Section 16(16) in Andhra Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff for Wheeling and Retail Sale of Electricity) Regulation, 2005

16.2The Distribution Licensee shall seek approval for individual schemes in the Capital Investment Plan at least 90 days before undertaking the investment in accordance with the Guidelines on Investment Approval. The individual schemes/projects submitted by the Distribution Licensee for Commission's approval must provide complete details including those relating to the cost and capitalisation for each year of the Control Period.