payments made to external agency.                        These

allegations are clearly intertwined with the claim made by

respondents 1 and 2 against State of Madhya Pradesh.

The allegations indicated in Charge No.6 cannot be

enquired pending consideration of arbitral proceedings.


     22.     Respondent No.1's own admission while raising

arbitral dispute wherein there is unequivocal admission

that the contract involved large expenditure and there

were compelling reasons to make payment from time to

time, the respondents have also indicated that failure to

make   advance      payments          would     have     justified   the

contractor    to   decline   to      proceed     with    the   project.

Petitioners who were implementing the project at Madhya
                                 - 28 -



Pradesh cannot be solely held accountable if the accounts

were released by the accounts section from the head

quarters, that too pending consideration of the arbitral

proceedings.


      23.    The respondents have initiated departmental

enquiry only on the count that the advances paid to these

four external agencies have become irrevocable as the

project is withdrawn by the NVDA. This factual aspect is

evidenced at the finding recorded by the Disciplinary

authority at Paragraph 19 of the Enquiry report.


      24.    The observations of the Disciplinary authority

reveal that the departmental charges are intricately linked

to   the     arbitral   disputes.    The    arbitral   proceedings

themselves reflect an admission by the respondents that

the project involved significant expenditures and that the

contractors       required   advance     payments      to   proceed

with the work. The Supreme Court, in cases such as

State       of    Uttar      Pradesh       v.   Kharak      Singh1




1 2008 AIR SC 0
                                    - 29 -



and Jaswant          Singh    v.      State       of    Punjab2,    has

emphasized the importance of conducting a fair and

independent inquiry by the disciplinary authority. In this

case, the respondents' admissions in the arbitration

proceedings, where they acknowledged that failure to

provide payments would have justified the contractor's

cessation of work, cast doubt on whether the petitioners

alone can be held responsible for the alleged financial loss.


        25.    It appears that the petitioners were acting in

accordance with the financial decisions taken at higher

levels within the organization. This raises a critical issue:

did the disciplinary authority adequately consider these

facts before deciding to impose the extreme penalty of

dismissal?


        26.    The disciplinary authority is duty-bound to

independently        assess    all          evidence,   including   the

petitioners' defense, rather than merely relying on the

findings of the Disciplinary authority. The Supreme Court

in State of Uttar Pradesh v. Saroj Kumar Sinha


2
    (1991 AIR 385)
                                     - 30 -



(supra) stressed that the disciplinary authority cannot be a

mere rubber stamp but must apply its own mind to the

findings and the material on record before arriving at a

conclusion. In this case, it is unclear whether the authority

took into account the entirety of the facts or simply

endorsed the Disciplinary authority's conclusions, which

would be a violation of the principles laid down in Union

of India v. H.C. Goel (supra).


         27.   The respondents' reliance on the Disciplinary

authority's report to impose a penalty on the petitioners,

without independently evaluating the broader context of

the arbitral proceedings and the operational difficulties

faced by the project, amounts to an unfair and incomplete

assessment of the facts. The disciplinary authority's

decision       appears     to    lack    the   required        independent

analysis,       as   emphasized         in Union    of    India     v.   P.

Gunasekaran3, where the Court reiterated that the

authority must give due consideration to all material

evidence before concluding on a disciplinary matter.



3
    (Civil Appeal No. 010386/2014 SLP No.(civil) 23631/2008)
                              - 31 -



     28.   Given the complex and intertwined nature of

the departmental proceedings with the ongoing arbitral

proceedings, the premature conclusion of the disciplinary

inquiry and the subsequent penalty inflicted upon the

petitioners cannot be sustained. The disciplinary authority

should have deferred its decision until the resolution of the

arbitration to avoid a miscarriage of justice.


     29.   Thus, based on the above analysis and the

principles laid down in several Supreme Court judgments,

the penalty of dismissal imposed on the petitioners is not

legally tenable and warrants reconsideration


     30.   On an overall assessment of the records,

respondents 1 and 2 have ventured in implementing

projects at Madhya Pradesh without having infrastructure

to undertake the said projects.             Respondents have

admitted in unequivocal terms that for want of staff, the

respondents were entirely dependent on external agencies

and sub-contractors. This departmental enquiry is clearly

an off-shoot of termination of contract by NVDA.             Had

NVDA    proceeded     with   the      projects,   probably   the
                               - 32 -



respondents would not have contemplated a departmental

enquiry against the petitioners. Though few heads have to

roll as public money is spent on risky projects beyond the

control of respondents 1 and 2 that cannot be at the cost

of petitioners alone.


     31.    The     respondents         could     have     initiated

proceedings only after conclusion of arbitral proceedings.

The penalty inflicted by the Disciplinary authority and

confirmed by the appellate authority are not sustainable.

For the reasons stated supra, the departmental enquiry is

held to be premature.


     32.    For the foregoing reasons, this Court proceeds

to pass the following:

                            ORDER

(i) Writ petitions are allowed.

(ii) The impugned proceedings dated 12.04.2012 of respondent No.1 held in the 169th Board Meeting under Subject No.169/25 confirming the order of respondent No.2 imposing penalty as per Annexure-U is hereby quashed. Consequently, the impugned official memorandum dated 13.09.2011 and the

- 33 -

endorsement dated 4/7.5.2012 issued by respondent No.2 as per Annexures-R and V are also quashed.

(iii) The respondents are accordingly directed to grant all consequential and retiral benefits to the petitioners in accordance with law.

SD/-

(SACHIN SHANKAR MAGADUM) JUDGE *alb/-