Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 9, Cited by 92]

Supreme Court of India

State Of Punjab vs Sri Hardyal on 10 April, 1985

Equivalent citations: 1985 AIR 920, 1985 SCR (3) 649, AIR 1985 SUPREME COURT 920, (1985) 1 PUN LR 683, 1985 87 PUN LR 683, 1985 BBCJ 81, 1985 (2) SCC 629, (1985) 2 CIVLJ 129, (1985) 2 CURCC 182

Author: R.B. Misra

Bench: R.B. Misra, O. Chinnappa Reddy

           PETITIONER:
STATE OF PUNJAB

	Vs.

RESPONDENT:
SRI HARDYAL

DATE OF JUDGMENT10/04/1985

BENCH:
MISRA, R.B. (J)
BENCH:
MISRA, R.B. (J)
REDDY, O. CHINNAPPA (J)

CITATION:
 1985 AIR  920		  1985 SCR  (3) 649
 1985 SCC  (2) 629	  1985 SCALE  (1)675


ACT:
     Arbitration Act  1940 sections 3 and 28 (1) and (2) and
clause 3  of the First Schedule-Written agreement-Containing
arbitration  clause-No	 period	 fixed	 for  giving  award-
Statutory period-Applicability	of-Parties participating  in
the proceedings	 after	the  expiry  of	 prescribed  period-
whether amounts	 to extension  of  time	 for  making  award-
Extension  of	time  for   making   award-Jurisdiction	  of
arbitrator-Court's exercise  of discretion  in extension  of
time-Doctrine of waiver and estoppel whether applicable.



HEADNOTE:
     By a  written agreement  ,	  the respondent  agreed  to
construct bridges  and culverts	 for State  Government.	 The
agreement contained  an arbitration clause ,  the Arbitrator
being the  Superannuation intending  Engineer. However ,  no
period was  fixed for  giving the   And	 . therefore  ,	 the
statutory  period  of  four  months  for  giving  the  award
prescribed  in	clause	3  of  the  First  Schedule  to	 the
Arbitration Act was applicable.
     A dispute	arose between  the parties.  The  respondent
sent a notice to the Arbitrator requesting him to accept his
claim  and   give  his	 award.	  The	respondent   claimed
compensation on	 two counts  ,	 namely ,  (I) that the Sub-
Divisional Officer  got certain bridges demolished which had
been construed strictly in terms of the agreement ,  and (2)
that the respondent had also been directed to stop the work.
     The Arbitrator  gave his  award against  the respondent
after the  expiry of the prescribed period ,  the respondent
having participated  period ,  in the proceedings before the
Arbitrator even	 after the  expiry of  the statutory period.
The respondent	challenged the	award but  the	trial  Court
overruled the objection and upheld the award.
     On appeal	to the High Court ,  a Single Judge referred
two points  for decision  by a Division Bench ,	 (l) Whether
the award  given after	the expiry  of the prescribed period
without extension of time by the Court was invalid ? and (2)
Whether the  participation in  the  arbitration	 proceedings
even after the
650
expiry of  the period  of  limitation  prescribed  would  by
necessary implication  amount to extending the time under s.
28 of the Arbitration Act by the Court ?
     The  Division   Bench  allowed  the  objection  of	 the
respondent regarding  delay in	giving the  award ,  holding
that a	party to  an arbitration  agreement is	not estopped
from challenging  the 'award  of the  ground of delay merely
because it  had participated  in the arbitration proceedings
even after  the expiry	of the prescribed period without any
demur ,	  that	mere dismissal	of the	objection  regarding
delay in  the award  does not amount an extension of time by
the Court under s. 28 (l) of the Arbitration Act ,  and that
time can  be extended  by the court by the exercise of sound
judicial discretion.  The appeal  was allowed  and the	case
remanded to  the trial	Court for  deciding whether it was a
fit case  for condoning the delay in giving the award by the
Arbitrator.
     Allowing the Appeal of the State in part,
^
	 HELD: l. The provisions of ss. 3 and 28 (1) and (2)
and clause  3 of  First Schedule to the Act indicate that it
is open	 to the	 parties to  an arbitration agreement to fix
the time  within   which the Arbitrator must give his award,
but it	has to	be so stated in the agreement itself. If per
chance no  time has  been specified  by the  parties in	 the
arbitration agreement  ,  then by virtue of operation of s.3
with read  clause 3  of the First Schedule the award must be
given within  four months  of the arbitrator entering on the
reference or  after having been called upon to act by notice
in writing  from any  party to	the arbitration agreement or
within such extended time as the Court may allow. [654A-B]
     2. Sub-section  (t) of  s.28 is  very wide	 and confers
full discretion	 on the	 Court to enlarge time for the award
at any	time ,	 which	should ,   however  ,	be exercised
judiciously. Sub-section  (2) of s. 28 makes it evident that
the Court  alone has  the power	 to extend  time. It further
provides that  a clause	 in the arbitration agreement giving
the Arbitrator power to enlarge time shall be void and of no
effect	except	 when  all   the  parties  consent  to	such
enlargement. It	 is not	 open to  Arbitrators at  their	 own
pleasure without  the consent of parties to the agreement to
enlarge the for making the award.[655 A-B]
     H.K Wattal v V.N. Pandya [1974] 1 SCR 259 ,  followed.
	 3 Once the law precedes parties from extending time
after the  matter has  been referred to the Arbitrator ,  it
will be	 contradiction to  hold that  the same result can be
brought about by the conduct of the parties. There can be no
estoppel against  a statute. The time to be fixed for making
the award was initially one of agreement between the parties
but it	does not  follow ,   that  in the  face of  a  clear
prohibition by law that the time fixed under clause 3 of the
said Schedule  can only be extended by the Court and not b y
the parties  at any  stage. It	still remains  a  matter  of
agreement and  the rule	 of estoppel  operates. The  Act has
injuncted the  Arbitrator to  give  an	award  with  in	 the
prescribed
651
period of  four months	unless the  same is  extended by the
Court. The  Arbitrator has  no jurisdiction to make an award
after the  fixed time.	If the award made beyond the time is
invalid the  parties are  not estopped by their conduct from
challenging the	 award on the ground that it was made beyond
time merely  because of	 their having  participated  in	 the
proceedings before  the Arbitrator  after the  expiry of the
prescribed period. [656H; 657 A-C]
     Shambbu Nath v Surja Devi ,  AIR 1961 All. 180; Shivlal
v. Union  of India  AIR 1975  M.P.40; and  Ganesh Chandra v.
Artatrana AIR 1965 Orissa 17 over ruled.
     4. The  policy of	law seems to be that the arbitration
proceedings should  not be unduly prolonged. The Arbitrator,
therefore ,   has  to give the award within time  prescribed
or such	 extended time	as the ,  Court concerned may in its
discretion extend  and the  Court alone	 has been  given the
power to extend time for giving the award. The Court has got
the power  to extended	time even  after the  award has been
given or  after the  expiry of the period prescribed for the
award. But  the Court  has to  exercise its  discretion in a
judicial manner.  In the  instant case ,  the High Court was
justified in  taking the view that it did. This power can be
exercised even	by the	appellants court.  In  view  of	 the
policy of  law and in view of the fact that the parties have
been taking  willing part  in  the  proceedings	 before	 the
Arbitrator without  a demur  ,	 this will be a fit case for
the extension  of time.	 the time  for giving  the award  is
extended and  the award will be deemed to have been given in
time The  case is  however ,  remanded to the High Court for
decision on the other issued involved. [657 E-G; 658]



