Union of India - Subsection

Section 30(2)(b) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

(b)an additional rate of return on equity of 0.25% shall be allowed for every incremental ramp rate of 1% per minute achieved over and above the ramp rate of 1% per minute, subject to ceiling of additional rate of return on equity of 1.00%: