State of Rajasthan - Subsection

Section 26(3) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016

(3)The open access consumer shall restrict the sum of his total drawal from all sources including open access and Distribution Licensee up to the total sanctioned contract demand with the Distribution Licensee.Provided that open access may be allowed over and above the contract demand to a consumer who sources power both by captive generation and Discom to the extent of captive power supply subject to availability of transmission and/or distribution system as the case may be.Provided further that long term open access may be allowed over and above the contract demand to the extent of sanctioned open access capacity.