JUDGMENT:

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1980 of 1970.

From the Judgment and order dated 16.11.69 of the High Court of Punjab & Haryana in F.A.O. No. 120/62.

Mrs. Urmila Kapur and S.K. Bagga for the Appellant. The Judgment of the Court was delivered by MISRA , J. Hardyal , the respondent , entered into a contract with the State of Punjab , Public Works Department (Buildings and Roads Branch) for the construction of certain bridges and culverts on the Mukerian-Naushehra Road. The agreement between the parties was evidenced by a writing. The written agreement contained an arbitration clause which provided that dispute , if any , between the parties would be referred to the Superintending Engineer, Public Works Department (Buildings and Roads) , Jullundur Circle. It 11 appears that no period was fixed in the agreement of reference for giving the award and therefore Period of four months as prescribed 652 in clause 3 of the First Schedule attached to the Arbitration Act would be the statutory period for giving the award.

Some dispute did arise between the parties. The respondent , therefore , sent a notice on January 7, 1960 to the Superintending Engineer requesting him to accept his claim to the tune of Rs. 7,568 and give his award accordingly. The respondent claimed this amount of compensation broadly on two counts: (1) that the sub- Divisional Officer had got certain bridges demolished which according to the respondent had been constructed strictly in terms of the agreement , and (2) that the respondent had also been directed to stop the work.

The arbitrator gave his award against the respondent on April 28 , 1961 , but after the expiry of the prescribed period. It is , how ever admitted by the respondent that he participated in the proceedings before the arbitrator even after the expiry of the statutory period. The respondent challenged the award by filing an objection under s. 30 of the Arbitration Act on a number of grounds. On the pleas taken by the respondent the Senior Sub-Judge framed the following four issues: (I) whether the objections were premature , (2) whether the arbitrator had misconducted himself or the proceedings , (3) whether the award was against natural justice , and (4) whether the award was made after inordinate delay.

