Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0]

Patna High Court

Smt. Urmila Devi vs Bihar State Housing Board And Ors on 16 April, 2019

Author: Anil Kumar Upadhyay

Bench: Anil Kumar Upadhyay

          IN THE HIGH COURT OF JUDICATURE AT PATNA
                  Civil Writ Jurisdiction Case No.12698 of 2013
     ======================================================
     Smt. Urmila Devi W/O Late Heera Lal, Resident Of Village- Sakunath Kala,
     P.S.- Bihar Sharif, District- Nalanda


                                                               ... ... Petitioner/s
                                         Versus
1.   Bihar State Housing Board, 8, Sardar Patel Marg, Patna through Managing
     Director
2.   Manager, Estate Officer, Bihar State Housing Board, 8, Sardar Patel Marg,
     Patna
3.   Executive Engineer, Bihar State Housing Board, Patna Division No. 1
4.   Revenue Officer, Bihar State Housing Board, 8, Sardar Patel Marg, Patna


                                                             ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s   :       Mr.Abhinay Raj
     For the Respondent/s   :       Mr.Anshuman Singh
     ======================================================
     CORAM: HONOURABLE MR. JUSTICE ANIL KUMAR UPADHYAY
     ORAL JUDGMENT
      Date : 16-04-2019

                    Heard learned counsel for the petitioner and learned

     counsel representing the Bihar State Housing Board.

                  2) Petitioner is aggrieved by the arbitrary determination

     of fine for delay in construction. In the counter affidavit stand has

     been taken that petitioner has caused delay of 18 years in

     construction and as such the Housing Board is justified in charging

     fine from the petitioner for causing delay in construction.
 Patna High Court CWJC No.12698 of 2013 dt.16-04-2019
                                           2/5




                    3) Mr. Devendra Kumar Sinha, learned Senior Counsel,

       appearing for the petitioner submits that husband of the petitioner

       had participated in auction on 15.01.1985 and was declared

       successful. Husband of the petitioner died on 11.11.1985. After the

       death of her husband petitioner approached the Housing Board for

       transfer of the plot in her name in place of her deceased husband.

       Mr. Sinha submitted that vide Annexure-4 to the writ application

       the Housing Board granted possession to the petitioner. On 25th

       May, 1989 hire purchase agreement was executed. In terms of the

       said hire purchase agreement petitioner was required to construct

       the house within five years and in the event of failure to construct

       the house the petitioner was liable to pay fine. Vide Annexure-4

       petitioner was handed over possession on 28.05.1993. After the

       possession was handed over to the petitioner she approached the

       PRDA for sanction of map for construction. After the map was

       sanctioned by the PRDA on 31.01.1994 the petitioner approached

       the Estate Officer for approval of the map which was sanctioned

       by PRDA the map was approved by the PRDA was sanctioned by

       the Housing Board on 5.5.1004. On 22.11.2000 water connection

       was sanctioned by the Executive Engineer of the Housing Board

       and on 22.11.2000 agreement of sale was executed.
 Patna High Court CWJC No.12698 of 2013 dt.16-04-2019
                                           3/5




                    4) Petitioner paid the entire price of the plot in question

       as per the agreement. The only issue in the instant case is the

       liability to pay fine by the petitioner for causing delay in

       construction. With reference to Annexure-C learned counsel for

       the Housing Board submits that construction was not complete

       even up to 12.02.2013. In view of the above conflicting stand of

       the parties the only issue required to be adjudicated in the instant

       case is whether the petitioner is liable to pay fine on her failure to

       complete the construction within the stipulated period and how

       much delay petitioner has committed in completion of

       construction?

                    5) Material available on record would manifest that

       after the death of the husband name of the petitioner was entered

       on 9.1.1987, Thereafter, agreement was made on 5.5.1989.

       Learned counsel for Housing Board submits that five years period

       would reckon from the date of agreement dated 5.5.1989.

       However, prima facie the Court feel that the Board is justified if all

       the formalities on the part of the Housing Board were completed

       and possession of the plot was handed over to the petitioner. In

       fact, possession was handed over only on 28.5.1993 and as such

       there is absolutely no question of reckoning the period of five

       years before handing over possession. So in any view of the matter
 Patna High Court CWJC No.12698 of 2013 dt.16-04-2019
                                           4/5




       reckoning of five years period will begin from the date of handing

       over possession, i.e. on 28.5.1993. After the PRDA sanctioned the

       plan on 21.1.1994 the Housing Board approved the plan on

       5.9.1994

. Water connection was given on 22.11.2000 which indicates that house was constructed that is why water connection was given to the petitioner. So the period of delay in construction shall be counted from 28.5.1993 to 22.11.2000. Any other date for counting the delay is wholly impermissible as prior to handing over possession counting of period of five years is unsustainable and once the water connection was extended the Housing Board is precluded from raising the issue of incomplete construction.

6) Under the aforesaid circumstances, the Court does not approve the claim of the Housing Board that there was delay of 18 years in making construction. The construction period in between 28.5.1993 to 22.11.2000 shall be the period of actual construction and shall be decisive for counting delay and the petitioner shall be liable to pay fine for the period beyond five years from 28.5.1993 to 22.11.2000 and as such the respondent- Board is directed to raise fresh demand for such fine within a period of 30 days from today. In case fresh demand is raised the petitioner has to pay fine for the period as indicated hereinabove within a further period of 30 days from the date of such demand.

Patna High Court CWJC No.12698 of 2013 dt.16-04-2019 5/5

7) With the aforesaid, the writ application is allowed and disposed of.

mrl./-                                      (Anil Kumar Upadhyay, J)
AFR/NAFR                NAFR
CAV DATE                N.A.
Uploading Date          17.04.2019
Transmission Date