The learned Judge overruled all the objections and upheld the award. Issue No. l Was not pressed before him. The contention of the respondent that reasonable opportunity had not been afforded to him to adduce evidence , by the arbitrator , was also repelled by the learned Judge. He observed "One of the grounds taken up for setting aside the award as stated in the application was that the petitioner was not afforded a reasonable opportunity to adduce evidence. But the record of the proceedings dated 24th of April , 1961 shows that the parties did not want to say any thing further and the hearing of the case was , therefore, closed under such circumstances."

The plea regarding misconduct on the part of the arbitrator was also overruled and dealing with this point the learned Judge observed:

653
"Nothing has been POINTED out to me in the court during the course of the arguments as to how the arbitrator has misconducted himself and the proceedings."

The plea regarding delay in giving the award was rejected on the ground that the respondent had been participating in the proceedings before the arbitrator even after the expiry of the prescribed period of limitation.

The respondent took the matter in appeal to the High Court. When the matter came up before a learned Single Judge he referred the following two points for decision by a Division Bench on account of the importance of the question involved in the case and also on account of conflict of judicial opinion on the point:

1. Whether the award given after the expiry of the prescribed period without extension of time by the court was invalid ?
2. Whether the rejection of the objection regarding delay in giving the award on the ground that the objector had participated in the arbitration proceedings even after the expiry of the period of limitation prescribed would by necessary implication amount to extending the time under s. 28 of the Arbitration Act by the Court ?

The Division Bench allowed the objection of the respondent regarding delay in giving the award holding that a party to an arbitration agreement is not estopped from challenging the award on the ground of delay merely because it has participated in the arbitration proceedings even after the expiry of the prescribed period without any demur. On the second point the High Court held that mere dismissal of the objection regarding delay in the award does not amount to extension of time by the court under s. 28(1) of the Arbitration Act and indeed time can be extended by the Court by the exercise of sound judicial discretion. Accordingly the appeal was allowed , the order of the Senior Sub-Judge was set aside and the case was sent back to the trial court for deciding afresh whether it was a fit case for condoning the delay in giving the award by the arbitrator after affording opportunity to the parties to adduce evidence, 654 The State has now come up in appeal on a certificate granted by the High Court under Art. 133(1)(c) of the Constitution , as it then stood.

The same points have been reiterated before this Court. Before dealing with the points involved it will be convenient to refer to the relevant provisions of the Arbitration Act. Section 3 reads;

"3. An arbitration agreement , unless a different intention is expressed therein , shall be deemed to include the provisions set out in the First Schedule in so far as they are applicable to the reference."

Section 28 reads:

"28. (1) The court may , if it thinks fit , whether the time for making the award has expired or not and whether the award has been made or not , enlarge from time to time the time for making the award.
(2) Any provision in an arbitration agreement whereby the arbitrators or umpire may , except with the consent of all the parties to the agreement , enlarge the time for making the award , shall be void and of no effect."

Clause 3 of First schedule provides:

"3. The arbitrators shall make their award within four months after entering on the reference or after having been called upon to act by notice in writing from any party to the arbitration agreement or within such extended time as the court may allow."

A perusal of these provisions indicates that it is open to the parties to an arbitration agreement to fix the time within which the arbitrator must give award , but it has to be so stated in the agreement itself. If per chance no time has been specified by the parties in the arbitration agreement. then by virtue of operation of s. 3 read with cl. 3 of the First Schedule the award must be given within four months of the arbitrator entering on the reference or after having been called upon to act by notice in writing from any party to the arbitration agreement or within such extended time as the court may allow.

655

Sub-section (I) of s. 28 is very wide and confers full discretion on the court to enlarge time for making the award at any time. The discretion under sub-s. (I) of s. 28 should , however , be exercised judiciously. Sub-section (2) of s. 28 also makes it evident that the court alone has the power to extend time. It further provides that a clause in the arbitration agreement giving the arbitrator power to enlarge time shall be void and of no effect except when all the parties consent to such enlargement. It is not open to arbitrators at their own pleasure without consent of the parties to the agreement to enlarge time for making the award.

In H.K. Wattal v. V.N. Pandya(1) dealing with s. 28(1) of the Arbitration Act this Court observed:

"There is no doubt that the arbitrator is expected to make his award within four months of his entering on the reference or on his being called upon to act or within such extended time as the court may allow. Reading clause 3 of the Schedule along with section 28 one finds that the power to enlarge the time is vested in the court and not in the arbitrator. Clause 3 and section 28(1) exclude by necessary implication the power of the arbitrator to enlarge the time. This is emphasised by section 28(2) which provides that even when such a provision giving the arbitrator power to enlarge the time is contained in the agreement , that pro- vision shall be void and of no effect , The headnote of section 28 brings out the force of this position in law by providing that the power is of the court only to enlarge time for making the award. Sub-section (2) of section 28 , however , indicates one exception to the above rule that the arbitrator cannot enlarge the time , and that is when the parties agree to such an enlargement. The occasion for the arbitrator to enlarge the time occurs only after he is called upon to proceed with the arbitration or he enters upon the reference. Hence it is clear that if the parties agree to the enlargement of time after the arbitrator has entered on the reference , the arbitrator has the power to enlarge it in accordance with the mutual agreement or consent of the parties. That such a consent must be a post-reference consent , is also clear from section 28(2) which renders null and void a provision l. [1974] 1 SCR 259.
656
in the original agreement to that effect. In a sense where a provision is made in the original agreement that the arbitrator may enlarge the time , such a provision always implies mutual consent for enlargement but such mutual consent initially expressed in the original agreement does not save the provision from being void. It is , therefore, clear that the arbitrator gets the jurisdiction to enlarge the time for making the award only in a case where after entering on then arbitration the parties to the arbitration agreement consent to such enlargement of time.
The next question that crops up for consideration is what will be the effect if a party to the arbitration took part in the proceedings before the arbitrator even after the expiry of four months , that is , the period prescribed for giving the award. Some High Courts have taken the view that in such a situation the condition of four months period will be deemed to have been waived. Such a view has been taken by the Allahabad High Court in Shambhu Nath v. Surja Devi.(1) A learned Single Judge of that High Court observed:
"A party to an arbitration agreement who voluntarily takes part in the arbitration proceedings after the expiry of four months will be deem , d to have waived the implied condition as to time."

A similar view has been taken by the Madhya Pradesh High Court in Shivlal v. Union of India(2). In Ganesh Chandra v. Artatrana(3) a single Judge of the Orissa High Court observed:

"If the parties , after the expiry of four months, submit themselves to the jurisdiction of the arbitrators and take part in the proceedings enabling them to pass an award , it cannot be said that the arbitrators acted without jurisdiction. In such a contingency , the principle of waiver and estoppel would have full application.
Once we hold that the law precludes parties from extending time after the matter has been referred to the arbitrator , it will be (1) AIR 1961 All. 180.
(2) AIR 1975 M.P. 40.
(3) AIR 1965 Orissa 17.
657

contradiction in terms to hold that the same result can be brought about by the conduct of the parties. The age long established principle is that there can be no estoppel against a statute. It is true that the time to be fixed for making the award was initially one of agreement between the parties but it does not follow that in the face of a clear prohibition by law that the time fixed under cl. 3 of the Schedule can only be extended by the court and not by the 1 parties at any stage , it still remains a matter of agreement and the rule of estoppel operates. It need be hardly emphasized that the Act has injuncted the arbitrator to give an award within the prescribed period of four months unless the same is extended by the court. The arbitrator has no jurisdiction to make an award after the fixed time. If the award made beyond the time is invalid the parties are not estopped by their conduct from challenging the award on the ground that it was made beyond time merely because of their having participated in the proceedings before the arbitrator after the expiry of the prescribed period.

The policy of law seems to be that the arbitration proceedings should not be unduly prolonged. The arbitrator therefore has to give the award within the time prescribed or such extended time as the court concerned may in its discretion extend and the court along has been given the power to extend time for giving the award. As II observed earlier , the court has got the power to extend time even after the award has been-given or after the expiry of the period prescribed for the award. But the court has to exercise its discretion in a judicial manner. The High Court in our opinion was justified in taking the view that it did. This power , however , can be exercised even by the appellate court. The present appeal has remained pending in this Court since 1970. No useful purpose will be served in remanding the case to the trial court for deciding whether the time should be enlarged in the circumstances of this case. In view of the policy of law that the arbitration proceedings should not be unduly prolonged and in view of the fact that the parties have been taking willing part in the proceedings before the arbitrator without a demur, this will be a fit case , in our opinion , for the extension of time. We accordingly extend the time for giving the award and the award will be deemed to have been given in time.

The other questions involved in the case. however , have not been dealt with by the High Court and it rest content by making a 658 bald observation that there is no other point to be decided in this appeal. The objector-respondent had raised a number of pleas fore challenge the award giving rise to four issues. It was , therefore , obligatory for the High Court to consider those points unless they had been given up by the objector-respondent. There is nothing on the record to suggest that the respondent had given up those grounds. The case will , therefore , have to be sent back to the High Court for deciding the other issues involved in this case.

We accordingly allow the appeal in part and set aside that part of the order by which the High Court remanded the case to the trial court for deciding whether time should be extended. The case is sent back to the High Court for deciding other issues involved. In the circumstances of the case the parties shall bear their own costs.

A.P.J.					     Appeal allowed.
659